h MONTHLY R"" RTS (FOR GRAY BOOK PREPARATION>

NRC DISTRIBUTION FOR PART 50 DOCKET TERIAL (TEMPORARY FORM)

CONTROL NO:

FILE MONTHLY REPORT FILE FROM:Rochester Gas

& Elec.

Co.

Rochester, N.Y.

DATE OF DOC 7~7 75 DATE REC'D 7-11-75 LTR TWX RPT XXX OTHER NRC CLASS UNCLASS PROPINFO ORIG 1Signed INPUT CC OTHER NO CYS REC'D 1

SENT AEC PDR SENT LOCALPDR DOCKET NO:

50-244 DESCRIPTION:

Ltr trans the following:

PLANT NAMF.

RE Ginna 0 1 ENCLOSURES:

Monthly Report for Plant

& Component Operability & Availability This Report to be used in preparing Gray Book by Plans

& Operations.

NUMBER OF COPIES REC'D:

FOR ACTION/INFORMATION VCR 7-1&75 BUTLER (L)

W/ Copies CLARK!L)

W/ Copies PARR (L)

W/ Copies KNI EL (L)

W/ Copies SCHWENCER (L)

W/ Copies STOLZ (L)

W/ Copies VASSALLO (L)

'/

Copies

/PURPLE (L)

W/ Copies ZlEMANN (L)

W/ Copies DICKER (E)

W/ Copies KNIGHTON (E)

W/ Copies YOUNGBLOOD W/ Copies REGAN (E)

W/ Copies LEAR (L)

W/ Copies SPE LS W/ Copies (E)~ MIPC/PE W.4 Copies INTERNALDISTRIBUTION I

~NRC DR OGC, ROOM P-506A.

GOSSI CK/STAF F CASE G IAMBUSSO BOYD MOORE(L)

DEYOUNG (L)

SKOVHOLT (L)

GOLLER (L) (Ltr)

P. COLLINS DENISE REG OPR FILE 5 REGION (2)

T.R. WILSON STEE LE TECH REVIEW SCHROEDER MACCARY KNIGHT PAWLICKI SHAO STELLO HOUSTON NOVAK ROSS IPPO LITO TEDESCO J.

COLLINS LAINAS BENAROYA VOLLMER DENTON G R IMES GAMMILL KASTNER BALLARD SPANGLER ENVIRO MULLER DICKER KNIG HTON YOUNG8 LOOD BEGAN PROJECT LDR HAR LESS LIC ASST

~ R. DIGGS (L)

H. GEARIN (L)

E. GOULBOURNE (L)

P. KREUTZER (E)

J. LEE (L)

M. MAIGRET (L)

S. REED (E)

M. SERVICE (L)

S. SHEPPARD (L)

M. SLATER (E)

H. SMITH (L)

S. TEETS (L)

G. WILLIAMS(E)

V. WILSON (L)

R. INGRAM (L)

A/T IN D

~

BRAITMAN SALTZMAN ME LTZ PLANS

~MCDONALD

~CHAPMAN DUSE (Ltr)

E. COUPE PFTERSON HARTFIELD (2)

KLECKER EISENHUT WIGGINTON E

ERNAL DISTRIBUTION

~1 LOCALPDR Plrj~

M1 TIC (ABERNATI

)

(1)(2)(TO) NATIONALLABS

~1 NSIC (BUCHANAN) 1 W. PENNINGTON, Rm E-201 GT 1 ASLB 1

CONSULTANTS 1 Newton Anderson NEWMARK/8LUME/AGBABIAN ACRS HOLDING/SENT 1 P DR-SAN/LA/NY 1 BROOKHAVEN NAT LAB:

1 G. ULRIKSON, ORNL 1 AGMED (RUTH GUSSMAN)

Rm B-127 GT 1 J. D. RUNKLES, Rm E-201 GT

4 r >

~

wp, I

l c ~

~

1.

'I 2

0 "t t'V+

5 t-r, A,

II

c

~

A rsurzziu

//////

/I/

~fill/II

////////

.////I////////

ROCHESTER GAS AND ELECTRIC CORPORATION

  • )

~W% ~ 0% I4IhOi lOIW O'ICE o

89 EAST AVENUE, ROCHESTER, N.Y. 14649 7ELERHON E AREA coDE Tla 546-2700 Ginna Station July 7>

1975 Office of Plans and Schedules Directorate of Licensing U. S. Nuclear Regulatory Commission Washington>

D. C.

20555 q

L

,>4'./((g

J~<sz@~,.

Subject:

Monthly Report for June>

1975 Operating Status Information R.

E. Ginna Nuclear Power Plant Unit No.

1 Docket No. 50-244 Gentlemen:

Pursuant to the letter dated February 19>

1974 of Mr. L. Manning Muntzing, Director of Regulations, enclosed herewith is the re-quested operating status information of the Ginna Station for the month of June 1975.

Very truly yours, C

Charles E. Platt Superintendent CEP:fah Enclosures (3) cc:

Mr. James P. O'Reilly

L i

~

~

t 4

UNIT NAhlE'inna Station nit f51 July 3, 1975 DATE:

COhlPLETED BY:

Andrew E. McNamara, Operations Aide Telephone 8'1-716 -546-2700, Ext. 291-214 at Ginna OPERATING STATUS TO:

0001, 750601
2400, 750630 1.

REPORTING PERIOD:

GROSS HOURS IN REPORTING PERIOD:

720 2.

CURRENTLY AUTHORIZED POIVER LEVEL hHVt 1520 hlax. Depend.

Capacity (NVe-Net) 3.

POWER LEVEL TO 'iVHICH RESTRICTED (IF ANY): (MIVe Net) 4.

REASONS FOR RESTRICTIONS (IF ANY):

470 THIS MOHTH YEAR TO DATE CUMULATIVE TO DATE 5.

NUhlBER OF HOURS THE REACTOR WAS CRITICAL..

6.

REACTOR RESERVE SHUTDOWN HOURS..

~.

~...

~ ~..

7.

HOURS GENERATOR ON LINE~

~ ~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

8

~

UNIT RESERVE SHUTDOWN HOURS 533,79 103.88 520 2,518.21 290.39 23393 8.5 363836.37 290.39~'<

35,595.13

8. 5":

9.

GROSS THERhlAL ENERGY GENERATED (MWH).... ~

~

10.

GROSS ELECTRICAL ENERGY GENERATED (MWH)...

11.

NET ELECTRICAL ENERGY GENERATED (MWH).....

6243696 332463811 2013864 130603861 190 321 1 006 103 43391lgl30 143667>679 13 8573265 12. REACTOR AVAILABILITYFACTOR (1)..........

13.

UNIT AVAILABILTYFACTOR (2).

~..

~ ~.

~

~

14.

UNIT CAPACITY FACTOR (3) 16.

UNIT FORCED OUTAGE RATE (4). ".

~...

~. "

74.14 72.2 56.24 27.78 57.98 55.1 49.29 10.03 74.52 72.6 64.36 9.7 16.

SHUTDOWNS SCHEDULED OVER NEXT 6 hlONTHS, (TYPE, DATE AND DURATION OF EACH):

v<<Cumulative Data Commencing January 1,

1975

17. IF SHUT DOWN AT END OF REPORT PERIOD3 ESTIMATED DATE OF STARTUP:

18 'NITS IN TEST STATUS (PRIOR TO COhlhIERCIAL OPERATION):

DATE FORECASTED DATE ACHIEVED INITIAI CRITICALITY INITIAL ELECTRICAL POWER GENERATION COhIhIERCIAL OPERATION (2)

UNIT AVAILABILITYFACTOR (1)

REACTOR AVAILABILITYFACTOR =

HOURS REACTOR WAS CRITICAL GROSS HOURS IN REPORTING PERIOD HOURS GENERATOR ON-LINE GROSS HOURS IN REPORTING PERIOD 231 00

<100 (3)

UNIT CAPACITY FACTOR = NET ELECTRICAL POWER GENERATED

<<c1 00 CURRENTLY LICENSED POIVER LEVEL<<'GROSS HRS.

IN REPORTING PERIOD (4)

FORCED OUTAGE RATE

=

FORCED OUTAGE HOURS

<<3100 HOURS GENERATOR ON-LINE + FORCED OUTAGE HOURS 49 88

e

'I

~

'I

~

I 0

4 4

\\

W ~ 'I I

ENCLOSURE A

Ginna Station Unit 81 UNIT July 3, 1975 DATE'OhhPLETED BY Andrew E. McNamara, Operations ide h

8l elephone 81-716-546-2700 291-214 at Ginna DAILY PLANT POWER OUTPUT

June, 1975 MONTH DAY 10 13 15 16 17 18 19 20 21 22 23 AVERAGE DAILY MWe-net 218.88 250.21 320.71 382.96 434.04 106.92 331.71 427.25 429.21 430.46 431.04 446.37 460.00 459.46 459.71 458.17

.74.6 0

6<0 87

i. 88.8w

-224.4 ",

61.'08 0

DAY 25 26 28 29 30 31 AVERAGE DAILY MWe-net 6.33 172.58 322.42 432.67 456.00 4S ~ 87

'e I

h f%

f'

.~ ~

C'

SUMMARY

Reactor Power Levels varied during report month> for extended periods, from 25% to 100%..

Exceptions are outages listed below.

Ginna Station, Unit 81 DATE Jul 39 1975 COMPLETED BY Andrew E. McNamara, Operations Aide Telephone 81-716-546-2700>

Ext; 291-214 at Ginna REPORT MONTH PLANT SHUTDOWNS NO.

DATE TYPE F-FORCED S-SCHEDULED DURATION (HOURS)

REASON (I)

METHOD OF SHUTTING DOWN THE REACTOR (2)

COIVNENTS 6/6/75 12 Main steam isolation valves - malfunction 6/17/75 Loss of "A" Inverter 10 6/17/75 97'5 A

See Note Manual turbine trip due to excessive plant systems vibrations 6/23/75 F

86.75 Main steam isolation valves - malfunction NOTE:

Reactor did not trip.

Power below permissive for reactor trip coincident with turbine-trip.

Reactor manually placed in hot shutdown condition.

(I)

REASON:

A -

EQUIPMENT FAILURE (EXPLAIN) 8 - MAINT. OR TEST C - REFUELING D -

REGULATORY RESTRICTION E -

OPERATOR TRAINING AND LICENSE EXAMINATION F - ADMINISTRATIVE G -

OPERATIONAL ERROR (EXPLAIN)

(2)

METHOD:

A - MANUAL B -

MANUAL SCRAM C -

AUTOMATIC SCRAM

e