ML18082A452

From kanterella
Jump to navigation Jump to search
Forwards Combined IE Insp Repts 50-272/79-33 & 50-311/79-38 on 791216-800202 & Notice of Deviation
ML18082A452
Person / Time
Site: Salem  PSEG icon.png
Issue date: 03/07/1980
From: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Schneider F
Public Service Enterprise Group
Shared Package
ML18082A450 List:
References
NUDOCS 8005230568
Download: ML18082A452 (2)


See also: IR 05000272/1979033

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

631 PARK AVENUE

KING OF PRUSSIA, PENNSYLVANIA 19406

MAR

7 1980

Docket No. 50-272

Public Service Electric and Gas Company

ATTN:* Mr. F. W. Schneider

Vice President - Production

80 Park Place

Newark, New Jersey 07101

Gentlemen:

Subject:

Inspection 50-272/79-33

This refers to the inspection conducted by Mr. L. Norrholm of this office on

December 16, 1979 - February 2, 1980 at Salem Nuclear Generating Station, Unit l

of activities authorized by NRC License No. DPR-70 and to the discussions of our

findings held by Mr. Norrholm-with H. Midura of your staff periodically during

the-inspection.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which ts enclosed with this letter. Within

these areas~ the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, and observations by the

inspector.

Within the scope of this inspection, no items of noncompliance were observed.

However, one activity appears to be .a deviation frorn commitments made i ri the

Final Safety Analysis Report.

This item and reference to the specific commitment

ara listed in Appendix A to this letter.

In your reply, please include your

comments concerning this item, a description of any steps that have been or will

be taken to prevent recurrence, and the date all corrective actions or preventive

measures were or will be completed.

In accordance with Section 2*. 790 of the NRC' s "Rules of Practice," Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosures will

be placed in the NRC's Public Document Room.

If this report contains any infor-

mation that you (or your contractor) believe to be proprietary, it is necessary

that you make a written application within 20 days to this office to withhold

such information from public disclosure. Any such application must be accompanied

by an affidavit executed by the owner of the information, which identifies the

document or part sought to be withheld, and which contains a statement of reasons

which addresses with specificity the items which will be considered by the

Commission as listed in subparagraph (b) (4) of Section 2.790.

The information

sought to be withheld shall be incorporated as far as possible tnto a separate

part of the affidavit. If we do n6t hear from you in this regard within the

specified period, the report will be placed in the Public Document Room.

8 0 05 2305lo~ Q

Public Service Electric and Gas

Company

2

MAR

7 '980

Should you have any questions concerning this inspection, we will be pleased to

discuss them with you.

Enclosures:

1.

Appendix A, Notice of Deviation

Sincerely,

~

e. ~~

) v. A-c.+.,_, h

I

Eldon J. Brunner, Chief

Reactor Operatibns a:nd Nuclear--

Support Branch

2.

Office of Inspection and Enforcement Combined Inspection

Report Numbers 50-272/79-33 and 50-311/79-38

cc w/encls:

F. P. Librizzi, General Manager - Electric Production

E. N. Schwalje, Manager - Quality Assurance

R. L. Mittl, General Manager - Licensing and Environment

K. J. Midura, Manager - Salem Generating Station

.,*.