Forwards IE Insp Repts 50-272/80-17 & 50-311/80-13 on 800714-18 & Notice of Violation.Notice of Violation Withheld (Ref 10CFR2.790)
ML18085A229
Person / Time
Site: Salem  PSEG icon.png
Issue date: 08/22/1980
From: Martin W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Schneider F
Public Service Enterprise Group
Shared Package
ML18085A228 List:
References
NUDOCS 8011180443
Download: ML18085A229 (2)


See also: IR 05000272/1980017

Text

Docket Nos. 50-272

50-311

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

631 PARK AVENUE*

KING OF PRUSSIA, PENNSYLVANIA 19406

Public Service Electric and Gas Company

ATTN:

Mr. F. W. Schneider

Vice President - Production

80 Park Plaza 15-A

Newark, New Jersey 07101

Gentlemen:

Subject: Combined Inspection 50-272/80-17; 50-311/80-13

2 2 AUG 1980

This refers to the routine inspection conducted by Mr. R. J. Bailey of this

office on July 14-18. 1980 at the Salem Nuclear Generating Station, Units 1 and

2, of activities authorized by NRC License Nos. DPR-70 and DPR-75 and to the

discussions of our findings held by Mr. Bailey and members of your staff a.t the

contlusion of the inspection.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter. , Within

these areas, the inspection consisted of selective examinations of procedures

and*representative records, interviews with personnel. ~nd observations by the

inspector.

Based on the results of this inspection, it appears that certain of your activi-

ties were not conducted in full compliance with NRC requirements, as set forth

in the Notice of Violation, enclosed herewith as Appendix A.

These items of

noncompliance have been categorized into the levels as described in our corres-

pondence to you dated December 31, 1974. This notice is sent to you pursuant to

the provisions of Section 2.201 of the NRC's "Rules of Practice," Part 2~ Title

10, Code of Federal Re~uTations. Section 2.201 requires you to submit to this

_ office, within twenty (20) days of your receipt of this notice, a written state-

ment or explanation in reply including:

(1) corrective steps which have been

taken by you and the results achieved; (2) corrective steps which will be taken

to avoid further items of noncompliance; and (3) the date when full compliance

will be achieved.

tn accordance with Section 2.790(d) of the NRC's "Rules of Practice, Part 2.

Title 10, Code of Federal Regulations, documentation of findings of your control

and accounting procedures for safeguarding special nuclear materials and your

facility security measures for physical protection are deemed to be commercial

or financial information within the meaning of 10 CFR 9.S(a)(4) and shall be

subject to disclosure only in accordance with the provisions of 10 CFR 9.12~

therefore, the enclosed inspection report will ~at be placed in the Public

Document Room and will receive limited distribution.

  • <-

Public Service Electric and

Gas Company

2

2 2 AUG 1980

ti)

Should you have any questions concerning this inspection, we will be pleased to

discuss them with you.

Sincerely,

alter G. Martin, Chief

Safeguards Branch

Enclosures:

1.

Appendix A~ Notice of Violation (Contains 2.790 Info)

2.

Combined Office of Inspection and Enforcement Inspection

Report Number 50-272/80-17, 50-311/80-13 (Contains 2.790 Info)

cc:

F. P. Librizzi, General Manager - Electric Production (w report cover sheet

only)

E. N *. Schwalje, Manager - Quality Assurance (w report cover sheet only)

H. J. Midur~, Manager - Salem Generating Station (w report cover sheet only)

R. L. Mittl, General Manager - Licensing. and Environment (w .. r.epart. cover* sheet.

only)

R. A. Uderitz, General Manager - Fuel Supply Department (w report cover sheet only)