ML18025A862

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Repts 50-259/79-48,50-260/79-47 & 50-296/79-47 on 791210-800104 & Notice of Violation
ML18025A862
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 03/21/1980
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parris H
TENNESSEE VALLEY AUTHORITY
Shared Package
ML18025A860 List:
References
NUDOCS 8005200125
Download: ML18025A862 (4)


See also: IR 05000259/1979048

Text

~ RE0y

~O

"o

e

P~

0O

ee

<r+~

gO

+**++

Zn Reply Refer To:

RII:RFS

50-259/79-48

50-260/79>>47

50-296/79-47

UNITEDSTATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTAST., N.W., SUITE 3100

ATLANTA,GEORGIA 30303

MAR g g

J98O

~

~

Tennessee

Valley Authority

ATTN:

H. G. Parris

Manager of Power

500A Chestnut Street Tower II

Chattanooga,

TN

37401

Gentlemen:

This refers

to the inspection

conducted

by R. F. Sullivan of this office on

December

10,

1979 - January 4,

1980 of activities authorized

by NRC Operating

License

Nos.

DPR-33,

DPR-52,

and

DPR-68 for the

Browns Fe'rry facility, and to

the discussion of our findings held with H. L. Abercrombie and J. L. Harness at

the conclusion of the inspection.

Areas

examined

during the inspection

and

our findings are

discussed

in the

enclosed

inspection

report.

Within these

areas,

the inspection

consisted

of

selective

examinations of procedures

and representative

records,

interviews with

personnel,

and observations

by the inspectors.

During the inspection, it was

found that certain activities under your license

appear

to be in noncompliance

with NRC requirements.

This item and references

to pertinent requirements

are listed'in the Notice of Violation enclosed herewith

as Appendix A.

This notice is sent to you pursuant to the provisions of Section

2.201 of the NRC's "Rules of Practice," Part 2, Title 10, Code of Federal Regula-

tions.

Section .2.201 requires

you to submit to this office, within 20 days of

your receipt of this notice,

a written statement or explanation in reply including:

(1) corrective steps

which h'ave been taken by you and the results

achieved;

(2)

corrective steps

which will be taken to avoid further noncompliance;

and (3) the

date when full compliance will be achieved.

In accordance

with Section 2.790 of the NRC's "Rules of Practice," Part 2, Title

10, Code of Federal Regulations,

a,copy of this letter and the enclosed inspection

report will be placed in the NRC's Public Document Room. Ifthis .report contains

any information that you (or your contractor) believe to be proprietary, it is

necessary

that you make awritten application within 20 days to this office to

withhold such

information from public disclosure.

Any,such application must

include

a full statement of the reasons

on the ba'sis of which it is claimed that

the information is proprietary,

and should be prepared

so that proprietary infor-

mation identified in the application is contained in a separate

part of the

document. If we do not hear from you in this regard within the specified period,

the report willbe placed in the Public Document Room.

0

MAR 81

~ggp

Should you have any questions

concerning this letter',

we will be glad to discuss

them with you.

Sincerely,

g.c.

R.

C.

ewxs, Acting Chief

Reactor Operations

and Nuclear

Support Branch

Enclosures:

l.

Appendix A, Notice of Violation

2.

Inspection Report Nos. 50-259/79-48

50"260/79-47

and 50-296/79-47

cc w/encl:

H. L. Abercrombie

Plant Superintendent

P.

O. Box 2000

t

Decatur,

AL

35602

R. E. Rogers, Project Engineer

400 Chestnut Street

Tower II

Chattanooga,

TN

37401

E.

G. Beasley

Tennessee

Valley Authority

309 Grant's Building

Knoxville, TN

37902

Qii