ES-201 Examination Preparation Checklist Form ES-201-1 Facility:
Byron Station, Units 1 & 2 Date of Examination:
December 4-12, 2017 Developed by: Written: Facility NRC // Operating: Facility NRC Target Date*
Task Description (Reference)
Chief Examiners Initials 4/3/17
-240
- 1.
Examination administration date confirmed (C.1.a; C.2.a-b). For NRC-prepared exams, arrangements are made for the facility to submit reference materials (C.1.e; C.3.c; Attachment 3).
dwr 5/8/17
-210
- 2.
NRC examiners and facility contact assigned (C.1.d; C.2.f).
dwr 5/8/17
-210
- 3.
Facility contact briefed on security and other requirements (C.2.c). As applicable, the facility contact submits to the NRC any prescreened K/As for elimination from the written examination outline, with a description of the facilitys prescreening process (ES-401, D.1.b).
dwr N/A
-210
- 4.
Reference material due for NRC-prepared exams (C.1.e; C.3.c; Attachment 3).
N/A 5/8/17
-210
- 5.
Corporate notification letter sent (C.2.e).
dwr 5/22/17
-195
- 6.
NRC-developed written examination outline (ES-401-1/2 or ES-401N-1/2 and ES-401-3 or ES-401N-3) sent to facility contact (must be on the exam security agreement) (C.1.e-f; C.2.h; C.3.d-e).
dwr 7/7/17
-150
- 7.
Operating test outline(s) and other checklists due, including Forms ES-201-2, ES-201-3, ES-301-1, ES-301-2, ES-301-5, and ES-D-1, as applicable (C.1.e-f; C.3.d-e).
dwr 7/14/17
-136
- 8.
Operating test outline(s) reviewed by the NRC and feedback provided to facility licensee (C.2.h; C.3.d-e).
dwr 9/18/17 9/22/17
-75
- 9.
Proposed examinations (written, JPMs, and scenarios, as applicable) and outlines (Forms ES-301-1, ES-301-2, ES-D-1, ES-401-1/2 or ES-401N-1/2, and ES-401-3 or ES-401N-3);
supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, ES-401-6, ES-401N-6, and any Form ES-201-2 and ES-201-3 updates); and reference materials due (C.1.e-h; C.3.d).
meb N/A
-75
- 10. Examinations prepared by the NRC are approved by the NRC supervisor and forwarded for facility licensee review (C.1.i; C.2.h; C.3.f-g).
N/A 10/5/17
-60
- 11. Preliminary waiver/excusal requests due (C.1.m; C.2.c; ES-202).
meb 10/13/17
-50
- 12. Written exam and operating test reviews completed (C.3.f).
meb 10/27/17
-35 13.a Examination review results discussed between the NRC and facility licensee (C.1.i; C.1.k-l; C.2.h; C.3.g).
meb 11/13/17
-35 13.b The NRC and the facility licensee conduct exam preparatory week.
meb 11/2/17
-30
- 14. Preliminary license applications and waiver/excusal requests, as applicable (NRC Form 398) due (C.1.m; C.2.i; ES-202).
meb 11/17/17
-14
- 15. Final license applications and waiver/excusal requests, as applicable (NRC Form 398), due and Form ES-201-4 prepared (C.1.m; C.2.k; ES-202).
meb 11/27/17
-7
- 16. Written examinations and operating tests approved by the NRC supervisor (C.2.j-k; C.3.h).
meb 11/27/17
-7
- 17. Request facility licensee management feedback on the examination (C.2.l).
meb 11/27/17
-7
- 18. Final applications reviewed; one or two (if more than 10) applications audited to confirm qualifications/eligibility; and examination approval and waiver/excusal letters sent (C.2.k; ; ES-202, C.3.j; ES-204).
meb 11/27/17
-7
- 19. Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k).
meb 11/27/17
-7
- 20. Approved scenarios and job performance measures distributed to NRC examiners (C.3.i).
meb
- Target dates are based on facility-prepared examinations and the examination date identified in the corporate notification letter. These dates are for planning purposes and may be adjusted on a case-by-case basis in coordination with the facility licensee.