Proposed Tech Specs 3/4.5 Re Emergency Core Cooling Systems
ML18022B007
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 03/10/1997
From:
CAROLINA POWER & LIGHT CO.
To:
Shared Package
ML18022B006 List:
References
NUDOCS 9703190006
Download: ML18022B007 (8)


Text

3/4.5 EMERGENCY CO COOLING SYSTEMS 3/4.5.1 ACCUMULATORS COLD LEG INJECTION LIMITING CONDITION FOR OPERATION 3.5. 1 Each Reactor Coolant System (RCS) accumulator shall be OPERABLE with:

a. The isolation valve open with power supply circuit breaker open, A contained borated water volume of between 66 and 96K indicated level, A boron concentration of between 2400 and 2600 ppm. and
d. A nitrogen cover-pressure of between 585 and 665 psig.

APPLICABILITY: MODES 1, 2, and 3*.

ACTION:

With one accumulator inoperable, except as a result of a closed isolation valve restore the inoperable accumulator to OPERABLE

()t'yron Q0AL'.znIr0)~d>>

s a us wi in hour or be in at least HOT STANDBY within the next

/\os +hah lan&>f< 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and reduce pressurizer pressure to less than 1000 psig within the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.

With one accumulator inoperable due to the isolation valve being closed. either immediately open the isolation valve or be in at least HOT STANDBY within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and reduce pressurizer pressure to less than 1000 psig within the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.

SURVEILLANCE REQUIREMENTS 4.5. 1. 1 Each accumulator shall be demonstrated OPERABLE:

a. At least once per 12 .

)AS+u,AY)~ Y'CRd<n c Or

1. t Verifying, by e a sence o a arms, the contained borated water volume and nitrogen cover-pressure in the tanks. and
2. Verifying that each accumulator isolation valve is open.

9703f90006 9703i0 PDR ADQCK 05000400 P PDR

  • RCS e ure above 1'000 psig.

C.. 'w'dt one am~~<(~ter i>> oper IIc due& loaron conccnlrok<<nab<<J kh~ ~l>> 4, I

&si ~ +0 koran tAnneo tiia ~uhhi'n livhit4 wh4h '7z hog~ or 4< in ct )4~t- Q<l LQ<O

~46't Lion

/Sing Wild'n

~ p4O g bouffe GnL ran~ pre.ssurtzQ p('(u~rc,

~Allows~ $ f)gyre.

+ km ~i<

SHEARON HARRIS - UNIT 1 3/4 5-1 Amendment No. 30

3/4.5 EMERGENCY CO COOLING SYSTEMS DEBASES.

3/4.5. 1 ACCUMULATORS The OPERABILITY of each Reactor Coolant System (RCS) accumulator ensures that a sufficient volume of borated water will be immediately forced into the reactor core through each of the cold legs in the event the RCS pressure falls below the pressure of the accumulators. This initial surge of water into the core provides the initial cooling mechanism during large RCS pipe ruptures.

The limits on accumulator volume, boron concentration and pressure ensure that the assumptions used for accumulator injection in the safety analysis are met.

The value of 66K indicated level ensures that a minimum of 7440 gallons is maintained in the accumulators. The maximum indicated level of 96K ensures that an adequate volume exists for nitrogen pressurization.

The accumulator power operated isolation valves are considered to be "operating bypasses" in the context of IEEE Std. 279-1971, which requires that bypasses of a protective function be removed automatically whenever permissive conditions are not met. In addition, as these accumulator isolation valves fail to meet single fai lure criteria, removal of ower to the valve s required. Q( bbA< QbhCLnkoho~ phd ~<9ln I< mid The limits for operation with an accumulator inoperable for any reason except an isolation valve closed inimizes the time exposure of the plant to a LOCA event occurring concurrent with failure of an additional accumulator which ma result in unacceptable peak cladding temperatures. If a closed isolation valve cannot be immediately opened, the full capabi i y o one accumulator is not available and prompt action is requi red to place the reactor in a mode p, where this capability is not required.

3/4.5.2 AND 3/4.5.3 ECCS SUBSYSTEMS The OPERABILITY of two independent ECCS subsystems ensures that sufficient emergency core cooling capability will be available in the event of a LOCA assuming the loss of one subsystem through any single failure consideration.

Either subsystem operating in conjunction with the accumulators is capable of supplying sufficient core cooling to limit the peak cladding temperatures within acceptable limits for all postulated break sizes ranging from the double ended break of the largest RCS cold leg pipe downward. In addition, each ECCS subsystem provides long-term core cooling capability in the-recirculation mode during the accident recovery period.

With the RCS temperature below 350'F, one OPERABLE ECCS subsystem is acceptable without single failure consideration on the basis of the stable reactivity condition of the reactor and the limited core cooling requirements.

The limitation for a maximum of one charging/safety injection pump to be OPERABLE and the Surveillance Requirement to verify one charging/safety injection pump OPERABLE below 325'F provides assurance that a mass addition pressure transient can be relieved by the operation of a single PORV.

SHEARON HARRIS - UNIT 1 B 3/4 5-1 Amendment No. 19

'nsert A page B 3/4 5- l The boron in the accumulators contributes to the assumption that the combined ECCS water in the partially recovered core during the early reflooding phase of a large break LOCA is sufficient to keep that portion of the core subcritical. One accumulator below the minimum boron concentration limit. however, will have no effect on the available ECCS water and an insignificant effect on core subcriticality during refiood. Boiling of ECCS water in the core during reflood concentrates boron in the saturated liquid that remains in the core. In addition, current analysis demonstrates that the accumulators do not discharge following a large steam line break for HNP. Therefore, 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> is permitted to return the boron concentration to within limits.

EMERGENCY CORE COOL SYSTEMS BASER'CCS SUBSYSTEMS Continued The Surveillance Requirements provided to ensure OPERABILITY of each component ensures that at a minimum. the assumptions used in the safety analyses are met and that subsystem OPERABILITY is maintained. Surveillance Requirements for throttle valve position and flow balance testing provide assurance that proper ECCS flows will be maintained in the event of a LOCA. Maintenance of proper flow resistance and pressure drop in the piping system to each injection joint is necessary to: (1) prevent total pump flow from exceeding runout conditions when the system is in its minimum resistance configuration, (2) provide the proper flow split between injection points in accordance with the assumptions used in the ECCS-LOCA analyses, and (3) provide an acceptable level of total ECCS flow to all injection points equal to or above that assumed in the ECCS-LOCA analyses.

3/4.5.4 REFUELING WATER STORAGE TANK The OPERABILITY of the refueling water storage tank (RWST) as part of the ECCS ensures that a sufficient supply of borated water is available for injection into the core by the ECCS. This borated water is used as cooling water for the core in the event of a LOCA and provides sufficient negative reactivity to adequately counteract any positive increase in reactivity caused by RCS cooldown. RCS cooldown can be caused by inadvertant depressurization, a LOCA, or a steam line rupture.

The limits on RWST minimum volume and boron concentration assure that:

(1) sufficient water is available within containment to permit recirculation cooling flow to the core and (2) the reactor will remain subcritical in the cold condition following mixing of the RWST and the RCS water volumes with all shutdown and control rods inserted except for the most reactive control assembly. These limits are consistent with the assumption of the LOCA and steam line break analyses.

The contained water volume limit includes an allowance for,water not usable because of tank discharge line location or other physical characteristics.

The limits on contained water volume and boron concentration of the RWST also ensure a pH value of between 8.5 and 11.0 for the solution recirculated within containment after a LOCA. This pH band minimizes the evolution of iodine and minimizes the effect of chloride and caustic stress corrosion on mechanical systems and components.

SHEARON HARRIS - UNIT 1 B 3/4 5-2

3/4.5 EMERGENCY CO COOLING SYSTEMS 3/4.5. 1 ACCUMULATORS COLD LEG INJECTION LIMITING CONDITION FOR OPERATION 3.5. 1 Each Reactor Coolant System (RCS) accumulator shall be OPERABLE with:

a. The isolation valve open with power supply circuit breaker open,
b. A contained borated water volume of between 66 and 96K indicated level,
c. A boron concentration of between 2400 and 2600 ppm, and
d. A nitrogen cover-pressure of between 585 and 665 psig.

APPLICABILITY: MODES 1, 2. and 3*.

ACTION:

With one accumulator inoperable, except as a result of a closed isolation valve or boron concentration not within limits, restore the inoperable accumulator to OPERABLE status within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and reduce pressurizer pressure to less than 1000 psig within the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.

With one accumulator inoperable due to the isolation valve being closed, either immediately open the isolation valve or be in at least HOT STANDBY within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and reduce pressurizer pressure to less than 1000 psig within the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.

c. With one accumulator inoperable due to boron concentration not within limits, restore the boron concentration within limits within.72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in at least HOT STANDBY-within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and reduce pressurizer pressure to less than 1000 psig within the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.

SURVEILLANCE REQUIREMENTS 4.5. 1. 1 Each accumulator shall be demonstrated OPERABLE:

a. At least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> by
1. Verifying, by instrument readings or the absence of alarms, the contained borated water volume and nitrogen cover-pressure in the tanks, and
2. Verifying that each accumulator isolation valve is open.
  • RCS pressure above 1000 psig.

SHEARON HARRIS - UNIT 1 3/4 5-1 Amendment No.

3/4.5 EMERGENCY C COOLING SYSTEMS

,, BASES 3/4.5. 1 ACCUMULATORS The OPERABILITY of each Reactor Coolant System (RCS) accumulator ensures that a sufficient volume of borated water will be immediately forced into the reactor core through each of the cold legs in the event the RCS pressure falls below the pressure of the accumulators. This initial surge of water into the core provides the initial cooling mechanism during large RCS pipe ruptures.

The limits on accumulator volume, boron concentration and pressure ensure that the assumptions used for accumulator injection in the safety analysis are met.

The value of 66K indicated level ensures that a minimum of 7440 gallons is maintained in the accumulators. The maximum indicated level of 96K ensures that an adequate volume exists for nitrogen pressurization.

The accumulator power operated isolation valves are considered to be "operating bypasses" in the context of IEEE Std. 279-1971, which requires that bypasses of a protective function be removed automatically whenever permissive conditions are not met. In addition. as these accumulator isolation valves fail to meet single failure criteria, removal of power to the valves is required.

The limits for operation with an accumulator inoperable for any reason except an isolation valve closed or boron concentration not within limits minimi zes the time exposure of the plant to a LOCA event occurring concurrent with failure of an additional accumulator which may result in unacceptable peak cladding temperatures. The boron in the accumulators contributes to the assumption that the combined ECCS water in the partially recovered core during the early reflooding phase of a large break LOCA is sufficient to keep that portion of the core subcritical. One accumulator below the minimum boron concentration limit, however, will have no effect on the available ECCS water and an insignificant effect on core subcriticality during reflood. Boiling water in the core during.reflood concentrates boron in the saturated of'CCS liquid that remains in the core. In addition, current analysis demonstrates that the accumulators do not discharge following a large steam line break for HNP. Therefore, 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> is permitted to return the boron concentration to within limits. If a closed isolation valve cannot be immediately opened. the full capability of one accumulator is not available and prompt action is required to place the reactor in a mode where this capability is not requi red.

3/4.5.2 AND 3/4.5.3 ECCS SUBSYSTEMS The OPERABILITY of two independent ECCS subsystems ensures that sufficient emergency core cooling capability will be available in the event of a LOCA assuming the loss of one subsystem through any single failure consideration.

Either subsystem operating in conjunction with the accumulators is capable of supplying sufficient core cooling to limit the peak cladding temperatures within acceptable limits for al,l postulated break sizes ranging from the double ended break of the largest RCS cold leg pipe downward. In addition, each ECCS subsystem provides long-term core cooling capability in the recirculation mode during the accident recovery period.

SHEARON HARRIS - UNIT 1 B 3/4 5-1 Amendment No.

EMERGENCY CORE COOLI SYSTEMS

-,GASES

'CCS SUBSYSTEMS Continued With the RCS temperature below 350'F, one OPERABLE ECCS subsystem is acceptable without single failure consideration on the basis of the stable reactivity condition of the reactor and the limited core cooling requirements.

The limitation for a maximum of one charging/safety injection pump to be OPERABLE and the Surveillance Requirement to verify one charging/safety injection pump OPERABLE below 325'F provides assurance that a mass addition pressure transient can be relieved by the operation of a single PORV.

The Surveillance Requirements provided to ensure OPERABILITY of each component ensures that at a minimum, the assumptions used in the safety analyses are met and that subsystem OPERABILITY is maintained. Surveillance Requirements for throttle valve position and flow balance testing provide assurance that proper ECCS flows will be maintained in the event of s LOCA. Maintenance of proper flow resistance and pressure drop in the piping system to each injection point is necessary to: (1) prevent total pump flow from exceeding runout conditions when the system is in its minimum resistance configuration, (2) provide the proper flow split between injection points in accordance with the assumptions used in the ECCS-LOCA analyses, and (3) provide an acceptable level of total ECCS flow to all injection points equal to or above that assumed in the ECCS-LOCA analyses.

3/4.5.4 REFUELING WATER STORAGE TANK The OPERABILITY of the refueling water storage tank (RWST) as part of the ECCS ensures that a sufficient supply of borated water is available for injection into the core by the ECCS. This borated water is used as cooling water for the core in the event of a LOCA and provides sufficient negative reactivity to adequately counteract any positive increase in reactivity caused by RCS cooldown. RCS cooldown can be caused by inadvertant depressurization, a LOCA, or a steam line rupture.

The limits on RWST minimum volume and boron concentration assure that:

(I) sufficient water is available within containment to permit recirculation cooling flow to the core and (2) the reactor will remain subcritical in the cold condition following mixing of the RWST and the RCS water volumes with all shutdown and control rods inserted except for the most reactive control assembly. These limits are consistent with the assumption of the LOCA and steam line break analyses.

The contained water volume limit includes an allowance f'r water not usable because of tank discharge line location or other physical characteristics.

The limits on contained water volume and boron concentration of the RWST also ensure a pH value of between 8.5 and 11.0 for the solution recirculated within containment after a LOCA. This pH band minimizes the evolution of iodine and minimizes the effect of chloride and caustic stress corrosion on mechanical systems and components.

SHEARON HARRIS - UNIT 1 B 3/4 5-2 Amendment No.