ML18046A514

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-255/80-20 on 801103-26,1201-05 & 810116. Noncompliance Noted:Procurement Documents Did Not Ref Applicable Regulatory Requirements or Necessary QA Program Requirements
ML18046A514
Person / Time
Site: Palisades 
Issue date: 02/06/1981
From: Baker K, Gildner M, Jackiw I, Schulz R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML18046A511 List:
References
50-255-80-20, NUDOCS 8103190278
Download: ML18046A514 (31)


See also: IR 05000255/1980020

Text

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report No. 50-255/80-20

Docket No. 50-255

Licensee No. DPR-20

Licensee:

Consumers Power Company

212 West Michigan Avenue

Jackson, MI

49201

Facility Name:

Palisades Nuclear Generating Plant

Inspection At:

Covert, Michigan and Jackson, Michigan

Inspection Conducted:

November 3-26, December 1-5, 1980

Inspectors: ~~

- 1!7-1! ___ Jt.~t~

>i
Jir .... 1 Jackiw

//

~9f(_A...t1

R. D. Schulz

~--*

f M. L. Gildner

__

Approved By: ~

Nuclear Support Section 2

Inspection Summary

and January 16, 1981

-zjp;

/-S- 6!

2 -s-(f I.

  1. 1
  • ~dd-1

I

Inspection on November 3-26, December 1-5, 1980 and January 16, 1981 (Report

No. 50-255/80-20)

Areas Inspected:

Announced routine inspection of the licensee's implementation

of the Quality Assurance Program in the following areas:

QA/QC administration;

qualification of personnel; design changes and modifications; records control;

receipt, storage and handling; tests and experiments; procurement control;

document control; offsite review committee; audits; test and measurement*

equipment; surveillance and calibration; maintenance; nonroutine reporting;

and corrective action.

The inspection involved a total of 353 inspector-hours

onsite by four NRC inspectors including 0 inspector-hours onsite during off-

shifts.

The total inspector-hours also included 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> of inspection at

the licensee's corporate office by three NRC inspectors.

Results:

Of the fifteen areas inspected, no apparent items of noncompliance

or deviations were identified in six areas, ten items of noncompliance were

identified in nine areas (failure to reference applicable regulatory require-

ments in procurement documents - paragraph 7; failure to follow procedures

regarding nonconforming material reports - paragraph 8; failure to establish

measures for record control - paragraph 9; failure to provide timely review

of temporary procedure changes - paragraph 10; failure to control revisions

to drawings - paragraph 10; failure to adequately control purchased material

- paragraph 7; failure to perform required audits - paragraph 12; failure to

adhere to a technical specification requirement - paragraph 15; failure to

adhere to procedures - paragraph 6; and failure to implement corrective action

measures - paragraphs 15 and 17) .

- 2 -

DETAILS

1.

P~rsons Contact~d

R. W. Montross, Plant General Manager

H. J. Palmer, Technical Superintendent

G. G. Butler, I & C Engineer

C. H. Gilmer, Maintenance Superintendent

R. E. Mc Caleb, Quality Assurance Administrator

W. S. Skibitsky, Operation Superintendent

J. S. Rang, Operations/Maintenance Superintendent

G. C. Cheeseman, Quality Control Supervisor

M. M. Wilson, GPMD Field Representative

E. C. Huss, Material Services Supervisor

J. H. Dearth, I & C Supervisor

J. W. Roe, Calibration Supervisor

P. Wick, Document Control Center Supervisor

N. Hough, Training Supervisor

R. E. Mieras, Shift Supervisor

C. Thomas, Mechanical Maintenance Supervisor

J. F. Firlit, Director, QA-NO

J. J. Fremeau, QA Administrator - General Office

D. A. Bixel, SARE Chairman

D. P. Hoffman, Nuclear Licensing Administrator

S. R. Frost, Assistant Nuclear Licensing Administrator

P. T. Howe, Instrument and Measurement Services Supervisor

V. A. Anderson, Procurement Manager

K. W. Berry, Nuclear Activities - General Office

The inspectors also interviewed other licensee employees including

engineering and administrative personnel .

. On January 16, 1981, a management meeting was held in Consumers Power

Company corporate office in Jackson, Michigan.

The purpose of the

meeting was to discuss the findings identified during the Quality

Assurance inspection.

Attendees included the following:

NRC Region III

K. R. Baker, Chief, Nuclear Support Section 2

I. N. Jackiw,. Reactor Inspector

R. D. Schulz, Reactor Inspector

Consumers Power Company

R. B. DeWitt, Vice President, Nuclear Operations

J. G. Lewis, Director, Nuclear Services Department

J. F. Firlit, Director, Quality Assurance

D. A. Bixel, SARE Chairman

D. P. Hoffman, Licensing Administrator

- 3 -

S. R. Frost, Palisades Licensing Engineer

J. J. Fremeau, Quality Assurance Administrator

R. E. Mc Caleb, Palisades Quality Assurance Administrator

T. L. Briningstool, CPCo Testing Lab

F. S. Rettenhouse, Manager, Lab Services

J. A. Schneider, Manager,.Construction (GPMD)

2.

Licensee Action on Previous Inspection Findings

(Closed) Unresolved Item (50-255/78-30):

Reporting complet{on s~atus

of "open" items to SARE.

The inspector found that all open items are

reviewed during each quarterly SARE meeting.

(Open) Unresolved Item (50-255/78-30):

Auditing of QA Program for

adequacy as apposed to status. Refer to discussion in section 3 of

this report.

(Open) Unresolved Item (50-255/78-30):

Ballot type review process

used by SARE and PRC.

Refer to discussion in section 11 of this report.

(Closed) Unresolved Item (50-555/78-30):

Adequacy of jumper control

program vs. ANSI N18.7 requirements.

The following items were verified

by the inspector:

(1) jumpers used during non-routine operating, test

and maintenance functions are documented on a Jumper, Link and Bypass

Control Checklist.

Independent verification of jumper placement and

removal is performed at the time that tags are placed on the affected

equipment and (2) with regard to testing requirements, placement and

removal operability checks are performed.

These activities are documented on the Juinper Control Checklist.

3.

QA/QC Administrative Program

The licensee's program for administration of the QA/QC program was

inspected.

This included program boundary, QA/QC procedure control

and the mechanism for evaluating the QA program.

a.

Documentation Reviewed

QAPP No. 2, Quality Assurance Program

QAPP 2-52, Classification of Safety-Related Items and Operational

Safety Actions

QADPII-3, Review of Q-List

QADPV-1, Preparation, Review and Revision of Quality Assurance

Department Procedures and Program Procedures for

Operations

b.

Findings

No items of noncompliance or deviations were identified.

- 4 -


-

c .

Discussion

During a management inspection conducted by the Performance

Appraisal Branch (Inspection Report 50-255/78-30), it was noted

by the inspection team that the licensee was not evaluating the

adequacy (effectiven~ss) of their QA Program.

The licensee had

periodically used an outside contractor to perform a corporate

audit of the implementation of its program, but these corporate

audits did not assess the adequacy of the QA Program in achieving

its objectives.

This issue has not been resolved and is still identified as an

unresolved item.

Also, during discussions with licensee personnel the inspector

was informed that the licensee is in the process of revising

the Quality Assurance Program Policy Manual.

The revision will

include many changes to the program and will require submittal

to the NRC prior to implementation.

The inspector reviewed a draft copy of Quality Assurance Policy 1

and noted that one change being considered by the licensee is to

give the QA Department authorization to stop work to achieve the

appropriate corrective action.

The current revision states that

the QA Department can only recommend stoppage of.work.

4.

Qualification of Personnel Program

The inspector reviewed the licensee's administrative controls to

ascertain their *conformance with the regulatory requirements and

commitments made in the Quality Assurance Program.* The program w_as

reviewed to determine that controls have been established requiring

.minimum educational, experience, and qualification requirements for

the plant staff and that responsibilities have been assigned to assure

that these requirements will be satisfied.

a.

Documentation Reviewed

b .

QAPP No. 2, Quality Assurance Program

QAPP 2-54, Training for Operations

QADP 11-1, Training and Indoctrination of Quality Assurance

Department Personnel

QADP 11-2, Quality Assurance Indoctrination and Training of

Personnel

AP 130, Master Training Plan

Findings

No items of noncompliance or deviations were identified.

- 5 -

c .

Discussion

QADP II-1, provides instructions for the indoctrination and

training of Quality Assurance - Nuclear Operations (QA-NO) De-

partment personnel.

With regard to QC personnel, this procedure

states that Quality Control personnel are trained and certified

according to applicable sections of the plant manual and that the

QC Supervisor is certified a Level III by the Director, QA~No.

The inspe_ctor noted that the QC Supervisor is certified a

Level II and not a Level III as required by the department proce-

dure.

This observation was discussed with licensee representatives

during the exit interview.

Also, during the *exit interview, the

inspector stated this is an example where requirements are imposed

on the plant without an apparent evaluation of what impact the

requirement has.

5.

Design Changes and Modification Program

The inspector reviewed the Design Change and Modification Program to

ascertain whether the licensee is implementing a QA program that is in

conformance with the Consumers Power Company Quality Assurance Program,

ANSI Nl8.7 and 10 CFR SO, Appendix B.

The review of documents, listed below, included a verification of the

following:

Procedure to control design and modification requests have been

established.

Procedures and responsibilities for design control have been

established.

Responsibilities and controls to assure that design changes and

modifications will be incorporated into plant procedures and plant

drawings have been established.

Channels of communication between design organizations and responsible

individuals have been established.

Controls requiring that** implementation of approved design changes be

in accordance with approved procedures have been established.

Methods for reporting design change/modification to the NRC in

accordance with 10 CFR 50.59 have been established.

a.

Documentation Reviewed

QAPP No. 3, Design Control

QAPP 3-51, Design Control

QAPP 3-53, Minor Modification, Specification Field Changes and

Set Point Changes

-

6 -

QAPP 6-52, Distribution and Revision Control of Design Documents

QAPP 10-51, Maintenance and Minor Modification Inspection

QCP-P-09, Facility Change Completion Review

QADP-III-1, Review of Design Change Documents

AP 9.1, Plant Modifications - Minor

AP 9.2, Equipment Specifications and Minor Field Changes

b.

Findings

No items of noncompliance or deviations were identified.

c.

Discussion

'

The inspector found that on April 28, 1980, Maintenance Order (MO)

80-EPS-053 was performed to correct a problem where the plant

diesel generators 1 and 2 failed to auto start during a turbine

trip function on CL-36.

The cause of the problem was the failure

of the 362 AST relay.

The corrective action taken during this

maintenance activity consisted of removing the failed 362 AST

relay and replacing it with two Agastat relays 362 R/AST and

362 L/AST.

This installation required that these relays be

rewired and that drawings E-121 and 950SB9 be revised.

During the review of this maintenance package, the inspector was

unable to determine that a SFC was initiated.

The SFC was not

noted on the HO located in the maintenance department files.

Prior to the conclusion of the inspection, the inspector was

informed that SFC 80-120 had been written for this MO.

No

problems were noted during the review of the SFC.

6.

Test and Experiments Program

The test and experiments program was reviewed to verify that the

established administ~ative controls and their implementation comply

with the applicable requirements specified in the Palisades Nuclear

Generating Plant Technical Specifications and 10 CFR 50.59.

a.

Documentation Reviewed

The following Quality Assurance Program Policies, Quality

Assurance Program Procedures for Operations, Palisades Nuclear

Plant Administrative Procedures, and Palisades Nucleai Plant

Engineering Manual Procedures were reviewed to verify:

the

establishment of a mechanism for handling requests or proposals

for safety related test and experiments; requirements to utilize

approved procedures; assignment of responsibilities for review

and approval of test and experiment procedures; establishment of

- 7 -

a system for review of proposed test and experiments to determine

whether they are described in the FSAR; assurance that a written

safety evaluation is developed for applicable test and experiments;

and assignment of responsibility for reporting al.l test and

experiments conducted pursuant to 10 CFR 50.59.

QAPP No. 11, Test Control

QAPP No. 20, Program Reporting

QAPP 11-51, Test Control for Nuclear Operations

AP 3.0, Review and Audit

AP 6.0, Technical Administration

AP 10-1, Appendix A-5 Working Procedures

EMP-14, Special Test Procedures

b.

Findings

Noncompliance

Palisades Nuclear Generating Plant Technical Specification para-

graph 6.8.1.C states that written procedures shall be established,

implemented and maintained covering surveillance and testing

activities of safety-related equipment.

Quality Assurance Program Procedure for Operations No. 11-51,

Test Control for Nuclear Plant Operations, Section 5.7 states

in part that special test or experiments are conducted in

accordance with written procedures.

Contrary to the above, Special Test T-131B for the Endurance Test

of Steam Driven Auxiliary Feedwater Pump P-BB was not performed in

full compliance with the approved procedure.

Step 5.5 required a

pump cooldown period of at least eight hours.

Test data was taken

after a cooldown period of seven hours and fifty five minutes.

Step 5.2 and Attachment 1, Test Equipment Data Sheet, are missing

verification signatures as required by the approved procedure.

The completed and signed off Administrative Review and Technical

Review did not note the above problems.

During discussions with plant personnel, the inspector emphasized

that the significance of this noncompliance was the lack of a

strong review process.

The completed special test procedure had

gone through three levels of review and the missing verification

signatures had not been identified as discrepancies .

- 8 -

c.

Discussion

Palisades Nuclear Plant Administrative Procedure No. 6.0, Technical

Administration, Section 5.3.1 requires that the Supervisor/Engineer,

charged with conducting a special test, will upon completion of his

review, prepare a report and forward copies to the Plant Super-

intendent, the Technical Superintendent, the Plant Review Committee

and the Special Test File.

Several tests which were performed over

six months previous to the inspection still had not had reports

written and on file.

The reports should be written within a

reasonably short period of time to preclude the loss of detail

not reflected in test data sheets.

7.

Procurement Program

The procurement program was reviewed to ascertain its conformance with

regulatory requirements and commitments in the operational quality

assurance program.

Procurement documents were checked for technical

requirements, QA program requirements, 10 CFR 21 provisions, specific

identification of items, and statements concerning access to the

supplier's plant or records for purposes of audit.

Procedures were

reviewed to determine if responsibilities were assigned in writing

for: (a) initiation of procurement documents (b) review and approval

of procurement documents (c) making changes to procurement documents

and (d) basis for classification of procurement items.

An approved

vendors list was examined, along with the evaluation of suppliers

after being placed on the approved suppliers list.

Procurement

documents for various systems were checked, along with the supplied

materials documentation, ~ncluding traceability to the item.

a.

Documentation Reviewed

QAPP 4-51, Procurement

QAPP 7-51, Supplier Evaluation and Selection

QAPP 7-52, Source Surveillance and Inspection

QADP IV-1, Review of Procurement Documents

QADP IV-2, Procurement of Materials and Services

QADP VII-1, Source Surveillance and Inspection

QCP~P-06, Source Inspection

CMP 13-1, Procurement Process - General

CMP 13-2, Procurement of Material

Policy No. 4, Procurement Document Control

Policy No~ 7, Control of Purchased Material, Equipment and Services

- 9 -

b.

Findings

Noncompliance

(1)

10 CFR SO, Appendix B, Criteria IV, states, "Measures shall

be established to assure that applicable regulatory require-

ments, design bases, and other requirements which are

necessary to assure adequate quality are suitably included

or referenced in the documents for procurement of material,

equipment, and services, whether purchased by the applicant

or by its contractors or subcontractors.

To the extent

necessary, procurement documents shall require contractors

or subcontractors to provide a quality assurance program

consistent with the pertinent provisions of this appendix."

The following procurement documents did not reference a QA

program:

P. 0.

85378

30947

46324

23660

45113

1001-6797

1001-5489

1001-6960

1001-8792

1000-3215

1817913-Req. No.

1017944-Req. No.

1001-4411

1001-2796

1025786-Req. No.

1000-1463

1001-6528

UNIT

Sleeve Shaft

Motor

Motors

Shaft

Valve Discs/Disc Arm

Fittings

Fittings

Weld Rod

Valve

Impellars

Pump Shaft

0-Ring

Weld Rod

Fittings

Bevel Gear/Shaft Assy.

Dragon Valves (GPMD)

Asco Check Valve (GPMD)

USE

LPSI Pump

Diesel Engine Generator

LPSI Pump, Charging Pumps

HPSI Pump

Main Steam Isolation Valve

Ordered to ASME B & PV Code,

Section III, NC, 1974

Ordered to ASME B & PV Code,

Section III, NB, 1974

Ordered to ASME B & PV Code,

Section III, NB, 1974

Steam Dump Valves

HPSI Pump *

Chemical & Volume Control

Ordered to ASME B & PV Code,

Section III, NGA

Ordered to ASME B & PV Code,

Section III, NB, 1974

Ordered to ASME B & PV Code,

Section III, NB, 1974

Control Rod Drive System

Recirc. Pump

Recirc. Pump Trip

The following procurement documents did not reference 10 CFR 21:

P.O.

ITEM

1001-6797

Fittings

1001-5489

Fittings

- 10 -

USE

Ordered to ASME B & PV Code,

Section III, NC, 1974

Ordered to ASME B & PV Code,

Section III, NB, 1974

1001-6960

Weld Rod

1001-8792

Valve

1000-3215

Impellars

Ordered to ASME B & PV Code,

Section III, NB, 1974

Steam Dump Valves

HPSI Pump

1017913 Req. No.

Pump Shaft

Chemical & Volume Control

Ordered to ASME B & PV Code,

1017944 Req. No.

0-Ring

1001-4411

Weld Rod

1001-2796

Fittings

Section III, NCA

Ordered to ASME B & PV Code,

Section III, NB, 1974

Ordered to ASME B & PV Code,

Section III, NB, 1974

(2)

Noncompliane

ITEi'l

10 CFR 50, Appendix B, Criterion VII states:

"Measures

shall be established to assure that purchased material,

equipment, and services, whether purchased directly or

through contractor and subcontractors, conform to the

procurement documents.

These measures shall include pro-

visions, as appropriate, for source evaluation and selection,

objective evidence of quality furnished by the contractor

or subcontractor, inspection at the contractor subcontractor

source, and examination of products upon delivery.

The

effectiveness of quality by contractors and subcontractors

shall be assessed by the applicant or designee at intervals

consistent with the importance, complexity, and quantity of

the product or services.

Quali~y Assurance Program Policy No. 7 - Control of Purchased

Material, Equipment and Services states in section 3.2,

"Selection of suppliers is based on the quality assurance and

technical evaluations and the capability of t.he supplier to

provide established procurement requirements."

The following items did not meet the-procurement document

but were accepted and released for installation and use.

PURCHASE ORDER

NON CONFORMANCE

Sleeve Shaft

Plug valves

85378-Q

42604-Q

No certification to 316 S. S.

Certified to ASTMA-351 CF8M,

certification to 316 S. S.

was required.

11Nupro 11 valves

19144-Q

Certified to ASTM AS80,

certification to 316 L-Low

Carbon was required.

Two vendors, Midco Pipe & Tube and I.T.T. Harper were

placed on the approved vendors' list without the concurrence

of a quality assurance evaluation.

The quality assurance

-

11 -

evaluation on Midco Pipe & Tube, on September 8, 1978,

stated that Midco was only approved for non ASME B & PV

Code,Section III, pipe and fittings.

Midco was placed

on the approved suppliers' list for ASME B & PV Code,

Section III, pipe and fittings, and orders placed on

purchase order ~o. 's 1001-6797Q and 1001-5489Q for safety

related, code items.

Also, I.T.T. Harper was approved in

a quality assurance technical evaluation for nuts and bolts

only, but they were placed on the approved suppliers' list

for special extruded shapes and fasteners, in addition to

nuts and bolts.

In addition, Consumers Power. does not evaluate the effec-

tiveness of their suppliers quality assurance programs

either through analysis of nonconforming material reports,

for material received and inspected at the site, or through

inspections at manufacturing and supplier facilities.

c.

Discussion

Quality Assurance does not review the procurement document that

is sent to the vendor, but only reviews the initial document

for purchase.

Transposing errors that may occur concerning QA

program requirements are not checked by personnel with appropriate

training in the QA discipline.

Since the final document is sent

to the supplier, or vendor, the final document becomes the legal

document the supplier has contracted to, and is the reference

point for all subsequent communication between buyer and seller.

The final document is not checked by QA personnel until it is

received at site, and then it is checked against the initial

document by QC personnel*. for accuracy.

This may be a contributing

factor for errors in procurement documents, as the documents now

receive a single level of review by QA.

Section 5.7 of Quality Assurance Program Procedure 4-51, entitled

Procurement, discusses expedited procurement and does not estab-

lish criteria for accepting an item at site when purchased on an

expedited procurement basis.

The procedure implies that items

may be accepted for installation and used without determining

all requirements.

This concern was discussed with the Quality

Assurance Administrators at Jackson and Palisades, and they

indicated this concern would be addressed through a procedural

change indicating items would not be installed and used on a

significant risk basis without determining all requirements

beforehand.

The following procurement documents had deficiencies as noted

below:

- 12 -

Procurement Document

Req. #1026159

Req. #1026013

Req. #1026159

Deficiency

Unapproved vendor.

Asked for certificate of compliance,

requires certified material test

report.

Penetrant Test does not

specify standard or acceptance

criteria.

No QA review.

The licensee needs to establish a uniform method for securing the

right of access with their suppliers.

8.

Receipt, Storage and Handling of Equipment and Materials Program

Receipt, storage and handling of equipment and materials was reviewed

to ascertain whether the licensee is implementing a QA program that

is in conformance with regulatory requirements and commitments in the

Quality Assurance Program and implementing procedures.

The inspector

verified that responsibilities were assigned for receipt, acceptance,*

release, storage, and handling of items.

Nonconforming items were

reviewed for identification, segregation, control, and release.

Receipt inspection reports were examined for applicable signatures,

justification for use, damage recorded, and stipulated inspection

criteria.

Procedures were reviewed for levels of storage and

appropriate environmental conditions, including shelf life.

a.

Documentation Reviewed

QAPP 7-53, Receiving Inspection

QAPP 8-51, Control of Materials for Operations

QAPP 13-51, Control of Handling, Storage, Shipping

QAPP 15-51, Control of Nonconforming Items

QAPP 15-52, Reporting Nonconformances During Major Modifications

QAPP 16-51, Deviation Reporting and Corrective Action

QADP XVI-1, Corrective Action Follow-up and Trend Analysis

QCP-P~04, Receipt Inspection

QCP-P-05, Processing of Nonconforming Material

CMP-13-3, Material Control

CMP-13-4, Nonconforming Material

CMP-13-5, Control of Weld Materials

- 13 -

I

. I

Policy No. 8, Identification and Contol of Materials, Parts and

Components

Policy No. 13, Handling, Storage and Shipping

Policy No. 14, Inspection, Test, and Operating Status

Policy No. 15, Nonconforming Items

Policy No. 16, Corrective Action

b.

Findings

Noncompliance

10 CFR 50, Appendix B, Criteria V states "Activities affecting

quality shall be prescribed by documented instructions, proce-

dures, or drawings, of a type appropriate to the circumstances,

and shall be accomplished in accordance with these instructions,

procedures or drawings."

Quality Control Procedure, QCP-P-05 Rev. 5, Processing of Noncon-

forming Material, states in paragraph 5.2.1: "Upon notification

from the stockman that materials which are not in an "Accept"

status have been requested for issuance, the QC Supervisor

reviews the appropriate receipt inspection file and NMR Logs

(i.e., receipt and source inspection) to verify that an NMR has

already been generated.

If no NMR exists, he initiates one in

accordance with Section 5.1.1 of this procedure, unless the

material is being issued for repair, rework, inspection or test

and is to b.e returned to the stockroom."

The following procurement documents identify items that were

released for installation on a conditional release basis, without

a nonconforming material report written concerning deficiencies

and inadequacies in documentation:

Procurement

Document

Item

Use

1001-0820

Check Valve

ccw Penetration

DY-150

Globe Valve

Containment Spray Recir.

Line to SIRW Tank

DY-152

Globe Valve

Safety Injection Tank

Drain Line

0006-0645

Gage Pressure

Subcooled Margin

Transmitters

Monitor

Plant Quality Control personnel confirmed that NMR's are not

written as required by Quality Control Procedure, QCP-P-05 .

- 14 -

9.

Records Program

The records program was reviewed to ascertain that the licensee is

implementing a program relating to the control of records that is

in conformance with regulatory requirements, Operational Quality

Assurance Program, ANSI N18.7 and ANSI N45.2.9.

Record storage

controls were reviewed along with means of transferring records to

the vault.

Various records were reviewed for implementation of the

program and personnel were interviewed concerning storage, access,

and retrievability.

T~e record index was examined and duplicate

storage was checked against the criteria of ANSI N45.2.9.

a.

Documentation Reviewed

Technical Specification, Section 6.10

QAPP 17-52, Collection, Storage and Maintenance of Quality

Related Records for Operations

QADP XVII-I, Collection Storage and Maintenance of Department

Records

Policy No. 17, Quality Assurance Records

QAPP 17-1, Quality Records

AP 11, Plant Records

b.

Findings

Noncompliance

10 CFR 50, Appendix B, Criteria XVII states in part " ... Consistent

with applicable regulatory requirements, the applicant shall estab-

lish requirements concerning record retention, such as duration,

location and assigned responsibilities."

Quality Assurance Program Procedure, 17-52, revision 3, Collection

Storage and Maintenance of Quality-Related Records for Operations

states "Records are stored according to ANSI N45 2.9 requirements,

as modified by QA Policy 2, for duplicate record storage locations."

Contrary to the above, the following completed records were not

duplicated:

(1)

Material Properties Records

(2)

Nonconformance Material Reports

(3)

Welding Filler Metal Material Reports

(4)

Certificates of Compliance

(5)

Maintenance Orders (1979-1980)

(6)

Personnel Training Records

(7) Facility Changes (1979-1980)

(8)

Specification Field Changes (1979-1980)

- 15 -

Duplicate records are required in lieu of fire protection vault

requirements of ANSI N45 2.9-1974.

10 CFR 50, Appendix B, Criteria XVII, state$ in_part " ... records

shall include closely-related data such as qualifications of

personnel."

Quality Assurance Program Procedure, 2-54, rev. 2, Training for

Operations states "Records of training are maintained to provide

evidence of personnel qualification, and to support certification

where such is required."

The technical superintendent was certified as a Level III,

according to ANSI N45 2.6, without records to justify or support

this qualification.

Furthermore, the technical superintendent

certified a Level II on March 5, 1980, in areas requiring specific

training, without records that maintained his own qualifications

in these disciplines.

These areas included:

(a) Receipt Inspec-

tions (b) Maintenance Inspections (c) Processing of Non-conforming

Material (d) Operations Testing Inspections (e) Source Inspections

(f) Special Activities Inspections (g) Maintenance Order Review

(h) Facility Change Completion Review and (i) New Fuel Receipt

Inspection.

c.

Discussion

Maintenance Orders, Facility Changes, and Specification Field

Change Records are kept for a two year period prior to duplicating

or microfilming.

Many of these records have been completed for

over a year, as the duplication process for 1979 records would

not occur till the end of 1980 or beginning of 1981.

Since a

permanent record storage vault has not been constructed according

to the fire code requirements of ANSI N45 2.9, duplicating or

microfilming is requ1red.

The time span for these reproducing

processes is too long to assure protection and preservation of

records.

10.

Document Control Program

The document control program was reviewed for conformance to regulatory

requirements, Quality Assurance Program requirements and applicable

industry guides and standards.

Drawings, procedures, and technical

specifications were reviewed for current revisions, distribution lists,

and responsibilities assigned for implementation.

Quality Assurance

Program Manuals, Quality Assurance Department Procedures, Quality

Control Procedures, and as-built drawings were checked for current

revisions and distribution according to master indexes.

The control

room was additionally checked for current emergency procedures and

current P & ID's.

- 16 -

a.

Documentation Reviewed

QAPP 5-51, Development of Documents Controlling Quality Related

Activities During Operations

QAPP 6-51, Distribution and Control of Quality Related Documents

QAPP 6-52, Distribution and Revision Control of Design Documents

Policy No. 6, Document Control

QADP V-1, Preparation, Review and Revision of Quality Assurance

Department Procedures and Program Procedure for

Operations

QADP V-2, Development of Plant Quality Control Procedures

QADP VI-2, Processing and Control of Documents

AP 10-3, Document Distribution and Control

AP 10-3-1, Temporary Procedure Change

AP 10-4, Plant Drawings, Specifications and Instruction Manuals

Development

AP 10-5, Plant Drawings, Specifications and Instruction Manuals

Distribution and Control

AP 9.0, Plant Modifications - Major

b.

Findings

Noncompliance

(1)

10 CFR 50, Appendix B, Criteria VI, states in part "Measures

shall assure that documents, including changes, are reviewed

for adequacy and approved for release by authorized personnel

and are distributed to and used at the location where the

prescribed activity is performed."

Quality Assurance Program Policy No; 6, Revision 8, Document

Control, paragraph 3.1 states "A system for the preparation

of documents and revisions and their interdepartmental and

intradepartmental review, approval, and administration which

preclude the possibility of the use of outdated or inappro-

priate documents is defined by specific department procedures."

Document is defined in the QA*Program Manual as: "Instructions

procedures, drawings or other instructio-nal-type manuals or

material directly affecting a quality or safety-related

activity."

-

17 -

Contrary to the above, measures have not been established

to assure that changes to controlled drawings are distributed

and used at the location where the prescribed activity is

performed, to preclude the possibility of the use of outdated

or inappropriate documents.

The following controlled P & ID's used by the operators in

the control *room were not of the latest revision:

M-205/Rev. 28 is the latest revision.

M-208/Rev. 20 is the latest revision.

M-209/Rev. 23 is the latest revision.

M-210/Rev. 16 is the latest revision.

M-211/Rev. 28 is the latest revision.

M-213/Rev. 23 is the latest revision.

M-218/Rev. 22 is the latest revision.

M-219/Rev. 11 is the latest revision.*

M-220/Rev. 19 is the latest revision.

M...;224/Rev.

8 is the latest revision.

M-225/Rev. 11 is the latest revision.

The required red-lined changes were not on the control room

drawings.

However, all of the above drawings had red-lined

changes in the Document Control Center. It was confirmed

.with the shift supervisor that two sets of outdated drawings

were being used in the control room.

(2)

Technical Specification, Section 6.8, states in part:

" ... Temporary changes to procedures for surveillance and

testing activities of safety-related equipment may be made,

provided the change is documented, reviewed by the PRC at the

next regularly scheduled meeting and approved or disapproved

by the plant superintendent."

Contrary to the above, two test procedures, MI-2 and RI-2,

had temporary changes T-80~137 and T-80-138, respectively,

and were not reviewed by the Plant Review Committee at the

next regularly scheduled meeting.

Procedure MI-2 is

entitled Reactor Protective Trip Units, and procedure RI-2 is

entitled Thermal Margin/Low Pressurizer Pressure Channels.

These changes were reviewed in a later Plant Review Committee

meeting.

11.

Offsite Review Committee

The inspector reviewed the offsite review functions to ascertain

whether it is in accordance with Technical Specification requirements.

The inspection included a review of membership and qualifications,

subject matter, quorom requirements, safety evaluations and recom-

mendations, and frequency of meetings.

- 18 -

a.

Documentation Reviewed

QAPP No. 19, Program Review

QAPP 19-51, Safety and Audit Review Board Charter

b.

Fl.ndings

No items of noncompliance or deviations were identified.

c.

Discussion

During the management inspection conducted by the Performance

Appraisal Branch (Inspection Report 50-255/78-30), the inspectors

found that the licensee was using ballot type reviews for both

the PRC and the SARE.

The licensee was informed by letter from

Division of Operating Reactors dated July 12, 1979, that the

ballot type review does not conform with the position of NRR and

OI & E.

The licensee was also requested to review and propose a

Technical Specification change to bring the reviews by the

Palisades review committees into conformance with NRC positions.

In a letter from CPCO to D. L. Ziemann (NRR) dated September 12,

1979, the licensee stated that they are in the process of surveying

other utilities on how best to deal with the tremendous amount of

material being reviewed by ballot and that they intend to respond

more fully on this topic in about a month.

The licensee has not

yet responded.

At the exit meeting, the inspector stated that this item is being

reviewed by NRR.

The inspector also reviewed a number of SARB meeting minutes and

the following observations were made:

(1)

The Committee discussed the adequacy of "audits" and will

consider providing more guidance concerning the type of

information that needs to be contained in the audits.

(2)

Recurring problem areas at Palisades were discussed (i.e.,

problems in the training area which were identified during

audits conducted in 1976, 1977 and 1978; record storage

problems at Palisades).

(3)

The committee recommended that the audits specified by*

Technical Specifications be combined with QA audits.

And also that plants participate more in audit findings.

Based on the meeting minutes reviewed, the inspector concludes

that the SARB is adequately handling issues for which it is

responsible.

However, the inspector notes that some issues dis-

cussed by the SARB are not receiving timely attention regarding

corrective actions.

- 19 -

12.

Audits

The licensee's audit program was reviewed to ascertain whether the

licensee has developed and implemented a program that is in con-

formance with regulatory requirements and applicable industry guides

and standards.

The inspection included verification of the following:

scope of the program is consistent with Technical Specification

requirements; responsibilities for overall management of the program

have been assigned; and methods for identification and resolution of

audit findings have been defined.

a.

Documentation Reviewed

b.

c.

QAPP 18-51, Audits

QAPP XVIII-1, Audit Scheduling

Policy No. 2, Quality Assurance Program

Policy No. 18, Audits

QAPP 16-51, Deviation Reporting and Corrective Action

QAPP 16-52, Action Items

Findings

Noncompliance

10 CFR 50, Appendix B, Criteria XVIII, states, "A comprehensive

system of planned and periodic audits shall be carried out to

verify. compliance with all aspects of the quality assurance

program and to determine the effectiveness of the program: .. "

Quality Assurance Program Policy No. 18, states, "A representative

portion of the procedures and records related to each area is

audited during the scheduled period to assure a review of all

safety-related activities within a two-year period."

Contrary to the above, the audits performed for 1979 and 1980 did

not cover the entire QA Program, with the *audits scheduled for

1980 being only minimal and covering a very small portion of the

quality assurance program.

The following criteria of 10 CFR 50,

Appendix B, did not appear to be covered at all:

Criteria II, VII,

X, and XIII.

Discussion

A matter for consideration is the authority and responsibility

which is delegated to the Quality Assurance function and the

respective importance of the Quality Assurance audit group as

viewed by management.

-

20 -

The factor, communicated, was that upper management felt that many

QA findings were bothersome, insignificant, and too time consuming

at the plant level.

One of the audit reports stated, quite strongly,

that the QA auditors were worn down in trying to communicate with

management personnel and departmental supervisors at the Palisades

Plant.

Post audit conferences have been difficult to schedule by

Consumers Power QA auditors with Palisades Operational personnel,

due to a lack of interest in the audit program.

This is an area of concern and will be reinspected in future NRC

inspections.

Reference Audit Reports QP-78-10, QP-79-3, and

Nonconformance Report QG-79-1, dated 4/10/79.

13.

Test and Measurement Equipment Program

The program for control of test and measurement equipment was

reviewed to verify compliance with requirements of the Palisades

Nuclear Generating Plant Technical Specifications and Criteria XII

of 10 CFR 50, Appendix B.

The inspection conducted at the corporate

office will also be applicable to the Big Rock Point plant'.

a.

Documentation Reviewed

b.

The following Quality Assurance Program Policies, Quality Assurance

Program Procedures for Operations, Palisades Nuclear Plant Admini-

strative Procedures and System Protection and Laboratory Services

Department Procedures were reviewed to verify that controls have

been established which set forth the criteria and responsibility

for assignment of calibration frequency; a formal requirement for

marking or identifying calibration status for each piece of

equipment; a system which assures that each piece of equipment is

calibrated on or before the required date; a written requirement

which prohibits the use of equipment beyond its calibration

period; controls preventing use of out-of-calibration equipment;

and controls for evaluating the status of equipment and items

previously tested or measured using the equipment found to be

out-of-calibration.

QAPP No. 12, Control of Measuring and Test Equipment

QAPP 12-51, Control of Portable and Laboratory Measuring and

Test Equipment

AP 17.0, Control of Measuring and Test Equipment

AP 17.1, Control of PL-M & TE

SPLS-07, Control of Measuring and Test Equipment

Findings

No items of noncompliance or deviations were identified .

- 21 -

the inspector.

The licensee indicated that data sheets

and procedures were also scheduled for review.

This area

will be reviewed during a subsequent NRC inspection.

15.

Maintenance

The inspector reviewed the licensee's Maintenance Program to ascertain

whether the QA Program relating to maintenance activities is being

conducted in accordance with the Quality Assurance Program, 10 CFR 50

Appendix B requirements, and commitments in the QA Program.

The_following items were considered during this review:

written

procedures have been established for initiating requests for routine

and emergency maintenance; criteria and responsibilities have been

designated for performing work inspection of maintenance activities;

provisions and responsibilities have been established for the

identification of appropriate inspection hold points; methods and

responsibilities have been designated for performing testing following

maintenance work; methods and responsibilities for equipment control

have been clearly defined; and administrative controls for special

processes have been established.

The inspector also reviewed the licensee's Preventive Maintenance

Program and verified that a written program has been established

which includes responsibility for the program; a master schedule for

preventive maintenance; and documentation and review of completion

of preventive maintenance activities.

a.

Documentation Reviewed

QAPP No. 9, Control of Special Processes

QAPP No. 10, Inspection

QAPP 5-52, Documentation of Plant Maintenance

QAPP 9-51, Control of Special Process

QAPP 10-51, Maintenance and Minor Modification Inspection

QAPP 14-51, Operations Status Indicators - Tagging and

Documentation

AP 4.0, Operations Administration

AP 5.0, Maintenance Administration

b.

Findings

Noncompliance

10 CFR 50, Appendix B, Criterion XVI requires that in the case

of significant conditions adverse to quality, the measures shall

- 24 -

c.

Discussion

(1)

Storage of measuring and test equipment in the site I & C

shop was* cluttered and no attempt to separate controlled

calibration instruments from general test uncontrolled

equipment.

The licensee's audit program has identified

previous incidents where uncontrolled equipment was used

for calibrations.

Orderly storage of test and measuring

equipment with separation of controlled and uncontrolled

instruments could help prevent a reoccurrence of this type.

(2)

Inspection of the licensee's central instrument calibration

facilities found it to be in full compliance with both the

-requirements and intent of applicable industry standards

and regulatory requirements.

Its personnel appeared to be

qualified and dedicated to the program and its objectives.

14.

Surveillance Testing and Calibration Control Program

The program for surveillance testing, calibration, and inspection of

safety related components and instrumentation was reviewed to verify

compliance with the requirements of Palisades Nuclear Generating Plant

Technical Speci£ications and Criteria XI of 10 CFR 50, Appendix B.

a.

Documentation Reviewed

_The following Quality Assurance Program Policies, Quality

Assurance Program Procedures for Operations, Palisades Nuclear

Plant Administrative Procedures, and Palisades Nuclear Plant

Engineering Manual Procedures were reviewed to verify the estab-

lishment of a mechanism for:

scheduling of surveillance testing

and calibration of safety related components, rev1ew of completed

surveillance procedures and periodic activity procedures; and

maintaining the schedule to reflect system status.

QAPP No. 10, Inspection

QAPP No. 11, Test Control

QAPP 12-52, Control of Installed Plant Instrumentation

AP 5.0, Maintenance Administration

AP 17.0, Instrumentation Non-Conformance Action

AP 18.0, Surveillance Program Overview

AP 18.2, Procedure Scheduling and Issue

AP 18.3, Procedure Implementation

AP 18.4, Corrective Action

- 22 -

AP 18.5, Procedure Routing and Evaluation

AP 18.6, Procedure Filing and Record Storage

EM-09-01, Technical Sp~cificati6n Testing

b.

Findings

Noncompliance

Palisades Nuclear Generating Plant Technical Specification

paragraph 4.7.2.a requires that monthly the voltage of each cell

of the station batteries be measured to the nearest 0.01 volt and

recorded.

Contrary to the above, Technical Specification Surveillan*ce

Procedure ME-12, Battery Checks, has been performed since at

least May 1980 utilizing measuring instruments which did not

meet the required accuracy.

The three instruments used for this test were all Y2 controlled

instruments within their prescribed calibration interval.

All

three instruments were calibrated and certified to a user required

accuracy of +/-1.0% of reading.

With a nominal cell voltage of 2.30

volts, the instruments were only certified accurate to +/-0.023 volt.

c.

Discussion

(1)

The technical specification surveillance testing program has

recently undergone extensive revision including revised test

procedures.

Of the approximately twenty to thirty surveil-

lance tests sampled by the inspector, the above noncompiiance

was the only problem identified.

The nature of the above

noncompliance was such that it was not detectable by the

normal review process.

~

(2)

Testing, calibration, and periodic maintenance of safety

related components and systems which are not required by

the Technical Specifications are part of the Periodic

Activities Control Program.

The inspector's review of

this program found several areas of concern.

The program *

was not uniform in its implementation from one department

to another.

Instrument test and calibration data sheets

had a different acceptante criteria for "as found" values

and "final" values with no explanation.

Calibration pro-

cedures relied heavily on operator capability for proper

implementation.

The test and calibration equipment is not

always logged by the same identification numbers.

The section of the Maintenance Administration procedure

which described the Periodic Activity Control program is

under revision and a draft of the revision was reviewed by

- 23 -

assure that the cause of the condition is determined and corrective

action taken to preclude repetition.

QAPP No. 16 section 3.1 states that a failure of a safety-related

component which is significant to safety will always be evaluated.

AP 3.5, Corrective Action, defines a deviation as a nonconformance

or departure of characteristic from specified requirements.

One

example of a deviation is significant failures, malfunctions,

deficiencies and nonconformances of Q-listed materials, equipment

and structures.

Contrary to the above requirements, the inspector found that

on August 24, 1980, maintenance was performed on pressurizer

pressure indication PI-103B and no deviation report was initiated

to evaluate the nonconformance to determine if additional action

is required to prevent or reduce the possibility of recurrence.

Maintenance Order M080-PCS-lll stated that the pressurizer

pressure indicator on C-33 was reading zero and requested that

the indicator be fixed because it was needed for plant shutdown

per an EOP.

During the repair, it was discovered that the instru-

ment (PI-103B) had reversed wiring at 12-TU-4 in panel C-12.

The

immediate problem was identified and corrected.

However, the root

cause (such as personnel error; inadequate installation procedure;

or inadequate drawings) of the problem was not evaluated.

c.

Discussion

During the review of procedures relat"ing to the performance of

maintenance activities, the inspector noted that the plant

implementing procedures for inspection are not consistent with

the CPCO QA program policy.

Quality Assurance Program Policy No. 10, Inspection, section 3.3

states that inspection points are designated when deemed necessary

in the procedures and work does not proceed beyond the designated

inspection point until the inspection has been completed and

documented or written consent for bypassing the inspection has

been received from the organization responsible for performing

the inspection.

QAPP 10-51, Maintenance and Minor Modification Inspection,

states that if a representative of the inspection group cannot

be located, the work may proceed provided that the attempted

contact be documented.

The above statement in QAPP 10-51 appears to be in conflict with

the requirement of Policy 10 with regard to proceeding with the

work without the consent of the QC 'department.

Also with regard

to inspection hold points, the inspector found that criteria has

not been established for the selection of hold points for safety-

related activities. It appears that hold points are determined

- 25 -

1

based on manpower availability and not significance of the work

activity.

During discussions with licensee representatives the

inspector ~as informed. that this program deficiency had been

identified in licensee internal audits and that action has been

initiated to provide guidance for selection of inspection hold

points.

This item was discussed during the exit interview.

In addition, the following observat{ons were also made:

(1)

Controlled Material and Services Procedures Manual Proce-

dure 13-7 in section 5.2 makes reference to section 5.3.2.1

of Procedure 13-6.

This section in Procedure 13-6 does not

exist.

(2)

A new preventive maintenance procedure has been written and

is currently being routed for review and approval.

The

procedure contains instructions on how the Periodic Activity

Control Sheets (PACS) are controlled and the information

inputed into the computer.

(3)

Licensee representatives stated that a procedure is being

written to detail fire prevention requirements during welding

and cutting activities.

This is being initiated as a result

of enforcement action taken by the NRC during a previous

inspection.

16.

Nonroutine Reporting Program

The inspector reviewed the licensee'i progtam to ascertain responsi-

bilities have been assigned for the review of events and activities to

assure reports of a nonroutine nature will be submitted in conformance

to the applicable regulatory requirements.

a.

Documentation Reviewed

QAPP 16, Corrective Action

QAPP 15-51, Control of Nonconforming Items

QAPP 15-52, Repor~ing Nonconformance During Major Modifications

QAPP 16-51, Deviation Reporting and Corrective Action

QAPP 16-52, Action Items

QAPP 16-1, Corrective Action

AP 3.5, Corrective Action

b .

Findings

No items of noncompliance or deviations were identified.

- 26 -

17.

Corrective Action Program

The inspector reviewed this area to verify that measures have been

established to identify and correct conditions adverse to quality

  • such as failures, malfunctions, deficiencies, deviations, defective

material and equipment, and nonconformance.

Corrective action taken

to preclude repetition was also examined.

The area of nonconformances

was reviewed for prompt identification and correction.

a.

Documentation Reviewed

Shift Supervisor's Log - September 25, 1980 to October 10, 1980

QA Program Monthly Status Reports - August and September 1980

QAPP 16-1, Corrective Action

QAPP 16, Corrective Action

QADP XVI-2, Action Items

QADP XVI-4, Documenting, Evaluating, Correcting and Reporting

Conditions Adverse to Quality

QAPP 16-51, Deviation Reporting and Corrective Action

QAPP 16-52, Action Items

QADP XVI-1, Corrective Action Follow-*up and Trend Analysis

QADP XV-1, Nonconformance Control

QCP-P-05, Processing_of Nonconforming Material

QAPP 15-51, Control of Nonconforming Items

QAPP 15-52, Reporting Nonconfor~ances During Major Modifications

AP 3.5, Corrective Action

AP 4.0, Operations Administration

SOP 36, Reactor Protection System

.b.

Findings

Noncompliance

The following examples of items of *noncompliance were identified

in this area:

- 27 -

l

j

(1)

10 CFR SO, Appendix B, Criteria XVI, Corrective Action,

states that measures shall be established to assure that

conditions adverse to quality, such as. failures, malfunctions,

deficiencies, deviations, defective material and equipment,

and nonconformances are promptly identified and corrected.

In order to implement 10 CFR SO, Appendix B, Criteria XVI,

the licensee established completion due dates and evaluation

due dates.

Quality Assurance Program Procedure, 16-Sl,

revision 4, Deviation Reporting and Corrective Action states

in paragraphs S.1.2 and S.1.3 respectively:

Within.40 days

of the date originated, the individual who received the DR

for processing, or his alternate, assures that nonconforming

items are controlled according to QAPP lS-Sl, assigns an

individual to conduct the Evaluation and Disposition and

assigns an Evaluation due date and priority.

The reviewer

identifies the individual responsible for completion of each

corrective action, the completion due date and priority of

each corrective action.

Contrary to the above, four deviation reports were not

resolved for corrective action in accordance with established

completion dates and one deviation report did not meet the

40 day requirement concerning evaluator assignment, evaluator

due date and priority.

The deviation reports are D-QG-78-24,

D-QG-78-24A, D-QG-78-24C, D-QP-76-107, and D-QP-80-21.

Document No.

D-QG-78-24

D-QG-78-24A

D-QG-78-24C

D-QP-76-107

Document No.

D-QP-80-2,1 *

Completion Due Date

12/01/79

12/01/79

12/01/79

04/30/80

Subject

Temp proc change

involving unreviewed

safety question.

(MSLB reanalysis

concluded that the

containment pressure

would be exceeded

for a MSLB with the

Primary Coolant

System @S32F.

Cor-

rective measures

taken to reduce the

peak pressure in-

cluded filling the

containment spray

headers to allow

- 28 -

Status As of 10/18/80

10% complete

SO% complete

50% complete

20% complete

Status as of 10/18/80

This document was

originated 6/24/80.

To date an evaluator

has not been assigned.

This status has not

been updated since

6/24/80.

  • (Reported by QA

Consumers Power)

,

spray operation to

occur sooner dtlring

a MSLB.

On 5/22/80

with the PCS at

@532F, TC T80-96

was put into effect

to cldse both con~

tainment spray

header isolation

valves to facilitate

containment spray

pump testing.

(2)

10 CFR 50, Appendix B, Criteria XVI requires that for con-

ditions adverse to quality, measures shall be established

to assure the cause of the condition be determined and that

action be taken to prevent repetition.

QAPP No. 16 states

that a failure of safety related components is an item

requiring evaluation under their corrective action system.

SOP 36, Reactor Protective System Operating Procedure

requires that "Anytime a reactor protective system input

channel becomes erratic or its output value is questionable,

a deviation report QA-16, shall be initiated.

Immediate

action should be taken to correct the problem.

If analysis

shows that the deviation causes a nonconservative trip signal

to be generated, then the channel should be either bypassed

or put into the tripped condition until corrective action is

taken."

Contrary to the above, the High Power trip, B Channel, was

bypassed on C shift September 29, 1980, due to RPCIC drift.

No corrective action system report was initi"ated as required

by the QA program and the operating procedure.

Other items

of a similar nature were noted.

See discussion below and

Findings of.section 15, Maintenance.

c.

Discussion

A number of items were noted where the formal corrective action

system was not being implemented.

The inspector perceptions of

the underlying causes are discussed below.

These perceptions

were developed through study of the licensee's systems, reviews

of records and discussions with licensee personnel.

Many personnel do not fully understand the system and the need

for it.

One of the causes of this is the tendency of the licensee

to assign the evaluation and disposition back to the initiator.

For example, in dealing with instrumentation, the I & C supervisor

who identifies that an instrument is out of tolerance initiates

the devia.tion report (DR), is then assigned the evaluation and

disposition of that DR.

Human. nature then tends to view the

process as unneeded paperwork as he has already solved the

- 29 -

problem and the DR comes back to him a few weeks later to

evaluate.

This also presents some systematic problems which

the licensee should be aware of.

One, he is not establishing

a strong first line independent review.

Two, considering

human nature, there can be a tendency to gloss over the event

when it comes back the second time.

Events such as the measured 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> unidentified primary coolant

system leakage being greater than 1 gpm on September 29, 1980

and the failure of the 1-1 diesel generator to start following

maintenance were not placed in the DR system.

They were reviewed

outside the system leaving very few records of the events or how

they were resolved.

One advantage to be gained by an effective

corrective action system is a record of the review process and

tracking of any outstanding corrective actions.

On October 6, 1980, the lic~nsee released a batch of radwaste

liquid (Batch Number 80-013-L).

Log entries indicate that the

monitor kept tripping.

The following is quoted from the "Release

Order" - "Batch tripped and reset many times."

The radiation

monitor's function is to stop the release if release limits are

being exceeded.

It appears that the problem was probably a high

background at the monitor and no release limits were exceeded.

The inspector does have concerns regarding this mode of operation.

What would happen if there was a real problem with the release

such as a wrong tank?

Would the licensee finally release it by

continuing to reset?

The licensee appears to have taken no

.corrective action regarding this event.

No Maintenance Order,

Facility Change Request or Deviation Report was initiated.

Continued operation through problems such as this can establish

the "traps" that cause a licensee to get into regulatory or

safety problems in the future.

This was discus~ed with licensee

management.

In discussion with personnel, the inspector did not find one

positive attitude toward the Corrective Action system (DR).

No one expressed an opinion that the system was effective or

provided a benefit.

The Quality Assurance Program Policy 16 states that trends observed

which are adverse to quality are considered for corrective action.

The licensee does not appear to have developed any effective trend

analysis programs.

The QA Department has one procedure, QADP XVI-1,

that does deal with trend analysis.

This analysis relates cause,

organization and activity.

The inspector reviewed one report and

it appeared superficial and did not carry on far enough.

It

concluded that Palisades has more errors during outages than Big

Rock Point. It did not question the reasons for this or propose

any corrective actions to be taken:

- 30 -

Quality Assurance has a computer system for identifying correc-

tive action items.

The shortcoming of the system appears to be

in getting timely resolution in regards to both evaluation and

corrective action.

This area appears to be out of Quality

Assurance control, and any improvement in this area seems to rest

with upper management.

All of the items stated in the item of

noncompliance were more.than adequately identified by Quality

Assurance.

A facet discussed was placing only those conditions

in the corrective action system that are of significance.

18. Exit Interview

The inspectors met with the licensee representatives (denoted in

paragraph 1) at the conclusion of the inspection on January 16,

1981.

The purpose and scope of the inspection '~as summarized and

the inspectors then discussed the enforcement findings in each

area.

These findings had been previously discussed with licensee

representat1ves during meetings held throughout the inspection .

- 31 -