Letter Sequence Acceptance Review |
---|
EPID:L-2018-LLA-0053, Fleet License Amendment Request to Relocate Technical Specification Unit/Facility/Plant Staff Qualification ANSI N18.1-1971 and ANSl/ANS-3.1-1978 Requirements to the Exelon Quality Assurance Topical Report (QATR) (Approved, Closed) |
|
MONTHYEARRS-17-161, Fleet License Amendment Request to Relocate Technical Specification Unit/Facility/Plant Staff Qualification ANSI N18.1-1971 and ANSl/ANS-3.1-1978 Requirements to the Exelon Quality Assurance Topical Report (QATR)2018-03-0101 March 2018 Fleet License Amendment Request to Relocate Technical Specification Unit/Facility/Plant Staff Qualification ANSI N18.1-1971 and ANSl/ANS-3.1-1978 Requirements to the Exelon Quality Assurance Topical Report (QATR) Project stage: Request ML18092B2102018-04-0202 April 2018 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of Fleet License Amendment Request to Relocate Staff Qualification Requirements to Quality Assurance Topical Report Project stage: Acceptance Review ML18206A2822018-08-0202 August 2018 Issuance of Amendments to Relocate the Staff Qualification Requirements Project stage: Approval ML18283A1382018-10-10010 October 2018 Supplement to License Amendment Request - Proposed Changes to Technical Specifications Sections 1.0, Definitions, and 6.0, Administrative Controls for Permanently Defueled Condition Project stage: Supplement TMI-18-100, Supplement 2 to License Amendment Request - Proposed Changes to Technical Specifications Sections 1.0, Definitions, and 6.0, Administrative Controls for Permanently Defueled Condition2018-10-29029 October 2018 Supplement 2 to License Amendment Request - Proposed Changes to Technical Specifications Sections 1.0, Definitions, and 6.0, Administrative Controls for Permanently Defueled Condition Project stage: Supplement 2018-03-01
[Table View] |
NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of Fleet License Amendment Request to Relocate Staff Qualification Requirements to Quality Assurance Topical ReportML18092B210 |
Person / Time |
---|
Site: |
Calvert Cliffs, Dresden, Peach Bottom, Nine Mile Point, Byron, Three Mile Island, Braidwood, Limerick, Ginna, Clinton, Quad Cities, FitzPatrick, LaSalle |
---|
Issue date: |
04/02/2018 |
---|
From: |
Blake Purnell Plant Licensing Branch III |
---|
To: |
Mascitelli F Exelon Generation Co |
---|
References |
---|
L-2018-LLA-0053, RS-17-161, TMI-17-106 |
Download: ML18092B210 (3) |
|
Similar Documents at Calvert Cliffs, Dresden, Peach Bottom, Nine Mile Point, Byron, Three Mile Island, Braidwood, Limerick, Ginna, Clinton, Quad Cities, FitzPatrick, LaSalle |
---|
Category:E-Mail
MONTHYEARML24312A1662024-11-0707 November 2024 Request for Additional Information (11/7/2024 E-mail) - LAR to Revise TSs to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3 ML24298A1382024-10-24024 October 2024 Final RAI for FitzPatrick JAFP-24-0047 (L-2024-LLA-0134) ML24298A0202024-10-24024 October 2024 NRR E-mail Capture - Braidwood Station, Units 1 and 2, Byron Station, Units 1 and 2, Relief Request I4R-19 and I4-26, Associated with the Fourth and Fifth Inservice Inspection Intervals ML24282A7042024-10-0808 October 2024 NRR E-mail Capture - Acceptance Reviews of Relief Requests Associated with the Fifth Inservice Inspection Interval at Byron and Braidwood Stations ML24271A0282024-09-26026 September 2024 E-Mail - Dresden Nuclear Power Station, Unit 1 - Site Visit Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations ML24254A2082024-09-10010 September 2024 NRR E-mail Capture - Quad Cities, Unit Nos. 1 and 2 - Alternative to RV-08, Rev 1, SRV Testing Interval - Acceptance of Requested Licensing Action Re Relief Request Associated with Safety Relief Valve Testing Interval ML24250A1062024-09-0606 September 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24234A2772024-08-21021 August 2024 NRR E-mail Capture - Final RAI - Constellation Energy, LLC - Fleet Request - Proposed Alternative Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds (L-2024-LLR-0031) ML24233A2472024-08-20020 August 2024 Acceptance of Requested Licensing Action Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations ML24240A1902024-08-12012 August 2024 E-mail (8/12/2024) from R. Reynolds (CEG) to R. Guzman (NRC) - Corrected TS Pages for LAR TS Design Features Section to Remove the Nine Mile Point Unit 3 Nuclear Project, LLC ML24213A2202024-07-31031 July 2024 Updated Change in Estimated Review Schedule Revision to TS Design Features Section to Remove the Nine Mile Point Unit 3 Nuclear Project, LLC ML24228A1922024-07-29029 July 2024 Request for Additional Information Response Due Date Extension E-Mail String ML24197A0092024-07-15015 July 2024 Acceptance Review Determination for LAR to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling ML24199A1842024-07-15015 July 2024 RAI-LAR for Limerick EPID: L-2024-LLA-0079- Use This Version ML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24197A0482024-07-12012 July 2024 Information Request for the Quad Cities Nuclear Station Biennial Problem Identification and Resolution Inspection ML24185A1782024-07-0303 July 2024 NRC Email Response to Peach Bottoms Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations ML24180A0032024-06-28028 June 2024 NRR E-mail Capture - NRC Acceptance Review of Byron/Braidwood Amendment for Transition to Framatome Gaia Fuel (L-2024-LLA-0072) ML24180A0042024-06-28028 June 2024 NRR E-mail Capture - Acceptance Review for Braidwood and Byron - Request for Exemption from 10 CFR 50.46 and Appendix K (L-2024-LLE-0019) ML24306A0072024-06-26026 June 2024 NRR E-mail Capture - Verbal Relief for Byron, Unit 2, Three Specific Air-operated Valves in the Essential Service Water System (L-2024-LLR-0042) ML24176A0232024-06-21021 June 2024 NRR E-mail Capture - Dresden Nuclear Power Station, Units 2 and 3 - Acceptance Review of the Amendment Request to Adopt 10 CFR 50.69 ML24192A3642024-06-21021 June 2024 State Rad Health Reply Email Re Draft Environmental Assessment for the Three Mile Island Unit 2 ML24176A1292024-06-20020 June 2024 Estimated Completion Schedule Change Email ML24176A0182024-06-20020 June 2024 NRR E-mail Capture - NRC Acceptance Review of Byron/Braidwood Amendment to Remove Extraneous Detail Related to Beacon ML24170A3912024-06-18018 June 2024 NRR E-mail Capture - Revision of Estimated Hours to Complete Review of Byron/Braidwood Amendment to Revise TS 3.7.15, 3.7.16, and 4.3.1 (L-2023-LLA-0136) ML24159A0122024-06-0606 June 2024 NRR E-mail Capture - Dresden Nuclear Power Station, Units 2 and 3 - Acceptance of Licensing Amendment to Adopt TSTF-505 and TSTF-591 ML24156A1072024-06-0404 June 2024 NRR E-mail Capture - (External_Sender) Supplement for FitzPatrick TS 3.4.2-2 ML24156A0082024-05-31031 May 2024 NRR E-mail Capture - Constellation Energy, LLC - Fleet Request - Acceptance of Proposed Alternative Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds (L-2024-LLR-0031 ML24108A1352024-05-20020 May 2024 Email to Christian Williams Re Decision on the Exemption Request for Calvert Cliffs ML24141A2452024-05-20020 May 2024 NRR E-mail Capture - NRC Acceptance Review of Byron/Braidwood Amendment to Delete Technical Specification 5.6.5.b.5 (L-2024-LLA-0055) ML24108A1312024-05-15015 May 2024 Email to Christian Williams Re Availability of Environmental Assessment for the Calvert Cliffs Exemption ML24163A3522024-05-15015 May 2024 Meeting Feedback from May 14, 2024, Meeting with Constellation on Peach Bottom Atomic Power Station Units Nos. 2 and 3 ML24135A0182024-05-13013 May 2024 NRR E-mail Capture - Draft Request for Additional Information Quad Cities TSTF-505 Amendment ML24131A0612024-05-10010 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) NRC-2024-0085, Response from State of MD Regarding Review of EA for Calvert Cliffs Exemption Request2024-05-0909 May 2024 Response from State of MD Regarding Review of EA for Calvert Cliffs Exemption Request ML24107A9192024-05-0808 May 2024 Email to Christian Williams Re Decision on the Limerick Exemption ML24107A9202024-05-0303 May 2024 Email to Christian Williams Re Availability of Environmental Assessment for the Limerick Exemption ML24222A4092024-05-0303 May 2024 NRR E-mail Capture - Request for Additional Information Regarding Reactor Water Cleanup (RWCU) Pump Rooms - L-2023-LLA-0118 ML24122C6742024-05-0101 May 2024 Response to a Request from NRC Review of a Draft EA for an Exemption for the Limerick Generating Station ML24122B5072024-05-0101 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-591, Revision 0 ML24086A5182024-04-30030 April 2024 E-mail to Christian Williams Decision on the Exemption Request for Quad Cities ML24122C6702024-04-29029 April 2024 Request from NRC Review of a Draft EA for an Exemption for the Limerick Generating Station ML24131A1212024-04-29029 April 2024 Email to State of MD Requesting Review of the EA for Calvert Cliffs Exemption Request ML24086A4782024-04-24024 April 2024 Email to Christian Williams Availability of Environmental Assessment for the Quad Cities Exemption ML24114A1702024-04-15015 April 2024 Request for State Review of the Quad Cities HI-STORM Exemption Request Environmental Assessment ML24102A2422024-04-10010 April 2024 NRR E-mail Capture - Draft Request for Additional Information Quad Cities TSTF-505 and 50.69 Amendments ML24066A0802024-04-0101 April 2024 Email to Christian Williams Decision on the Exemption Request for Dresden Nuclear Power Station Unit 2 and Unit 3 Independent Spent Fuel Storage Installation in Morris, Illinois ML24089A0102024-03-29029 March 2024 NRR E-mail Capture - Quad Cities Unit Nos. 1 and 2 - Alternative to Core Spray Pump Testing - Acceptance of Requested Licensing Action Relief Request Associated with the Sixth Inservice Testing Interval ML24065A4892024-03-28028 March 2024 Email to Christian Williams Availability of Environmental Assessment for the Exemption Request for Dresden Nuclear Power Station Unit 2 and Unit 3 Independent Spent Fuel Storage Installation in Morris, Illinois 2024-09-06
[Table view] |
Text
NRR-DMPSPEm Resource From: Purnell, Blake Sent: Monday, April 02, 2018 1:49 PM To: Mascitelli, Francis J:(GenCo-Nuc)
Cc: Barstow, James:(GenCo-Nuc); Wrona, David; 'dcd-licensing2@exeloncorp.com'
Subject:
Exelon Generation Company, LLC - Acceptance of Fleet License Amendment Request to Relocate Staff Qualification Requirements to Quality Assurance Topical Report (EPID L-2018-LLA-0053)
Mr. Mascitelli, By application dated January 31, 2018 (Agencywide Documents Access and Management System (ADAMS)
Package Accession No. ML18060A266), Exelon Generation Company, LLC (the licensee) submitted a license amendment request for Braidwood Station, Units 1 and 2; Byron Station, Unit Nos. 1 and 2; Calvert Cliffs Nuclear Power Plant, Units 1 and 2; Clinton Power Station, Unit No. 1; Dresden Nuclear Power Station, Units 2 and 3; James A. FitzPatrick Nuclear Power Plant; LaSalle County Station, Units 1 and 2; Limerick Generating Station, Units 1 and 2; Nine Mile Point, Units 1 and 2; Peach Bottom Atomic Power Station, Units 2 and 3; Quad Cities Nuclear Power Station, Units 1 and 2; R. E. Ginna Nuclear Power Plant; and Three Mile Island Nuclear Station, Unit 1. The amendments would relocate the staff qualification requirements from the technical specifications to the licensees quality assurance topical report.
The purpose of this e-mail is to provide the results of the NRC staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staffs detailed technical review by separate correspondence.
Based on the information provided in your submittal, the NRC staff has estimated that the review of this licensing request will take approximately 250 hours10.417 days <br />1.488 weeks <br />0.342 months <br /> to complete. The NRC staff expects to complete this review by September 4, 2018, as requested. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.
These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and 1
review by NRC advisory committees or hearing-related activities. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.
If you have any questions, please contact me at (301) 415-1380.
Sincerely, Blake Purnell, Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. STN 50-456, STN 50-457, STN 50-454, STN 50-455, 50-317, 50-318, 50-461,50-237, 50-249, 50-333, 50-373, 50-374, 50-352, 50-353, 50-220, 50-410, 50-277, 50-278, 50-254, 50-265, 50-244, and 50-289 2
Hearing Identifier: NRR_DMPS Email Number: 267 Mail Envelope Properties (Blake.Purnell@nrc.gov20180402134900)
Subject:
Exelon Generation Company, LLC - Acceptance of Fleet License Amendment Request to Relocate Staff Qualification Requirements to Quality Assurance Topical Report (EPID L-2018-LLA-0053)
Sent Date: 4/2/2018 1:49:03 PM Received Date: 4/2/2018 1:49:00 PM From: Purnell, Blake Created By: Blake.Purnell@nrc.gov Recipients:
"Barstow, James:(GenCo-Nuc)" <James.Barstow@exeloncorp.com>
Tracking Status: None "Wrona, David" <David.Wrona@nrc.gov>
Tracking Status: None
"'dcd-licensing2@exeloncorp.com'" <dcd-licensing2@exeloncorp.com>
Tracking Status: None "Mascitelli, Francis J:(GenCo-Nuc)" <Francis.Mascitelli@exeloncorp.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 4228 4/2/2018 1:49:00 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: