ML18033A992

From kanterella
Jump to navigation Jump to search
Insp Repts 50-259/89-38,50-260/89-38 & 50-296/89-38 on 890816-0915.Violations Noted.Major Areas Inspected:Maint Observation,Surveillance Observation,Operational Safety Verification & Control of Licensed Operator Status & Mods
ML18033A992
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 10/02/1989
From: Carpenter D, Little W, Patterson C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18033A989 List:
References
50-259-89-38, 50-260-89-38, 50-296-89-38, NUDOCS 8910200123
Download: ML18033A992 (35)


See also: IR 05000259/1989038

Text

~p,ll AKC(1,

o

Cy

(l

x

O

++*sr+

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTASTREET, N.W.

ATLANTA,GEORGIA 30323

Report Nos.:

50-259/89-38,

50-260/89-38,

and 50-296/89-38

Licensee:

Tennessee

Valley Authority

6N 38A Lookout Place

1101 Market Street

Chattanooga,

TN

37402-2801

Docket Nos.:

50-259,

50-260

and 50-296

License Nos.:

DPR-33,

DPR-52,

and

DPR-68

Facility Name:

Browns. Ferry 1, 2, and

3

Inspection

Conducted:

August 16 - September

15,

1989

Inspector

R.

r

nt

,

S

e

anager

Dat

ned

tt

n,

RC Restart

oor snator

Accompanied by:

E. Christnot,

Resident

Inspector

M. Bearden,

Resident Inspector

.

K. Ivey, Resident

Inspector

B.

o

,

oj

En

neer

Approved by:

N. S. Li t

, Sect

on Chief

Inspection

rograms

TVA Projects Division

Da

Date Si

e

gned

SUMMARY

Scope:

This. routine resident inspection

included surveillance observation,.

maintenance

observation,

operational

safety verification, control of licensed

operator

status,

restart

test

program,

modifications,

and

site

management

and

organization.

Results:.

One violation was identified for failure to conduct adequate

PMT,. paragraph

3.

These

examples.

along, with the

PMT problems. identified. in IR 89-27. indicate a

~

~

~

~

~

weakness,

irr PMT.

Considering'he

volume of world activities at the site,.

adequate-

PMT is. an essential

part of the. recovery: effort..

Although: PMTs are.

designated

in MRs, examples

have

been

found where. there

was

no method to ensure

that

PMTs are complete prior to returning. equipment to service.

3910200123

391002

PDR

ADOCK 0 000259

0

PDC

Housekeeping

and identification of material deficiencies

needs

improvement in

the plant areas

not frequently traveled

(Paragraph

4.).

An unresolved

item

is identified in Paragraph

6 concerning

a

long standing

issue

over the

disposition of Restart Test

Progrgam

TEs.

An unresolved

item concerning

the

control of composite

crews

was identified in paragraph

8.

In the area of site

management

the Technical

Support Superintendent,

Outage

Manager,

and Assistant

Outage

Manager

have all resigned.

The licensee

had

adequate

notice of the

resignations

and is seeking replacements.

A non-cited violation concerning

a failure to conduct

a

JTG meeting

in

accordance

with procedures

was identified in paragraph

6.

REPORT

DETAILS

Persons

Contacted

Licensee

Employees:

  • 0. Zeringue, Site Director

G. Campbell, Plant Manager

  • R. Smith, Project Engineer

"J. Hutton, Operations

Superintendent

<<A. Sorrell, Maintenance

Superintendent

D. Mims, Technical

Services

Supervisor

G. Turner, Site guality Assurance

Manager

  • P. Carier, Site Licensing Manager
  • P. Salas,

Acting Compliance Supervisor

J. Corey, Site Radiological

Control Superintendent

R. Tuttle, Site Security Manager

Other

licensee

employees

or

contractors

contacted

included

licensed

reactor operators,

auxiliary operators,. craftsmen,

technicians,

and public

safety officers; and quality assurance,

design,

and engineering

personnel.

NRC'mployees

  • D. Carpenter,

Site Manager

  • C. Patterson;

Restart Coordinator

  • E. Christnot, Resident Inspector

<<M. Bear den, Resident Inspector

<<K. Ivey, Resident

Inspector

B. Long, Project Engineer

  • Attended exit intervie~

Acronyms used, throughout this report are listed in the last paragraph.

Surveillance Observation

(61726)

The inspectors

observed

and/or reviewed the SI procedures

discussed

below.

The inspections

consisted

of a review of the SIs for technical

adequacy

and

conformance

to

TS, verification of test

instrument calibration,

observation

of the conduct of the test,

confirmation of proper

removal

from service

and return to service of the system,

and

a review of the test

data.

The inspector also verified that limiting conditions for operation

were met, testing

was

accomplished

by qualified personnel,

and the

SIs

were completed at the required frequency.

a.

On; August, 15

1989;. the licensee- ran

a TS required'I

O'-SI-4'.2.8-67'

"RHR Service- Mater Initiation: Logic,." to verify proper operation of

the initiation logic for the

EECW/RHRSW pumps.

Subsequent

licensee

review identified that this SI inhibited the automatic start of all

EEL pumps

which is required

by the safety analysis.

The

EECM pumps

are required

to supply cooling water to the

DGs

upon

automatic

aebxation of the

DGs.

Failure to maintain the automatic

pump start

Ametion

made

the

EECM

pumps

and all eight

DGs inoperable.

On

August 24,

1989,

at 7:07 p.m.

(CDT), the

licensee

made

a 4-hour

ace-emergency

ENS report to the

NRC Duty Officer concerning this

event.

This will be followed up by the

NRC in a special

inspection

esmcerning SI's (IR 89-43).

b.

Bemng this reporting period, the licensee verified the control

rod

d'~ice integrity.

This activity involved the

use of

a

general

procedure,

a technical instruction

and

two surveillance instructions

as follows:

2-GOI-100-3

TI-20

2-SI -4.3.B.1. b

Refueling Operations

Control

Rod Drive System Testing

Control

Coupl ing

Integrity

Check

After

Refueling

or Maintenance

0

2-SI-4.10.B

Demonstration

of 'Source

Range'onitoring

System Operability During Core Alterations.

7hz 2-SI-4.3.B.1;b procedure

performe'd'y

the licensee fulfilled the

surveillance requirement to observe that the drive does

not go to the

evertravel

position

when the control

rods

are fully withdrawn the

First time after

each refueling outage

or after maintenance.

The

P-SE-4.10.B

procedure fulfilled the surveillance

requirement that the

SR'hall

be functionally tested

and

checked for neutron

response

prior to making any alterations

to the core.

The licensee

withdrew

arrd inserted

each

control

rod one at

a time during this activity.

%he inspector

observed

the operation

of the control

rods

and the

associated

control

room activity.

No deficiencies

were identified.

c.

%are

inspector

observed

a

scheduled

performance

of

procedure

2-SI-4.4.A.1,

Standby Liquid Control

Pump Functional Test.

This SI

$s performed

on

a quarterly frequency to determine

the operability of

the

SLC pumps

and includes

taking suction from the

SLC test tank

and

rezoning

the

pumps.

No deficiencies

were identified during the

performance of this SI.

3.

Naim@avance

Observation

(62703)

Pled

maintenance

activities of selected

safety

related

systems

and

camperreats

were observed/reviewed,

to ascertain if they were conducted. in

acceptance

with. requirements.

The: following'tems were" considered.

during.'his

renew:

the limiting; conditions for operations

were met,. activities

were accomplished-

using

approved

procedures,,

functional testing and/or

calibrations

were performed prior to returning

components

or systems

to

service,

quality control

records

were

maintained,

activities

were

accomplished

by qualified

personnel,

parts

and

materials

used

were

properly certified, proper tagout clearance

procedures

were

adhered to,

Technical

Specification

adherence,

and

radiological

controls

were

implemented

as required.

Maintenance

requests

were reviewed to determine

the status

of outstanding

jobs

and to assure

that priority was. assigned

to safety related

equipment

maintenance

which

might affect

plant

safety.

The

inspectors

observed/reviewed

the

below listed

maintenance

activities

during this

report period:

a.

Failure to Perform Post Maintenance

Testing

On

August

28,

1989,

the

licensee

identified that

PMT

was

not

completed for work performed

on the

"3C"

DG.

The

DG

was

taken

out-of-service

on August 2,

1989, for the

performance

of scheduled

maintenance activities.

MR A-893300

was performed

on August 4, 1989,

to calibrate

the

ASLR; however,

the

PNT identified on the

NR was not

completed

following the work.

The

DG was returned

to service

on

August 10,

1989.

Failure to perform the

PMT was

brought to the

attention of the

SOS

on August 28, 1989.

The licensee

then completed

the

PNT

and closed

out the

MR.

The

ASLR functions to keep the

DG

from starting

on

an automatic signal if the operator

has

stopped

the

DG, from running

by using the. emergen'cp fast stop pushbutton

or the

normal operating

handswitch

while an accident

signal is locked in.

Failure of the

ASLR in any

mode

would not inhibit the

DG from

starting

on receipt of an accident signal without operator action.

Other examples

of safety related

equipment

being returned to service

following maintenance

prior to completion of required

PMT occurred

when

the

"D2"

and

"D3"

RHRSW

pumps

were

declared

operable

on

August 16,

and

September

1,

1989 respectively.

In both

cases

the

errors

were not discovered until final review of the

MRs, at that

time the

PMTs

were

accomplished.

Subsequent

licensee

evaluation

determined

that

the

work was

associated

with non safety

related

components

(alarm

relays)

and

had

not directly

impacted

the

operability of the

RHRSW pumps.

Technical

Specifications

and administrative

procedures

require that

written procedures

be implemented

covering testing of safety related

equipment.

PMI 6.2,

"Conduct of Maintenance,"

requires that

PMT be

performed following corrective

maintenance

activities

and

SDSP 6.7,

"Post Maintenance

Test

Program,"

establishes

the

program to ensure

that

PNT is performed.

The failure to perform required

PMT following

maintenance

activities

is- a. violation of TS 6.8.1.1.c for failure to

implement procedures.

(VIO 259,. 260 296/89-38-01,. Failure to: Conduct

PNT)..

This'icensee

identified" viol'ation is, being: cited'ecause.

of

a'imilar

violation concerning

PMT in IR'9-27.

These

examples

indicate

a

weakness

in the control of

PMT.

Although

PMTs are

designated

on

MRs,

no checks

were performed to insure that the

PMTs

were completed prior to returning equipment to service.

b.

Flow Test of "2C"

RHR Room Cooler

This test

was

performed

under

a

new technical

instruction

and

MR

821382

on September

14,

1989.

The flow was determined

to be 10,325

cubic feet per minute which was within the acceptance

criteria of

10,000

a

10%.

No deficiencies

were identified.

4.

Operational

Safety Verification (71707)

The inspectors

were

kept informed of the overall plant status

and

any

significant safety matters related to plant operations.

Daily discussions

were held with plant management

and various

members of the plant operating

staff.

The inspectors

made routine visits to the control

rooms.

Inspection

observations

included

instrument

readings,

setpoints

and

recordings;

status

of operating

systems;

status

and alignments of emergency

standby

systems;

onsite

and offsite

emergency

power

sources

available

for

automatic

operation;

purpose of temporary tags

on equipment controls

and

switches;

annunciator

alarm status;

adherence

to procedures;

adherence

to

limiting conditions

for

operations;

nucl.ear

instrument

operability;

temporary alterations

in effect;. da~ily journals

and logs; stack monitor

recorder traces;

and control

room manning.

This inspection activity also

included

numerous

informal discussions

with operators

and supervisors.

General

plant tours

were conducted.

Portions of the turbine buildings,

each reactor building, and general

plant areas

were visited.

Observations

included

valve

positions

and

system

alignment,

snubber

and

hanger

conditions,

containment

isolation

alignments,

instrument

readings,

housekeeping,

proper

power supply

and breaker

alignments,

radiation

area

controls,

tag controls

on equipment,

wor k activities

in progress,

and

radiation

protection

controls.

Informal

discussions

were

held with

selected

plant personnel

in their functional areas

during these tours.

a ~

Unit Status

All three units

remained

in an extended

outage

as part of the

8FNP

recovery

plan.

Units

1

and

3 are

defueled

with Unit 2 in cold

shutdown

with fuel

loaded.

Work activities

continued

toward the

restart of Unit 2 in 1990.

The licensee

has identified

a series of

milestones

for returning

groups of systems

to service for restart.

The first milestone,

Condenser

Vacuum

Systems,

was

achieved

on

September

1,

1989 with the exception of some

items.

These

items

dealt mainly with the- closure of engineering

paperwork.

No worlc.

activities have

begun

on Units

1 and 3.

b.

c ~

RPS Circuit Protectors

On August 26, 1989, at 12:17 p.m.

(CDT), Unit 1 received

an automatic

ESF actuation

when

RPS

bus

1B was deenergized.

Unit

1 received

a

half-scram;

PCIS groups

2, 3, 6, and 8 isolations;

SBGT trains A, B,

and

C starts;

and actuation of CREV trains

A and

B.

Investigation

into the event revealed that

RPS circuit protectors

1B1 and

1B2 were

tripped.

The licensee identified the cause of the trip to be

RPS

MG

set voltage fluctuations

which resulted

in the circuit protectors

sensing

overvoltage

and tripping.

Recurring

problems with circuit

protector trips are

being followed up by the

NRC during reviews of

the

LERs submitted

on the separate

events.

(See

IR 89-40 paragraph

2.g)

Electrical

System

Walkdowns

During this reporting period,

the inspector

walked

down two of the

site electrical

systems.

One system,

the offsite power system,

is

non-safety related

and the other system,

the plant

DC system is both

non-safety related

and safety related.

The purpose of the walkdown

was to verify the as-built equipment status of both systems

in order

to have

a better understanding

of both systems

in case of a station

blackout.

The following drawings

were utilized..for the offsite power

system

walkdown:

45N500

0-15E500-1

3-15E500-3

Switchyard Wiring Diagram Single Line

Units

1 and 2,

Key Diagram of Normal

and Standby

Auxiliary System

Unit 3,

Key Diagram of Normal

and Standby Auxiliary

Power System.

The offsite power system at the

BFN facility consists

of three main

transformers,

500

KV to 20.7

KV, and

two

common station

service

transformers,

161

KV to 4.16

KV.

The site

has

seven

500

KV feeder

lines

and two 161

KV feeder lines.

During plant operations,

the 20.7

KY sides of the three main transformers

are fed from the Units

1 thru

3 generators,

with

a direct tie to

a total of six unit service

transformers,

20.7

KV to 4.16

KV, two UST per main transformer.

The

most significant equipment

arrangement

for the

BFN offsite

power

system is that

each unit generator

has

an output breaker

located

between

the generator

and the respective

mai.n transformer.

With this

type of arrangement

during

a reactor

scram,

the output breaker for

the turbine trips. open

and the main transformer

back feeds

from the

500

KY grid system

to the unit transformers.

Consequently,

the

electrical'ystem

has. a bumpless transfer..

0

0

The following drawings

were utilized for the

DC

power

systems

walkdown:

0-45E701-2,

45E701-2

Battery Boards 1,2,3 and 4

0-45E702-1,

45-E702-2

0-45E702-3,

45-E703-1

0-45E703-2,

45-E704

1-45E705,

2-45E706

3-45E707

Turbine'uilding 250 Volt Distribution

0-45E709-1,

3-45E709-2

Shutdown

Boards

250 Volt Batteries

and

Chargers

0-45E786-9,

0-45E786-10

120 Volt DG Batteries

and Chargers

3-45E786-17,

3-45E786-18

The

DC power

system at the

BFN facility consists of six subsystems:

the four 250 volt unit boards with batteries

and chargers;

the three

250 volt Turbine Building Distribution, which receive

power from the

unit boards;

the

250 volt shutdown

boards

control

power system with

batteries

and chargers;

the

120 volt

DG panels

with batteries

and

char gers;

the

two

48 volt annunciator

distribution

systems

with

batteries

and chargers;

and the three

+24 volt -24 volt

DC system

with batteries

and

chargers.

.

The .most significant

equipment

arrangement for the

BFN

DC systems

is the versatility of the

250 volt

sections

of the four unit battery boards.

This system

can

be lined

up to feed

normal

and alternate

power to

a variety of systems,

including

DC motors which can provide power to the unit preferred

NG

sets for IKC AC power,

MOVs for the

ECCS

and to air compressors

in

the

DG starting air systems.

No deficiencies

were identified during

the walkdown.

d.

RHRSW Cable Tray Tunnel

Walkdown

On August 19,

1989,

two

NRC inspectors

toured the

RHRSW Cable Tray

Tunnel.

This tunnel

runs

from the intake structure

underground

to

the turbine building.

The cable trays hold one division of the

RHRSW

pump cables.

RHRSW provides

cooling water from the ultimate heat

sink at

BFNP.

From the

number of deficiencies

identified,

in

general,

the tunnel

area cleanliness

and housekeeping

were considered

unsatisfactory.

The following items were identified:

There were num>rous burnt out light bulbs which required the use

of a flashlight in portions of the tunnel.

None of the bulbs

had protective

guards.

The light bulbs are near

a persons

head

in height

and

some

areas of the tunnel

contained

two to three

inches of water on: the floor..

Water was found in several

cable trays near

an area

where seven

three inch conduit outlets enter the tunnel.

Water was dripping

out of the outlets;

and

a splash

pan

was

inadequate

to prevent

standing water in several

cable trays.

Examples

were found where cables

changed

from one cable tray to

another tray,

and

cables

were found hanging

underneath

cable

trays suspended

by wire ties.

Water in-leakage

was observed at several

grouted

areas

between

sections of the tunnel.

The last

monthly

check

of

two

permanently

mounted fire

extinguishers,

T2 and T3, was performed in May 1989.

guestionable

splicing of several

cables

located in the trays

was

identified.

A junction box or splicing

box was located in the

cable tray, not seismically supported.

There

were several

loose wires, wires cut,

and

abandoned

wires

without any identification.

Several

examples

were clustered at

location 72C4.

Miscellaneous

trash

was identified in several

trays.

A fire hose, of questionable

nature

and material condition,

was

running along the floor of the tunnel in the water.

In the area of the tunnel

near the turbine building entrance

an

open junction box without a cover was observed

in the overhead.

There

was

a

maze of wires dangling outside

and

between

cable

trays at the turbine building entrance.

The magnitude of these

deficiencies

was

discussed

with the Plant

Manager

on August 19,

1989.

The inspector took the Plant Manager

and

members

of his staff

on

a tour of the

area

on August 24,

1989.

During this tour, the inspector observed that steps

had been

taken to

remove the standing water on the floor, improve lighting, update fire

extinguisher inspections,.

and general

housekeeping.

Drywell Walkdown

On August 18,

1989,

two

NRC inspectors

inspected

the Unit 2 drywell.

The general

condition of the drywell was what would be anticipated

for

a unit in

an

outage.

There

was

evidence

of ongoing

work

activities

by the scaffolding,

temporary

power cords,

and rigging

equipment.

A~ few. minor items of concern: were observed..

The upper walkways

had fire extinguishers

standing

up without

being, tied off or being, laid. on their side.

The monthly fire extinguisher

check for fire extinguisher

812

was last performed in June,

1989.

Several yellow hard hats

were abandoned

on the top walkway.

The

licensee

had recently initiated

a program that requires

hard

hats to be used in contaminated

areas.

Personnel

exchange their

hard hat for a yellow one at the area entrance

and are

supposed

to bring the yellow hard hat to the area exit.

Various

sections

of loose

thermal

insulation lying outboard

against the drywell wall.

A light bulb was not covered

by a protective cover similar to

other bulbs in the area.

This was near penetration

2-X-26.

Most of the ventilation outlets

had loose or damaged directional

vanes to direct the air flow.

Other deficiencies

were identified by plant tags

as

problems.

The

plant health

physics staff was

most helpful

and interested

in any

health physics

concerns identified by the inspectors.

The results of

the drywell tour were discussed

with the Plant Manager following the

tour.

f..

Radwaste, Building Walkdown

On September

1,

1989, the inspector toured the radwaste

building due

to

a recent

problem at another facility concerning

routine flooding

of a room containing

55 gallon storage

drums.

Based

on discussions

with a radwaste

supervisor,

no rooms are routinely flooded and there

have

been

no flooding problems in the radwaste building.

Some

sumps

are

located

below

ground

level

but are

designed

as

sumps.

In

general,

housekeeping

in the radwaste building was good.

g.

Control

Room Tour

On

September

7,

1989,

the

NRC inspector

noted

several

items of

concern

during

a tour of the Unit 2 control

room.

These

items were

discussed

with the operations

manager

following the tour

and are

listed below:

The drywell floor drain

sump level

abnormal

annunciator

was

illuminated because

of an equipment

problem but no maintenance

request

had

been written to correct the problem.

.This alarm

indicates

a

high or low level

in

the* sump

and the actual

condition must

be verified by

a local

gauge

in the reactor

building

The operator stated, the alarm. occurs. after the

sump

pump stops, pumping: and: the. level. was. actually lower=

Area

Radiation

Chart

Recorder,

2-RR-90-1,

was

recording

meaningless

information.

The chart

has

a rotating wheel

which

is supposed

to print the

number of the monitor points which is

being recorded.

No numbers

were being printed and only red dots

recorded.

Several

other recorders

with the

same

problem were

2-TR-56-2Y, 2-TR-85-7A, 2-TR-85-7B, 2-TR-85-7C,

and 2-TR-56-3.

Deficiency tags

were

on emergency

equipment.

For example,

an

emergency

battery

powered

lantern

contained

a deficiency tag

dated

6/12/89

stating

that there

was

corrosion

inside

the

lantern.

An emergency

stretcher

cabinet

had three deficiency

tags

hung on it.

The condenser

vacuum

gauge

on the main control panel 9-7 was in

units of absolute

pressure

which was inconsistent with the plant

annunciator

response

procedure

2PA-47-125 which was in inches of

vacuum.

Plant operators

expressed

a concern

regarding

the modification

elevating

the

SOS work station in the control

room.

The work

station

was

being partitioned off with office partitions. which

were not transparent.

From the reactor operators

desk,

these

partitions restricted 'their view of some panels.

These

concerns

were discussed

with the operations

manager following

the tour.

h.

Fire Barrier Penetration

Seals

An inspector

toured

selected

areas

of the plant to observe

the

condition of the fire barrier penetrations,

and requested

to review

the

gC inspection

records for the fire seals

on the wall between

the

Unit 1/Unit 2 reactor

and turbine buildings, near the turnstiles, at

the 565'levation.

The records

were not provided

by the licensee

prior to the

end of the inspections.

Demonstration

by the licensee

that

the

selected

fire barrier

penetrations

had

been

properly

installed

and

adequately

inspected

by

gC

was identified

as

IFI

89-38-02,

Proper Installation of Fire Seals.

In conclusion,

based

on recent plant tours of the

SBGT room (IR 89-33)

and

RHRSW

cable. tray tunnel,

housekeeping

and identification of material

deficiencies

in areas

not frequently traveled

needs

improvement.

Plant

management

has

been

responsive

to these

concerns

as

observed

by cleanup

crews

in other

areas

such

as

the

condensate

storage

tank pipe gallery

tunnel

and ventilation towers.

General

plant tours

and the tour of the

drywell indicate housekeeping

efforts have

been satisfactory in frequently

traveled areas.

No violation or deviations. were- identified.

10

Control of Licensed Operator

Status

(41701,

71707)

An inspector

reviewed the licensee's

program for control of assignment

of

licensed operators

to Unit 2 control

room duties.

Specifically the review

was conducted

to determine if licensee

controls

were adequate

to prevent

non-licensed

or non-qualified

licensed

operators

from willfully or

inadvertently assuming responsibility for licensed operator watch stations

at

Browns Ferry.

This review resulted

from a recent

event at another

facility where

a

licensed

operator

who

had failed his

most recent

requalification examination

had

assumed

the watch in the control

room as

the operator-at-the-controls.

This event

had

gone undetected

by onshift

management

for approximately

three

hours

due to the lack of current

information in the control

room

and failure to aggressively

implement

existing procedures.

The inspector

held discussions

with

NRC Region II Operator

Licensing

Section

personnel,

TVA Operations

and Training Management

personnel,

and

TVA Operations shift personnel.

Control

room logs

and operations shift

schedules

for the months of July and August 1989 were reviewed along with

lists of qualified licensed

operators

provided both

by

NRC Region II and

TVA's training

department.

The inspector

noted that

the applicable

procedural

requirements

were

contained

in Plant

Manager

Instruction

(PMI) - 12.12,

Conduct

of Operations.

PMI-12.12,

Section

4.6.2.1,

requires

that all

off-going operators

shall

not relinqui sh their

responsibilities

until satisfied. that the. oncoming

operator

is fully

qualified. and/or licensed

to assume

the shift position.

Section 4'.5.12,

requires

that the

oncoming

SOS

make shift assignments

to implement the

weekly shift schedule.

The

program is further

implemented

through

established

policies

and practices

rather than documented

procedures.

The inspector visited the control

room on two backshifts

and requested

the

SOS

demonstrate

the ability to determine

up-to-the-minute

status

of

selected

licensed

personnel.

In both cases

this

was accomplished

by use

of the published weekly shift schedule

which was annotated with codes for

those respective

personnel

that either were not qualified or restricted

in

the

performance

of licensed

duties.

The inspector

noted= that

as part of

the shift relief each

oncoming

SOS reviews the qualifications of oncoming

personnel

at the beginning of the shift and

makes

an operating

log entry

of the

number of available

SRO

and

RO licensed

individuals present that

will be part of the relieving crew.

The inspector

reviewed the above

two lists of qualified licensed

operators

and compared that information to the information contained

on the current

weekly operations shift schedule.

The names of 10 licenced operations

and

training, personnel

that the inspector determined

were not qualified due to

recent

exam failures or were otherwise restricted

from licenced duties

were compared

to, the Unit 2 operating

logs. for July and August,, 1989.

No

probTems'ere

identified': during, that. review.

The inspector

noted. that

each

of. these

10; individuals

was. properly reflected. on the current weekly

schedule

as not being qualified.

0

11

Primary responsibility for notification of on-shift

management

of

a

disqualifying event

associated

with

a particular individual appears

to

depend

on the

nature

of the

event.

For example,

for failure of a

requalification

exam,

the training section is responsible for grading the

exam

and direct notification of personnel

assigned

to the training

department,

while the Operations

Supervisor

must notify personnel

in his

section.

For

personnel

assigned

to the

operations

sections,

the

operations

supervisor is notified via telephone

by the Training Section

Supervisor.

Requalification

exams

are normally given

on Fridays of each

cycle training week with the

exams

graded

no later than Tuesday of the

following week.

The Operations

Supervisor is responsible for tracking the active status of

all licensed

personnel.

At Browns Ferry, active status

is maintained

by

working a minimum of seven

8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> shifts or five 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> shifts performing

licensed

duties

per calendar

quarter.

In the

case of requalification

failure or loss of active status,

the operations

supervisor is responsible

for notifying on-shift management

(SOS) that

a particular person

can

no

longer

be

used for licensed

duties.

The notification is to

be

made

immediately

following determination.

This

system

results

in verbal

notification of on-shift management

within the

same

workday with written

notification by way of the following weekly shift schedule

which would

include an update of that individual's status.

The inspector determined that although several

licensed operators

recently

failed, requalification

examinations

there

has

not

been

a significant

impact

on the ability of the licensee

to properly man operating shifts in

the present

mode (shutdown/refuel)

without the use of excessive

overtime.

For* example,

in the present

mode only

1

SRO and

3

RO licenced

personnel

are required

to meet technical

specification

requirements.

There

are

normally at least

2

SROs

and

5

ROs

on each shift.

There could exist

a

shortage

of licensed

operators,

particularly

SROs with active status,

to

support Unit 2 startup.

Out of 36 licenced

SROs

on site only 13 are

maintaining current active status.

The inspector

noted that the licensee's

program appeared

adequate

not only

for providing on-shift management

with current information covering requal

exam failures but also reflects other information useful for the

purpose

of making decisions

concerning

the proper manning of the shift crews.

The

weekly schedule

also contains

information about medical restrictions

and

expired active status.

Additional information is included which provides

the qualification levels of non-licensed

operators

and yearly cumulative

overtime totals for each individual.

No violations or deviations

were

identified.

Restart Test Program

(99030B)

The. inspector. maintained'ognizance

of. ongoing, restart test acti.vities

ant monitored particular activities in detail

as appropriate.

Specific

inspection observations

are discussed

below:

12

a.

RTP Test Exceptions

The

RTP

generates

test

exceptions

whenever

difficulties

are

encountered

during the conduct of a restart test.

This activity is

governed

by

SDSP

12.1,

Restart

Test

Program,

Section

6.6,

Test

Exceptions.

The following is stated

in section 6.6.1 of SDSP 12.1:

Test

Exceptions

shall

be

documented

on

a

Test

Exception

Form

(SDSP-94),

inserted

into the test

package,

and

be

indexed

on

Appendix B.

TEs may consist of any of the following items:

(1)

Unexpected

or unusual

data

(2)

Procedural difficulties (not to be used in lieu of change)

(3)

Data outside acceptance

criteria

4)

Damage

or failure

of plant

structures,

systems,

and/or

components

(5)

Operates

in a suspected

adverse

manner

(6)

Inability to signoff a step,

but will be signed off as written

later

(7)

Partial release

by JTG.

NUREG 1232,

Volume 3,

BFN Nuclear Performance

Plan, section 4.6.2.2,

Implementation,

subsection

(3)(a) states:

The

RTP is not

a stand

alone activity.

The licensee

has

been

reluctant to issue

and

process

a condition adverse

to quality

report

(CARR) for TEs that clearly should require

such reports

under

TVA's CA( program.

The tendency

has

been

to identify

problems

and fix them

by investigation,

analysis,

evaluation,

and

sometimes,

resolution of problems identified in the

RTP,

solely under the

TE activity.

This action is not consistent

with the

CA( program that should

cover all plant activities

affecting quality.

These

concerns

have

been

discussed

with

Browns

Ferry managers.

TVA has

stated

that it will provide

CA(Rs in parallel with TEs where conditions warrant

them.

The

NRC staff will continue to monitor this activity.

Under the

Browns Ferry

RTP, it is possible

to satisfactorily

close

out

a test without closing all

TEs against that test.

Those

TEs should

be classified

by their significance

and tracked

on the

SNPL.

However,

the overall

program to provide for the-

appropriate identification, tracking, resolution,

and closure of

the significant

TEs identified in the

RTP should

include the

CA(R.

The

NRC inspector

monitoring the

RTP reviewed

TEs, both

opened

and

closed,, identified during the performance of four RTP procedures.

13

b.

Specific

RTP Test Exceptions

Review

The inspector

reviewed

a total of 84

TEs identified during the

performance of four RTP test procedures

as follows:

(1)

2-BFN-RTP-031A,

Control

Bay

Heating

Ventilating

and

Air

Conditioning System.

The

RTP test

group documented

a total of

ten

TEs

as

a result of the performance of this procedure.

The

inspector

noted that TE-08

was left as

an

open

TE due to the

fact that

EMI 60,

Inspection

and Preventative

Maintenance

of

Control

Bay Chillers,

had not been

completed

by the time the

RTP

procedure

was

reviewed for closure.

The closure of TE-08 is

dependent

on completing

EMI 60,

which in turn requires

the

completion of

DCN

W0156,

replacement

of temperature

control

valve 0-TCV-67-62.

TE-07, which documented

the fact that the

Unit

1 and

2 Control

Bay chill water

pumps

and the air handling

unit chilled water flows failed to meet acceptance

criteria,

was

reviewed

and

the inspector

noted that this significant test

exception did not result in the generation of a CA(R.

Further

review of the

completed

procedure

indicated

that

TE-07

was

reviewed

by the

RTP group using criteria established

in

SDSP

" 3.13,

Corrective

Actions.

However,

section

6.6,

CARR

Determination,

subsection

D states:

Test deficiencies

which,

by evaluation,

indicate that the

item does. not comply with the license design

basis

or will

affect plant technical

specifications

shall

be placed

on

a

CARR if "accept-as-is"

or "repair"

actions

are

being

considered.

(2)

It should

also

be

noted that

SDSP

3.12,

CSSC

and

non-CSSC

Listing,

attachment

B,

Critical

Structures

System

and

Components,

section

6.0,

Main Control

Bay,

subsection

6.2,

Control

Bay

and

Shutdown

Board

Room Air-Conditioning systems

lists air handling unit and

pumps.

The licensee's

decision not

to use

a

CARR to document this deficiency does not appear to be

consistent

with

the

plant

methodology

for identifying

significant deficiencies.

Additional

review of this

item

indicated that TE-10 was

added to the procedure after

RTP Test

results

were

approved.

TE-10 indicated that TE-07

was

being

closed

out

by

the

use

of

a

Temporary

Alteration,

TACF

0-88-002-031.

This

use of a

TACF to closeout

a significant TE

also

does

not appear

to

be consistent

with plant deficiency

identification and closeout methodology.

2-BFN-RTP-031B, Control

Bay HVAC.

The

RTP test group documented

a total of 28

TEs

as

a result of the

performance

of this

procedure

The inspector noted: TEs 24'5~ 26,, and, 28'ere left

as:

open

TEs.

Closeout

of these

TEs,

was,

dependant

on

modifications being completed,

maintenance

or the performance of

technical instructions.

TE-27, which was considered

closed,

was

reviewed

and referenced

a post modification test,

PMT 161,

as

a

method for closing the TE.

A review of PMT 161 indicated that

a

test deficiency,

TD-5,

was

documented

and

addressed

the fact

that

flow balance

criteria

could

not

be

met.

The

TE-27

indicated that

based

on interim approval

of TD-5, the

TE was

considered

closed.

During the

review of this

item,

the

inspector

did not observe

any documentation

that the

TD was

reviewed against baseline

requirements.

This is another

example

of what appears

to be

an activity not in keeping with the plant

identification

and

close

out

of significant

deficiency

methodology.

(3)

2-BFN-RTP-074, Residual

Heat Removal

System.

The

RTP test group

documented

a total of 37 TEs

as

a result of the performance of

this

procedure.

The

inspector

noted that TE-ll and

TE-35

discussed

the discovery of a wiring error between

panels 9-3 to

9-32

and 9-33.

These

TEs resulted

in the initiation of a

CARR

88-0668

which identified

a significant TE. It was also noted

that

TEs

08

and

34 also discussed

a wiring error within panel 9-33,

however,,

a

CARR

was

not generated

to, identify this

significant TE.

This inconsistency

is not in keeping with the

plant identification

and

closeout

of significant deficiency

methodology.

I

(4)

2'-BFN-RTP-099,. Reactor Protective

System

The.

RTP Test group

documented

a total of nine TEs as

a result of the performance of

this procedure.

The inspector

noted that

TEs 4, 5,

and

6 were

written to indicate that portions of RTP-099 would be performed

as part of other

RTP procedures,

RTP-001,

Main Steam

Restart

Test

and

RTP-047,

Turbine Generator

Control.

These

TE do not

meet

the criteria for TEs

and should

have

been

processed

as

intent changes

rather than TEs.

The inspector discussed

these observations

with the licensee

and they

indicated that certain activities

by the restart test group were not

in keeping with the

RTP as discussed

in the

NPP Volume I or the

SER.

This is identified

as

URI 259,

260, 296/89-38-03,

Possible

Failure

to Follow the

BFN Program for Identifying and Closing Significant

Test

Exceptions

and

to Control

Procedure

Changes.

Additional

reviews of these test

procedures

indicated that the

RTP test

group

identified several

concerns

involving the

use of uncalibrated volt

meters,

the shorting out of pressure

switches,

equipment

not being

maintained,

and the overall inability to get specific items repaired.

These

items

are

discussed

in the conclusions

and

recommendations

sections

of the

RTP completed

procedures.

The inspector could not

verify- that. any corrective action

had

been initiated by management

as

a. resul't of the RTP'roup observations

and. recommendations

written in the test summaries.

15

c.

Joint Test Group

On August 16, 1989, the inspector attended

a meeting of the JTG.

The

meeting

was convened to approve

new members of the JTG.

The JTG is a

subcommittee

of

PORC

and is the review, approval,

and coordinating

body of the Restart Test Program.

The list of membership

was being

expanded

to include

members

from the

Nuclear

Fuels

Department

in

preparation for the

power ascension

testing

program planning.

The

chairman for the meeting

was the Restart Test Manager

who had

been in

licensed operator training for the past

few months.

SDSP 27.4, Revision 4, "Plant Operations

Review Committee," requires

the

JTG chairman to

be the Technical

Support

Superintendent

or

a

designated

PORC

member.

PORC

members

are designated

in writing by

the Plant

Manager.

The Restart

Test

Manager

was not

a designated

PORC

member.

This item was discussed

with the Acting Restart

Test

Manager

who stated

that

up through

Revision

3 of

SDSP

27.4,

the

Restart

Test

Manager or

a designated

PORC

member

was

allowed to

chair

JTG meetings.

A draft of

a revision to correct this

was

reviewed immediately after the meeting

by the inspector.

A NCV was identifieg for this,

NCV 259. 260, 296/89-38-04,

Failure to

Conduct

JTG Meeting in Accordance

With Plant Procedure.

TS 6.8.1.1.j

requires

that

procedures

shall

be established,

implemented,

and

maintained

covering

the

administrative

procedures

which control

technical

and cross-disciplinary

review.

This

NRC. identified Level

V

violation is

not

being

cited

because

criteria

specified

in

Section

V.A of the

NRC Enforcement

Policy were satisfied.

This

violation will

be

tracked

to

avoid

repetitively

exercising

'enforcement discretion for the

same

issue.

The

JTG meetings

should

be conducted

in accordance

with plant procedures

and

known problems

corrected prior to the meetings.

Another

JTG meeting

was

attended

on

August

23,

1989.

At this

meeting,

the

JTG membership

changes

were resubmitted

because

of the

chairman conflict on August 16,

1989.

This meeting

was chaired

by

the Technical

Support Superintendent.

7.

Modifications (37700,

37828)

The- NRC inspector

reviewed

and observed

the licensee's

activities in the

modifications area.

This included review of procedures;

discussions

with

craft,

gC inspectors,

supervisors

and

managers;

observations

of field

activity; and review of WPs,

DCNs,

and

FCNs.

The review and observation

consisted of the following:

a.

The inspector

reviewed

the following procedures:

flAI 3.2,

Cable

Pul'1'ing; for.. Insulated'ables:

up. tor 15,000'olts

dated June 24:1989;.

and MAI 3.3:,, Cable Terminating; and. Splicing for Cable

Rated. to 15,000

Volts.

The

inspector

noted

that

each-

procedure

had

several

16

attachments.

Each attachment

contained the individual activities

and

attributes

that the craft supervisor

and the

gC inspector

signs

as

being completed.

b.

DCNs and

ECNs

The

NRC inspector.

reviewed

DCN 0479A,

DCN 0480A, and

FCN P7137.

The

two DCNs dealt with the

BFN ampacity issue

and the

ECN dealt with the

AC/DC calculation deficiencies.

Each

DCN/ECN generated

several

MPs.

, Of the

DCN,

ECN,

and

WPs the following reviews

and observations

were

made:

DCN N0479A

WP 2304-88,

This item required

the

replacement

of undersized

cables for 2-FCV-74-52

and 2-FCV-74-104 in the

RHR system.

The

NRC inspector

observed

the electrical craft

and

gC inspector

routing the

replacement

cables

for 2-FCV-74-52 through

cable

trays located in the Unit 2 reactor building.

MP2309-88.

This item required

the replacement

of undersized

cables

for 2-FCV-74-57,

58,

and

59 in the

RHR system.

The

inspector

observed

the electrical

craft

and

gC

inspectors

routing the replacement

cables for 'these

valves

through cable

trays located in Unit 2 reactor building.

All field activities for these

two

WPs were accomplished

in an

organized

manner

according

to

procedures

with cooperation

displayed

between

the craft and

gC inspectors.

DCN MOBOA

0'P

2387-88.

This. item required

the replacement

of cables

to

RHRSM

pumps

B2

and

B3.

This

DCN was

returned

to

PORC for

additional

licensee

reviews.

The review

was

prompted

by the

fact that the replacement

cables

are larger than the old cables

and may have resulted in routing problems.

The

NRC inspector

noted

that

the

MAI procedures

indicate

what

attributes

the

gC inspectors

are to use in monitoring craft activity.

However,

the

gC inspectors

have their own procedures

referred to as.

IPs.

There

appears

to be

some conflict between

what the MAIs direct

the

gC inspectors

to do and what the IPs direct the

gC inspectors

to

do.

The

NRC inspector will followup the

gC inspector activities in a

later inspection.

No: violations or deviations

were identified;

Site Management.

and. Organization

(36301

36800',.

40700)'n

inspector

reviewed the corrective actions

taken at

BFNP in response

to

a violation previously identified at

Sequoyah

Nuclear Plant involving

composi,te

maintenance;

crews.

On March. 14,, 1988 the-

NRG. issue

an

NOV.

17

against

Sequoyah

for

implementing

composite

crews

without

having

established

training

and qualification requirements

for

1)

foremen

and

general

foremen

supervising

personnel

in other crafts,

2)

craftsmen

performing

work outside

of their craft,

and

3)

craftsmen

performing

independent

verificati ons

outside

of their

craft

( Violati on

327,

328/87-78-02).

TVA admitted

the violation and committed to address

the

generic implications of the violation at other sites.

Requirements

for foremen supervising

composite

crews

were

issued

in an

NIZAM guality Notice on July 6, 1988.

The notice required that foremen of

composite

crews

who did not meet the ANSI 18.1-1971

requirement for four

years

experience

in each craft or discipline which they supervised either

be provided direct access

to technical

support in other disciplines or be

given

documented

training equivalent

to the required

experience.

The

requirements

of the

NIZAM guality Notice were

implemented at Browns Ferry

by

PMI 6.2,

"Conduct of Maintenance",

Section 4.2.

PMI 6.2 distinguishes

between

"composite"

and "mixed" maintenance

crews.

Composite

crews contain multiple craft disciplines,

such

as electricians

and mechanical craft,

and are not used at Browns Ferry.

Although

MOVATS

work is performed

by both electrical

and mechanical

craft,

each

group

reports

to their

own foreman

and the task are separated

on the training

matrix

by discipline.

The

procedure

requires

the

foreman

to

have

cross-discipline

equivalency training for properly making work assignments

and to ensure

adequate

understanding

of the scope of work. If the foreman

does, not have. task equivalency'raining'a

lead

craftsman

with the

required qualifications must assist

the foreman in his duties.

Mixed maintenance

crews

are defined

as combinations of the various crafts

within the

mechanical

discipline,

such

as

machinists,

fitters,

and

insulators.

Foremen of mixed maintenance

crews require four years of

experience,

but do not require four years

in each

area

being supervised.

The equivalency training requirements

and lead craftsman provisions

do not

explicitly apply.

The

inspector

was

concerned

that

the

foremen

qualification. policy for mixed

crews

might not

be in accordance

with

ANSI 18.1 and the

NIZAM.

At Sequoyah,

procedure

SgM-70

was

issued to address

the qualifications of

composite

crew members

performing work outside their craft.

No analogous

procedure

was

issued

at Browns Ferry to specifically establish

the method

of operation

and responsibilities

for the

use of composite

maintenance

crews.

BFN management

stated that cross-training

between

craftsmen within

the

general

mechanical

discipline

eliminated

the skill-of-the-craft

concerns

documented

in Sequoyah

IR 327, 328/87-78.

Based

on. interviews

with selected

craftsmen

assigned

to mixed crews,

the inspector

was

concerned

about the validity of this assumption.

The inspector.

determined. that SDSP5:

"Independent

Veri,fication."'

applied; adequately

to composite

crews

in that the procedure- required.

independent

verifications to

be

performed.

by individuals qualified to

perform

the

steps

be'ng

verified.

However,

licensee

management

18

acknowledged

that only one

member of a composite

crew was required to be

qualified to perform each task being worked.

The inspector questioned

how

the independent

verification requirements

of SDSP 3.15 could

be properly

implemented with only one qualified individual assigned

to the work.

The

licensee

responded

that craft from other crews were frequently brought in

to sign the verifications.

Licensee

management

also stated that many of

the independent verifications performed during jobs which are

on the task

matrix require

no expertise

or established

qualifications.

The inspector

identified the area of independent verifications by composite

crews to be

a concern.

Prior to

NRC inspection

327,

328/87'-78,

the

TVA

NNRG conducted

an

evaluation of composite maintenance

crews at Browns Ferry and Matts Bar in

response

to allegations

received

by the

NRC and the

BFNP

ECP.

The

NNRG

administered

an oral

questionnaire

to

a

number of craftsmen

who

had

received

waivers of required

OJT in areas

outside of their craft.

The

questionnaire

was

designed

to

measure

the ability of craftsmen

to

independently

perform the waived task.

The

study,

found that

a high

percentage

of those

examined failed to demonstrate

the necessary

level of

knowledge.

Deficiencies

were

also identified in the waiver process

criteria, execution, quality assurance,

and records

handling.

In response

to the

NMRG findings,

BFN plant management

upgraded

the waiver process,

and initiated

a waiver review and validation program which redid a(l the

waivers

and

also

included

a

computer

printout of craftsman

task

qualifications to

be

used for making job assignments.

During, September

1988,. the-

NRC inspect'or

reviewed the Engineering

and. Technical

Training

Section Letters applicable to Training permanently

assigned

mechanical

and

electrical craft,

and

compared

the requirements

of these

procedures

to

ANSI N18.1-1971.

The inspector also reviewed

and revised waiver criteria,

reviewed

selected

records,

and

observed

examples

of the waiver review

process

in progress.

No deficiencies

were identified in the material

reviewed.

Subsequent

to Sequoyah

inspection

327, 328/87-78,

the licensee

performed

an evaluation at

Browns Ferry

and

Sequoyah

to determine

what corrective

actions

would be necessary

to resolve the identified deficiencies

in the

training and qualification of composite

crews

and to determine whether

any

rework would be necessary

as

a result of those deficiencies.

Cases

were

identified where

documentation

of training for a particular task

being

performed

did

not exist,

although

this

finding also

applied

to

non-composite

crews.

The study did not identify any rework done

as

a

result of composite

crew deficiencies.

The following recommendations

were

presented

in a licensee

memorandum

dated

December

21, 1988:

Issue

a corporate

standard

on composite= crew operations.

Increase

management

attention to the- training and waiver process,

and

implement improvements

in~ maintenance training

0

19

Administratively limit the use of composite

crews

and ensure

adequate

supervision of composite

crew operations until a procedure similar to

S(Ns

SgM-70,

which defines

composite

crew operations,

can

be

implemented at BFN.

Procedurally

address

the issue of the number of qualified individuals

per

crew required to provide

needed

expertise for the tasks

to be

performed.

The licensee

report also

documented

a concern regarding

compliance of the

qualifications of mixed crew foremen

and general

foremen with ANSI 18.1.

The Plant

Manager

issued

a

memorandum

dated

February

15,

1989,

which

responded

to the recommendations

of the composite

crew report.

As of the

time of the inspection,

the

licensee

had

not

completed

the

actions

specified in the memorandum.

Although significant

progress

toward

procedural

controls of composite

crews

was evident, sufficient information

was not available

during the

inspection to conclusively establish

that qualifications of mixed crews

were adequately

covered

by existing, plant procedures,

and, that procedural

requirements

were

being

acceptably

implemented.

Verification that

adequate

corrective

actions

have

been

completed

at

Browns

Ferry in

response

to

Sequoyah

violation

327,

328/87-78-02

was

identified

as

Unresolved

Ltem 89-38-05

and resolution

is required prior to Unit 2

restart.

No violations or deviations. were identified.

9.

Exit Interview (30703)

The inspection

scope

and findings were

summarized

on September

15,

1989

with those

persons

indicated

in paragraph

1

above.

The

inspectors

described

the

areas

inspected

and discussed

in detail

the inspection

findings listed below.

The licensee

did not identify as proprietary

any

of the material

provided to or reviewed

by the inspectors

during this

inspection.

Dissenting

comments

were not received

from the licensee.

Item

259, 260, 296/89-38-01

259, 260, 296/89-38-02

259,, 260, 296/89-38-03

~0i ti

VIO, Failure to Conduct

PMT, paragraph

3.

IFI, Proper

Installation of Fire

Seals,

paragraph

4.

URI, Possible

Failure to Follow the

BFN

Program

for

Identi fying

and

Cl os ing

Significant. Test. Exceptions- and. to; Control

Procedure

Changes

paragraph 6;

20

Item

~cont'd)

259, 260,. 296/89-38-04

259, 260, 296/89-38-05

Acronyms

Descri tion

NCV, Failure

to

Conduct

JTG

Meeting

in

Accordance

With Plant Procedure,

paragraph

6.

URI, Corrective Action on Composite

Crews,

paragraph

8.

ANSI

ASLR

BFNP

CAQR

CDT

CFR

CREVS

CSSC

DCN

DG

ECCS

ECN

ECP

EECW

EMI

ENS

EO

ESF

FSAR

GOI

HVAC

IFI

IR

JTG

KV

LER

MG

MOV

MR

NCV

NMRG

NOV

NPP

NIZAM

NRC.

PMI'MT

PCIS

PORC

American National Standards

Institute

Auto Start Lockout Relay

Browns Ferry Nuclear

Power Plant

Condition Adverse to guality Report

Central Daylight Time

Code of Federal

Regulations

Control

Room Emergency Ventilation System

Critical Structures,

Systems,

and

Components

Design

Change Notice

Diesel

Generator

Emergency

Core Cooling Systems

Engineering

Change Notice

Employee

Concerns

Program

Emergency

Equipment Cooling Water

Electrical Maintenance Instruction

Emergency Notification System

Environmental qualification

Engineered

Safety Feature

Final Safety Analysis Report

General

Operating Instructions

Heating, Ventilation,

8 Air Conditioning

Inspector

Followup Item

Inspection

Report

Joint Test Group

Kilovolt

Licensee

Event Report

Motor Generator

Motor Operated

Valve

Maintenance

Request

Non-cited Violation

Nuclear Manager

Review Group

Notice of Violation

Nuclear Performance

Plan

Nuclear guality Assurance

Manual

Nuclear Regulatory

Commission

PTant Manager Instruction

Post Maintenance/Modification Test

Primary Containment Isolation System

Plant Operations-

Review Committee.

21

QC

RHR

RHRSW

RO

RPS

RTP

SBGT

SDSP

SER

SI

SLC

SMPL

SOS

SRO

SRM

TACF

TCV

TD

TE

TI

TS

TVA

URI

UST

VIO'P

Quality Control

Residual

Heat Removal

Residual

Heat Removal

Service Water

Reactor

Operator

Reactor Protection

System

Restart Test Program

Standby

Gas Treatment

System

Site Director Standard

Practice

Safety Evaluation Report

Surveillance Instruction

Standby Liquid Control

Pump

Site Master

Punch List

Shift Operations

Supervisor

Senior Reactor Operator

Source

Range Monitor

Temporary Alteration Change

Form

Temperature

Control Valves

Test Deficiency

Test Exception

Technical Instruction

Technical Specifications

Tennessee

Valley Authority

Unresolved

Item

Unit Service Transformer

Violation,

Work Plan