Forwards IE Insp Repts 50-400/80-25,50-401/80-23, 50-402/80-23 & 50-403/80-23 on 800929-1031 & Notice of Violation
ML18017B301
Person / Time
Site: Harris  Duke Energy icon.png
Issue date: 11/28/1980
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Jackie Jones
CAROLINA POWER & LIGHT CO.
Shared Package
ML18017B300 List:
References
NUDOCS 8012190359
Download: ML18017B301 (3)


See also: IR 05000400/1980025

Text

In Reply Refer To:

RII'GFM

50-400/80-25

50-401/80-23

50-402/80-23

50"403/80-23

UNITED STATES

I~IUCLEAR REGULATORY COMMISSION

REGION II

104 MARIETTAST., N.W., SUITE 3100

ATLANTA,GEORGIA 30303

goy

0 8 198C

Carolina Power and Light Company

ATTN

J. A. Jones

Senior Executive Vice President

and

Chief Operating Officer

411 Fayetteville Street

Raleigh,

NC

27602

Gentlemen:

This refers

to the

inspection

conducted

by

G. F. Maxwell of this office on

September

29 - October 31,

1980,

of activities authorized

by

NRC Construction

Permit Nos. CPPR-158,

CPPR-159,

CPPR-160,

CPPR-161 for the Shearon Harris facility,

and to the discussion of our findings held with R.

M. Parsons

at the conclusion

of the inspection.

Areas

examined

during

the inspection

and

our findings

are

discussed

in the

enclosed

inspection report.. Within these

areas,

the inspection

consisted

of

selective

examinations of procedures

.and representative

records,

interviews with

personnel,

and observations

by the inspector.

Durin'g the inspection it was

found that certain activities under your license

appear to be in noncompliance with NRC requirements.

These

items

and references

to pertinent requirements

are listed in the Notice of Violation enclosed herewith

as Appendix A.

Corrective actions to prevent recurrence

were completed prior to

the conclusion of this inspection; therefore,

a reply is not requested.

In accordance

with Section 2.790 of the

NRC's

"Rules

of Practice,"

Part 2,

Title 10,

Code of Federal

Regulations,

a

copy of this letter and the enclosed

inspection report will be placed in the

NRC's Public Document

Room. If this

report

contains

any information that you (or your contractor)

believe to be

proprietary, it is necessary

that you make

a written application within 20 days

to this office to withhold such information from public disclosure.

Any such

application

must include

a full statement

of the reasons

on the basis of which

it is claimed that the information is proprietary,

and should

be prepared

so

that proprietary information identified in the application is contained

in a

separate

part of the document. If we do not hear from you in this regard within

the specified period, the report will be placed in the Public Document Room.

s 0zs >so >'59

Carolina Power and Light Company

"2-

grjg o p 580

Should you have any questions

concerning this letter,

we will be glad to discuss

them with you.

Sincerely,

C. E. Murphy~

x

Reactor Construction

and Engineering

Support Branch

Enclosures:

l.

Appendix A, Notice of Violation

2.

Inspection Report Nos. 50-400/80-25

50-401/80-23,

50"402/80-23

and 50-403/80-23

cc w/encl:

R. Parsons,

Site Manager

'