ML18036A804

From kanterella
Jump to navigation Jump to search

Insp Repts 50-259/92-24,50-260/92-24 & 50-296/92-24 on 920617-0717.Violations Noted.Major Areas Inspected: Surveillance Operation,Maint Operation,Operational Safety Verification,Unit 2 Preoutage Work & Unit 1 Activities
ML18036A804
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 07/31/1992
From: Kellogg P, Patterson C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18036A801 List:
References
50-259-92-24, 50-260-92-24, 50-296-92-24, NUDOCS 9208110181
Download: ML18036A804 (25)


See also: IR 05000259/1992024

Text

fp0

Cy

C

O

R

Cy

gO

+**++

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTASTREET, N.W.

ATLANTA,GEORGIA 30323

Report Nos.:

50-259/92-24,

50-260/92-24,

and 50-296/92-24

Licensee:

Tennessee

Valley Authority

6N 38A Lookout Place

1101 Market Street

Chattanooga,

TN

37402-2801

Docket Nos.:

50-259,

50-260,

and 50-296

License Nos.:

DPR-33,

DPR-52,

and

DPR-68

Facility Name:

Browns Ferry Units 1, 2,

and

3

Inspection at Browns Ferry Site near Decatur,

Alabama

Inspection

Conducted:

une

17

July 17,

1992

Inspector:

atters

en>or

i

nspector

ate

1gne

l

Accompanied

by:

E. Christnot,

Resident

Inspector

W. Bearden,

Resident

Inspector

Approved by:

a

.

e

R actor

,

ection

A

Division of Reactor Projects

SUMMARY

a e

>gne

Scope:

This routine resident

inspection included surveillance operation,

maintenance

operation,

operational

safety verification, Unit 2

preoutage

work, Unit

1 activities, Unit 3 restart activities,

reportable

occurrences,

and action

on previous inspection

findings.

One hour of backshift coverage

was routinely worked during the

workweek.

Deep backshift inspections

were conducted

on June

20,

June

27, July 4,

and July 11,

1992.

A NRC Non-Destructive

Examination

Team conducted

an inspection of

Unit 3 pipe replacement

from July 6 July 16,

1992.

The team

concluded that the program

was adequate for the applicable

code

cycle.

The results of the inspection will be documented

in

inspection report 92-23.

9208110181

920803

PDR

ADOCK 05000259

8

PDR

Unit 2 continued to operate

at power this period without

significant problems,

paragraph

four.

At the end of the period

the unit had

been

on line 78 days.

This exceeded

the previous

longest period of continuous

operation of 73 days since the Unit

was restarted

May 1991.

Some pre-outage modification and scaffold

staging

has occurred in Unit 2 operating

spaces.

This has

been

closely monitored for impact

on the operating Unit.

Unit 3 recovery activities continued with recirculation

and

reactor water cleanup piping proceeding

on schedule.

Other

activities were control

room design review work, drywell chiller

installation,

and cooling tower refurbishment.

Significant

problems

were encountered

with the cooling tower work.

This work

was being performed

as

a pilot program to demonstrate

usage of the

system turnover process.

Several electrical installation

deficiencies

were identified resulting in three incident

investigation reports

by the licensee.

These

problems indicated

a

more aggressive

quality oversight is needed.

Resolutions of these

issues

and incorporation of lessons

learned is essential

to insure

timely and quality completion of Unit 3 recover efforts.

Unit

1 walkdown started

during this period,

paragraph

six.

These

activities are being performed

on

a limited scope to determine

work activities to be performed during the Unit 2 Cycle

6 outage.

This will be the only scheduled

time all three Units will be

defueled.

These

walkdowns are being monitored daily in the plan

of the day meetings.

One violation was identified for failure to use the current design

pressure

during hydrostatic testing after installation of

corrosion monitors in the residual

heat

removal service water

system piping, paragraph five.

The licensee identified that the

design data

was taken from test data sheets

and not actual flow

diagrams.

A limiting condition for operation

was entered

because

a loop of containment cooling was declared

inoperable until the

correct hydrostatic test

was conducted.

The system

had

been

technically inoperable for 17 days.

One unresolved

item concerning

a missed

Appendix

R firewatch was

identified, paragraph four.

A computer malfunction of the

computerized

hold order process

caused

a tracking item to default

nonconservatively.

The licensee

is reviewing this problem for

other causes

which may have occurred

and correction of the

problem.

One inspector followup item was identified concerning

incorporation of lessons

learned

from the problems with the

cooling tower refurbishment,

paragraph

seven.

REPORT DETAILS

Persons

Contacted

Licensee

Employees:

  • 0. Zeringue,

Vice President,

Browns Ferry Operations

  • H. HcCluskey,

Vice President,

Browns Ferry Restart

  • J. Scalice,

Plant Manager

J. Rupert,

Engineering

and Modifications Manager

J. Swindell, Restart

Manager

M. Herrell, Operations

Manager

J.

Haddox, Project Engineer

  • H. Bajestani,

Technical

Support

Manager

R. Jones,

Operations

Superintendent

A. Sorrell, Special

Programs

Manager

C. Crane,

Maintenance

Manager

  • G. Turner, Site guality Assurance

Manager

  • R. Baron, Site Licensing Manager
  • P. Salas,

Compliance Supervisor

J.

Corey, Site Radiological

Control Manager

A. Brittain, Site Security Manager

Other licensee

employees

or contractors

contacted

included licensed

reactor operators,

auxiliary operators,

craftsmen,

technicians,

and

public safety officers;

and quality assurance,

design,

and engineering

personnel.

NRC Personnel:

P. Kellogg, Section Chief

."C. Patterson,

Senior Resident

Inspector

E. Christnot,

Resident

Inspector

M. Bearden,

Resident

Inspector

  • Attended exit interview

Acronyms

and initialisms used throughout this report are listed in the

last paragraph.

Surveillance Observation

(61726)

The inspectors

observed

and/or reviewed the performance of required SIs.

The inspections

included reviews of the SIs for technical

adequacy

and

conformance to TS, verification of test instrument calibration,

observations

of the conduct of testing,

confirmation of proper removal

from service

and return to service of systems,

and reviews of test data.

The inspectors

also verified that

LCOs were met, testing

was

accomplished

by qualified personnel,

and the SIs were completed within

the required frequency.

The following SIs were reviewed during this

reporting period:

a.

2-SI-3.7.A.3.a(A),

Reactor Building Suppression

Chamber

Vacuum

Relief Channel Calibration.

This SI is performed quarterly to

b.

C.

check the calibration of the Reactor Building-Suppression

Chamber

Vacuum Relief differential pressure

requirements

of TS 3.7.A.3.a

and 4.7.A.3.a.

The inspector

reviewed the completed

SI package

for the most recently performed testing performed

on Hay 29,

1992.

No discrepancies

were identified.

O-SI-4-11.B.l.b,

High Pressure

Fire Protection

System Valve

Position Verification (Inside Loop).

This SI is performed monthly

to verify proper operation of the

HPFPS, Sprinkler Systems,

Raw

Service Water System,

and

CO< Systems

by verifying proper valve

alignment in accordance

with TS 4. 11.B. l.b, 4. 11.C. l.a,

and

4. ll.d. 1.

The inspector

reviewed portions of the completed

SI

performed from Hay 27-31,

1992.

The inspector

noted that several

test deficiencies

were generated

as the result of this SI.

The

TDs were associated

with several

HPFPS valves that were closed

under hold orders.

In each

case

the closed valves

were tracked

under

an Attachment

F with the proper compensatory

measures

in

place.

No other discrepancies

were identified.

O-SI-4.9.A.l.a(D), Diesel

Generator

Honthly Operability Test.

This SI is performed monthly to verify operability of Diesel

Generator

1D in accordance

with TS 4.9.A. l.a and 4.5.C. l.a.

This

test also

implements the

ASHE Section

XI program of TS 4.6.G. 1 as

it pertains to the fuel oil and starting air systems

and monthly

maintenance

checks

recommended

by the vendor.

The inspector

reviewed the completed

SI package for the test performed

on July

7,

1992

and identified no discrepancies.

No violations or deviations

were identified in the Surveillance

Observation

area.

3.

Haintenance

Observation

(62703)

Plant maintenance activities were observed

and/or reviewed for selected

safety-related

systems

and components

to ascertain that they were

conducted

in accordance

with requirements.

The following items were

considered

during these

reviews:

LCOs maintained,

use of approved

procedures,

functional testing and/or calibrations

were performed prior

to returning components

or systems to service,

gC records maintained,

activities accomplished

by qualified personnel,

use of properly certi-

fied parts

and materials,

proper

use of clearance

procedures,

and

implementation of radiological controls

as required.

Work documentation

(HR,

WR,

and

WO) were reviewed to determine

the

status of outstanding

jobs

and to assure that priority was assigned

to

safety- related

equipment

maintenance

which might affect plant safety.

The inspectors

observed

the following maintenance activities during this

reporting period:

e

b.

c ~

lA DG Outage

The inspectors

followed licensee activities associated

with the

scheduled

outage

on the

1A DG. Outage activities observed

included

replacement

of 3 cells

and interconnectors

on the

DG Battery due

to evidence of copper contamination. Additionally the inspector

reviewed

LCO 0-92-72-3.9.B.3

which was associated

with this work.

The

LCO was entered

at 4:35

am on June

23,

1992,

and exited at

1:00

pm on June

24,

1992.

No problems

were identified.

Thermocouple

Recorder

The inspectors

observed

ongoing activities associated

with

WO 92-

52031-00 which was issued to troubleshoot

Point Number

2 on the

2B

Recirc

Pump Hotor Winding and Bearing Recorder,

2-TR-68-84.

This

point was associated

with thermocouple,

2-TE-68-73E,

which ap-

peared to be open.

,The inspector

observed

work and reviewed the

uncompleted

work package.

The work instructions

were of

sufficient detail to allow for adequate

performance of the work

activity.

No problems

were identified.

P.H.

on Recirculation

Pump

The inspectors

observed activities associated

with WO 92-55507-00

which was issued to perform routine preventive maintenance

on the

2B Recirc

Pump Hotor Winding and Bearing Recorder,

2-TR-68-84.

This work was performed with the work activity described

in

WO 92-

52031-00.

A mechanical

alignment in accordance

with IHSI-3016,

Leeds

and Northrup Recorders

Hodel

257 was to be accomplished

on

this recorder after completion of troubleshooting.

The inspector

reviewed the uncompleted

work package.

The work instructions

were

of sufficient detail to allow for adequate

performance of the work

activity.

No problems

were identified.

No violations or deviations

were identified in the Haintenance

Observation

area.

Operational

Safety Verification (71707)

The

NRC inspectors

followed the overall plant status

and

any significant

safety matters related to plant operations.

Daily discussions

were held

with plant management

and various

members of the plant operating staff.

The inspectors

made routine visits to the control rooms.

Inspection

observations

included instrument readings,

setpoints

and recordings,

status of operating

systems,

status

and alignments of emergency

standby

systems,

verification of onsite

and offsite power supplies,

emergency

power sources

available for automatic operation,

the purpose of tempo-

rary tags

on equipment controls

and switches,

annunciator

alarm status,

adherence

to procedures,

adherence

to LCOs, nuclear instruments

operability, temporary alterations

in effect, daily journals

and logs,

stack monitor recorder traces,

and control

room manning.

This

inspection activity also included

numerous

informal discussions

with

operators

and supervisors.

General

plant tours were conducted.

Portions of the turbine buildings,

each reactor building,

and general

plant areas

were visited.

Observations

included valve position

and system alignment,

snubber

and

hanger conditions,

containment isolation alignments,

instrument

readings,

housekeeping,

power supply and breaker alignments,

radiation

and contaminated

area controls,

tag controls

on equipment,

work

activities in progress,

and radiological protection controls.

Informal

discussions

were held with selected

plant personnel

in their functional

areas

during these tours.

a 0

Plant Status

b.

C.

During this period, the unit operated

at power without any

significant problems.

At the

end of the period, the unit had

been

on-line for 78 days.

This exceeded

the previous longest

run of 73

days since the unit was returned to operation.

Operator Overtime

During this inspection period, the inspector reviewed the

licensee's

work and overtime log for the operating shifts.

This

review as well as discussion

with Operations staff indicate that

overtime is regularly worked but is not excessive.

Operations

overtime remained within the guidelines established

in SSP 1.7,

Overtime Restrictions.

No discrepancies

were identified.

Hissed Appendix

R Fire Watches

On June

12,

1992

a hold order was placed

on

DG 3C, battery charger

A.

2-SSP-1,

BFNP Unit 2 Appendix

R Safe

Shutdown

Program,

requires

the charger to be restored to service within seven

days

or a firewatch be established.

The firewatch was not established

until July 4,

1992, twenty-two days later.

The hold order process

is computerized

and certain attributes of a component

are

automatically completed

on the hold order forms and

abnormal

configuration log sheets

when the component is identified.

One of

these is

a question

about Appendix R.

A computer malfunction that

occurred earlier apparently

caused

the system to default non-

conservatively

and indicated that this component is not

an

Appendix

R component.

An Incident Investigation is being

conducted.

The item will remain

open

as

UNR 260/92-24-01,

Hissed

Appendix

R Required Firewatch,

pending review of the licensee's

evaluation of this issue.

d.

Firewatches

An inspector

selected

several

active

LCOs associated

with fire

protection requirements

from the licensee's

tracking list for

0

review.

Specific requirements

included continuous or roving

firewatches

in the Unit 2 Reactor Building, Control

Bay, or Unit

1/2

DG Building.

LCOs reviewed included the following:

LCO

Action Re uired

0-92-044-3. 11.C

Maintain hourly roving firewatch in Unit 1/2

DG

Building due to scaffolding blocking sprinkler

heads.

0-92-066-3. 11.A

Maintain hourly roving firewatch in Unit 1/2

DG

Building due to covered

smoke detectors.

1-92-034-3. 11.G

Maintain hourly roving firewatch in Unit 1/2

DG

Building due to inoperable fire door.

2-92-159-3. 11.C

Maintain continuous firewatch in Unit 2 Reactor

Building elevation

565 due to blocked sprinkler.

2-92-160-3. 11.G

Maintain hourly roving firewatch in Shutdown

Board

Room

C due to breached fire barrier.

2-92-161-3.11.C

Maintain continuous firewatch in Unit 2 Reactor

Building elevation

593 due to blocked sprinkler.

2-92-163-3. 11.A

Maintain hourly roving firewatch in Unit 2

Reactor Building elevation

565 due to covered

smoke detectors.

2-92-164-3. 11.G

Haintain hourly roving firewatch in Unit 2

Reactor Building due to inoperable fire door.

2-92-165-3. 11.A

Maintain hourly roving firewatch in Control

Bay

due to covered

smoke detectors.

3-92-063-3. 11.G. 1 Maintain hourly roving firewatch in Unit 3

Computer

Room due to breached fire barrier.

During the review of Attachment

F Number 92-0201 associated

with

LCO 2-92-159-3.11.C

the inspector noted that no continuous fire

watch was present at the elevations

565 and

519 southeast

quadrant

of the Reactor building as specified

on the Attachment

F.

On

further investigation the inspector determined there

was

no need

for a fire watch in that quadrant

and the required fire watch was

actually

on the 565 elevation in another quadrant

where

scaffolding was blocking

a section of sprinkler piping. This

discrepancy

appeared

to be

known by personnel

in the field

performing fire watch duties but no effort had

been

made to

correct the Attachment

F.

The inspector discussed

this issue with

operations

management

personnel

and the Attachment

F was

immediately corrected to specify the correct area.

The inspector

noted that in spite of the administrative error present

on the

licensee's

form to control this required

compensatory

measure

the

actual

requirements

were being met due to the efforts of personnel

in the field.

Additionally, the inspector

reviewed all available copies of round

sheets

hourly roving fire watches for personnel

assigned

to the

control

bay and compared

them to the respective

LCO and Attachment

F.

These

sheets

are normally left at permanently installed

boxes

at several

locations in the various buildings.

The inspector

reviewed the forms to verify that recent tours

had

been

performed

at the required times

and that all roving fire watches

required

by

outstanding

LCOs for the Control

Bay were being satisfied.

The

inspector

also selected

several

locations that required routine

checks

and waited at those locations to verify that the roving

fire watch did visit the area

when due.

One roving fire watch was

accompanied

on

a complete tour of.all areas

to verify that the

tours could be made

as required.

Other than the above mentioned

administrative error no discrepancies

were identified during this

review.

e.

Spent

Fuel

Pool Inventory

The licensee

videotaped

and identified the contents of the spent

fuel pool.

This was in response

to

a commitment

made in an

Enforcement

Conference

which was held to discuss

discrepancies

in

the control of SNM.

The results of this effort identified three

areas of concern that were presented

to

PORC for resolution.

These

items

and their resolution

are

as follows:

Three pieces of LPRN were found located in

a spent fuel rack

and could not be easily removed.

Two of these

pieces

were

LPRN "cold ends" with the remaining piece being

a "hot end".

The licensee

removed the pieces,

verified they contained

no

SNM,

and shipped

them offsite.

A bucket containing miscellaneous

components

and three

channel

fasteners

was found on the pool bottom.

The

contents of the bucket were inventoried

and all components

were shipped offsite.

The area

underneath

the spent fuel racks contains

a large

amount of sediment that cannot

be reached with the

conventional

pool

vacuum

on site.

Currently there

are

no

plans to remove this material.

This c'ompleted the licensee

actions to resolve

SNH problems.

No violations or deviations

were identified in the Operational

Safety

Verification area.

0

5.

Unit 2 Pre-Outage

Work (37700)

During this period, the inspectors

noted

a significant increase

in Unit

2 modifications work.

This was being performed using

a licensee

task

managed

approach of contractor activities.

Examples of the work are

as

follows:

Modify Miscellaneous

Steel - Units

1 and

2

RB Crane

Integrated

Computer System

Emergency Lighting in the Spreader

Room

Installing new Telecommunication

Equipment

Small

Bore Supports

(COz System)

Evacuation

Alarm Upgrade

Small

Bore Supports

(HVAC System)

New HVAC System for Control

Bay

Radwaste Air Compressors

Samll

Bore Supports

(Standby Liquid Control)

HVAC Duct and Supports -

DG Bldg. Units

1 and

2

The inspectors

discussed

with licensee

management

the increase

in

scaffolding in the plant

and the potential for modifications work or

scaffolding to affect operating

equipment.

Plant management

reviewed

the reason for each scaffold in the field and ways to minimize the time

the scaffolding was in place.

The inspector will continue to monitor

these activities.

'a ~

Improper Hydrostatic

Test Pressure

The inspectors

were informed by licensee

personnel

that

a portion

of the Unit 2

RHR System

had

been unintentionally rendered

inoperable for 17 days

due to an incorrectly specified hydrostatic

test pressure

used during post modification testing.

This

licensee

determination

was based

on the identification by a

licensee modifications engineer that

a lower than required

hydrostatic test pressure

had

been

used.

This resulted

in the

determination

by operations

personnel

that the piping downstream

of RHRSW Check Valve, 2-23-530,

associated

with the 28

RHR HXCH

did not meet

ASME Section

XI requirements.

The affected

components

were isolated

from Loop II of the

RHR System

on June

20,

1992,

and

Loop II of Containment Cooling was declared

inoperable

as required

by TS 3.5.B.5.

This

LCO allowed continued

reactor

operation of Unit 2 for a period not to exceed

30 days

provided the remaining

RHR Pumps,

associated

heat exchangers,

all

D/Gs,

and all access

flow paths of the

RHR System for Containment

Cooling are operable.

While Loop II was out of service

a plug was

welded in place to perform hydrostatic testing at the correct test

pressure.

A hot-tap tool was

used to redrill the plug and the

2B

RHR HXCH returned to service at 12:00

pm on June

22,

1992.

Upon further evaluation the licensee

found that several different

sets of corrosion monitors were affected

by this problem which

appeared

to be due to failure of the licensee's

program to

adequately

define the required

source of hydrostatic test

information.

The effects of this problem"can

be placed in one of

three categories.

The first category consists of components

that

were hydrostatically tested

using

a design pressure

of 185 psig

while the system flow diagram only specifies

150 psig

as the

design pressure.

This problem affects three corrosion monitors

and

one sample valve located in the

EECW System.

The inspector

was informed that Nuclear Engineering

had evaluated this potential

problem and determined that

no damage to system piping had

occurred.

The next category includes

components hydrostatically

tested to requirements

of ASHE Section

XI (1. 1 times design

pressure)

instead of USAS B31. 1 (1.5 times design pressure)

as

required

by HAI 4.7A.

The

G29 Process

Specification

allowed the

use of ASNE Section

XI instead of USAS B31.1.

This problem

affects ll corrosion monitors

and four sample valves located

on

RHRSW piping on all three units.

The inspector

was informed that

these

components

did not impact plant operations

since the piping

was actually B31.1 rather than

ASHE and the hydrostatic pressures

used in these tests did demonstrate

structural integrity although

a licensee

procedure

(HAI 4.7A) had

been violated.

The final

category includes

components hydrostatically tested

using

a design

pressure

of 185 psig while the system flow diagram

shows

450 psig.

This includes six corrosion monitors

and two sample valves

installed in the Units 2 and

3

RHRSW lines.

One of the sample

valves

and three of the corrosion monitors are those

components

associated

with the

2B

RHR HXCH.

The remaining components

had no

direct impact

on plant operations

since hot-tap drilling had not

yet occurred.

The corrosion monitors were installed

under

DCNs W17010

and

W17046.

The specified hydrostatic test boundaries

were limited to

the access fittings and sockolets to the outside face of the

associated

piping. After weld inspections

and testing is performed

to verify structural integrity of the welds

and installed

components

a hot-tap tool is used to drill through the piping to

place the corrosion monitor in service.

System integrity is not

affected until this drilling occurs.

In both

DCNs the

modification criteria required testing of fitting welds to 185

psig prior to hot-tap drilling of holes.

Workplan 0136-91

had

been

performed to install three corrosion

monitors,

2-SUCH-023-5109A,B,

and

C,

and sample valve,

2-SNV-023-

5109, in the

RHRSW inlet to the

2B

RHR HXCH.

An inspector

reviewed the Unit 2 ASOS

Log and

LCO Log for June 5-

22,

1992, to determine

the impact of any redundant

equipment that

may have

been

removed

from service during the time that operations

personnel

were unaware that

Loop II was inoperable.

Three

examples of redundant

components

were identified as follows:

On June 8,

1992, at 4:00

am the

1C

DG was tagged

out for

scheduled

outage work.

This placed Unit 2 in a

7 day

LCO

provided all

CS,

RHR, systems

were operable.

However, since

Loop II was inoperable

the unit should

have

been in cold

shutdown within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />

(TS 3.9.B.3).

This

LCO was exited

at 2:00

am on June

9,

1992

(22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br />).

On June

15,

1992, at 5:00

pm 2-SI-4.2.B-45A(a) I, Functional

Testing of RHR Loop I Automatic Initiation Logic and

Injection Valve Opening Pressure

Permissive

Logic, started.

This SI resulted

in Loop I of RHR and Containment

Cooling

not being operable.

This would have normally placed the

unit in

a

7 day

LCO provided

Loop II was operable

(TS 3.5.B.6).

Since

Loop II was not available then

TS 3.5.B.8

applied

and the unit would have

had to be in cold S/D in 24

hours.

The

LCO associated

with the SI was exited at 8:00

pm

on the

same

day

(3 hrs).

On June

17,

1992,

at 4:31

pm 2-SI-4.2.8-45A(c) I, Functional

Testing of RHR Loop I Valve Logic and Interlocks, started.

This SI resulted

in Loop I of RHR and Containment

Cooling

not being operable.

This would have normally placed the

unit in

a 7 day

LCO provided

Loop II was operable

(TS 3.5.B.6).

Since

Loop II was not available then

TS 3.5.B.8

applied

and the unit would have

had to be in cold S/D in 24

hours.

The

LCO associated

with the SI was exited at 10:00

pm on the

same

day (5 1/2 hrs).

These

examples

represent

three

cases

where the licensee

would have

placed the operating unit in a condition that required licensed

personnel

to commence

an orderly shutdown

and

be in

a cold S/D

condition within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Although each

example represented

short system outages

of less

than

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in length they still

represent

entry into a condition which would require

an immediate

plant shutdown.

These failures to prevent

usage of an incorrect

hydrostatic test pressures

in approved workplans constitutes

usage

of inadequate

procedures

and is

a violation of 10 CFR 50 Appendix

B Criterion V.

This is Violation 259,

260, 296/92-24-02,

Incorrect Hydrostatic Test Pressures.

RHR Interlock

The inspector

reviewed

and observed

design activities

and

identified

a weakness

involving the Unit 2

RHR system.

This

weakness

dealt with pre-field activity work.

One involved

installation problems with DCN W17065A, issued to install

interlocks

on certain Unit 2

RHR valves to preclude

an inadvertent

drain down of the reactor vessel.

The inspector

reviewed

an

incident investigation performed

by the licensee

on the

installation problems

associated

with DCN W17065A.

The II stated

that problems

occurred in the section of the

DCN that called for

the installation of wiring on internal limit switches in

RHR valve

e

10

2-FCV-74-57.

When personnel

opened

the valve electrical

connection

box it was discovered that the required limit switches

were not present.

Additional reviews indicated:

the design

engineer

interpreted

schematic

drawing,

2-45W799-11,

as indicating

the valve contained

the necessary limit switches;

the electrical

connection

diagram,

2-45N2749-8,

did not depict the limit

switches;

the limit switch development

drawing,

2-47A370-74-52,

also did not depict the necessary limit switches;

the design

engineer relied on verbal

information from the

TVA/HOV group to

confirm the existence of the limit switches;

and additional

information such

as the

EQ binder was not used

by the design

engineer to confirm the verbal information.

One violation was identified in this paragraph.

6.

Unit

1 Activities

7.

A limited number of walkdowns occurred in Unit

1 spaces

necessary

to

obtain information to support Unit

1 work during Unit 2 Cycle

6 outage

that must

be accomplished

with all three units defueled.

These

activities were tracked in the

POD and discussed

at the

POD meeting.

Unit 3 Restart Activities

(30702)

The inspector

reviewed

and observed

the licensee's

activities involved

with the Unit 3 restart.

This included reviews of procedures,

post-job

activities,

and completed field work; observation of pre-job field work,

in-progress field work,

and

QA/QC activities; attendance

at restart

craft level, progress

meetings,

restart

program meetings,

and management

meetings;

and periodic discussions

with both

TVA and contractor

personnel,

skilled craftsmen,

supervisors,

managers

and executives.

a

~

Work Activities

b.

During this report period the recirculation

and

RWCU piping

replacements

were performed

on schedule.

Inspection of these

activities was documented

in a regional

IR 92-26.

Other

activities were cooling tower refurbishment,

drywell chiller

installation,

and

CRDR.

While these activities are proceeding,

the problems

encountered

with the cooling tower work must

be

resolved to insure timely and quality completion of Unit 3

recovery efforts.

Cooling Tower Refurbishment

The inspector

reviewed the work activities associated

with the

cooling tower refurbishment.

The licensee identified moisture in

several

cooling tower fan motors after the motors

had

been

previously refurbished.

The motors meggered

bad

and nine motors

were pulled to be dried.

The cause of this problem was initially

determined to be from water running

down conduit into the motor

lead connections.

The licensee initiated II-B-92-042, Moisture

11

Found in Cooling Tower Fan Hotors, to fully review the problem.

Also,

an electrical splice in cooling tower

1 located

on

a cable

supplying

480V power to

a fan motor had failed under load.

Additional observations

and reviews indicated that

a total of 61

such splices

were identified in towers

1, 5,

and 6.

The inspector

observed

the failed splice,

which came completely apart

under load

causing

a faulted circuit.

Additional splices

were observed

some

of which appeared

to be

on the verge of failing.

II-B-92-044,

Failure of Splices

On Power Supply Cable to Cooling Tower Fan

Hotors,

was initiated to fully review the splice problem.

Identification of these

problems

when fan testing

was in progress

for a scheduled

completion date of June

30,

1992 was alarming.

This problem appeared

to be the cause of the fire that completely

destroyed

the number four tower on Hay 10,

1986.

UNR 259,

260,

296/88-16-02

was closed

in IR 88-27

based

on the actions

taken

and

the cooling towers being deenergized.

The investigation

team

report

on the fire by the U.S.

Bureau of Alcohol, Tobacco

and

Firearms,

issued July 17,

1986,

determined

the cause of the fire

to be the result of a short to ground in a 440 volt electric power

cable feeding the cooling tower fan motor.

The cooling towers are non-safety related

equipment

and are not

needed to place

an operating unit in a safe

shutdown condition.

The units were originally placed into operation without the use of

cooling towers;

however,

cooling towers were later- added

and

operated

to maintain cooling water discharged

into the Tennessee

River within environmental

temperature limits.

Subsequently,

the

environmental

temperatures

were relaxed

and the cooling towers

were not routinely used during plant operation.

There were six

cooling towers,

two per reactor.

This year because

of less than

average rainfall and

a river temperature

of 80 degrees,

the

cooling towers

are expected to be needed.

Identification of these

problems with the cooling tower fans

nearing completion of the refurbishment

work is indication of a

lack of quality oversight in the maintenance

and modifications

work.

Since this is one of the first major tasks to be completed

by the construction

contractor, this indicates

a more aggressive

approach to quality workmanship is strongly needed.

Overhaul of

an electric motor and replacement

in a system with the

corresponding

meggar checks,

etc. is basic electrical

maintenance

work.

Later in the report period another

problem was reviewed which

involved the contractors

replacement

of defective cable splices in

the electrical

power feeds to the fan motors.

The splices

done by

the contractor were not installed in accordance

with requirements.

The requirements

indicated that when installing these

types of

splices the connections

were to be torqued

and the torquing

recorded.

The construction craft supervision

apparently

decided

that because

the cooling towers are non-safety related the

0

12

torquing was not required

and that all electrical

connections

could be

made

snug tight.

The inspector

observed

and reviewed the constructor's

corrective

action involving the installation of electrical

connections

in

cooling towers

1, 5,

and 6.

Part of the corrective action

was to

gather,

on

a shift basis, all electrical craft personnel,

in the

contractor's training facility and hold

a class

room session

on

electrical

work at

BFN.

The inspector

attended

a session

and

noted that the contractor's

management

emphasized

to all craft

personnel

the importance of following the licensee's

procedures.

The management

also emphasized

that for electrical

work there

was

no difference

between safety-related

and non-safety related.

The

requirements for making electrical

connections

were the

same for

both.

The inspector will do additional followup in this area

as

more information becomes

available.

This is identified as

an

Inspector

Followup Item IFI 259,

260, 296/92-24-03,

Lessons

Learned

From Inadequate

Cooling Tower Electrical Installation

Activities.

These

are documented

in Incident Investigation

Reports

II-B-92-042, 044,

and 048.

Stop

Work on Electrical Calculations

On June

26,

1992, the site quality manager

issued

a stop work

order for the issuance

and

use of electrical distribution

calculations

prepared

in accordance

with the Unit 3i contract with

Bechtel.

The stop work order was issued after

a series of

corrective actions

by the contractor to address

calculation

deficiencies

were not effective.

The calculations

reviewed

by TVA

corporate

engineering

contained technical

errors although they had

been through the final Bechtel corrective action.

A SCAR was

written to document the problems

and track the corrective actions.

Of four calculations

reviewed three contained deficiencies.

The

three with errors

are listed below:

o

ED-93057-920035,

Diesel Generator

Load Study

ED-(3057-920036,

4 KV Short Circuit Study

o

ED-(3057-910236,

4

KV Short Circuit

For example,

the

DG load study did not document multi-unit

operation

adequately.

The inspector questioned if the current problem was related to

problems

using the rollover process

in DCN preparation identified

several

months

ago.

A meeting

was held with licensee

management

and the problem was stated to be unrelated.

Previous corrections

related to the rollover process

would not have corrected

the

calculation problems.

13

The inspector

reviewed the three calculations

and the problems

were technical

and not process

type problems.

This was not

related to the rollover process

problems.

In the civil area the

calculation quality was good.

The licensee

developed

an action plan to correct the problems.

No

DCNs were issued that involved these calculations.

The

calculations

were

some of the first ones

issued.

The action plan

will consist of a joint review of ten issued calculation, root

cause identification,

and

a detailed action plan.

The inspector

will continue to followup the licensees

action plan to correct the

identified issues.

Pilot/Prototypical

Program

1.)

Walkdown

The inspector continued to monitor and review the licensee's

pilot/prototypical program involving the

SPOC/SPAE

process

for the cooling towers.

The inspector

accompanied

licensee

representatives

from various departments

on

an electrical

walkdown of cooling towers

1,

5,

and 6,

and the 4160

V

transformers

and switchgear.

The walkdown was performed in

accordance

with approved

procedures

and approximately

50

deficiencies,

the majority being minor in nature,

were

identified.

The inspector reviewed the resul.ts of the

walkdown and noted that

on the spot corrections

were made,

service request,

work requests,

and work orders

were written

to correct the deficiencies.

2.)

Testing

The inspector monitored

and reviewed the licensee's

activities involved with cooling towers

1, 5,

and 6.

The

licensee

stopped testing

on the cooling towers

due to the

electrical installation problems.

The inspector

attended

two JTG meetings

which were conducted

in accordance

with an

approved

procedure.

The main topic of discussion

was pre-

operational test procedure

3-RTP-027C.

The objectives of the test were to satisfy the baseline test

requirements

and additional test requirements

necessary

to

return Cooling Towers

1, 5,

and

6 to service.

Specific

objectives

were:

Design Baseline Test Requirements,

2/3-BFN-BTRD-027, were

Provide

warm water channel

level indication in the

Hain Control

Room,

Hode 027-01.

Provide forebay level indication in the Hain Control

Room for manual

operator actions,

Hode 027-02.

14

o

Provide cooling tower lift pump discharge

water high

temperature

signal to the

4

KV Power Distribution

System

and the corresponding

cooling tower lift pump

trips for Pumps lA, 1B,

5A, 5B,

6A,

and 68,

Modes 027-

03 and 57-5-05.

o

Provide manual

vacuum breaking capability to prevent

backflow of cooling tower warm water discharge

into

the forebay

upon trip of the

CCW Pumps,

Mode 027-04.

o

Provide forebay/warm water channel differential level

indication in the Hain Control

Room,

Mode 027-05.

Additional Test Requirements

were,

o

Verify that Cooling Tower Blowdown flow

instrumentation

indicates flow when valves

1-FCV-27-

148 and 2-FCV-27-148 are

opened during Cooling Tower

system Helper Mode operation.

o

Verify that Cooling Tower system

Gate

lA2 operates

locally and from the Hain Control

Room Panel

0-9-56

subsequent

to deletion of gate automatic controls.

o

Verify the operation of Cooling Tower 5 and

6 Lift

Pumps through the Cooling Tower bypass lines.

The

JTG recommended

approval of the test to the plant

manager.

Construction Activities

The inspector monitored

and reviewed the construction activities

performed

on the

new drywell chiller system.

The

new drywell

chiller system involved

DCN 17913A and implementing

WP 0583-92,

which installed the electrical

equipment,

conduit

and cable for

the two drywell chillers.

The inspector

noted that the work

documents

and support information were present

at the work site,

all work activities were controlled

and supervision

and

engineering

support were present.

The inspector

noted that

a

cable

bend radius

problem was identified by the electrical craft

involving the power feed to the south chiller.

The inspector

observed

a TVA field engineer

and

a construction field engineer

doing field observations

and issuing

a

FDCN to adequately

address

the

bend radius problem.

The inspector will continue to monitor

the field design activities

on the

new drywell chiller

installation.

1 5

8.

Reportable

Occurrences

(92700)

The

LERs listed below were reviewed to determine if the information

provided met

NRC requirements.

The determinations

included the

verification of compliance with TS and regulatory requirements,

and

addressed

the adequacy of the event description,

the corrective actions

taken,

the existence of potential

generic- problems,

compliance with

reporting requirements,

and the relative safety significance of each

event.

Additional in-plant reviews

and discussions

with plant

personnel,

as appropriate,

were conducted.

(CLOSED)

LER 260/92-001,

Average

Power

Range Nonitors

(APRNs)

Failure

Due to Flow Converter

Power Supply Which Caused

the

APRN

Output Trip Relays to Fail to Trip.

On February 21,

1992, during

performance of an

APRN functional test it was determined that the

Hi-Hi Flux Thermal

Flow Biased Trip associated

with "A", "C", and

"E" channels of the "A" APRN was inoperable.

The failure was

determined to be due to welded contacts

on the three

K19 relays

which apparently resulted

from chattering.

A previous review of

this

common

mode failure and the licensee

subsequent

investigation

is discussed

in more detail in Inspection

Report 92-05.

As the

result of this unforseen failure the licensee

has revised 2-SI-

4.2.C-7(A-I), Power

Range

Neutron Nonitoring System

Loop A Flow

Bias Instrumentation Calibration

and Functional Test, to require

that the appropriate

relays

be checked for damage if portions of

the SI are performed in Run Node due to degraded

flow channel

output.

Based

on the above review and licensee's

actions

completed in this area the inspector determined that adequate

licensee

actions

have occurred to preclude

a recurrence of this

event.

9.

Action on Previous

Inspection

Findings

(92701,

92702)

a

~

(CLOSED) IFI 259,

260, 296/92-05-01, Activities of the Unit 3

Restart

Review Board

and Unit 2/3 Restart Criteria.

The inspector

identified this item during

a review of the licensee's

management

meetings

involving Unit 3 specific restart

items.

The inspector

noted that during the management

meeting the group was referred to

as the Restart

Review Board.

During the Unit 2 recovery,

the

RRB

was tasked with specific areas

to review and determine restart

status.

In the recovery of Unit 3,

a

RRB was determined

as not

necessary

because

the Unit 3 restart

would have the

same criteria

and the

same corrective actions

as Unit 2.

The inspector

was

informed by the licensee that the meeting

was not

a Unit 3 RRB.

The meetings

were established

to determine

the applicability of

non-programmatic

design

changes

implemented

in Unit 2 to the Unit

3 restart effort.

The inspector

was also informed that in order

to facilitate the reviews the group decided to use the Unit 2

RRB

format.

The inspector

reviewed three licensee

documents,

two from the

licensee to the

NRC,

and

one internal

document.

The two documents

16

from the licensee

were dated January

9,

1991

and July 16,

1991.

Both documents clearly stated

and outlined the criteria and

restart

items required for Units

1 and 3.

The third document

stressed

the need to clarify the process

for controlling

NRC

commitments

down to the working level of the onsite organizations.

This document also stressed

the need to explain the regulatory

frame work for the recovery of all three

BFN units.

The inspector

concluded

from this review that the responsible

onsite

organizations

were aware of the criteria for the restart of Unit

1

and

3 and the meetings

were not for purpose of changing restart

criteria.

b.

(CLOSED) VIO 296/91-26-03,

Fuel Handling Errors.

This item

involved two fuel handling errors in the Unit 3 spent fuel pool

while performing fuel sipping operations.

On June

29,

1991,

a

fuel movement error occurred

due to fuel handlers incorrectly

identifying and moving

a fuel assembly different from the one

identified on the transfer form.

Prior to restarting fuel

movement

second party verification was

added but another error

occurred

on July 6,

1991.

The licensee

conducted

an incident

investigation of the events

and contractor personnel

involved were

given disciplinary action.

Communications

were improved by

placing

a supervisor

on the bridge to monitor fuel handling

activities

and communications.

An operator's

communication aid

(list of questions)

was established

to formalize oral

communications

between the bridge

and the

SRO,

and

a radio was

provided to the bridge

and the

SRO to assist

in communications.

The inspector

had reviewed the events

at the time of occurrence.

A followup review of the licensee's

closure

package

was conducted.

The actions taken

addressed

the violation.

10.

Exit Interview (30703)

The inspection

scope

and findings were summarized

on July 17,

1992 with

those

persons

indicated in paragraph

1 above.

The inspectors

described

the areas

inspected

and discussed

in detail the inspection findings

listed below.

The licensee

did not identify as proprietary

any of the

material

provided to or reviewed

by the inspectors

during this

inspection.

Dissenting

comments

were not received

from the licensee.

Item Number

Descri tion and Reference

260/92-24-01

259,

260, 296/92-24-02

259,

260,

296/92-24-03

UNR, Hissed Appendix

R Firewatch,

paragraph

four.

VIO, Incorrect Hydrostatic Test Pressure,

paragraph five.

IFI, Lessons

Learned

from Inadequate

Cooling Tower Electrical Installation

Activities, paragraph

seven.

0

17

Licensee

management

was informed that

1

LER,

1 IFI, and

1 VIO were

closed.

Acronyms

and Initialisms

ASME

ASOS

AUO

BFNP

CFR

CRDR

CS

DCN

DG

EECW

FCV

HPFPS

HVAC

HXCH

IFI

II

IR

LPRM

LCO

MOV

MR

NRC

POD

PORC

PSI

QA

QC

RB

Recirc.

RHR

RHRSW

SCAR

S/D

SI

SNM

SSP

TS

TVA

UNR

VIO

WO

WR

American Society of Mechanical

Engineers

Assistant Shift Operations

Supervisor

Auxiliary Unit Operator

Browns Ferry Nuclear Plant

Code of Federal

Regulations

Control

Room Design Review

Core Spray

Design

Change Notice

Diesel

Generator

Emergency

Equipment Cooling Water

Flow Control Valve

High Pressure

Fire Protection

System

Heating, Ventilation, Air Conditioning,

and Cooling

Heat Exchanger

Inspector

Followup Item

Incident Investigation

Inspection

Report

Local

Power

Range Monitor

Limiting Condition for Operation

Motor Operated

Valve

Maintenance

Request

Nuclear Regulatory

Commission

Plan of the

Day

Plant Operations

Review Committee

Pounds

Per Square

Inch

Quality Assurance

Quality Control

Reactor Building

Recirculation

Residual

Heat

Removal

Residual

Heat

Removal

Service

Water

Significant Corrective Action Report

Shutdown

Surveillance Instructions

Special

Nuclear Material

Site Standard

Practice

Technical Specifications

Tennessee

Valley Authority

Unresolved

Item

Violation

Work Order

Work Request