ML18082A437

From kanterella
Jump to navigation Jump to search
Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in IE Insp Rept 50-272/80-02. Util Ltr to Be Withheld (Ref 10CFR2.790)
ML18082A437
Person / Time
Site: Salem PSEG icon.png
Issue date: 04/28/1980
From: Martin W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Schneider F
Public Service Enterprise Group
Shared Package
ML18082A438 List:
References
NUDOCS 8005220360
Download: ML18082A437 (3)


See also: IR 05000272/1980002

Text

631 PARK AVENUE

KING OF PRUSSIA, PENNSYLVANIA 19406

2 8 APR 1980

Docket No. 50-272

Public Service Electric and Gas Company

ATIN:

Mr. F. W. Schneider*

Vice President - Production

80 Park Place

Newark, New Jersey 07101

Gentlemen:

Subject:

Inspection 50-272/80-02

This refers to your letter dated April 10, 1980, in .response to our letter

dated March 21, 1980.

In accordance with Section 2.790(d) of the NRC 1 s

11Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, documentation of your control and

accounting procedures for safeguarding special nuclear materials and facility

security procedures are exempt from disclosure; therefore, the enclosures to

the referenced letter will not be placed in the Public Document Room.

Thank you for informing us of the corrective and preventive actions documented

in your letter.

These actions will be examined during a subsequent inspection

of your licensed program.

Your-cooperation with us is appreciated.

cc:

Sincerely,

Walter G. Martin, Chief

Safeguards Branch

F. P. Librizzi, General Manager - Electric Production

E. N. Schwalje, Manager - Quality Assurance

H. J. Midura, Manager - Salem Generating Station

R. L. Mittl, General Manager -- Licensing and Environment

/l

1?

80 0"522 0360

'**-* ---~~-~--*-*.--.-,,_---,-~.,.------.... -~ .. , ........ _______ ,,...~-~.. . -. "~-.. ---~* -- .. ---, ..... -. -* .-----*-----*----**--****---:. .... ~-----*--****--------.---*--.... **---..

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

631 PARK AVENUE

KING OF PRUSSIA, PENNSYLVANIA 19406

Docket No. 50-272

Public Service Electric and Gas Company __

ATTN:

Mr. F. W. Schneider

Vice President - Production

80 Park Place

Newark, New Jersey 07101

Gentlemen:

Subject: Inspection Report No. 50-272/80-02

2 1 MAR 1980

This refers, to the inspection condu.cted by Mr. _R. J. Bailey of this

offi.ce on January 21-25, 1980 at the Salem Nuclear Generating Station,

Unit 1, Hancocks Bridge, New Jersey of activities authorized by NRC

License No. DPR-70 and to the discussions of our findings held by Mr.

Bailey with Mr. Midura at the conclusion of the inspection and during

the meeting at Region I on February 26, 1980 with Mr. Librizzi and other

members of your staff.

Areas examined during this inspection are described in the Office of

Inspection and Enforcement. Inspection Report which is enclosed with this

. letter~ Within these areas, the inspection consisted of selective

examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

Our inspector also verified the steps you have taken to correct the

items of noncompliance brought to your attention in a letter dated

October 15, 1979.

We have no further questions regarding your action at

this time.

Based on the results of this inspection, it ap~ears that certain of your

activities were not conducted in full compliance with NRC requirements,

as set forth in the Notice of Violation, enclosed herewith as Appendix

_A. - These items of noncompliance have been categorized into the levels

as described in our correspondence to you dated December 31, 1974. This

notice is sent to you pursuant to the provisions of Section 2.201 of the

NRC's "Rules. of P;ractice,

11 Part 2, Title 10, Code of federal Regulations.

Section 2.201 requir~s you to submit to this office, within twenty (20)

days of your receipt of this notice, a written statement or explanation

in reply including:

(1) corrective steps which have been taken by you

and the results achieved; (2} corrective steps which will *be taken to

avoid further items of noncompliance; and (31 the date when full compliance

will be achieved.

s 0 0*5 2 2 0.8 6 4

....

Public Service Electric and Gas Company

2

2 1 MAR 1980

In accordance with Section 2.790(d) of the NRC's "Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, documentation of your

control and accounting procedures for safeguarding special nuclear

materials and your facility security procedures are exempt from disclosure;

therefore, the enclosures to this letter will *not be placed in the

Public Document Room and will receive limited distribution.

Should you have any questions concerning this inspection, we will be

pleased to discuss them with you.

Enclosures:

Si"ncerely,

~~94.d:S

Walter G. M~rtin, Chief

S~feguards Branch

1. Appendix A, Notice of Violation (Contains 2. 790 {d) Information)

2.

Office of Inspection and Enforcement Inspection

Report Number 50-272/80-02

(Contains 2.790(d) Information)

cc w/o encls:

F. P. Librizzi, General Manager - Electric Production

E. N. Schwalje, Manager - Quality Assurance

H. J. Midura, Manager - Salem Generating Station

R. L. Mittl, General Manager - Licensing and Environment