Docket No. 50-255 Serial No. PAL-89-010
- Mr. Kenneth W. Berry Director, Nuclear Licensing Consumers Power Company 1945 West Parnall Road Jackson, Michigan 49201
Dear Mr. Berry:
June 30, 1989 *
SUBJECT:
ACTION ITEMS FROM MARCH 30, 1989 TELECON - COMPLIANCE WITH 10 CFR 50.62 (TAC NO. 59123)
On March 30, 1989, the staff held a telephone conference call with Consumers Power Company representatives with the objective of discussing Class lE qualification of equipment proposed to be used by the Palisades Plant ATWS mitigation/prevention circuits. The enclosure to this letter contains notes of the call, the resulting action items, and a'statement relating to staff's conclusion regarding review prior to implementation of the ATWS circuits.
Compliance of equipment qualification with 10 CFR 50.62 will be determined by a post-implementation inspection.
Enclosure:
As stated cc w/enclosure:
See next page DISTRIBUTION:
Docket File NRC & Lotal PDRs PD31 R/F MVirgilio PShuttleworth ADeAgazio OGC EJ.ordan BGrimes ACRS (10)
Hli
-~907100177 8906jci PDR ADOCK n~nQO?~~
P
-~-
~Be-Sincerely,
~ginat signed by Albert W. De Agazio, Senior Project Manager Project Directorate III-1 Division of Reactor Projects - III, IV, V & Special Projects Office of Nuclear Reactor Regulation O!Jl{)/
I PM/PD31:DRSP ADeAgazio (A)D/PD3f :DRSP L Yan de 11 *:!VJ 61'f!f89 I
61)7189
--~
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 Docket No. 50-255 Serial No. PAL-89-010 Mr. Kenneth W. Berry Director, Nuclear Licensing Consumers Power Company 1945 West Parnall Road Jackson, Michigan 49201
Dear Mr. Berry :
June 30, 1989
SUBJECT:
ACTION ITEMS FROM MARCH 30, 1989 TELECON - COMPLIANCE WITH 10 CFR 50.62 (TAC NO. 59123)
On March 30, 1989, the staff held a telephone conference call with Consumers Power Company representatives with the objective of discussing Class lE qualification of equipment proposed to be used by the Palisades Plant ATWS mitigation/prevention circuits. The enclosure to this letter contains notes of the call, the resulting action items, and a statement relating to staff's conclusion regarding review prior to implementation of the ATWS circuits.
Compliance of equipment qualification with 10 CFR 50.62 will be determined by a post-implementation inspection.
Enclosure:
As stated cc w/enclosure:
See next page Sincerely, aad~/~*
Albert W. ~g~zio, ~~;:~~oj~t Manager Project Directorate III-1 Division of Reactor Projects - III, IV, V & Special Projects Office of Nuclear Reactor Regulation
Mr. \\Kenneth W. Berry Consumers Power Company cc:
M. I. Mi 11 er, Esquire Sidley & Austin 54th Floor One First National Plaza Chicago, Illinois 60603 Mr. Thomas A. McNish, Secretary Consumers Power Company 212 West Michigan Avenue Jackson, Michigan 49201 Judd L. Bacon, Esquire Consumers Power Company 212 West Michigan Avenue Jackson,.Michigan 49201 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137 Jerry Sarno Township Supervisor Covert Township 36197 M-140 Highway Covert, Michigan 49043 Office of the Governor Room 1 - Capitol Building Lansing, Michigan 48913 Mr. Gerald B. Slade Plant General Manager Palisades Plant 27780 Blue Star Memorial Hwy.
Covert, Michigan 49043 Resident Inspector c/o U.S. Nuclear Regulatory Commission Palisades Plant 27782 Blue Star Memorial Hwy.
Covert, Michigan 49043 Palisades Plant Nuclear Facilities and Environmental Monitoring Section Office Division of Radiological Health P.O. Box 30035 Lansing, Michigan 48909 I
1
~
TELEPHONE CONFERENCE CALL WITH CONSUMERS POWER COMPANY MARCH 30, 1989 The main purpose of these notes 1s to document the Action Items agreed upon in a telephone conference call (telelcon) with Consumers Power Company, licensee for the Palisades Plant, held on March 30, 1989, By letter dated June 20, 1987, the licensee forwarded to the NRC a seismic report issued to Telemecanique, Inc. supporting the claim of qualification for the* JlO series relay as qualified Class lE device. The licensee proposes to use the relay in safety-related circuits and also use it as a qualified isolation device between safety-related circuits and non-safey-related circuits.
During the telecon, the licensee was infonned that the Telemecanique report did not invoke 10 CFR Part 50, Appendix B and 10 CFR Part 21 for Class lE devices and did not specifically identify the relay models tested or in use at the Palisades Plant. The report also did not properly address how modifications to these relays would be handled.
In addition to discussing the seismic report, the licensee told the staff that an equipment change has been made in the ATWS circuits. The licensee had planned to replace the existing dual setpoint indicators with triple setpoint indicators; however, the triple setpoint indicators failed the seismic tests and now the licensee is planning to use Rochester Instrument Systems (RIS) Model ET-1219.
The licensee indicated that the ET-1219 may also be used as an isolator.
The Action Items agreed to by the licensee are:
- 1.
The licensee will up-grade the seismic. report on the Telemecanique relay to include all of the criteria required for the qualification of a Class lE device and to identify the specific relays in use in the ATWS circuits.
- 2.
The licensee will provide the qualification reports for the RIS Model ET-1219 setpoint generators.
- 3.
For any device to be used as an isolator, the licensee will qualify the device to the criteria contained in Attachment 2 to the 11-3-86 RAI. This is in addition to the IEEE 323 and 344 qualification of Class lE equipment.
The staff has concluded that the above mentioned reports need not be submitted for staff review prior.to the implementation of the ATWS c.ircuits by but instead should be made available at the Palisades Plant for staff review during an onsite post-implementation of the ATWS circuits.