ML18093A721

From kanterella
Jump to navigation Jump to search
Insp Rept 50-272/87-38 on 871221-23.No Violations or Deviations Noted.One Unresolved Item Noted.Major Areas Inspected:Containment Integrated Leak Rate Testing & Preliminary Results Evaluation & Test Prerequisites
ML18093A721
Person / Time
Site: Salem PSEG icon.png
Issue date: 02/26/1988
From: Eapen P, Murphy K
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML18093A720 List:
References
50-272-87-38, NUDOCS 8803170232
Download: ML18093A721 (9)


See also: IR 05000272/1987038

Text

U.S. NUCLEAR REGULATORY COMMISSION

REGION I

Report No.

50-272/87-38

Docket No.

50-272

License No.

DPR-70

Licensee:

Public Service Electric and Gas Company

P. 0. Box 236

Hancocks Bridge, New Jersey 08038

Facility Name:

Salem Generating Station Unit 1

Inspection At:

Hancocks Bridge, New Jersey

Inspection Conducted:

December 21-23, 1987

Inspectors:

K.

DRS

Approved by:

Q K - f:.~

P. K. Eapen, Ch~EB, DRS

~Id.bl~

'dite I

Inspection Summary:

Routine unannounced inspection of Containment Integrated

Leak Rate Testing (CILRT) and Preliminary Results Evaluation (Report

No. 50-272/87-38).

The inspection verified that the test prerequisites and

test conduct were in accordance with approved procedures.

The test results

indicated an acceptably low containment leak rate.

The test went smoothly

as a result of thorough preparation and use of experienced supervision and

technicians.

QA coverage was thorough.

One unresolved item requires licensee

attention.

During the test the three operating Containment Fan Cooling Units

(CFCUs) tripped ostensively due to motor overcurrent caused .bY increased fan

loading at high containment pressure.

The licensee is verifying the root

cause of these failures and is reviewing fan operation and testing to assure

high confidence that these units are available during a design basis LOCA and

that future fan tripping during CILRTs does not occur.

Results:

No violations or deviations were identified.

One unresolved item .

8803170232 880229

PDR

ADOCK 05000272

G

PDR

DETAILS

1.0 Persons Contacted

  • William Treston, CILRT, Test Director
  • George Druffner, PSE&G, R&T Lab

Robert Brandt, Chief, Inservice Testing

Steven Miltenberger, Vice President, Nuclear Operations

Mark Gross, QA

Michael Wita, QA

Jack Curham, Engineering (C.F.C. System Engineer)

United States Nuclear Regulatory Commission

Thomas Kenny, Senior Resident Inspector

Kathy Gibson, Resident Inspector

  • Indicates those present at the exit meeting on December 23, 1987.

The inspector also held discussions with technicians and engineers

involved in the containment leak test.

2.0 Containment Integrated Leak Rate Testing

During the period of December 20-23, 1987, a Containment Integrated Leak

Rate Test (CILRT) was performed at Salem 1, as required by 10 CFR 50,

Appendix J.

The test was conducted with containment isolation boundaries

in an

11As-Left

11 condition.

Testing was performed in accordance with

Inservice Inspection Procedure M9-ILP-CT-1, Revision 6, Issue Date 12/18/87.

The Inspector reviewed the test procedure and witnessed portions of the

test.

The purpose of the inspection was to assure that the test was con-

ducted in compliance with the requirements and commitments set forth in

the following section, that test anomalies are identified and acted upon,

and that the test results met the leak rate acceptance criteria.

2.1

Reference Documents

Salem 1 Technical Specifications 4.6.1.2(a), (b) and (c), Type

11A

11 Test

10 CFR 50, Appendix J, Primary Reactor Containment Leakage

Testing for Water Coolent Power Reactors.

Final Safety Analysis Report (FSAR)

ANSI/ANS 56.8-1981, Containment System Leakage Testing

Requirements

3

USNRC I&E Information Notice No. 85-71:

Containment Integrated

Leak. Rate Tests.

2.2 Other Documents Reviewed

M9-ILP-CT-1, Revision 6, Reactor Containment Building Integrated

Leak.age Rate Test Salem Unit 1.

Station QA Surveillance Reports Nos. 87-1785, 87-1786, and 87-1788.

Internal Memorandum for J. Curham to W. Treston,

11 Containment

Fan Coil Unit Operation During Type

11A

11 Testing,

11 dated

December 10, 1987.

Portion of

11 Reactor Containmnet Fan Cooler, Westinghouse

Technical Manual Unit 1 and 2, Salem Nuclear Generating

Station,

11 PSBP No. 139970.

Safety Evaluation Report S-2-M945-NSE-Revision 0,

11Tripping of

Fan Coil Unit (FCU) Motors Durin.g Type

11N 1 Test and Inlet Vain

Damper Settings.

For Fan Coil Unit, Unit No. 2 Salem Nuclear

Generating Station,

11 July 1, 1983.

Nuclear Department memorandum from J. Vargas to H. Berrick,

11 CFCU Fan Peformance/Type A Testing, SRG OPEN Item R-0104,

11

June 26, 1984.

2.3 Administrative Control of CILRT and Procedure Review

The inspector reviewed the test procedure, the CILRT test log and

the PSE&G Research Corp event log to verify that:

Test directors were designated and their responsibilities were

clearly defined.

The procedures were adequately detailed to assure satisfactory

performance.

Test prerequisites were met.

All required parameters were being recorded at the required

frequencies.

The inspector noted that adequate attention was paid to the procedure

as evidenced by keeping the step-by-step sign-offs current.

Test

personnel were being carefully briefed prior to each test evolution.

Plant personnel not directly involved with the test were briefed on

keeping

11 hands-off 11 in the areas affected by the test; this was re-

inforced by restricting personnel from the test areas.

Control of

the test by the test director was adequa~e .

4

The inspector noted several weaknesses in the test procedure itself

as follows*:

a.

Section 5.13 of the test procedure states that if leakage

occurs

11 to the extent that it would interfere with the

_

satisfactory completion of the tests, then leakage paths may be

isolated and the Type A test continued.

11

This statement is in

direct opposition to 10 CFR 50, Appendix J, III.A.l(a). This

disagreement was brought to this attentton of the test director.

b.

Section 6.3 and Attachment 3, step 5.1.C concerning the throttling

of Containment Fan Cooling Units (CFCU) and CFCU data recording

appears to be insufficient as indicated in Section 2.6 of this

report.

2.4 Test Witnessing

The inspector witnessed portions of the following test activities:

1.

2.

3.

4 .

5.

6.

Containment pressurization and licensee walkthroughs for

identifying component leakage.

Four hour stabilization.

Twenty-four hour CILRT.

Metered release in preparation for verification test.

One hour instrument verification test.

Start of containment depressurization.

These activities were witnessed to verify that the CILRT was

conducted in accordance with the test procedure, that test personnel

demonstrated adequate levels of knowledge, that no equipment

anomalies were evident, and the test results were, in fact, within

the requirements of 10 CFR 50, Appendix J.

The inspector attended

briefings with test personnel, interviewed data collection engineers

and leak crew technicians, and made walkdowns with the test director

and other test personnel.

The inspector noted that test

personnel were experienced in conducting the test with senior test

personnel having conducted a number of similar tests in the past.

No adverse leakage paths were identified during the walkdowns and

the installation of the tygon tubing and vent bottles were as required.

The chronology of major events were as follows:

Chronology of Events

December 21, 1987

1400; noted fumes in control room from operation

of air compressors

5

1420; commenced containment pressurization

  • 1735; dispatched first leak inspection team

2300; Reached 40.68 PSIA at about 3 psi per hour

December 22, 1987

0030; dispatched leak inspection team

0355; #13 CFCU tripped [at about 57 psia, per

calculation by inspector]

0425; #15 CFCU tripped [at about 58 psia, per

calculation by inspector]

0530; dispatched leak inspection team

0550; began securing air compressors at 62.43

psi a

0619; all compressor secured

0630; began stabilization period

0702; #14 CFCU tripped, all fan coil units out

of service

6

0830; disp~tched leak inspection team, Ele. 100'

airlock appears to have small leak, suspect a l~ak

in inner -ball valve per past LLRT.

1030; stabilization complete

1045; start of CILRT

December 23, 1987

1045; completion of CILRT

1453; start of verification test

1553; completion of verification test

1711; start of depressurization

Startup of the nine portable diesel powered air compressors, that

were located between buildings next to-the turbine building, resulted

in exhaust gases being dra~n into the adjacent building including

the Salem 1 control room.

The licensee determined that this

condition was not hazardous to personnel and the condition subsided

as the compressors were loaded.

A minor_ leak into the vestibule of

the airlock at Elevation 100' was the only component leak detected

as a result of the walkdown by the leak crews.

The only abnormal

event during the pressurization phase was the tripping out of the

three operating Containment Fan Cooling Units (tFCUs) which is discussed

in the next section.

2.5 Tripping of Containment Fan Cooling Units (CFCUs)

Three CFCU's were in operation at the start of pressurization.

At

approximately 57 psia the #13 CFCU tripped followed by #15 CFCU at

approximately 58 psia.

The last unit, #14 CFCU, tripped about one

hour after containment pressure reached the test pressure of 63 psia.

7

The inspector held discussions with the CFCU system engineer to determine

if tripping of these uni ts ca 11 into question their availability

during design basis accidents and whether the CILRT prerequisites

concerning the fans where adequate.

Discussions with the engineer

and subsequent review of Westinghouse design documents and PSE&G

internal memoranda revealed that the licensee had experienced trip-

ping of these fans in past CILRT tests.

The licensee conducted

engineering analyses to determine an appropriate solution to the

problem.

These memos indicate that ihe fans become overloaded under

the test conditions and trip out due to motor overcurrent.

The

engineering documents reviewed did not provide a complete picture of

whether the fans design bases are fully satisfied. Specifically:

1.

The fact that #14 CFCU tripped after operating for one hour with

a constant containment pressure of 63 psia may indicate a cause

other than motor overcurrent.

This should be investigated.

The inspector was not provided with any firm evidence that

motor overcurrent is, in fact, the sole root cause of fan

tripping.

2.

A complete engineering analysis that accurately predicts fan

flow, motor current, component temperatures and the other para-

meters potentially affecting fan availability both during an

CIRLT and the various design basis requirements in Section 6.2.2.2

of the FSAR should be provided.

3.

The above engineering analyses should provide assurance that

fan surveillance testing at normal containment conditions is

adequate to ensure availability during design basis accidents.

4.

The tripping of the fans during the latest CILRT was apparently

caused by an error in adjusting the inlet vane settings.

What

actions will the licensee take to as-sure future errors in setting

the inlet vains do not occur; especially when restoring the fans

to their normal operating condition?

To this end it should be

noted that Westinghouse report PSBP #139970 suggests that motor

amp readings be taken.

Accurate amp readings could provide a

diverse means of verifying that fan load conditions are correct.

In addition, trending amp readings during a C.I LRT would verify

the air density versus load characteristic of the fan units.

5.

Determine whether fan surveillance and CILR test procedures

require modification in view of the answers to the above items.

Pending resolution of the above concerns, this item remains unresolved

(50-272/87-38-01).

2.6

8

CILRT Leak Rate Measurements and Results

The inspector monitored the data acquisition throughout the test and

reviewed the computer data reduction methods.

The calibration

records of the pressure, temperature, flow, and humidity instruments

had been calibrated within 6 months of the test and were traceable

to the National Bureau of Standards as required.

All instruments

were operable throughout the test with no apparent malfunctions.

The computer based data acquisition and reduction activites appeared

faultless with the system being thoroughly tested prior to test ini-

tiation.

The data collection personnel from the Licensee's Research

and Testing Laboratory were certified under the Laboratory's quality

assurance program for leak testing, Level I and Level II.

The

licensee computed the following leak rates at the conclusion of the

test:

24 HR CILRT

(Weight% per day)

Total Time Method

Mass Point M~thod

Calculated (Lam)

0.041

0.044

0.075

0.039

0.043

0:075

Lam + Upper Confidence Limit

Acceptance Criteria

The inspector made independent calculations using an NRC approved computer code

that showed close agreement with the licensee calculations.

3.0 QA/QC Coverage

The inspector interviewed the QC inspectors that provided coverage of the

CILRT and reviewed three QC reports documenting QC findings during the

test.

Instrument calibration, test personnel certification, and test

procedure implementation was covered along with checking 58% of the valve

positions.

The QC inspectors showed thorough knowledge of the purpose and

requirements of the test.

Well prepared QC check lists for the CILRT were

used in assure coverage of important test aspects.

Several valves were

found to be out of position by QC, the QC inspectors followed through to

find the reasons for these discrepancies and were satisfied that the test

director had given permission to Operations to change the valve position

and that there was no effect on the test.

The inspector concluded that

QC coverage was adequate.

4.0

- - - -

9

Exit Meeting

The findings of the inspector were periodically discussed with the test

director and were summarized at the exit meeting on December 23, 1987.

Attendees at this exit meeting are listed in Section 1.0 of this report.

At no time during this inspection was written material provided to this

licensee by the inspector.