ML18058A569

From kanterella
Jump to navigation Jump to search
Insp Rept 50-255/92-12 on 920225-0528.Violations Noted.Major Areas Inspected:Inservice Insp Activities,Program Procedures,Observation of Work Activities & Data Review Evaluation
ML18058A569
Person / Time
Site: Palisades 
Issue date: 06/22/1992
From: Schapker J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML18058A567 List:
References
50-255-92-12, NUDOCS 9206290040
Download: ML18058A569 (26)


See also: IR 05000255/1992012

Text

U. S. NUCLEAR REGULATORY COMMISSION

REGION III

Report No.:

50-255/92012(DRS)

Docket No.:

50~255

Licensee:

Consumers Power Company

1945 West Parnall Road

Jackson, MI

49201

Facility Name:

Palisades Nuclear Power Plant

Inspection At:

covert, MI

49043

License No.:

DPR-20

Inspection Conducted:

February 25-27, April 3, 9, 27-28, 30, and

May 27-28, 1992 (Region III)

Inspector:

Inspection Summary

23 through April 3, 1992. (Region I)

es Section

6 ..-..,_ 'L- --?' .,__

Date

Inspection on February 25-27. April 3, 9, 27-28, 30, and May 27-

28, 1992 (Region III); March 23 through April 3. 1992 (Region I)

(Report No. 50-255/92012(DRS)).

Areas Inspected:

Routine announced .inspection of inservice

inspection (ISI) activities including review of program (73051),

procedures (73052), observation of work activities (73753), data

review and evaluation (73755), and inspection of the ventilated

concrete cask (VCC) fabrication performed on the Palisades site*

(37700).

Selected areas inspected by the NRC Mobile NDE

Laboratory were the safety injection and refueling line (SIRW),

main steam (MSS), feedwater (FWS), chemical volume control (CVC),

containment spray (CSS), long term cooling (LTC), and safety

injection (SIS) systems.

Results:

Of the areas inspected, two violations of NRC

requirements and eight unresolved items were identified in the

ISI areas.

Inspections of the VCC fabrication identified some

quality control/quality assurance weaknesses and lack of

contractor oversight resulting in an unresolved item.

9206290040 920622

PDR

ADOCK 05000255

G

.

PDR

The NRC inspectors noted the following:

Implementation of ISI was generally considered weak.

Examples of deficiencies include omission of a number of

.welds from the ISI program, incomplete documentation of

examination results, and some questionable examination

techniques.

-

0

Observations of the fabrication of the vcc identified

examples of work activities and QA/QC.implementation which

failed to meet applicable specifications and standards.

oversight of the contractor activities on site was weak .

2

': .-

--

DETAILS

1.

Persons Contacted

Consumers Power Company CCPCol

  • J. Amthor, Construction Superintendent
  • D. Engle, Senior Engineer
  • R. Smedley, Staff Licensing Engine~r
  • T. Newton, Senior Nuclear Operations Analyst
  • T. Fouty, Senior Nuclear Operations Analyst
  • V. Beilfuss, Assistant Outage Manager

R. Vanwagner, ISI Supervisor

s. Wellman, NDT Project Supervisor

Pacific Sierra Nuclear Corporation CPSN)

  • W. Lee, Vice President

+J. Massey, Project Manager

J. A. Jones

F. Slatton, Project Superintendent *

  • u. s. Nuclear Regulatory Commission CNRCl
  • J. Heller, Senior Resident Inspector
  • Denotes those attending the exit interview on May 28, 1992.

+Attended the exit interview via telecon.

Other licensee and contractor personnel were contacted

during the course of the inspection.

2.

Inservice -Inspection CISI) (73051, 73052, 73753, 73755)

a.

Eddy Current (ET) Examination of Steam Generator Tubes

The licensee replaced steam generators (SGs) in the

1990-91 outage. * This was the first examination for the

first operating cycle of the replacement SGs.

The

inspection included full length tube examination of

1,599 tubes in the "A" SG and 1,597 tubes in the "B" SG

utilizing a bobbin coil probe and multifrequency (MIZ-

18) eddy current examination data acquisition system.

3

Results of the examination identified no1 defective

tubes in either SG; however, degradation was

identified in 45 tubes.

While the results of the ET

examination appeared to exhibit substantial degradation

for the first operating cycle, comparison with the

baseline ET performed prior to installation revealed

that little, if any, degradation had actually occurred

during the operating cycle.

The degradation recorded

during this inspection was identified during the

baseline inspection and had not substantially changed.

The NRC inspector observed ET in progress, verified

calibration/certification of ET equipment and

calibration standards, and reviewed the

examiner/analyst qualification certifications.

The NRC

inspector also reviewed the ET Data Analyst Guidelines

and observed evaluations being performed by the

analysts.

The licensee has contracted with Westinghouse Electric

corporation (~) for a Steam Generator Reliability

Program.

This program includes ET services, chemistry

control, cleaning services, and general maintenance to

reduce and control degradation in the SGs.

The licensee's SG reliability program appears to be

conservative in assuring the safe operation of the SGs.

b.

Observation of ISI Work Activities (73753)

The NRC inspector observed the following ISI work

activities in progress:

ET examination of SG tubes. 2

UT examination of reactor vessel closure head

studs.

MT examination of reactor vessel stud nuts and

washers.

PT examination of SG feedwater piping.

1 Technical Specifications require those tubes with excess of

20% wall thinning (wastage) be reported as degraded, t_ubes in

excess of 40% are considered defective and must be repaired or

plugged.

2 ET work activities observed are described in Paragraph 2.a

of this *report.

4

Work activities were* performed in accordance with

approved procedures, utilizing calibrated NOE equipment

and certified personnel.

Detection: and evaluation of

flaws detected.by NDE procedures were completed in

accordance with ASME Code and regu-latory . requirements.

c.

ISI Documentation Review* (73755)

The *irac inspector reviewed documents relating to the

following:

0

0

0

0

0

NDE procedures for wor~ activities observed.

NOE personnel c.ertification:s in accordance with

SNT-TC-lA.

NOE equipment calibration and examination reports.

Liquid penetrant mat.erial certifications.

ET examination reports.

ET data analysis guidelines.

No violations or deviations were identified.

3.

Inspection of the Ventilated Concrete Cask Fabrication at

the Palisades Site

a*-

Background .

The licensee contracted with Pacific Sierra Nuclear

Corporation (PSN) to design and construct a dry cask

spent fuel storage facility to be partially constructed

  • onsite for long term temporary storage of spent fuel.

The licensee i.s currently documenting a 10 CFR 50.59

evaluation as required by 10 CFR 72.212 (Subpart K),

showing that use of .the general license .for storage of

spent fuel at the power reactor site will not involve

an unreviewed safety question or Technical

Specification (TS) change.

The PSN cask desig~ consists of a steel multi~assembly

basket (MSB) which holds 24 spent fuel assemblies

(sealed) and a steel clad ventilated concrete cask

(VCC) which provides biological shielding and MSB

protection.

The PSN cask design has not yet been granted a

Certificate of Compliance by the NRC which would add it

to the list of approved spent fuel.storage casks in 10

CFR '}2.214.

This inspection was conducted in terms of

5

b.

the specifications, standards, codes, and commitments

described in the licensee's request for design

certification.

Inspection*

The NRC inspector's initial observation of work

activities onsite was the welding of the ventilation

ducts to the steel liner of the VCC.

The NRC inspector *

reviewed procedures, specifications, and qualification

records for the welding in progress.

Specification CVCC-89-001, Revision 1, dated February

1991, entitled "Fabrication for The Ventilated Concrete

_Cask" was reviewed.

Section 3.10, "Steel Fabrication

and Welding"'" required that all welding be perforpied to

approved drawings, and. that welders and weld inspectors

be qualified/certified to AWS D.1.1.

The NRC inspector's review confirmed the use of AWS

approved weld procedures and welders; however, no AWS

certified weld inspector was assigned onsite to perform

inspections.

The vendor (PSN) subsequently initiated a

Document Change Notice (CPC-041). dated April *14, 1992,

which deleted the AWS b1.1 requirement in the

fabrication specification.

The safety significance of this deletion was minimal

because the welds in question serve no structurally

significant purpose.

However, the inadequate

implementation of the specification requirements is

considered a weakness in both contractor implementation

and licensee oversight of contractor activities.*

Inspection of the. first concrete pour (April 3 O, -1.992)

identified wea.knesses in training of the craft in

performance of their assigned task.

The NRC inspector observed the placement of concrete in

the VCC forms.

The consolidation of the concrete was

being performed with mechanical vibrators.

Initial

placement/consolidation was being performed by placing

the vibrators in the concrete and vibrating to both

consolidate and move the concrete within the forms.

Using the vibrators to move the poured concrete

violates the requirements of the American Concrete

. Institute (ACI) Standard 301.

The NRC inspector

questioned the craft to determine the extent of their

knowledge and training in the use of vibrators.

The

craft was unaware of the ACI requirements with respect

to moving concrete with the vibrators *

6

The NRC inspector immediately informed the contractor

.

. superintendent that the craft were improperly using the

vibrators.

The contractor superintendent took prompt

corrective action and instructed the craft in the

proper method of consolidation and placement of

concrete in the form.

Due to the prompt. identification

of the improper practice and corrective action taken

.during the initial placement in the concrete forni of

the first VCC, the NRC inspector believes that no

segregation of concr.ete materials was likely and

therefore, the concrete placement was*acceptable.

The NRC inspector also observed placement of concrete

in the fourth VCC (May 28, 1992).

Prior to the day of

the pour, the contractor informed _the NRC.inspector

that the PSN representative had been reassigned to

another project.

The NRC inspector inquired as to who

the PSN inspector would be for the-.upcoming pour of the

fourth vcc.

No inspector was assigned at that time; .

however, because of the NRC's iriquiry, the PSN

inspector was required to report to the site to perform

inspections of the pour.

Discussions at the exit

meeting with the PSN Project Manager disclosed that .*the

inspections for the concrete pour we~e waived by PSN,

and the licensee and the fabrication contractor were to

perform the inspections. .However, the fabricator did

not have any individuals who were qualified or

sufficienctly independent to perform the inspection.

Subsequent discussions identified that the licensee had

no knowledge of this agreement; and, no one had been

_assigned by the licensee to perform the inspections.

Furthermore, the licensee had not, a$ of this

inspection, performed any onsite audits or

.. surveillances of the contractor* s work*.

The fabrication contractor's (J. A. Jones) standard

operating procedures for fabrication of the vcc were

reviewed by the NRC inspector prior to the first pour

of VCC #1.

These procedures describe the inspection

responsibilities of the contractor superintendent.

No

inspection procedures for PSN were available for review

onsite; however, the PSN inspector had completed an

inspection check sheet and recorded the appropriate

dimensions and inspection characteristics.

The NRC inspector also reviewed the Quality Assurance

Data Package for VCC #1, #2 and completed portions of

  1. 3.

CVCC-89-001, Paragraphs 4.2.3 and 4.2.4 required

the vendor to use fabrication travelers and record all

critical dimensions in the traveler however, the

process control sheets or travelers were not completed .

7

i

j

,.

Hold points and witness points were not signed by the

J. A. Jones superintendent or the .PSN inspector.

In summary, contractor oversight and QA/QC

implementation was weak.

Examples of weaknesses

identified during this inspection include failure' to

follow procedures, insufficient training of craft, and

inadequate definition of QA/QC responsibilities.

These

weaknesses are collectively considered an unresolved

item and a written response describing the licensee's

evaluation of the extent of the problems and corrective

actions taken is requested (50-255/92012-11)

Subsequent to the exit interview on May 28, 1992, the

licensee issued a Stop Work Order on May 29, 1992

(Enclosure 4).

No violations or deviations were identified .

.

'

4.

Unresolved Items

5.

Unresolved items are matters about which more.information is

required in order to ascertain whether they are acceptable

items; violations, or deviations. An unresolved item

disclosed during the inspection is discussed in Paragraph

3.b of this report *

Exit Interview

The inspector met with licensee representatives (denoted in

Paragraph 1) at the conclusion of the inspection on May 28,

1992.

The inspector summarized the scope and findings of

the inspection activities.

~he licensee acknowledged the

inspection findings.

The inspector also discussed the

likely informational content of the inspection report with

regard to documents. or processes reviewed by the inspector

during the inspection.

The licensee did not identify any

such document/processes as proprietary .

8

Docket No ..

License No.

Licensee:

ENCU'.>suRE 3

U.S. NUCLEAR REGULATORY COMMISSION

REGION 1

DPR-20

Consumers Power

212 West Michigan Avenue

. fackson. Michigan 49201

Facility Name:

Palisades* Power Station

Inspection At:

Covert. MI

Inspection Dates:

February 24 to March 6. 1992

Inspectors: . . * . Ham{

hmc1an

Mobile NDE Laboratory, EB, DRS

P. M. Peterson, Technician

Mobile NDE Laboratory, EB, DRS

. D. M. Wiggins; TET~ Inc.; Mobile, Alabama

W. M. Mingus; TET, Inc.; Mobile, Alabama

ApprOved by: ~

_,*

'

~NDE

Laboratory,

Engineering Branch, DRS

Dale

2

Inspectfon Summary and Conclusions: An announced inspection was conducted at the

Palisades NuCiear Power Station ~uring the period March 23 to* April 3, 1992, using the

NRC Mobile NDE Laboratory (Report 50-255/92~012). The purpose of this inspection was.

the independent nondestructive evaluation (NDE) of components and welds in order to

ascertain the accuracy of the NDE performed by the licensee. 'During this inspection forty-

eight (48) welds and/or components located in 7 pl3.!lt.systems were examined by

nondestructive methods by the NRC. J'he results obtained by the NRC during this

  • evaluation, when compared with those of the licensee, were not consistent with the variations
  • expeeted* in teehnique and revealed an ISi system with weaknesses.

Areas InspeCted: Selected areas from the safety injection and refueling line (SIRW), main

steam (MSS), feedwater (FWS); chemical volume control .(CVC), containment spray (CSS),

long term cooling (LTC)., and safety injeetion (SIS) system were independently examined by

the NRC utilizing various nondestructive methods. An evaluation of the licen~ee's quality

program, including NDE, was performed using NRC promulgated procedures iri conjunction

. with the licensee's approved procedures.

. Results: . The inspection. found a number of weaknesses in the ISi system at Palisades. These

weaknesses were contained in both the programmatic and testing portions of the ISi system. *

In addition to the violation *for failure to identify or examine welds and the viol~tion of.

inadequate volumetric coverage there are eight unresolved findings. * The vi?lations are *

discussed in Paragr~phs 2.3 and 3A.

3

1.0

Introduction

The Code of Federal Regulations (CFR), Title 10, Part 50.55a (10 CFR 50.55a),

requires inservice inspection (ISi) of safety related equipment to identify system*

degradation. Before the licensee generated program *of inspection is applied- to the

-equipment it must be approved by the Nuclear Regulatory Commission (NRC) under

the authority embodied in 10 CFR 50.55a (g) (4) (iv). The required inspections are

qetailed in the American Society of Mechanical Engineers .(ASME) Boiler and

Pressure Vessel Code,Section XI for Inservice Inspection as embraced in 10 CFR

50.55a (b). The NRC inspection described in this report was made using the Mobile

Nondestructive Examination (NDE) Laboratory. The Mobile NDE Laboratory is

capable of independently performing the examinations required of the licensee. This

capability provides the NRC with unique insights into the licensee's inservice -

inspection program and on a sampled basis, the adequacy and accuracy of the -*

licensee's specific NDE inspections.

The scope of this inspection was to review the administrative portions of the program

and to perform NDE of the systepls that were avfillable. *

2.0

Inservice Inspection Program Review

2.1 -

NDE Procedures (73052)

Before a license's program of inspection is used, it must be approved by the

Nuclear Regulatory Commission under the authority embodied in 10 CFR

50.55a (g) (4) (iv). The required inspections are detailed in the American

Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code,

Section XI for Inservice faspection as embraced in 10 CFR 50.55a (b). For

any inspection program, the code edition and addenda used is determined in

- accordance with the requirements of 10 CFR 50.55a (g). For Palisades Power

Station the applicable code edition is 1983 with the Summer of 1983 _addenda

(a. k.a., 83S83). It was found during this inspection that the following

procedures had been revised to comply with the 1983 Edition with Winter of

1984 Addenda (a.k.a.,83W84) editic,m of the ASME code even though this

edition was not approved for use at the plant by the NRC: NDT-PT-01, Rev 9;

NDT-PT-02, Rev 5; NDT-RT-01, Rev 8; NDT-MT-01, Rev 7; NDT-UT-02,

Rev 4; NDT-UT-08, Rev 2. These procedures were revised in this manner in

-

-

order to be able to use them uniformly through out the Consumers Power

system; both at Big Rock Nuclear Power Station, Palisades Power Station in_

addition to their fossil fueled plants. No evidence was available showing that

a technical review of the procedures had been undertaken to determme if the

revision impacted any technical specification or quality commitment at the

plant. This is unresolved (50-255/92012-01) pending the licensees review.

Paragraph IWA 2120 and Mandatory-Appendix III, Paragraph 2300 (p) *

requires the approval of the ANI for all NDE procedures. This requirement

for approval includes, in the former paragraph, the requirement that each

'_,

procedure "shall include, as a minimum, the following information:* ... (p)

. approval of the procedure as reciuired by IW A 2120." This requires some

form of testimony on the procedure, that the ANI has approved the procedure.

The simplest way of fulfilling this obligation is by. having. the ANI sign* off the

procedure a~ a matter of course. Palisades. had no such testimony on the

procedures. The only proof that the ANI was involved in the process was a

. sheet with his signature listing a number of instances where each procedure*

had been used during an actual inspection. These inspections were dated .

approximately 11h to 5 months after the procedure was issued. Although the

code does not state specifically that the procedure must l:)e approved by the

ANI before use, the method submitted by Palisades does not preclude the use

of the procedure for 5 months without ANI approval. Had the ANI

disapproved the procedure it would fall to Palisades to prove that the*

procedure had not been used in the interim or, failing that, reinspect all the

items that had been inspected in the interim. Pending the licensees revision of

. the procedure to make_ them plant specific, this will remrun an unresolved

finding (50-233/ 92012-02).

The radiographic procedure at Palisades (NDT-RT-01, Revision 8) listed a . *

table in paragraph 10.6.3.l for double wall radiography. This procedure, as

noted earlier, . was revised to the Winter '84. Addenda to Section XI. The table

of paragraph 10.6.3.1, is a reflection of an earlier edition of ASME Section V,

Article 2.. The code has since dropped the table. It is no longer applicable to

Section V *(referred to by Section XI for radiography) either for the

Summer '83 or Winter '84 Edition of the code. According to the licensee the

table remained since the procedure was used in a fossil plant where it was still

applicable under ASNI B31.l for power piping. The table did not conform to

the current requirements of ASME Section XI and Section V, since it required

the use of a 25 penetrameter at 2T sensitivity for the thickness range of 1 to

and including 11/2 inches and the code requires that a 20 penetrameter at 4T

sensitivity be used in the range of 1 to and including l 1A inches, The licensee

was unable to give a satisfactory technical justification for this deviation from

the code and it remains as an unresolved item (50-255/92012-03).

5

The following procedures were reviewed by the inspection team:

Title

No./Rev.

Visual Examination

NDT-VT-01, Rev. 10

Liquid Penetrant Examination.

NDT-PT-01, Rev. 9

Liquid Penetrant Examination

NDT-PT-02, Rev. 5

Nonstandard Temperature

RadiOgraphic Examination of Welds

NDT-RT-01, Rev. 8 -

Ultrasonic Examination of Ferritic

NDT-UT-01, Rev. 8

and Austenitic Piping and Branch

Connection Welds

Magnetic Particle Examination

NDT-MT-01, Rev. 7

Ultrasonic Thickness Measurements

NDT-UT-02, Rev. 4

Ultrasonic Examination of Nuts, Studs,

NDT-UT-07, Rev. 4

Bolts and Pins

Ultrasonic Examination of Vessel Welds

NDT-UT-11, Rev. 1

Ultrasonic Examination of Nozzle-To-

NDT-UT-12, Rev. 1

Vessel Welds and Nozzle Inner Radius

Sections

Ultrasonic Examination of Reactor

NDT-UT-08, Rev. 2

Coolant Pump Flywheels of the Palisades

Nuclear Plant

Each procedure was reviewed for compliance with ASME Section XI and V

requirements to the 83983 edition. In addition, the results of examinations

were compared with these procedures for compliance with stated

commitments. With the exception of the previously noted findings, the

procedures were found to be in compliance with the requirements.*

6

2.2

ISI Program <73051)

It is the intent of ASME in formulating the requirements of Section XI for an

inservice inspection program to track iri.dications for trends; as well as detect

them ... This is reflected in ASME Section XI, Paragraph IWB 3131 (for class

1 and 3 piping) and Paragraph IWC 3131 (for class 2 welds).* Detailed in

these references is the stipulation to compare the current state of an indication

with its previous state. Volumetric and surface. examination results "shall be

compared with recorded results of the preservice examination and prior

. inservice examinations." Th.is is further strengthened in IWB 3131.1 and IWC

3131.1 when it'states that if the "volumetric or surface examination either

reconfirms the absence of flaw indications or reveals flaw indications that do

not exceed the acceptance standards listed . . .

11 the component shall be deemed *

acceptable for continued service. Palisades was not doing this analysis for all

indications; just those that were rejected. This makes Palisades far less able to

trend indications in the plant and develop an early warning system for any

generic category of indication. This is an unresolved finding pending the

licensees review of reports (50-255/92012-04).

The licensee has a written system that identifies a method of orientation for the

-- recording of indications on the final reports as required in ASME Section XI, *

Paragraph IW A-2610, and .this system meets the intent of the requirement. .

However the identification system does not include any requirement to

  • permanently mark the weld centerline. This is an important basis for

repeatability of the NDE and is further required in mandatory* appendix III,

paragraph III 4320. It is important enough for the code to dedicate a full page *

supplement to appendix III describing suggested ways of accomplishing the

marking system. The licensee has centerline marked welds as part of

modifications in safety systems but does not mark existing welds. -Pending the

licensees evaluation of a method for conclusively determining the centerline of .

. existing welds this will remain an unresolved item (50-255/92012-05).

2.3

  • ISi Data Review (73755)

The NDE evaluation of weld flaws, for acceptance, under Section XI is based

on the stress of the_ indication in a plane. If two flaws are located sufficiently

close to _each other they are considered to be one flaw, This evaluation is

required in Paragraph IW A 3300 as diagramed in Figure IW A 3330-1. The

final Palisades ISi penetrant report for weld ESS-12-SIS-2Bl-1 noted two, with

the assumption that round penetrant indications are as deep a 112 their

diameter). This is also an unresolved finding pending the licensees revision of

the report form and/or penetrant procedure to include the requirement to

determine flaw separation (50-255/92012-06).

Consumer Power NDE procedure NDT-UT-01 Rev 8 (not one of the -

procedures revised to 83W84) paragraph 10.6 requires the axial shear wave

scanning of welds-in two dire.ctions on the crown of and along the weld. The

7

procedure under paragraph 10.5, in compliance With Section XI para 111-4430

(a), requires the entire weld and HAZ be scanned by the longitudinal method

  • on the face of the weld if the weld can not be examined from two opposing

sides. According to the note on the ultrasonic report for weld ESS-12-SIS-2Bl

the weld could only be examined from one side due to restriction of a valve

taper on the opposing side. In addition the report notes that the_ longitudinal

scan could not be done due to weld crown configuration. If the longitudinal

scan could not be done with a 1/2" transducer it follows logically that a

transverse examination with the additional interference of a 45 degree

transducer shoe could not have been done. The failure to do the 45 transverse .

examination is not noted on the report nor is there any description as to what

is done with this weld since only one of four examinations was performed. It *

is very difficult to determine exactly what surface has been used to scan and

what direction since the requirement of ASME Section XI, para III-4500(t) is

not complied with i.e.: "The_following data shall be recorded on an

examination data sheet: ... (t) surface from which examination is conducted".

This weld examination had been. accepted by Consumers Power. Failure to

adequately document the inability to perform an inspection of the Code.

required weld volume is a violation of 10 CFR 50, Appendix B, Criterion

XVII (50-255/92012-07).

2.4

ISi Performance (75753)-

An 80% of DAC reflector (intermittent in length) was not recorded for weld

FWS-18-FWL-2Sl-243 per the requirements of ASME Section XI, para IWA-

2232 (b), CP Procedure NDT-UT-OL Rev 8, para 11.1 and ISi plan Rev 3,

Appendix 6A, Parts Band E. The licensee was unable to duplicate the NRC's

results in this regard. The equipment used by the licensee and the NRC was

essentially the same and the transducer was the same type, brand, size and

. frequency from the same manufacturer. The NRC Mobile NDE Laboratory*

subjected the two transducers to a frequency spectrum analysis. As can be

seen in Figure 1, below, the NRC transducer displays an evenly changing *bell

curve that contains no lobes, while in Figure 2 the licensee transducer shows

side lobes. The indication to the right in the diagrams is the amplitude display

from the same side drilled hole reflector used to obtain the spectrum scan.

..

8

.9999

1.563

3.125 *m

6.250

tGllfll* 9.375

10.94

12.50 *

31.5 . . . .

'

'

' . . . . . '

. . . ..

199Y.

I

I

I * t

I

I

I

I

I

I

I

I

I

~

0 1

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I _.I

I

I

I

I

,* I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I,

I

I

"1

I

I

I

  • ,

I

I

  • .I

25.2 I I I: I I I: I I: I I:*. I I; I I I; 1°1 I: I I I: I I I: I I I~ I I I; I I I; t I I: I I I: I I I; i I I 89

t

I

I

I

0

I

I

I

I

I

I

0

0

I

,

'

.

I

I 0: I

0 I: 0

I I:

I I: I

0 0: 0

°1 I: 0

I I: I

I I: 0

I

1 1 :

0 Io.: I

I I: I

I 0: I

I I: I l*I: I

0 I: I

I

I

1"

I

I

o"

I

f

I

I

I

I

I

I

I

I

I

A

M

P 18 9 ... ; ... ; .. ; ... ; ... ; ...

I

I

I

I

1

I

I I

I I. I

I I. I

I

I

I I

I

I

I I I, .* I

I

I

I I. I

I I. I

I I

I

I

I

61'.li

I

I

I

I

I

I

I

I*

,*

a

I

I

IA v

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

12 6

.

.

'. '

I

I

I ..

I

I

I

I

I

I ! I

I

'.

1

1

1

f 1

I

I

I

t

I

I

I

I

I

I

41'.li

    • 1 *** 1 ***. ! . , . ! *** , *** , *** , **. ! *.*., .... a

I

I

I

1

I

I

  • .t

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

1 t

I I

1

I

I I

1

I

1 1*1

1

1 I

I

I

I I

I

I

I I

I

I

I I

I

I

I I 1*1 I 29

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

0

I

I

I

I

I

I

I

0

~~~~~~~:t:cc:==~~~C.::.:?:i::cz::z::i:z:i:~~9

12.56

15.12

~ *20~24

[l!liJ

25.36

27.92

39.48

Figure 1

. ,9Q99

1.563

3 .125 w

35.4

6.259

tGllflJ

9;375

19.94

12.59

199X

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

,I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

j

I

I

I

I

I

I

I

I

I*, I

28 .3

I

I

I

I

I

I

I

I I-.

1

I

I

I

I

I

I

I

I

I

I

I

I

I

O

I

I

I

I

I

, I

I

I

I

0

I*

I

I

I

I

I

I

I

I

I

I

I.' 89

"

I

I

I

I I

I

I

I

.

I

I

n

I

I I: I

I I:

I

I

I

I

I I:; I I: I

I I: I

I I: I

I I: I

I I: I

I I: I

I

I

I

I I: I

I I: I

I I: I

I I: I

I

I

M

.

.

.

.

.

.

.

.

.

.

P 21 '2

I

I

I

I

I

I'. I

I

I

I

I

I

I

I

I

1

1

l.1

1

1 I

I

I

I

I

1

1.1 I

I

I

I

I

1

1

1

I

1

1

I

I

I

I

I

I

I

I

I

I

I

I

I

I.

I

I

I

I

I

I

I

I

I

I

I

I

0

0

I

I

I

I

I

0 If t

I

I

I

I

I

I

..

I

I

I I' I

I

I

1'

I

I

I

lft 14 2

.

'

'

'

'

'

.

.

'

I

I

1

I

o

1

I

I

I

o

I

I

I

I

I

I

I

I

I

I

I

I

I I' I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

.: ... :'.':'. ':' .. 69

I

I

I

I

41'.li

' * I ** ,. I*, * ' I ' * ' I ' * '

II

I

I

I

I

t

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

0

0

0

'

0 ':'

0 ':'

0

0 29

v 711 ::::.::.-:<:~.::::!:::!::::::::::.:::::::

I

I

I

I

I

- -

11U_o/\\-'JO./~........,.....,......

n

1i......;. ................................................................................................ .w.i;&.u;;;.:. ....... .;;o;;..,;;;,.,w;._..........;~ II

1.264

.9477

1.196

.1589

.3159

!!li1U

.6318 ~

I

Figure 2

The

11 A

11 scan is the one normally seen on the ultrasonic instrument. As can

be seen there is no apparent difference in the A scan. However the spectrum

display clearly shows that the damping material in the licensee transducer has

loosened to such a degree as to create ringing. This ringing leads to a .

reduction of sensitivity of the transducer and explains why the licensee* was

unable to duplicate the results of the NRC. The spectrum analysis performed

by the NRC is available on the instrument used by the licensee. The NRC

considers this another unresolved item since the licensee needs to dispose of *

the indication in the above weld and determine what other transducers might

be in inventory that suffer from the same deterioration. (50-255/92012-08).

9

Consumer Power procedure NDT-UT-01 Rev 8,. para 7.2.2.2 D. states:

"Search unit size, frequency, and angle shall generally be selected according to*

Table 1." Table 1 for a nominal material thickness of 1.00" to 1.5" lists a

transducer size *of 3/8" to 1 /2" iri size at an angle of 45 ° or 60 °. The

thicknesses listed on the final ultrasonic examination reports for welds* MSS-

36-MSL-2S 1-219, MSS-36-MSL-2Sl-217 and MSS-36-MSL-2Sl-218, are less~ .

than 1.5". According to the Consumer Power procedure a 1/2" or less

transducer would have been used. There are no weld, geometry or

. interference restrictions which would have caused any other choice of

  • transducer. However the welds were examined with a. l" diameter transducer.

The large 45° shoe of this transducer (2 1/8 ... long by 1 11/16" wide) along

with the wide crown of the minimally prepared surface of the* weld meant that

the required coverage of the 1/3 zone could .not be obtained on the first 1/2 *

node. Instead. of exercising the options contained in_ ASME Section XI Para

III-3230 (a) (1) and/or (2) along with.Consumer Power procedure NDT-UT-

01, Rev 8, para 7.2.3 A. and/or B., which would have guided them back to

the smaller transducer of their Table 1, they decided to exterid. the scan to a

full 1 and 1/2 nodes in order to obtain coverage. This means a sound path

that is 3 times longer than a smaller transducer with the inherent lose of

sensitivity to small indications.

The NRC examined weld 219 with a 1/2" diameter transducer using the first

. 1/2 node. This examination revealed an indication that is 26 '1 long and up to

100 % of the reference level. The nature of the indication seems to be

geometric but would require further examination to more fully categorize.

Consumer Power was made aware of this discovery and repeated the

  • examination with the 1" transducer and the transducer that was later

.

.

determined by the Nl{C to suffer from a loss of sensitivity. This remains an

unresolved item pending further evaluation by the licensee (50-255/92012-09).

3.0

Nondestructive Examinatfon (NDE)

During this inspection 48 welds and/or components located in 7 plant systems were

examined by nondestructive methods by the NRC. Selected areas from the SIRW,-

MSS, FWS, CVC, CSS, SIS, and LTC were independently examined by the NRC

utilizing various nondestructive methods. An evaluation of the licensee's quality

program, including NDE, was performed using NRC promulgated procedures in

conjunction with the licensee's approved procedures .

10

3.1

,Visual Examination (57050)

3.2

Thirty-Nine (39) safety related pipe weldments and adjacent base material (1/2

inch on either side of the weld) were visually examined in accordance with

NRC procedure NDE-10, Rev. 0, Appendix A; and associated site procedure

NDT-VT-Ol_Rev.10, QC documents, isometrics and as-bui~t drawings.

Examined-during this inspection were ASME Class 1, and 2 pipe weldments

selected from SIS, MSS, CVC, FWS and CSS. Inspections were performed

specifically to identify any cracks or linear indications, gouges, leakage, -arc

strikes with craters, or corrosion, which may infringe upon the minimum pipe

-wall thickness and modifications to piping or components. Mirrors, flash

lights, and w_eld gauges were used to aid in the inspection and evaluation of _

the examination.

Results: The welding and overall workmanship inspected was satisfactory. No

cracks, gouges, corrosion or any indication that may be detrimental to the

operation of those systems insp~ted, were revealed. *

Inspection Hanger/Support (57050)

During this inspection fiftee~ (15) safety related hanger/supports were visually

inspected per NRC procedure NDE-:10, Rev.O, Appendix A and B in

conjunction with site procedure NDT-VT-oi-R.ev.10, and QC documents and

associated isometric/drawings. Included in this inspection were hanger/supports

selected from the SIS, and CVC system. In the area of welds, the accessible

surface area and adjacent base metal for a distance of one-half inch on either

side of the weld was examined. In the area of component integrity, specific

attributes examined were proper installation, configuration, or modification of

supports, evidence of mechanical or structural damage, corrosion, bent, and

missing or broken members. Table #2 is a list of sp~ific hanger/supports

inspected._

Results: The overall condition of hanger/supports inspected was satisfactory.

-

-

-

1

-

3.3

Liquid Penetrant Examination (57060)

Twenty-six (26) safety related pipe weldments and adjacent base material (1/2

inch on either side of the weld) were examined using the visible dye, solvent

removable method per NRC procedure NDE-9, Rev.O, in conjunction with the _

licensee's procedure NDT-'-PT-01 Rev.9. Included in this inspection was

-

ASME Class 1 and 2 carbon and stainless steel pipe, ~ite _field and vender shop -

weldments selected from the SIS, CSS, CVC and LTC.

Results: The surface areas examined were properly prepared for the

examination. Interpretation of indications located in the same area needed to

be strengthened.

-

-*

11

3 .4 . Ultrasonic Examination (57080)

Nineteen (19) safety related pipe weldments were ultrasonically examined using NRC

procedure NDE-1, Rev. 1 in conjunction with the licensee's procedure* NDT-UT-01,

Rev. 8 and associated isometric drawings and ultrasonic.data reports. included in this.

_examination were ASME Class 1 and 2 pipe weldments selected from the SIS, FWS

and MSS. To* obtain the greatest possible repeatability, in performing the NRC

independent measurements the examinations were. performed utilizing transducers and

cables that matched those used by the licensee as closely as possible. A distance

amplitude correction curve was established utilizing Consumer Power calibration

standards 21 PAL, 44 PAL, 50 PAL and 14A PAL per procedure NDT-UT-.01, Rev.

8.

.

Results: The ultrasonic examinations performed by the licensee were at best

minimum by the ASME Code standard with many of the examinations performed

from one side of the weld. To be ctble to perform the required volumetric

examination the technician had to inspect areas of the weld using the third leg (or * 1

112 node) of the ultrasonic sound path. This. may cause problems in highly

attenuative materials such as stainless steel.

Section XI of the Code requires that longitudinal welds be examined at the

circumferential weld intersection for a length of 2.5 times the wall thickness. Upon

examination of welds MSS-36-MSL-ISI-211, MSS-36-MSL-2Sl-212, and MSS-36-

MSC-2Sl-219 on the main steam system, it was noted that the intersecting

longitudinal welds had not been examined and were not included in the licensee's ISi

program. Failure to examine these welds as required by the Code is a violation of 10

CFR 50.55a (50-255/92012-10).

Subsequent to the NRC identification of this issue, the licensee identified an add~tional

27 longitudinal welds which had not been included in* the ISi program. The licensee's

immediate actions were to perform the required examination of these welds.

3.5

Radiographic Examination (57090) *

. Radiographs for nine (9) *safety related pipe weldments recently completed in the *

SIRW line *were reviewed by the NRC inspectors. These included welds FW-110 to

arid including FW-118. The procedure and technique used to make the radiographs

was in accordance with site procedure, NDE-:10, Rev. 18. Approximately one-

hundred and twenty radiographs were reviewed for weld integrity, technique and

  • radiographic quality. Also reviewed were associated isometric/drawings and

radiographic data reports.

12

Results: Although no violations were identified and the radiographs and welds met the

stated requirements, it was noted that the reader sheets were very confusing. The *

industry practice of including one weld, and sequence of repairs, on one reader sheet

or radiographic report in one package of radiographs is not practiced at this plant. It

makes it very difficult to track the welds. In addition the welds are radiographed by

placing the film around the weld in keepirig with the fossil practice of 0, 60 and 120

degrees or 0, 120 and 270 degrees (depending on pipe size) even though the section

markers are in even increments of 1 inch. This leads to very odd sequences of for

example 4-12 on one weld and 2-10 on the next, since the 120 degree mark is not the

same as the 0 inch mark on each weld.

4.0

Erosion/Corrosion (49001)

Concerns regarding erosion/corrosion in balance of plant piping systems has

heightened as a result of the December 9, 1986 feedwater piping line rupture which

occurred at Surry. This event_ was the subject of the NRC Information No-tice 86-106,

issued December 16, 1986, and its supplement issued on February 13, 1987.

The licensee's actions with regard to the detection of erosion/corrosion in plant

components were reviewed with respect to NUREG-1344, "Erosion/Corrosion

Induced Pipe Wall Thinning in U. S. Nuclear Power Plants", dated April 1989,

Generic Letter 89.;08 issued May 2, 1989, and NUMARC Technical Subcommittee

_ Working Group on Piping and Erosion /Corrosion Summary Report, dated

June 11, 1987. The licensees -procedure, EM-09-08, Rev.2, outlines the minimum

requirements for the erosion/corrosion program. Tbe areas that were reviewed by the

NRC were system selection, component selection, ultrasonic inspection, and data

evaluation.

The selection of systems to be model~ were based on the systems susceptibility to

erosion/corrosion (flow velocity, steam quality, material of the components and

temperature). The parameters used to identify those systems are similar to those used

by EPRI for the CHECMATE program. The computer program used at Palisades to

model the systems is Krautkramers PIPE program. Fourteen systems were selected to

be modeled by the computer program. Modeling determines the ranking of

component susceptibility to erosion/corrosion. The component ranking goes from the -

highest projected wear rate to the lowest projected wear rate. Only the components

with the highest wear rates will be inspected for wall.thinning.

-

Ultrasonic thickness inspection is used to locate areas of wall thinning. -Five

components, (item numbers 6.8.BB, 5.2, 9.lB, 6.18B and 6.18Bl) were

independently inspected by the NRC to determine the accuracy of the licensees

measurements. The thickness readings the NRC obtained* matched those of the

licensee .

The ultrasonic data was entered into Krautkramers DA TAMATE computer program

for reporting and evaluation. If the component had a remaining wallthickness greater

than code minimum wall, it was accepted. If the remaining wall thickness was less

  • than code minimum, engineering analyses is performed per Palisades J\\dministrative

13

Pr.ocedure 9.11. * Accordirig to the Palisades program, EM-09-08, if the highest

ranked components are found acceptable after three consecutive outages, the system

no longer needs to be inspected for wall thinning

Results The program has a potential to be comprehensive. . One weakness in the

program is the failure to update the computer model with current plant data. Not

updating the model will give false predication of time to thickne~s critical or T crit.

Another weakness is the failure to inspect components with low susceptibility ranking.

The use of engineering judgement and industry experience could highlight low

ranking components which have had problems in the past and may never be inspected

according to this program. .

An effective erosion/corrosion program should be a "living" procedure with_

continuously updating and inputting data to accurately predict component .failures.

Palisades erosion/corrosion program does not have the flexibility to change with the

plant changes. *

14

5. 0

Examination Results

I

NRC INDEPENDENT MEASUREMENTS

I

TABLE N0.1

WELD ID. No.

SYS

NONDESTRUCTIVE TEST I

SHT.# 1 I

on.

OR

ISO/DRAWING

LIN

E

CL

RT EI:JWEJWEJ

ESS-6-SIS-lBl-4

SIS

1

x

x

x

x

ESS-2-SIS-lAl:.6

SIS

1

x

x

x

ESS-2-SIS-lAl-7

SIS

1

x

x

x

ESS-2-SIS-lAl-18

SIS

  • l

x

x

x

ESS-(i-SIS-1B6-204

SIS

2

x

x

x

ESS-8-SIS-2B6-201

SIS

2

x

x

x

ESS-6-SIS-lHP-224

SIS

2

x

x

x

ESS-i2-SIS-1A5-218

SIS

2

x

x

x

ESS-12-SIS-1 eS-220

SIS

2

x

x

x

ESS-12-SIS-leS-221

SIS

2

x

x

x

ESS-12-SIS-2Bl-2

SIS

2

x

x

x

x

ESS-12-SIS-2Bl-1

SIS

2

x

x

x

x

ESS-2-LTe-1 B-32

LTe

. 1

x

x

x

ESS-2-LTe-lB-33

LTe

1

x

x

x

eVC-2-LDL-2B5-2

eve

1

,

x

x

x

eVC-2-LDL-2B5-1

eve

1

x

x

x

FWS-1~-FWL-lSl-244 *

FWS

2

x

x

x

FWS:-18-FWL-2S 1-243

FWS

2

x

x

x

MSS-36-MSL-lSl-211

MSS

2

x

x

x

MSS-36-MSL-2S 1-212

MSS

2

x

x

  • X

MSS-36-MSL-2Sl-219

MSS

2

x

x

x

..

15

.,

NRC INDEPENDENT MEASUREMENTS

TABLE NO. 1

WELD ID. No

SYS

NONDESTRUCTIVE TEST

SHT.# 2

OR

OR

ISO/DRAWING

LIN

CL

RT

UT

PT

M,

VT

AC

REJ

E

T

c*

ESS-14-CSS-IPA-201

css

2

x

x

x

~

ESS-14-CSS-IPA-202

css

2

x

x

x

...

ESS-l 4-CSS-IPA-203

css

2

x

x

x

ESS-14-CSS-IPA-'208

css

2

x

x

x

ESS-10-CSS-IPA-209

css

2

x

x

x

ESS-14-SIS-LPA-216

SIS

.2

x

.x

x

MSS-36-MSL-lSI-217

MSS

2

x

x

x

MSS-36-MSL-2SI-218

MSS

2

x

x

x

  • MSS-36MSL-2SI-213

MSS

  • 2

x

x

x

MSS-36-MSL-1SI-210

MSS

2

x

x

x

MSS-36-1 SI-MSL-216

MSS

2

x

x

x

'

FWS-l 8-FWL-lSI-242

FWS*

2

x

x

x

FWS-l 8-FWL-2SI-242

FWS

2

x

x

x

MSS-36-MSL-lSI-208

MSS

2

x

x

x

MSS-36-MSL-2SI-208

MSS

i

x

x

x

ESS-6-SIS-CHR-225

SIS

2

x

x

x

x

  • ESS-6-SIS-CHR-226

SIS

2

x

x

x

x

  • ESS-lO-CSS-lPA-227

css

2

x

x

x

16

,.

NRC INDEPENDENT MEASUREMENTS PROGRAM

HANGER/SUPPORTS

TABLE2

IDENTIFICATION.

SYS

CL

AC ' REJ

COMMENTS.

c

ESS-12-SIS-lBl-7PR

SIS

B

x

ESS~ 12-SIS-2Al-4PR

SIS

A

x

ESS-12-SIS-2Al-6PR.

SIS

A

x

ESS-12-SIS-2Bl-6PR

SIS

B

x

ESS-6-SIS-2HP-PR 1

SIS

B

x

ESS-6-SIS-2HP-PR2

SIS

B

x

ESS-6-SIS-2HP~ PR3 *

SIS

B

x

ESS~6-SIS-2HP-PR4.

  • SIS

B

x

ESS-6-SIS-2HP-PR5

SIS

B

x

ESS-6-SIS-CHR-236PR

SIS

A

x

ESS-6-SIS-CHR-234-1

SIS

A

x

ESS-6-SIS-CHR-234-2

SIS

A

x

ESS-6-SIS-CHR-223PR

SIS

B

x

ESS-6-SIS~CHR-226PR

SIS

B

x

ESS-14-CSS-IPA-201PR

css

B

x

. *~

. '"

17

6.0

Persons Contacted-

Consumers Power Company

Tom Fouty

Tom Newton

Dennis Ziegler

Richard Humphrey

James Schepes

P. Donnelly .

R.Orosz

Richard Kasper *

. R. Van Wagner

James Kuemin

Systems Engineer

Nuclear Operations

Special Projects

NDT Supervisor

Assessment Specialist

Plant Safety and Licensing

Nuclear Engineer

Maintenance Manager

Systems Engineer

Licensing

U.S. Nuclear Regulatory Commission

R. Rodin

John Jacobson

Jerry Schapker

Jacque Durr*

Resident Inspector Riii

Chief, Engineering Brah ch Riii

Reactor Inspector Riii

Chief Engineering Branch RI

The above listed personnel were present at the.exit meeting. The inspector also

'

contacted other administrative and technical personnel during the inspection.

7.0

Unresolved Items

Unresolved items are matters about which more information is required in order to

ascertain whether they are acceptable items or violations.

8.0

Management Meetings

Licensee management was informed of the scope and purpose* of the inspection at the

entrance interview on March 23, 1992. The findings of the inspection were discussed

with the licensee representatives during the course of the inspection and presented to .

licensee management at the exit interview. The licensee did not indicate that

  • proprietary information was involved within the scope of this inspection.

..

.

'**

..

..... *

  • 'II

13:58

PRLI~;ADES RES.: DEl'ff WSPEC. CIFF,

consumers

Power

l'llWllUR

M1£11111All'I,.,.,,,,,...,

ENCLOSURE.4

  • P*llHdH Nual11r Pte111: 27780 llut 9ttr Memori*I lilg!iwey, Ccwtn, Ml 49043

JCA 34*92

May 29, 1992

John V. Massey

Sierra Nuclear Corporation

S619 Scott* Vall*y Drive #240

Scotti Valley, CA

9'066

,

Subj*ct:

Palisade* Nuclear Plant

Dry Fuel Storage Projfllct

F'. 02

A.a a r**ult of the NRC audit exi.t meeting May 28, 1992, uveral i.uuu were

id*ntified regarding th* ~**pon~1bi11ti*1 and implementation of the Quality

Anul:'ance Plan for fabrication (if 'dry futl atorage ca*.ka.

Therefcu, in

acccrd.ance with our t*hphone c~:inve*uation today, .May 29, 1992 at 11:30 a.m.

EST, you are direot*d to.cea1e B11 work, effecti~e immediately, r~lating to

fab:i;'ication and con1t~uction of oa1ka until thas*. iaauea are 1atiefaccorily

~~*olved. You will' be notifi*d in writing by this office when work activities

may b* reconvened,

Sincer*ly,

John c. Amthar, P, E.

1

.

Canatruction S~p*r1nt*ndent

CC: ==.w~l

Rl>Oro1z, Pali1ade1

TJPalmi1ano 1 Pali1ad**

JPPomar&n1k1, Pali1ade1

OJVandaWalle, Pali1ad**

ERVanHoof, P26*302B