Discusses Integrated Startup Test Program for Insp & Testing to Be Completed Prior to Return to Plant Operation After Steam Generator Repair Program.Apps A-D Encl
ML18139B103
Person / Time
Site: Surry Dominion icon.png
Issue date: 02/26/1981
From: Sylvia B
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Harold Denton, Varga S
Office of Nuclear Reactor Regulation
References
081, 81, NUDOCS 8102270629
Download: ML18139B103 (48)


Text

)

e VIRGINIA ELECTRIC AND POWER COMPANY~'.:;

~ICHMOND, V:r:aGIN J:A 2 3261 February 26, 1981 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulations Attn:

Mr. Steven A. Varga, Chief Operating Reactors Branch No. 1 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D. C.

20555 Gentlemen:

SURRY POWER STATION UNIT 1 INTEGRATED STARTUP TEST PROGRAM i\\~).

i....

,i.*. -

Serial No. 081 NO/JLW/DWL:ms Docket No. 50-280 License No. DPR-32 We are submitting, for your review, our Integrated Startup Test Program for inspection and testing to be completed prior to returning Surry Power Station Unit No. 1 to operation after the Steam Generator Repair Program.

This letter is to meet the requirements of Amendment No. 46 to the Operating License for Surry Power Station Unit No. 1 to submit the test program sixty days prior to fuel loading.

The Integrated Startup Test Program is comprised of two phases:

Preoperational Tests and Startup Tests.

The format of the program follows the intent of Regulatory Guide 1.68, Revision 2, August, 1978, "Preoperational and Initial Startup Test Programs for Water-Cooled Power Reactors."

In some cases interpretation is necessary since Surry Unit No. 1 is a previously licensed PWR plant that has undergone major equipment replacement and modification rather than being new construction.

The tests in the Preoperational Test phase are designed to provide assurance that components and subsystems of new, modified, and original systems function safely within established design criteria.

The Preoperational Tests on a new or modified system are conducted prior to fuel loading.

This test phase also allows the plant operating staff to become familiar with the operation of a new or modified system and to verify by trial use, to the extent practical, that the operating procedures are adequate.

The tests in the Startup Test phase are designed to provide assurance that systems that were previously demonstrated as functioning safely, and the new or modified systems will function to "(1) provide for safe normal operation and high tolerance for systems malfunctions and transients, (2) ensure that, in the event of errors, malfunctions, and off-normal conditions, the reactor protection systems and other design features will arrest the event or limit its consequences to defined and acceptable levels, and (3) ensure that adequate safety margins exist for events of extremely low probability or for arbitrarily postulated hypothetical events without substantial reduction in the safety margin for the protection of public health and safety." The Start-up Tests are performed during and after fuel loading to confirm the design basis and demonstrate that the plant will continue to operate in accordance with design.

. *. 8 1 0 2 2 7 0 to:J.9*

f

/Jo)-7

.s

,/vo

)

e 2

VIRGINIA ELECTRIC AND POWER COMPANY TO Per Criterion 1 of Appendix A to 10 CFR 50 all structures, systems, and components will be tested or demonstrated operable to levels commensurate with the importance of the safety functions.

In addition, the extent of testing will vary directly with the amount of construction done to and around the particular equipment or system.

The sequence of tests will be conducted so that the safety of the plant is never totally dependent on the performance of untested structures systems or components.

The key points of the Integrated Startup Test Program are presented below. The referenced Appendices provide additional details of the program.

Further information including the Integrated Startup Test Schedule is available for the NRC site inspector at the station.

These Appendices are working documents that will be revised as required within the framework of this letter.

ORGANIZATION Appendix D contains the "Procedure for Conducting the Integrated Startup Test Program for Post Steam Generator Replacement and PO&M Design Changes.

11 This document defines the organizations, responsibilities, actions, and administra-tive controls for each phase of the program.

The management and direction of the Integrated Startup Test Program is under the direct control of Vepco with principal authority assigned to the Superin-tendent of Operations for Surry Power Station.

The Startup Group is composed of Stone & Webster Engineering Corporation advisory engineers and Vepco station operations and engineering personnel.

The Startup Group has overall responsibility for implementation and documentation of the program.

The conduct and direction of the tests in the Preoperational Test phase are controlled by the Startup Group.

The conduct and direction of the tests in the Startup Test phase are controlled by Vepco Station operations and eqgineering staff with technical support from the Startup Group.

In all cases the test procedures require approval of the Station Nuclear Safety and Operating Committee prior to implementation.

Deviations to approved test procedures are documented and become part of the final test results.

Administrative controls for making changes to approved procedures are provided in the Vepco Nuclear Power Station Quality Assurance Manual.

The acceptance criteria for all tests are approved by the Station Nuclear Safety and Operating Committee.

Design related deficiencies are resolved by the Startup Group with the assistance of the Vepco project engineer and Vepco operations or outside consultants as deemed necessary.

TEST PHASES Preoperational and Startup Test Phases are shown on the network in Appendix A and defined in more detail in Appendix D.

Each phase of the Integrated Start-up Test Program is composed of a.series of tests as described below:

1.

Preoperational Test Phase The Preoperational Test phase consists of functional tests of new, modified and affected original equipment and systems.

This phase includes tests, adjustments, calibrations, and systems operations

e e

3 VIRGINIA ELECTRIC AND POWER COMPANY TO necessary to assure that the subsequent testing' can be safely under-taken.

This phase also includes a walkdown of systems adjacent to construction work for damage.

Any repairs and subsequent testing of equipment will be accomplished by a field change to the Design Change.

Major milestones during the Preoperational Test phase are outlined in Appendix A.

Major Preoperational Tests are listed in Appendix B.

The actual sequence of individual tests is formulated prior to performance of the tests considering equipment and system availability and is maintained on an Integrated Startup Test Sche-dule.

The Startup Group analyzes the preoperational test results.

The acceptance c~iteria for all tests are approved by the Station Nuclear Safety and Operating Committee.

In instances where perfor-mance of components or systems deviates from predicted results, further engineering evaluations, rework, and/or retesting is per-formed to resolve the discrepancies before the test is considered satisfactory.

Assistance from the Vepco project engineer and Vepco operations or outside consultants is solicited as deemed necessary.

Systems which have to be modified as a result of the Preoperational Test are retested to verify acceptance performance.

The major pre-fuel loading Preoperational Tests are outlined in Appendix B.

Components and systems are tested and evaluated according to approved testing procedures.

Preoperational Tests are performed to verify, as near* as possible, the performance of the system under actual operating conditions.

Where required, simulated signals or inputs are used to verify the full operating range of the system and to calibrate and align the systems and instruments at these conditions.

2.

Startup Test Phase The major testing milestones during the Startup Test phase are identified on the network (Appendix A) and discussed below.

Maj or Startup Tests are listed in Appendix C.

a.

Post-Fuel Loading Tests Systems that are not used during normal plant operat:i.on, but must be in a state of readiness to perform safety functions, are tested or demonstrated operable prior to plant conditions requiring them to be available as defined in the Technical Specifications.

Abnormal unit conditions are simulated during testing as required and when such conditions do not endanger personnel or equipment, or contaminated systems whose cleanli-ness has been established.

Fuel loading begins when all prerequisite system tests and operations are satisfactorily completed.

Upon completion of fuel loading, the reactor upper internals and pressure vessel head are installed.

Additional mechanical and electrical tests are performed on the rod control system, rod position indication, and in-core moveable detector system.

The purpose of this segment of the Startup Test Phase is to prepare the system for nuclear operation and to establish that all design requirements necessary for opera-tion are achieved.

e 4

VIRGINIA ELECTRIC AND POWER COMPANY TO

b.

Hot Functionals

c.

Prior to initial criticality, the following hot functional tests are performed:

heatup of the primary system, thermal expansion testing of affected systems, vibration testing of construction affected equipment, and reactor coolant pump coast down time check.

The primary system operational pressure test is conducted in accordance with the Technical Specifi-cations.

Criticality and Low Power Physics Tests On completion of hot functional tests, nuclear operation of the reactor begins.

These final segments of Startup Testing include criticality and low power physics testing.

The purpose of these tests is to verify the operational characteristics of the unit and core, to acquire data for the proper calibration of set points, and to ensure that operation is within license requirements.

Appendix C

  • includes the major Startup Tests which are performed from fuel loading to rated power.

The actual sequence of tests is formulated by station engineer-ing and operating personnel considering test requirements and equipment availability.

Procedures are prepared to specify the sequence of tests and

  • measurements and the conditions under which each is to be performed to ensure safety of operation and consistency of the results obtained. If significant deviations from design calcu-lation exist, unacceptable behavior is revealed,. or apparent anomalies develop, the testing would be suspended.and the situation reviewed to determine whether a question of safety is involved prior to resumption of testing.
d.

Power Level Escalation Testing When the operating characteristics of the reactor and unit are verified by low power physics testing, a program of power level escalation in successive stages is used to bring the unit to its full rated power level.

Both reactor and unit operational characteristics are examined at each stage of the power escalation program.

e.

At Power Testing On completion of power level escalation testing the following at power tests are performed:

final steam generator carryover

testing, secondary plant heat balance
checks, condensate polishing chemistry performance testing, and load rejection testing with the condensate polisher in service.

e 5

VIRGINIA ELECTRIC AND POWER COMPANY TO EXTENT OF TESTING All Unit No. 1 systems and systems common to both Unit No. 1 and Unit No. 2 are included in the Integrated Startup Test Program.

These programs are listed in the System Index (Attachment 8. 4 of Appendix D).

This listing includes all systems associated with Unit No. 1 that have undergone major modification, new systems, and systems that have remained operational since Unit 1 shut down.

The purpose of this breakdown is to identify all station systems and to determine the degree of Preoperational Testing required.

  • Because of the various amounts of construction done to and around each system, a graded approach for the extent of the testing is employed.

The tests required for individual components within a system will be developed by the Startup Group and listed on a test matrix for that system.

In areas such as Unit No.

1 containment, where extensive work has been performed, all equipment and systems will be checked during the Preoperational Testing.or Startup Testing phase.

In other areas, such as the Auxiliary Building where little work has been performed, selected system walkdowns will be employed in conjunction with normal station startup procedures to verify the operability of the equipment.

Those systems that are new or have undergone major design basis changes will undergo complete component testing and performance testing to verify design and installation.

SUMMARY

This letter outlines in detail the Integrated Startup Test Program we plan to implement to demonstrate our ability to safely return Surry Power Station Unit No. 1 to power.

The Integrated Startup Test Prgram will provide the necessary assurance that the plant can be operated in accordance with design requirements and in a manner that will not endanger the health and safety of the public.

cc:

Mr. James P. O'Reilly, Director Office of Inspection and Enforcement Region II Atlanta, Georgia 30303 Very truly yours,

~~

Manager - Nuclear Operations and Maintenance

e LIST OF APPENDICES APPENDIX A STARTIJP NEIIDRK APPENDIX B UST OF MAJOR PREDPERATIONAL 'IESTS AND CHECKS APPENDIX C LIST OF MAJOR STARTUP TESTS AND CHECKS APPENDIX D PROCEDURE FOR OONDUCTING TI-IE INIEGRATED STARTUP PRCX;RAM

SEC.

HYDRO Preoperati RIMARY HYDRO Test STARTUP NETWORK SURRY UNIT N0.1 ECCS NTEGRATE TEST e

FUEL LOAD "A" LEAK HOT TEST F NCTIONAL START artup st Phase HOT UNCTION COMPLETE e

ULL LOA PERATIO

e APPENDIX B UST OF HAJOR PREOPERATICNAL 'IESTS AND CHECKS

TITLE OF TEST OR CHECK LIST OF PREOPERATIONAL TESTS AND CHECKS PLANT CONDITION/PREREQUISITE TEST OBJECTIVE

1.

Nuclear Instrumentation

2.

Process Instrumentation

1.

Pressure Boundary Integrity Tests

a.
b.

Hydrostatic test Baseline data for inservice inspection

2.

Component Tests

a.

Pressurizer Safety Valve I.

PLANT INSTRUMENTATION Prior to core loading Ambient and/or at temperature Nuclear instruments are aligned and source, range detector response to a neutron source checked as the primary source is loaded.

Required equipment is aligned per station procedures.

.~

II.

REACTOR COOLANT SYSTEM 0

Below 200 F (after verification of cleanliness and fill of system)

During preoperational testing Ambient pressure Cold hydrostatic testing of each Reactor Coolant System loop will be performed at test pressures as specified by ASME standards for the system.

Prior to pressurization, the effected portions of the system will be heated above the minimum temperature for pressurization.

The pressure is then increased in increments, and at each increment inspections are made for leakage.

Leaky valves or mechanical joints are not~

basis for rejecting the test. Overpressur~

protection is provided during testing, Systems and components that require inspection in accordance with Section XI of the ASME Code are examined for base line data.

Data from these inspections provide base line data for subsequent inservice inspections.

The setpoints of the safety valves are verified using existing station procedures.

Appendix B (Page 1 of 5)

TITLE OF TEST OR CHECK

1.

Automatic Reactor Power Control Test Systems

1.

Reactor Protection System

2.

Engineered Safety Features

1.

Residual Heat Removal System Test LIST OF PREOPERATIONAL TESTS AND CHECKS PLANT CONDITION/PREREQUISITE III.

REACTIVITY CONTROL SYSTEMS Preoperational testing IV.

REACTOR PROTECTION SYSTEMS Prior to core loading Prior to core loading V.

POWER CONVERSION SYSTEM Done under Startup Testing VI.

AUXILIARY SYSTEMS Prior to core loading TEST OBJECTIVE The system alignment is verified at preoperational conditions to demonstrate the response of the system to simulated inputs.

These tests are performed to verify that the systems will operate sat isfactorily at power.

Prior to core loading the Reactor F~

tection is tested to demonstrate op~-

bility, proper logic, redundancy, and coincidence.

The protection channels are verified through to tripping of the reactor trip breakers.

Prior to core loading the Engineered Safety Features logic systems are tested to demonstrate operability, prope logic, redundancy, and coincidence.

This system essentially remained in service except for maintenance work on the pumps and the addition of an expan-sion loop to the recirculation line.

Normal system OP's and PT's will be used to run the system in support of various pre-core loading tests.

Appendix B (Page 2 of 5)

LIST OF PREOPERATIONAL TESTS AND CHECKS TITLE OF TEST OR CHECK

2.

Containment Instrument Air System

3.

Neutron Shield Tank Cooling System

4.

Leak Detection System Tests

1.

Emergency Power Systems

1.

Reactor Containment Tests PLANT CONDITION/PREREQUISITE Prior to core loading After core loading Prior to and during preoperational tests VII.

ELECTRICAL SYSTEM Prior to core loading VIII.

CONTAINMENT SYSTEMS

- After core loading TEST OBJECTIVE The instrument air system, including.

compressors, is tested to verify proper operation.

The system is operationally checked out to verify heat exchange operability.

Temperature detectors in the drain line~

from pressurizer safety_valves and.--

reactor vessel head seal and their rm functions are checked.

Pressurizer relief tank level and temperature sensors ar:e calibrated and associated alarms checked.

The automatic starting and loading of the diesel generators is demonstrated under loss of emergency buss alternating current power.

Containment Type A leakage tests will be perf orrned in accordance with USNRC A approved topical report BN~ToP~l Rel'!"!,

which provides for a reduced duration test.

Containment Type*B & C leakage tests will be performed in accordance with Appendix J to 10CFRSO.

Appendix B (Page 3 of 5)

TITLE OF TEST OR CHECK LIST OF PREOPERATIONAL TESTS AND CHECKS PLANT CONDITION/PREREQUISITE

2.

Containment Isolation Tests Prior to core loading TEST OBJECTIVE The operation of *actuation systems and components used for containment isolation is verified.

IX.

GASEOUS RADIOACTIVITY REMOVAL SYSTEMS Systems remained in service.

No special testing will be performed other than normal OP's and PT's.

X.

EMERGENCY CORE COOLING SYSTEM

1.

High Pressure Safety Injection Tests After core loading

2.

Low Pressure Safety Injection Tests Prior to core loading The High Pressure Safety Injection Test~

will officially be performed during Hot Functional Testing.

The Charging System will actually be used during many of the pre-fuel loading tests and normal opera-tions under OP's and PT's.

Additional performance tests, other than OP's and PT's will be accomplished during Hot Functionals when the testing can be performed at actual plant conditions.

This approach will be taken since no major rework was performed on this sytem.

Components that are discon-nected during the Steam Generator Replace-ment Project are individually tested under station approved procedures.

The Low Read Safety Injection System is.~

checked to verify design flow, flow pattllllllll" and pump operating characteristics. More specifically thats a,

Valves installed for redundant flow path operate as designed.

Appendix B (Page 4 of 5)

LIST OF PREOPERATIONAL TESTS AND CHECKS TITLE OF TEST OR CHECK PLANT CONDITION/PREREQUISITE XI.

FUEL STORAGE AND HANDLING SYSTEM

1.

Refueling Equipment (hand tools and power equipment, including protective interlocks)

Prior to core loading XII.

REACTOR COMPONENTS HANDLING SYSTEM Done during startup XIII.

RADIATION PROTECTION SYSTEM

1.

Criticality and area monitor tests Prior to core loading

b.

c,

d.

TEST OBJECTIVE Pwnp operating characteristics are verified with the reactor coolant system at ambient conditions.

1 Valves and motors operate on operator:

initiation and/or automatically on 1

initiation of safety injection signal.

Level and pressure instruments are properly calibrated.

Tests are performed prior to core loading to demonstrate the functioning *of the fuel transfer system.

The radiation alarms associated wit.

core loading are checked out and th alarm setpoints verified.

Appendix B (Page 5 of 5)

APPENDIX C LIST OF MAJOR STARTUP TESTS AND CHECKS

LIST OF STARTUP TESTS AND CHECKS r

  • TITLE OF TEST OR CHECK
1.

Nuclear Instrumentation (excore)

2.

Process Instrumentation (Temperature, pressure, level, and flow instruments)

1. Vibration and amplitude 2,

Expansion and Restraint

3.

Integrated Hot Functional Tests PLANT CONDITION/PREREQUISITE I. PLANT INSTRUMENTATION Prior to criticality Ambient and/or at temperature II.

REACTOR COOLANT SYSTEM After fuel load During plant heat-up Heatup and at temperature Hydro-static testing has been satis~

factorily completed and Reactor Coolant System instruments aligned and operational.

Assoc-iated auxiliary systems shall be operational to the extent re-quired to support hot functional

  • testing.

TEST OBJECTIVE Just before criticality all channels are checked to verify high level trip functions, alarm setpoints, audible count rates where applicable, and operation of strip chart recorders, and any auxiliary equipment.

Equipment is aligned per station procedures.

e Vibration sensors on the main coolant pumps are monitored in order to check for excessive vibration while starting and stopping the pumps.

During the heat~up to operating tempera~

ture, selected point on components and piping of the Reactor Coolant System are checked at various temperatures to verif) unrestricted expansi'on.

Points of interference detected during the h.~up are corrected prior to increasing temperature.

The Reactor Coolant syatem is tested using pump heat to reverify heat,up procedures and to demonstrate satis-:-

factory performance of components and systems exposed to reactor coolant system temperature.

Proper operation of instrumentation, controllers and alarms, is checked against design operation conditions of auxiliary systems and setpoints verified.

Among the demon-strations performed are:

Appendix ~. (Pa~e 1 of 11)

TITLE OF TEST OR CHECK

4.

Components Tests

a.

Pressurizer LIST OF STARTUP TESTS AND CHECKS PLANT CONDITION/PREREQUISITE At operating temperature.

TEST OBJECTIVE

a.

To check that water can be charged b the Chemical and Volume Control

b.
c.

d,

e.
f.
g.
h.

To check letdown design flow rate fo each operating mode.

To check response of system to chang in pressurizer level.

flt To check operation of the excess letdown and seal water flow paths.

To check steam generator level instrumentation response to level changes.

To check thermal expansion of selec-ted system components and piping.

To perform isothermal calibration of resistance temperature detectors and incore thermocouples.

To operationally check out the.a11111111.

Residual Heat Removal System. ~

During the hot functional testing the pressure controlling capability of the pressurizer is demonstrated to be within the controlling band.

With reactor coolant pumps operating and with full spray, the pressure-reducing capability of the pressurizer is verified.

With the spray secured and all heaters ener-1 gized, the pressure-increasing capabilit of the pressurizer is verified.

Appendix C (Page 2 of 11)

5.

LIST OF STARTUP TESTS AND CHECKS TITLE OF TEST OR MEASUREMENT

b. _Reactor Coolant_Pumps and Motors
c.

Steam Generators Pressure Test of Reactor Coolant System PLANT OONDITION/PREREQUISITE At ambient conditions and during heat-up and at temp-erature.

At ambient conditions and during heat-up and at temperature Prior to criticality TEST OBJECTIVE Pressurizer.Relief valves are func-tionally checked.

As the pumps and motors are placed in operation they are checked for:

1
1.

Direction of rotation (initial start, only)

, ~-

2.

Vibration

3.

Power requirements

4.

Lubrication

5.

Cooling

6.

Megger and hi pot test (as applicable

7.

Overload protection

8.

Correct power supply voltage The proper operation of instrumentation and control system of steam generators are checked during heat-up and at

~

temperature.

The heat transfer capdllllll" bility of the steam generators is demon-strated.

The functioning of the blow-down system will be checked.

Following core loading and installation of the Reactor Vessel head and torquing of the reactor vessel heads studs, pressure testing is performed in accor-dance to Tech. Spec.

Appendix C (Page 3 of 11)

TITLE OF TEST OR MEASUREMENT LIST OF STARTUP TESTS AND CHECKS PLANT CONDITION/PREREQUISITE

6.

Chemical Tests (to establish water quality)

Prior to heat-up during startup testing

7.

Reactor Coolant Flow Test

1.

Chemical and Volume Control System Tests Prior to plant criticality III.

REACTIVITY CONTROL SYSTEMS At ambient and/or at operating conditions.

System components operationally checked out.

TEST OBJECTIVE Water for Reactor Coolant System fill*

and makeup is analyzed for chloride content, conductivity, total suspended solids, pH, clarity, and fluorides to requirements specified by the chemistry manual for NSSS.

Following core loading_

and prior to exceeding 250 °F, hydrazin.e; is added to scavenge oxygen prior to critical operation.

Prior to, at A criticality, and* during power escal1'i.on!

chemical analysis is performed to verify requirements.

Following core loading, measurements are made of elbow tap differential pressures to make relative comparison.

At hot shut.down conditions following core loading, measurement of loop elbow differential pressure drops were made.

Using these data with the reactor coolan1 pump performance curve, the calculated flow is verified to the design flow.

Flow coastdown and transients following reactor coolant pump stoppages are also determined at shutdown conditions.A following core loading.

11111111" Makeup and letdown oper~tions are conduc*

ted with the Chemical and Volume Control System to check out the different modes of dilution and boration and verify flow, in the different modes.

The adequacy of of heat tracing to maintain the required Boric Acid concentration in solution is verified.

The ability to adequately sample is demonstrated.

Appendix C (Page 4 of 11)

TITLE OF TEST OR CHECK

2.

Emergency Boration System Tests

3.

Incore Monitor System Test

a.

Incore Thermocouples

b.

Moveable Detector System

4.

Control Rod Systems Tests

a.

Rod Control System LIST OF STARTUP TESTS AND CHECKS PLANT CONDITION/PREREQUISITE During hot functional During heat-up and at temperature.

At ambient conditions following core loading and critical testing.

Ambient conditions following core loading and hot conditions after core loading.

TEST OBJECTIVE The flow path of the Emergency Boration system is verified by pumping into the Reactor Coolant System.

During heat-up and at temperature.

the incore thermocouples are calib ed to the average of the Reactor Coolant System resistance temperature detectors.

All readout and temperature compensating equipment is checked during the calibra-tion and isothermal corrections for the operative thermocouples are determined.

After core loading, the installation checkout of the moveable detector system will be completed.

During the installation check of this system it is energized and operati-lly checked out with mechanisms connec to each power supply.

The aliility of the system to step mechanism is verifiedi the alarm and inhibit functions checked out and the correct values of system parameters adjusted to specified values.

After core loading the operation of each rod over its full range of travel is demonstrated.

AEJ?endix C (Page 5 of 11)

TITLE OF TEST OR CHECK

b.

Rod Drop Tests

c.

Rod Position Indication

1.

System Tests

a.

Vibration Frequency and Amplitude

b.

Expansion and Restraint LIST OF STARTUP TESTS AND CHECKS PLANT CONDITION/PREREQUISITE Cold and hot plant *conditions following core loading.

At ambient conditions and at temperature following core loading.

IV. REACTOR PROTECTION SYSTEM TEST OBJECTIVE At cold and hot plant conditions followit core loading the drop times of the fufl I

length rods are measured.

The drop time' is measured from the release of the rod until the rod enters the top of the dashj pot.

This time was verified to be less l than the maximum value specified in the ;

Technical Specifications.

  • * ~-

During rod control system tests the~

position indication system was alignea to provide rod movement indication.

Rod bottom setpoints will be adjusted during these tests.

After plant heat-up individual rod positions are calibrated to within tolerances specified by the tes procedure.

Done during Preoperational Testing V.

POWER CONVERSION SYSTEM Hot Functional Testing and/or plant heat-up following criticality During heat-up, and at temperature When the main turbine is rolled, vi~io readings are monitored.

(Turbine vibra-tions are also monitored throughout the power escalation program.)

Major equip-ment (e,g., feedwater pumps and condensat pumps)are operated as they become availa-ble and are observed for indications of excessive vibration, During heat-up to operating temperature, selected points on the components and and piping of the systems are checked at various temperatures to verify that they can expand unrestricted.

,A..ppe1:1_d~_G (Page 6 o{ 11)

TITLE OF TEST OR CHECK LIST OF STARTUP TESTS AND CHECKS PLANT CONDITION/PREREQUISITE

2.

Components and Individual System

a.

Steaill Generator Pressure Relief and Safety Valves

b.

Emergency Feedwater (Auxiliary) System

c.

Turbine Control and Bypass Valves

d.

Feedwater and Feedwater Control System Pressure Conditions Prior to criticality Hot Functional testing and/or power operation following criticality Hot functional testing and at Power TEST OBJECTIVE The setpoint of safety valves was verified by in-plant tests at pressure and temperature conditions when the unit was shutdown.

Setpoints were ched by using a pressure assist device which adds to the force due to pressure.

Once the valve leaves the seated position the assist device was vented, allowin~e valve to reseat *immediately.

Stea111' relief valve setpoint checks were made during instrument alignment.

Prior to criticality the emergency feedwater system is checked out to verif its ability to feed the steam generators Automatic starting is checked during checkout of the safeguards logic system tests.

During hot functional testipg the turbine control system will be demon-strated in turbine operation up to and including a period of operation at synchronous speed.

The turbine bY.illL_ss valves to the condenser and their.a, associated control systems are operationally checked out during hot functional testing.

The feedwater and condensate pumps are operationally checked out during hot functional testing.

During power esca-lation the power is increased and the ability of the feedwater pumps and control system to maintain level in the system generators are aligned.

Prior t filling the system and during fill, the system is used to monitor level in the steam generator.

AnnPn~i~ r. (~~op 7 nf 11)

  • I LIST OF STARTUP TESTS AND CHECKS TITLE OF TEST OR CHECK PLANT CONDITION/PREREQUISITE
e.

Condenser Circulation Water

f.

Makeup Water and Chemical Treatment

1.

Reactor Coolant System Makeup Test (CVCS)

Prior to hot functional testing During Steam generator fill.,

hot functional testing and at power VI.

AUXILIARY SYSTEMS

2.

Seal and Pump Cooling Water Prior to heat-up and Test (CVCS) at temperature

3.

Secondary Vent and Drain System Test

  • During hot functional testing
4.

Component Cooling System Test Ambient and/or hot plant conditions

5.

Residual Heat Removal System Test Prior to and during hot functional testing TEST OBJECTIVE Prior to hot functional testing the main circulating water system valves are tested to verify operability.

The makeup system to the steam genera-tors is checked out during hot functional*

testing and at power.

The chemical treatment system is checked out when chemicals are added to the steam genera-tors at heat-up t_o steaming conditi-See III REACTIVITY CONTROL SYSTEM, Item 1.

Prior to reactor coolant pump operation and with the system pressurized,flow to the pump seals and cooling water is set.

Flow is adjusted to specified values using installed instruments.

During hot functional testing when at operating temperature and pressure, seal and coolini flows and temperatures are checked.

During hot functional testing follow~

core loading the secondary system i~

vented while pressurizing the second-ary system.

Secondary drains are tested for unrestricted flow in accor-dance with operating procedures.

Component cooling flow to the various components in the affected systems is adjusted, the system operationally checked out, and setpoints verified.

Heat removal capability demonstrated.

Appendix c. (Page 8 of 11)

LIST OF STARTUP TESTS AND CHECKS TITLE OF TEST OR CHECK

6.

Service Water System Test

7.

Control Rod Drive Mechanism and Rod Position Indication Coil Cooling System Test

8.

Primary Sampling System

9.

Primary Pressure FeliefSystem PLANT CONDITION/PREREQUISITE Prior to hot functional Prior to and/or during hot functional testing Prior to and/or during hot functional testing Prior to hot functional testing and at pressure conditions VII.

ELECTRICAL SYSTEM TESTS TEST OBJECTIVE The system is operationally checked out to verify pressure and flow.

Service*

water flow is verified to components in the system.

The system is operationally checked out to verify air flow, temperatures and motor current.

Operations are performed to:

a.

Demonstrate that liquid and gas samples can be obtained from sample points.

b.

Demonstrate that valves, instruments, and controls function properly.

c.

Verify proper functioning of the sample cooler.

The pressurizer relief tanl&i associated valves and instrumentation are checked out to verify performance of design functions.

For testing of pressurizer relief and safety valves see II

~

REACTOR COOLANT SYSTEM.

,a, Done during Preoperational Testing VIII.

CONTAINMENT SYSTEMS

1.

Containment Ventilation System Test Prior to and/or during hot functional testing The system is operated to balance air flows and to verify the ability to maintain temperatures below maximum allowable limits; Appendix C (Page 9 of 11)

LIST OF STARTUP TESTS AND CHECKS TITLE OF TEST OR CHECK

2. Post Accident Heat Removal System Tests (Containment Sprays)
1. Accumulator Tests
1. Spent Fuel Storage Radiation Monitoring Equipment
1. Reactor Component Handling System (Polar Crane)

PLANT CONDITION/PREREQUISITE Prior to criticality TEST OBJECTIVE Tests are performed to verify pump operating characteristics, and response to control signals, sequencing of pumps, valves and controller (and to ensure that spray nozzles were unobstructed.)

IX. GASEOUS RADIOACTIVITY REMOVAL SYSTEMS Done during Preoperational Testing X. EMERGENCY CORE COOLING SYSTEM During hot functional Flow through the accumulator lines is initiated to demonstrate that the check valves are free to open.

Tests are also made to verify that accmnulator pressure could be maintained.

XI.

FUEL STORAGE AND HANDLING SYSTEM Prior to plant startup Refer to Appendix B, XIII RADIAITON PROTECTION SYSTEM, Item 1.

XII.

REACTOR COMPONENTS HANDLING SYSTEM Prior to use for installation of components within the containment XIII.

RADIATION PROTECTION SYSTEM Testing was conducted on the polar 8ne in accordance with standard crane test-ing procedures during steam generator replacement.

Done during Preoperational Testing Appendix C (Page 10 of 11)

LIST OF STARTUP TESTS AND CHECKS TITLE OF TEST OR CHECK PLANT CONDITION/PREREQUISITE TEST OBJECTIVE XIV.

INITIAL CRITICALITY AND LOW POWER TESTS

1. Initial Criticality Plant at hot shutdown XV.

POWER ASCENSION

1. Power Ascension Criticality The objective is to bring the reactor critical from the plant conditions speci-
fied, Prior to start of rod withdrawal, the nuclear instrumentation had been aligned, checked, and conservative reactor trip setpoints made per procedures.

At preselected points in rod withdrawal, data is taken and inverse count rate plots made to ena e

extrapolating to the expected critical rod position.

In addition, the following tests associated with modified system will be performed:

blowdown system capability test and thermal expansion monitoring, Normal post re~ueling testing will apply for power ascension.

In addition the following design tests associated with modified systems will be performed:

steam generator carryover tests -

steam generator thermal and hydraulic performance verification steam generator water level stability and control demonstration condensate polishing per~ormance testing load rejection testing with condensate polisher Appendix C (Page 11 of 11)

APPENDIX D PROCEDURE FOR CONDUCTING THE INTEGRATED STARTUP TEST PROGRAM

'\\

e PROCEDURE FOR CONDUCTING THE INTEGRATED STARTUP TEST PROGRAM FOR POST STE&~ GENERATOR REPLACEMENT AND P.O. & M. DESIGN CHANGES SURRY POWER STATION VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA Lead Advisory Engineer:

e INTEGRATED STARTUP TEST PROGRlu~

TABLE OF CONTENTS

1.0 Purpose and Scope

2.0 References 3.0 Definitions 4.0 Participating Organizations 5.0 Construction Phase 6.0 Preoperational Test Phase 6.1 General 6.2 Responsibilities 6,3 Release for Startup Testing 7.0 Startup Test Phase 7.1 General 7.2 Responsibilities 7.3 Startup Release Points 8.0 Attachments

e SURRY UNIT 1 VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 1.0 PURPOSE AND SCOPE 1.1 To provide a procedure for the accomplishment of the tests and checks to be completed prior to plant operations.

1.2 To define the phases of the Integrated Startup Test program.

1.3 To define the responsibilities of the organizations participating in the Integrated Startup Test program.

1.4 To provide the necessary administrative controls to ensure all pre-requisites are complete prior to commencing the next phase of test-ing.

1.5 To define responsibilities for the preparation of test procedures and test matrices.

2.0 REFERENCES

2.1 VEPCO Nuclear Power Station Quality Assurance Manual 2.2 Stone & Webster Logic Diagrams and System Descriptions 2.3 VEPCO Calibration Procedures 2.4 Final Design Change Packages for each modification 3.0 DEFINITIONS 3.1 Phases of the Integrated Startup Test Program The Integrated Startup Test program is divided into two phases:

Preoperational Tests and Startup Tests.

The objectives and responsibilities of each phase are defined below.

The Preoperational Tests are under the direction of the Startup Group and are designed to assure proper functioning of new, modified and existing equipment, subsystems and systems.

The Startup Tests are under the direction of Station Operations and are designed to assure the proper integrated operation of all required systems prior to the next sequence of power operation.

3.2

  • General Electrical, Instrument and Mechanical Test Procedures These procedures are referred to as TEP's TIP's and TMP's.

These generic procedures are approved by the Station Nuclear Safety and Operating Committee and are used to verify proper installation and initial operability of equipment.

These procedures are used during Preoperational Test phase.

3.3. Cleaning And Flushing 3.3.1 3.3.2 Cleaning Procedures Cleaning will be performed in accordance with issued guides and general procedures to ensure satisfactory cleanliness of systems and components.

Cleaning will include mechanical cleaning and hand cleaning, The Station.Nuclear Safety and Operating Committee shall designate cleanliness grades for individual systems via approved design change packages.

Flushing Procedures A written procedure to ensure strict compliance with cleanliness requirements for nuclear steam supply and safety related systems.

Station Nuclear Safety and Operating Committee approval is required for generic flushing procedures and design change controlling procedures.

3.4 Electrical Checks Checks performed as part of design change package to ensure that an instrument or electrical control loop is complete and correctly connected.

These checks shall include, but not be limited to, breaker tests, insulation tests, and motor control center tests to ensure the integrity of the control circuit or equipment.

3.5 Mechanical Checks A set of checks performed for the purpose of verifying that a piece of mechanical equipment (pump, compressor, blower, etc.)

is ready for initial startup.

These checks shall include, but not be limited to, alignment, coupling, manufacturers' recommended lubrication, packing gland adjustment, etc., as applicable for the equipment being readied for startup.

3.6 Hydrostatic Test Pressure testing to meet the applicable erection code and to ensure system integrity.

The Station Nuclear Safety and Operating Committee approval is required for these generic procedures.

e e 3.7 Calibration 3.8 3.9 Quantitative adjustments of instruments and control devices, including characterization of analog signals, quantitative setting on all control and monitoring loop elements and verification of response characteristics.

It also applies to those calibration checks which verify quantitative accuracy and functional integrity of the devices or instrument loop previously calibrated by others, or to verify functional integrity of the devices or instruments which are not adjustable by normal means, such as thermocouples, conductivity cells, thermo-meters, etc.

Calibrated Loop Check A set of tests performed for the purpose of verifying that an in-strument loop is acceptable in terms of quantitative agreements proper inter-relationship, and expected responsiveness of several loop elements.

This set of tests is performed with all loop com-ponents in place, individually calibrated and documented, and devices energized by applying simulated inputs and measuring or observing loop performance.

Functional Loop Check A set of tests performed for the purpose of verifying that a control and/or telemetering loop is acceptable in terms of functional integrity and interrelationship of the several loop elements.

This set of tests is performed with all loop components in place, structurally complete, and energized, by applying simulated inputs and observing loop performance.

Loop elements need not be individually calibrated.

3.10 VEPCO Electrical Check-Out VEPCO electricians, for 480 V circuit breakers, will perform contact inspection, dashpot and mechanism inspection, set trip values with multi-amp tester, and megger insulation.

For 4160V, they will perform contact and mechanism inspection and check trip and close times with analyzer.

Additionally, dielectric checks will be made on 4160V cables, doble tests and ratio 4160/480V trans-formers and doble test 4160V circuit breakers.

3.11 Preoperational Check-Out Test of an individual item of equipment, subsystem or minor system to verify readiness for operations.

3.12 Operating Procedure(OP)

A station procedure developed by VEPCO and approved by the Station Nuclear Safety and Operating Committee for normal opera-tion of equipment and systems.

e 3.13 Periodic Test Procedure (PT)

A station procedure developed by Vepco and approved by the Station Nuclear Safety and Operating Committee to meet Tech.

Spec. or surveillance requirements for operability.

3.14 Special Test Procedure (ST)

A station procedure developed by Vepco and approved by the Station Nuclear Safety and Operating Committee to obtain data, associated equipment performance, or other technical data required for engineering or operational evaluation.

3.15 Functional System Operability Procedure (FSOP)

A procedure developed by the Startup Group to verify and docu-ment the functional operation of equipment and/or controls.

It will verify and document the functional operation of critical controls.

FSOP's are generally written to utilize existing logic diagrams.

3.16 Electrical, Instrument and Mechanical Maintenance Procedures And Maintenance Operability Procedure

.These generic station procedures are referred to as EMP's, IMP's, MMP's and MOP's.

These procedures are used by station personnel to checkout previously installed equipment that has undergone maintenance and to remove and replace safety related equipment in service.

3.17 Test Matrix A matrix that indicates which TEP, TIP, TMP, and/or existing station procedure (OP, PT, ST, IMP, EMP, MMP or MOP) will be performed on an individual test loop, instrument, valve, device or component.

The test matrix may also list tests required by Design Changes, Engineering Task Assignments (ETA), and Functio-nal System Operability Procedures (FSOP).

4.0 PARTICIPATING ORGANIZATIONS AND RESPONSIBILITIES 4.1 Station Nuclear Safety and Operating Committee 4.2 Consisting of representatives from Surry Power Station as desig-nated in the Vepco Nuclear Power Station Q.A. Manual.

The Station Nuclear Safety and Operating Committee reviews and approves all test procedures.

The committee reviews a summary of test results and approves release to the next phase of Startup Testing.

VEPCO Operating Staff Consists of VEPCO employees engaged in the operation and main-tenance of systems, subsystems, or portions of the station under the supervision of the station manager.

.' VEPCO Operating Staff will perform necessary and timely

inspections and perform evaluations as necessary to effect a smooth release of systems for Preoperational testing.

VEPCO Operating Staff will conduct Preoperational and Startup testing and is responsible for the operation of the plant and the permanent~y installed plant process equipment connected to an energized power source.

4.3 Westinghouse Electric Corporation (W) 4.4 4.5 4.6 4.7 4.8 The term Westinghouse or W shall be limited to equipment and services furnished as part of or under the contract for the-nuclear steam supply and turbine generator systems.

NUS Corporation (NUS)

The term NUS shall be limited to equipment and services furnished as a part of or under the contract between Vepco and NUS Corpora-tion.

NUS shall furnish engineering services where required by Vepco.

)

Stone & Webster Engineering Corporation - Engineering Department (S&W-BOSTON)

S & W shall furnish engineering services where required by VEPCO.

Daniel Construction Company (Daniel)

Daniel shall furnish construction services as required by Vepco.

Vepco Project Engineers This group of engineers is responsible to resolve component and system deficiencies discovered during the construction and the Preoperational Test phase.

Quality Control Consists of Quality Control related functions as defined in approved design change packages and test procedures.

4.8.1 Vepco MPP Q.C.

This group is responsible for quality control for all con-struction work as defined in the Vepco Multiple Power Projects Surry Quality Assurance Program.

4.8.2 Vepco Station Q.C.

This group is responsible for quality control during the Preoperational Test phase and Startup Test phase.

The level and extent of Q.C. coverage is defined in the individual procedure.

4.9

  • Startup Group The Startup Group is responsible for the development and implemen-tation of the Integrated Startup Test program. It consists of S & W Advisory Engineers under the direction of the S & W Lead Advisory Engineer and designated VEPCO operators under the direction of the designated VEPCO Shift Supervisor each responsible to the Station Superintendent of Operations.

The S & W Lead Advisory Engineer is responsible for the implemen-tation of the Integrated Startup Test program described herein and as outlined in station directives and applicable regulatory guides.

In conjunction with the VEPCO Shift Supervisor, he will provide the technical direction and expertise to ensure the timely completion of the required testing.

He will also be responsible for the*

development and management of the necessary documentation to support the Integrated Startup Test program.

The designated VEPCO Shift Supervisor is responsible for the execution of the Integrated Startup Test program.

He will provide coordination with the operation staff for*the safe operation and the interfacing of existing plant systems to support the Integrated Startup Test program.

In conjunction with the Lead Advisory Engineer, he will direct the assigned personnel and provide operational guidance to ensure the timely completion of the required testing.

The Startup Group is responsible for conducting the test and checks under their jurisdiction.

The group will ensure that all required test procedures and test matrices are developed and are available for use.

The Startup Group is responsible for assuring all tests in the Integrated Startup Test program are performed in accordance with approved test procedures and for reviewing and approving all test data through the Preoperational Test Phase.

The group is responsible that all design change test procedures and test matrices are written and approved to support Preoperational and Startup testing.

4.10 VEPCO Construction Staff The construction program functions under the direction of the Resident Engineer construction.

The Resident Engineer con-struction will be responsible for all rework associated with the Steam Generator Replacement Project (SGRP) and other design change modifications.

4.11 Superintendent of Operations The overall responsibility for the direction and management of the Integrated Startup Test program is under the control of the Station Superintendent of Operations.

  • e 4.12 Superintendent Projects (Startup Co-ordinator)

The Superintendent Projects reports td the Station Manager.

One of his responsibilities is Startup Co-ordinator for the Unit 1 outage.

In performance of this duty, he will report directly to the Superintendent of Operations.

He will have responsibility for insuring timely completion of technical reviews and tracting of release documentation for systems.

4.13 Superintendent of Technical Services The Superintendent of Technical Services will provide the required engineering review and analysis of the Integrated Startup Test Program.

He will be responsible for the development, safety analysis, engineering review and analysis of the selected Preopera-tional tests and the major Startup tests.

5. 0 CONSTRUCITOO PHASE The construction phase for new and modified systems is the responsibility of the Resident Engineer Construction.

All activities of the construction phase shall be performed in accordance with specifications and design change packages and other approved procedures, as applicable.

As the construction phase of the Design Change Package is completed, the responsible system construction engineer will walkdown the release and insure that all work has been completed and the system is ready for initial operation and preoperational testing.

Any items that are found to be incomplete shall be documented on a deficiency list.

Those deficiencies that limit preoperational testing will be resolved prior to system release.

The system is presented to the Startup Group for preoperational testing via a System Release form (Attachment 8.1) and a Deficiency Punch List (Attachment 8.2).

The Startup Group either "accepts" or "rejects" the system release based on the deficiency list. A rejected system release is returned to the Resident Engineer Construction for completion of preoperational testing limiting deficiencies.

6.0 PRIDPEPATIONAL '1EST PHASE 6.1 General When a system or subsystem is sufficiently complete and other re-lated systems have progressed far enough so it can perform its assigned function, the Startup Group, accepts the released system for preoperational testing.

Prior to signing the system release form (Attachment 8.1), the Startup Group will make a thorough review of all the attached documents and a member of the Startup Group will walkdown the system to insure that there is no outstanding item that will affect safe operation of equipment or system.

If any items are found to be unsatisfactory the required acceptance signatures will then be withheld by the Startup Group until these items are resolved.

The Preoperational Test Phase for modified, new and existing systems is the responsibility of the Startup Group and will be accomplished by Vepco operations staff supplemented by construc-tion craft.personnel.

As the system releases for new and modified systems are accepted by the Startup Group, the required preoperational testing will begin.

During this phase, field changes will be generated to resolve problems discovered during testing and operations.

System release forms (Attachment 8.1) or System Walkdown release forms (Attachment 8.3) will be generated by the Startup Group for all remaining systems affected by construction or maintenance work.

The existing systems not associated with design changes can be classified as follows:

remained in service, affected by maintenance, or in area of design change construction.(See Attachment 8.4)

The extent and level of testing assigned by the Startup Group to testing of these systems will be based on this classification.

Vepco I & C will calibrate instruments and controls as the precalibration tests are completed by the Startup Group.

Preoperational testing includes all designated tests procedures (TIP, TEP, and TMP) along with applicable station procedures (ST, PT, OP, MOP, EMP, IMP, MMP) and Design Change testing.

(See Attachment 8.5).

The tests associated with this phase include: dynamic MOV check-out, uncoupled and coupled motor runs, uncoupled and coupled vibration tests, I & C functional checkout, AOV/AOD setup and checkout, I & C hydrostatic test, AOV/AOD dynamic checkout, air balancing, pump curve verification, flushing and FSOP'S.

6.2. Responsibilities 6.2.1 Construction Group Responsible as noted on the Deficiency Punch List (Attachment 8.2) for correction of construction deficiencies.

6.2.2 Startup Group The Startup Group is responsible for:

ensuring the timely Preoperational testing of systems and components, documen-tation of discrepancies determined during testing; maintain-ing a status of all outstanding deficiencies for existing systems that did not require modification, providing technical direction in the preparation of systems and components to support planned Preoperational tests, assuring that all Electrical, Mechanical and Instrument tests are performed in accordance with established test procedures, (TEP, TIP and TMP's), reviewing and approving of all test data, writing additional detailed procedures as needed for

6.3

  • e implementation of general procedures and obtaining resolutions for all deficiencies, The group will also be responsible for initial I & C and electrical setup of new equipment.

The Startup Group shall be responsible for determining if a system has reached a point where it ca~ be presented to *the Station for approval for unrestricted operation.

6. 2. 3 Vepco Station Qual*ity Control This group shall perform required inspections and audits to assure that the Preoperational Test phase is conducted in accordance with the approved procedures.

Vepco Station Q.C. shall ensure the requirements for system documentation of the Station Nuclear Safety and Operating Committee are met.

6.2.4 Vepco I & C and Electrical These groups shall perform calibration and maintenance on equipment per system test matrices.

All TIP and TEP data sheets will be completed and returned to the Startup Group.

Release For Startup Testing Upon successful completion of all Preoperational tests, the Startup Group will review all system documentation and test data as required to verify the functional operability of the system.

The Startup Group system engineer will walkdown the equipment to ensure the system is ready for unrestricted operations by the station.

Any items found to be incomplete but not limiting for unres-tricted operation will be documented on the Deficiency Punch List (Attachment 8.2).

The Startup Group will then sign the System Release form (Attachment 8,1).

The System Release and the required documentation will then be turned over to the Superintendent of Operations for review and acceptance.

Prior to the Superintendent of Operations final review of the system, the Station Quality Control Department will review the documentation to insure that all documents are complete.

Any deficient items will be turned back to the Startup Group for resolution.

Upon completion of an acceptable audit, the Station Quality Control Department will sign the required sig-nature block on the release.

The Station Superintendent of Operations will then review the deficiency list to approve the items to be carried on the Master Deficiency List.

Any items that are not acceptable will be :returned to the Startup Group for resolution.

When all deficient items are acceptable to the Station Superintendent of Operations, he will then sign the Transmittal accepting the Release for the Station allowing Unrestricted Operations of the system.

7.0 e

STARTUP TEST PHASE 7.1 General When a system has completed Preoperational testing and is accepted by the station for unrestricted operations it is ready for Startup testing.

Prior to initiation of the Startup Test phase the Station Nuclear Safety and Operating Committee will review the systems that are available for unrestricted operation to ensure safe operation and testing conditions.

The first event is fuel loading.

The sequence for subsequent Startup testing is determined by the Startup Matrix and initial conditions and prerequisites of the station startup procedures.

The Startup Matrix is designed to control the testing evolution from fuel load to full power operations. It is structured on a plateau basis.

All items identified on a lower plateau must be completed prior to advancing to the next plateau.

This sequencing may only be deviated from with prior approval of the Superintendent of Operations or his designee.

The Station Nuclear Safety and Operating Committee will review all deviations in accordance with the Nuclear Power Station Quality Assurance Manual.

The specific plateaus chosen are as follows:

Phase I - Fuel load Phase II - prior to going above 140 OF (Refueling Shutdown)

Phase III - prior to going above 200 OF (Cold Shutdown)

Phase IV - prior to Containment Integrity Phase V - prior to going above 350 OF/450 psig Phase VI - prior to Criticality Phase VII - prior to going above 10% Power Phase VIII - prior to extended 100% power operation The detailed tests within the phases will be available at the Surry Power Station for review.

The Startup Matrix is a working document and may be revised as necessary to incorporate additional test requirements or reduce unnecessary requirements that may arise through the balance of the startup effort.

The Station Nuclear Safety and Operating Committee will review the status of systems and test results at major milestones throughout the Startup Test phase.

At no time will the safety of the plant be totally dependent on the performance of untested structures, systems or components.

The comprehensive Startup Testing phase is to ensure that equipment and systems perform in accordance with design criteria.

This phase*

includes test, adjustments, calibrations, and system operations necessary to ensure that criticality and subsequent power operation can be safely undertaken.

These procedures will be normal station startup procedures, PTts, OP's supplemented as required by Special Tests and Design Change tes*ting.

7.2

-11~

e Preoperational tests are performed to verify as near as possible, the performance of the system under actual operating conditions.

Where required, simulated signals or inputs are used to verify the full operating range of the system and to calibrate and align the systems and instruments at these conditions.

During Startup testing, systems and instruments that are used for normal operations are verified and calibrated under actual operating conditions.

Systems that are not used during normal plant operation, but must be in a state of readiness to perform safety functions, are checked under test conditions prior to unit startup.

Responsibilities 7.2.1 VEPCO Operating Staff Virginia Electric and Power Company has the overall responsibility for development~ supervision, performance, and documentation of all Startup Testing at the Surry Power Station.

Test preparation and all test performance during Startup Testing are under control of VEPOO to ensure proper and effective emphasis is maintained on personnel and plant safety by all individuals participating in the testing p~ogram.

The Superintendent of Technical Services will be responsible for providing the safety analysis for all major tests and will provide engineering review and coverage to ensure the conduct of the major tests satis-fies the necessary design and safety criteria.

7.2.2 Startup Release Points The following milestones in the Startup Test phase of the Integrated Startup Test Program Schedule require Station Nuclear Safety and Operating Committee review and approval prior to implementation:

a.

Fuel Loading

b.

Hot Functional Testing

c.

Criticality and Lower Power Physics Testing

d.

Power Range Testing

e.

Extended Full Power Operation The Startup Group and Station Operations department will be responsible to present evidence that all required testing is successfully complete and proper documentation available.

8.0 ATTACHMENTS 8.1 System Release for Preoperational Testing and Unrestricted Operation.

8.2 Deficiency Punch List 8.3 System Walkdown Release for Unrestricted Operation

  • 8.4 Unit #1 System Index 8.5 Preoperational Test Index

TTACHMENT 8.1 SUR.RY POWER STATION UNlT NO, 1 SYSTEM RELEASE FOR PREOPERATIONAL TESTING AND UNRESTRICTED OPERATIONS SYSTEM NO.

DESCRIPTION OF EQUIPMENT:

THE ATTACHMENTS WITH THIS RELEASE ARE INTENDED TO INDICATE THE BOUNDARIES OF THIS RELEASE.

FUTURE CHANGES THAT MAY BE MADE TO THIS SYSTEM ARE INTENDED TO BE CON-SIDERED A PART OF THIS RELEASE IF WITHIN THESE ESTABLISHED BOUNDARIES..

ATTACHMENTS DEFINING BOUNDARIES:

RELEASED FOR PREOPERATIONAL TESTING I

Daniel's Proj. Mgr/Asst. Proj. Mgr.

Date Vepco Resident Engineer Date Vepco Q.C.

(MPP)

Date Construction Deficiency List Attached ACCEPTED FOR PREOPERATIONAL TESTING I

Vepco Operations Superintendent Date Lead Advisory Engineer Date RELEASED FOR UNRESTRICTED OPERATIONS I

Vepco Operations Superintendent Date Lead Advisory Engineer Date Vepco Q.C.

(Station)

Date The Following Items Are Attached:

Test Matrix Completed Pre-Op Tests Vepco Deficiency Punch List ACCEPTED FOR UNRESTRICTED OPERATIONS I

Vepco Operations Superintendent Date

DEFICIENCY NO.

- DESCRIPTION VEPCO DEFICIENCY PUNCH LIST

~TTACHMENT 8.2 SYSTEM NO*--~----~--

DATE '------------

PAGE ________ OF _______ _

DATE RESPONSIBILITY RESOLVED

ATTACHMENT 8 3.

SURRY roWER STATION UNIT 1 SYSTEM WALKDOWN RELEASE FOR UNRESTRICTED OPERATIONS SYSTEM NO.

DESCRIPTION OF EQUIPMENT:

ATTACHMENTS DEFINING BOUNDARIES:

SYSTEM WALKDOWN I

I Walkdown Performed By Date Vepco Deficiency Punch List Attached RELEASED FOR UNRESTRICTED OPERATIONS I

Vepco Operations Superintendent Date Lead Advisory Engineer Date Vepco Q.C.

(Station)

Date ACCEPTED FOR UNRESTRICTED OPERATIONS I

Vepco Operations Superintendent Date

System.No.

1-2-2-1 1-2-2-2 1-2-2-3 1-2-3-1 1-2-4-1 1-2-5-1 1-3-1-1 1-3-2-1 1-3-3-1 1-3-3-2 1-3-3-3 1-4-1-1 1-4-1-2 1-4-1-3 1-4-2-1 1-4-2-2

  • 1-4-3-1 1-4-3-2 1-4-3-3 1-4-3-:4 1-4-3-5 1-4-3-6 1-4-3-7 1-4-3-8 1-4-3-9 1-4-3-10 1-4-3-11 1-4-3-12 1-5-1-1 1-6-1-1 1-6-2-1 1-6-3-1 1-6-4-1 1-7-1-1 1-7-2-1 1-7-3-1 1-7-4-1 1-7-5-1 1-7-6-1 1-7-6-2 1-7-6-3 1-9-1-1 1-9-2-1 STATUS KEY UNIT fll SYSTEM INDEX

System Description

Circulation Water Waterbox Vacuum Priming

    • ATTACHMENT 8.4 ra~e ~ c;d; I Circulation & Service Water Radiation Monitors Discharge Vacuum Priming Screen Wash Pumps & Traveling Screens Condenser Tube Cleaning Main Steam Extraction Steam Auxiliary Steam Auxiliary Boiler Fuel Oil Condensate Storage Tank Main Condenser Condensate Low Pressure Heater Drains Secondary Miscellaneous Drains Condensate Polisher Ultrasonic Resin Cleaner Condensate Polisher Waste Neutralization Condensate Polisher Regeneration

.Condensate Polisher Bypass Condensate Polisher Vessel "A" Condensate Polisher Vessel "B" Condensate Polisher Vessel "C" Condensate Polisher Vessel "D" Condensate Polisher Vessel "E" Condensate Polisher Vessel "F" Condensate Polisher Vessel "G" Condensate Polisher Panel Condenser Air Removal Feedwater High Pressure Heater Drains Steam Generator Blowdown Auxiliary Feedwater Radiation Monitors CR!r-MG Sets, Full & Part-Length Control Rods Nuclear Instrumentation Incore Instrumentation Rod Position Indication Solid State Protection Safeguards Test Cabinets Auxiliary Relay Cab.inets Component Cooling Chilled Component Cooling Status 1

2 4

4 3

2 1

2 4

3 4

4 1

1 2

2 1

1 1

1 1

1 1

1 1

1 1

1 1

3 3

1 1

1 3

4 4

4

'4 4

4 2

1 (1) AFFECTED BY DESIGN CHANGE (2) IN AREA OF DESIGN CHANGE CONSTRUCTION (3) AFFECTED BY MAINTENANCE (4) REMAINED IN SERVICE

System No.

1-9-3-1 1-9-4-1 1-9-5-1 9..:.5-2 1-9-5-3 1-9-6-1 1-12-1-1 1-12-2-1 1-12-3-1 1-13-1-1 1-13-1-2 1-13-2-2 1-13-2-3 1-13-2-4 1-13-2-5 1-13-7-2 1-14-1-1 1-14-1-2 1-15-1-1 1-15-1-2 1-15-2-1 1-15-3-1 1-15-4-1 1-16-1-1 1-16-2-1 1-16-3-1 1-16-4-1 1-16-5-1 1-16-6-1 1-16-7-1 1-16-8-1 1-21-1-1 1-21-2-1 1-22-1-1

.1-22-2-1 1-22-3-1 1-22-4-1 1-22-5-1 1-22-6-1 1-22-7-1 1-22-8-1 1-22-8-2

'1-22-9-1 1-22-10-1 1-22-11-1 1-22-12-1 1-22-13-1 1-23-5-1 1-23-5-2 1-23-5-3 1-24-1-1 STATUS KEY (1)

(3)

System Description

ATTACHMENT 8.4 Page 2 of 3 Status Chilled Water 1

Neutron Shield Tank Cooling 4

Service Water 1

Service Water to Recirculation Spray Hx 4

Service Water to Charging Pump Coolers 1

Bearing Cooling 4

Instrument Air 4

Service Air 4

Containment Instrument Air 1

Chemical Feed 1

Condensate Polisher Chemical Feed 1

Unit 1 Caustic Supply 1

Unit 1 Acid Supply 1

Unit l Dilution Water Heater 1

Unit 1 Flash Evaporator & Demin.

1 Blowdown Treatment 1

Nitrogen Supply 4

Hydrogen Supply 4

Fire Protection - Hose Reel Stations 1

Fire Protection - Sprinkler & Deluge 1

Fire Protection -

CO2 System 1

Fire Protection - Smoke Detectors 1

Fire Protection - Miscellaneous 1

Turbine Generator - Gland Steam 3

Turbine Generator - Lube Oil 3

Turbine Generator - Seal Oil 3

Turbine Generator -

EHC Fluid & Controls 3

Turbine Generator - Supervisory Main Turbine Main Generator & Controls Generator H2 & co2 Secondary Plant Sampling Primary Plant Sampling Instrumentation 3 3

3 3

4 1

Main and Station Service Transformers Normal 4160V & 480V Busses Emergency 4160V & 480V Busses Emergency Diesels Station Batteries & 120VDC Distribution Vital Busses & 120VAC Distribution Station Lighting Heat Tracing (Safety Related)

Heat Tracing (Non-Safety Related)

Main Computer Main Annunciator Main Control Board Secondary Plant Process Racks Primary Plant Process Racks Safeguards & Valve Pit Sumps Containment Sumps Turbine Building Sumps CRD Cooling Fans 4

4 1

1 4

4 1

1 4

4 4

4 4

4 4

1 4

2 AFFECTED BY DESIGN CHANGE (2) ~N AREA OF DESIGN CHANGE CONSTRUCTION AFFECTED BY MAINTENANCE (4) REMAINED IN SERVICE

f '

System No.

1-24-1-2 1-24-1-3 1-24-1-4 1-24-2-1

  • 1-24-3-1 1-24-4-1 1-24-5-1 1-24-6-1 i.-25-1-1 1-26-1-1 1-26-2-1 1-27-1-1 1-27-1-2 1-27-2-1 1-27-3-1 1-27-4-1 1-27-4-2 1-27-4-3 1-27-6-1 1-27-6-2 1-27-6-3 1-31-1-1 1-31-2-1 1-33-1-1 1-34-1-1 1-34-1-2 1-35-1-1 1-35-1-2 1-37-1-1 1-38-1-1 STATUS KEY:

ATTACHMENT 8.4 Page J of d

System Description

Status Containment Air Recirculation Fans 1

Containment Iodine Fans 2

Safeguards Supply & Exhaust Fans 1

Auxiliary Building Ventilation 1

Turbine Building Supply & Exhaust 4

Con~rol Room & Relay Room Ventilation 4

Turbine Building Heating Steam 4

Containment Purge Ventilation 1

Reactor Coolant 1

Charging, Letdown, and High Head SI 1

Boric Acid Transfer & Blender 4

Low Head Safety Injection 1

Safety Injection Accumulators 2

Residual Heat Removal 2

Containment Vacuum 2

Refueling Water Storage Tank & Recirculation Pumps 1

Chemical Addition Tank 1

Containment Spray 1

Outside Recirculation Spray 1

Inside Recirculation Spray 1

Post DBA H2 Recombiner 1

Primary Drains 1

Process Vents 2

Containment Leakage Monitor 1

Refueling Purification 4

Reactor Cavity 1

Containment Elevator 2

Containment Cranes 1

Fuel Transfer System 1

Steam Generator Recirculation & Transfer 1

(1) AFFECTED BY DESIGN CHANGE (2) IN AREA OF DESIGN CHANGE CONSTRUCTION (3) AFFECTED BY MAINTENANCE (4) REMAINED IN SERVICE

(,.

ATTACJU1ENT 8. 5 PREOPERATIONAL TEST INDEX TEP-1 INSULATION RESISTANCE MEASUREMENTS - ELECTRICAL EQUIPMENT TEP-2 CONTROL CIRCUITRY CHECKOUT TEP-3 LOW-VOLTAGE SWITCHGEAR TEP-4 STATIC OPERATION OF MOTOR OPERATED VALVES TEP-40 DYNAMIC OPERATION OF MOTOR OPERATED VALVES TEP-5 480 MCC BREAKERS AND 480 SWITCHGEAR BREAKERS TEP-7 AC ELECTRIC MOTOR UNCOUPLED MOTOR OPERATION

. TEP-8 DC MOTORS AND CONTROLLERS MOTOR OPERATION TEP-9 STATION COMPUTER-TEP-10 ANNUNCIATOR/GRAPHIC DISPLAY AND SEQUENCE OF EVENTS SYSTEM TEP-11 MACHINERY VIBRATION ANALYSIS TEP-12 ELECTRIC HEAT TRACING

.TIP-1 INSTRUMENTS AND CONTROLS CIRCUIT INSTALLATION CHECKOUT TIP-2 INSTRUMENTS AND CONTROLS MECHANICAL INSTALLATION CHECKOUT TIP-3 INSTRUMENT AND CONTROLS FUNCTIONAL LOOP CHECKOUT TIP-4 CHECKOUT PROCEDURE FOR AIR-OPERATED VALVES AND DAMPERS TIP-40 DYNAMIC OPERATION OF AIR OPERATED VALVES AND DAMPERS TIP-5 INSTRUMENT LEAK TEST TMP-1 SPECIAL MAINTENANCE PROCEDURE FOR INSPECTION OF STUDS ON CONTAINMENT LINER TMP-2 VENTILATION AIR BALANCING TMP-3 CENTRIFUGAL PUMP HEAD CURVE VERIFICATION TMP-4 RELIEF & SAFETY VALVE SETPOINT VERIFICATION TMP-5 LEAKAGE TESTING OF DUCTWORK TMP-6 WATER CLEANING OF PIPING TMP-7 SYSTEM HYDROSTATIC/PNEUMATIC TESTING