Revised Average Daily Unit Power Level,Unit Shutdowns & Power Reductions & Operating Experience Summary Repts for Nov 1993
ML18059A631
Person / Time
Site: Palisades Entergy icon.png
Issue date: 11/30/1993
From: Vanwagner M
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
Shared Package
ML18059A629 List:
References
NUDOCS 9401130060
Download: ML18059A631 (3)


Text

..

AVERAGE DAILY UNIT POWER LEVEL MONTH _..:..:.NO=V=E""""MB=E=R_-__..;..:.RE=-=V'--=-I""'"'S E=D'--

DAY AVERAGE DAILY POWER LEVEL (MWe Net)

1.

0

2.

0

3.

0

4.

0

5.

0

6.

73

7.

0

8.

95

9.

277

-~

10.

322

11.

578

12.

613

13.

661

14.

798

15.

796

16.

799 INSTRUCTIONS:

DAY

17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.

DOCKET NO 50-255 UNIT Palisades DATE 12/03/93 COMPLETED BY MMVanWaqner TELEPHONE (616)764-8913 AVERAGE DAILY POWER LEVEL (MWe Net) 797 798 795 800 796 797 797 798 798 790 806 797 801 796 On this format, list the average daily unit power level in MWe-NET for each day in the reporting month.

Compute to the nearest whole megawatt.

REPORT MONTH NOVEMBER 1993 - REVISED No.

Date Type 1 02 930604 s

03 931112

1.
2.

F:

Forced S:

Scheduled Duration 2

Reason (Hours) 176.4 c

0 A

Reason:

A-Equipment Failure (Explain)

B-Maintenance or Test C-Refue ling D-Regulatory Restriction E-Operator Training & License Examination F-Administrative G-Operational Error (Explain)

H-Other (Explain)

UNIT SHUTDOWNS AND POWER REDUCTIONS Method of Licensee Shutting Event Down Reactor3 Report #

4

3.

Method:

1-Manual 2-Manual Scram*

3-Automatic Scram 4-0ther (Explain)

4.

System Component Code4 Code5 Exhibit G - Instructions for Preparation of Data Entry Sheets for Licensee Event Report (LER) File (NUREG-0161)

Cause & Corrective Action to Prevent Recurrence DOCKET NO UNIT DATE COMPLETED BY TELEPHONE Official conclusion of 1993 Refueling Outage Electrohydraulic fluid leak, attempt to isolate resulted in closing intercept valve.

5.

Exhibit I - Same Source 50-255 Palisades 12/02/93 MMVanWagner' (616)764-8913 e

.. =' * *.

<J~

SUMMARY

OF OPERATING EXPERIENCE FOR NOVEMBER 1993 Initial criticality for Cycle 11 was attained on November 3, 1993 at 1109.

The generator went on-line November 5, at 0432, but went off-line at 0731 to repair an EHC leak on November 5, 1993.

Return to power took place at 0944 on November 6-, 1993.

On November 6, the turbine was taken off-line at 2105 to perform overspeed trip testing.

The test failed, repairs were made, and the turbine was returned to service November 8, at 0534.

At 1419, the turbine was taken off-1 ine, the overspeed test was reperformed staisfactorily and the turbine was back on-line at 1705.

The outage officially ended at this time.

November 12 at 1115, commenced emergency power reduction as a result of an attempt to repair an electro~hydraulic fluid leak.

At 1117, stabilized at 62%

power.

On November 13, 0258 power escalation began.

Full power was reached by approximately 2030 on November 13 and continued for the remainder of the month.