ML18009A360
| ML18009A360 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 01/11/1990 |
| From: | Belisle G, Scott Sparks NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | |
| Shared Package | |
| ML18009A358 | List: |
| References | |
| 50-400-89-35, NUDOCS 9002050408 | |
| Download: ML18009A360 (23) | |
See also: IR 05000400/1989035
Text
<g ))ac>
P0
~
4O
4u
O
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
101 MARIETTASTREET, N.W.
ATLANTA,GEORGIA 30323
Report No.:
50-400/89-35
Licensee:
Carolina
Power and Light Company
P. 0.
Box 1551
'Raleigh,
NC
27602
Docket, No.:
50-400
Facility Name:
Harris
1
License No.:
Inspection
Conducted:
December 4-8,
1989
Inspector:
S.
Sparks,
Team 1.eadem
Daie Signed
Team Members
Approved by
P. Taylor
S.
Tingen
L. Zerr
, 2P.
G. A. Belisle,
Chi f-
Test
Programs
Section
Engineering
Branch
Division of ReacT, or Safety
Date Signed
SUMMARY
Scope:
This routine,
unannounced
inspection
was
conducted
in the
areas
of inservice
testing,
complex surveillance,,and
action
on previous inspection findings.
Results:
A violation with three
examples
was identified for inadequate
inservice testing
( IST).
These
examples
indicate that licensee's
review of the deficiencies
and
NRC staff positions identified in Generic Letter 89-04,
Guidance
on Developing
Acceptable
Inservice Testing
Programs,
was
not, thorough,
paragraphs
3 and 5.
A weakness
was identified in
MOV stroke timing, par agraph
5.
The
licensee's
interpretation
of Technical Specification 3.4.4
regarding
operability
of power
operated
relief valves
did not
agree
with the
NRC's
position,
and
as
such
a
reevaluation
of the
licensee's
interpretation
is
requested,
paragraph
7.
i+OO20i'<C)4C))
s
po~
~QIC)i .I>>
I.J
v00$ I 2.,
()',j)j!O+OI.)
I>>) II .
Significant
weaknesses
associated
with the
proper
selection,
setting,
and
maintaining
valve
operator
switches
were
identified
in
the
licensee's
motor-operated
valve
(NOV) program,
paragraph. 8.
These
weaknesses
indicate the
need
for additional
management
attention
to
insure
safety-related
motor
operated
valves will accommodate
the
maximum differential pressures
expected
during plant transients.
REPORT
DETAILS
Persons
Contacted
Licensee
Employees
- J. Brooks, Shift Foreman,
Operations
"C. Gibson, Director, Projects
and Procedures
"J.
Hammond,
Manager,- Onsite Nuclear Safety
- C. Hinnant, Plant General
Manager
- A. Howe, Senior Specialist,
Regulatory
Compliance
- M: Pugh, Project Specialist,
Inservice Inspection
'J.
Schaub,
Technical
Support
- F. Strehle,
Project
QA Engineer,
QA/QC
- D. Tibbitts, Director, Regulatory
Compliance
- R. Van Metre,
Manager,
Technical
Support
"M. Wallace,
Senior Specialist,
Regulatory
Compliance
- L. Woods,
Engineering
Supervisor,
Technical
Support
Other
licensee
employees
contacted
during
this
inspection
included
craftsmen,
engineers,
operators,
mechanics,
technicians,
and
administrative personnel.
NRC Resident
Inspectors
J.
Tedrow, Senior Resident
Inspector
M. Shannon,
Resident
Inspector
- Attended exit interview.
and abbreviations
used
throughout this report are listed in the
last paragraph.
2.
IST Introduction (73756)
10 CFR 50 . 55a(g)
and
TS Surveillance
Requirement
4.0. 5 require that
Code Classes
1, 2,
and
3 pumps
and valves
be inservice tested
in accordance
with Section
XI of the
ASME Boiler and
Pressure
Vessel
Code.
Section
XI
specifies
rules
and
requirements
for IST to assess
operational
readiness
of certain
Classes
1,
2,
and
3
pumps
and valves
which are
required
to-
perform
a
specific
function
in shutting
down
a
reactor
to
the
cold
shutdown condition or in mitigating the consequences
of an accident.
The
licensee
is committed to the requirements
of ASME Code,
Section XI, 1983
Edition through
the
Summer
1983
Addenda.
During this inspection,
the
inspectors
reviewed
the licensee's
Inservice
Test
Program,
implementing
procedures,
and test results
that accomplish
Section
XI pump
and valve
IST.
The results
of this review are
stated
in paragraphs
3 through
6.
Pumps
and
valves that
are
in the
system
or interface with the
system,
pressurizer
safety
valves,
and
PORVs were
reviewed during this
ins ection.
P
3.
Check Valve Full Stroke
and Reverse
Flow Testing (73756)
The inspectors
reviewed
the full stroke
and reverse
flow IST methods
and
results
obtained
during the previous
two year period for the following
CS-17.8
CS-206
CS-344
CS-477
CS-500
CS-179
CS-207
CS-385
CS-483
CS-536
CS-192
CS-279
CS-426
CS-486
CS-546
CS-193
CS-294
CS-471
CS-497
The inspectors
reviewed
the following procedures
which 'performed
on
the above
ISI-203,
Rev. 6: ASME Section
NI
Pump
and Valve Program
Plan
OST-'1006,
Rev.
3, Boration System Operability Monthly Interval,
Modes 1-2-3-4-5-6
OST-1007,
Rev.
3,
CVCS/SI System Operability quarterly Interval,
Modes 1-2-3-4
. OST-1501,
Rev.
1,
ECCS Check Valve Full Flow Verification quarterly
Interval,
Mode
5
OST-1505,
Rev.
1. Boric Acid Flow Path
Check Valve ISI Test
quarterly Interval,
Mode
5
OST-1106,
Rev.
2,
CVCS/SI System Operability quarterly Interval,
Modes 4-5-6
OST-1801,
Rev.
3,
ECCS Throttle Valve CSIP
and Check Valve
Verification,
18 Month Interval,
Mode
6
Requirements
for full stroke
and reverse
flow exercising
check valves are
contained
in Section XI, Subsection
IWV-3520 of the Code.
A review of ISI-203,indicated
that
CS-525
was
not in the
licensee's
IST program,
and
thus
was
not full stroke tested.
This check
valve is located in the gravity feed flow path from the boric acid tank to
the
CSIP
suction.
In
an interoffice correspondence
dated
November
15,
1988,
the
licensee
evaluated
the
need
to forward flow test this
check
valve,
which at
that
time
was
in their
program.
The
licensee
concluded'hat
the
check
valve did not require
inclusion
in the
program,
based
on the following:
The valve/flow path is not mentioned in Chapter
15 of the
The flow path is addressed
in TS, but requires
manual initiation
The flow path is only used
when
both boric acid transfer
pumps are
and suction
from the
RWST is lost
Forward flow testing would be difficult
The
inspectors
noted
that
the
gravity
feed
flow path
can
be
used,
according
to procedure
OST-1006, to satisfy
TS 3. 1.2. 1.
This
TS requires
during Modes 4, 5,
and 6,
as
a minimum, that
one of the following boron
injection flow paths shall
be operable:
Boric acid tank via either boric acid transfer
pump and
a CSIP
Boric acid tank via
a gravity feed connection
and
a CSIP
Refueling water storage
tanl
via
a CSIP
The
bases
of
TS 3. 1.2. 1 are that during
modes
4,
5,
and
6,
one
injection flow 'path is acceptable
without single'ailure
consideration
due
to the
stable
reactivity condition of the
reactor
and
the
additional
restrictions prohibiting core alterations
and positive reactivity changes.
The
inspectors
concluded
that
check
valve
CS-525
meets
the
scope
of
IWV-1100, which defines
IST in
terms
of valves
which are
required
to,
perform
a
specific.
function
in shutting
down
a reactor
'to the
cold
shutdown
condition
or in mitigating
the
consequences
of
an
accident.
Since
the gravity feed
flow path
can
be
used
by OST-1006 to satisfy
TS
3; 1'.2. 1, check valve CS-525 must
be included in the licensee's
IST program,
and tested
accordingly.
Failure to test
check valve CS-525 is
a violation
of, IWY-3521,
and is identified
as
Part
A to violation 50-400/89-35-01,
Failure
to
Perform
on
Check
Valve CS-525.
The licensee
initiated
prompt corr'ective
ac;ion
by reviewing
completed
OST-1006
procedures
and
verified that the gravity feed flow path
had never
been
used to satisfy
TS
3. 1.2. 1.
In addition,
OST-1006
was revised
during
the
inspection
such
that the gravity feed flow path could not be used
as
an operable
flow path
until CS-525 is adequately
tested.
The inspectors
also
noted that
CS-775
and
CS-776
were
not
included in the licensee's
IST program,
and thus were not tested.
Each of
these
check valves are located in a flow path which cross-connects
the
pump discharge
to the
CSIP suction.
Failure of these
check valves to open
would preclude
the
use
of the
CSIPs
during .the
recirculation
phase
following a
LOCA.
The inspectors
concluded
these
meet
the
scope of IWV-1100, which defines
IST in terms of valves which are required
to perform
a specific function in shutting
down
a reactor
to the cold
shutdown
condition
or in mitigating the
consequences
of
an
accident.
Failure to test
CS-775
and CS-776 is
a violation of IWV-3521,
and is identified
as
Part
A to violation 50-400/89-35-01,
Failure
to
Perform
IST on Check Valves CS-775
and CS-776.
The
inspectors
also
questioned
the
licensee
on testing
check
valves
CS-179,
CS-207,
and
CS-193.,
These
valves
are
located
in
the
CSIP
mini-flow line,
and
are full stroke exercised
by procedures
OST-1007
and
OST-1106.
The
procedure
determines
full stroking
each
check
valve
by
opening
an'OV
downstream
of the
check
valves,
and listening for
an
audible tone
change-when
the
CSIP is operating.
The inspectors
concluded
that this
method
only verifies that
an
unknown quantity of flow passes
through
the
check
valve,
and
does
not verify that
each
check
valve
full-strokes
open.
In addition,
GL 89-04 states
that
a valid full stroke
by flow requires
that the flow through
the valve
be
known.
Failure to
adequatelv
test
check
valves
CS-179,
CS-207,
and
CS-193
is
a violation
of IWV-3522,
and is identified
as
Part
B to violation 50-400/89-35-01,
Failure to Adequately Perform
IST on Check Valves CS-179,
CS-207,
and CS-193
provides
guidance
in the
area
of IST, particularly for check
valve testing,
review of IST programs to ensure
adequate
scope of testing,
generic
deficiencies,
and
NRC staff positions
on
acceptable
testing
methods.
In addition,
GL 89-04 discusses
other testing
requirements,
such
as
10 CFR 50, Appendix A, Criterion 1, which requires,
among other things,
that
components
important
to
safety
be
tested
to quality
standards
commensurate
with the importance of the safety functions to be performed.
10 CFR 50, Appendix B, is also discussed
in GL 89-04,
and includes testing
for safety-related
components
as
part of
a quality
assurance
program.
Paragraph.
(g) of 10 CFR 50.55a requires
the
use of Section
XI of the
Code for inservice testing of components
covered
by the
Code.
For other
components
important to safety
but outside
the
scope
of
Section
XI
testing,
the licensee
also
has the-burden of demonstrating their continued
operability,
as required
by Appendix A and
B to
Based
on the
multiple examples
of the
IST related violation identified in this report,
the
inspectors
concluded
the
licensee's
review of
GL 89-04 was'ot
thorough.
The inspectors
also
reviewed
check
valve reverse
flow testing,
which is
required by, the
Code for check valves which perform
a safety function in
the closed position.
Subsection
IWV-3522 requires
check valve testing in
a
manner
that verifies
the disk travels
to
the
seat
on cessation
or
reversal
of flow.
As stated
in relief request
RV-l, the licensee
performs
a
Appendix J,
type
C local
leak rate test
for containment
isolation
check
valves
CS-344,
CS-385,
CS-426,
CS-471,
and
CS-477,
to
verify these
perform their safety
function.
The inspectors
reviewed
procedure
EST-212,
Rev.
3,
Type
C
Local
Leak
Rate
Test,
associated
results,
and verified that
analysis
of
leakage
rates
and
corrective
actions
were in conformance
with the requirements
of IWV-3426
and
IWV-3427.
Within the
areas
inspected,
two
examples
of the
IST violation were
identified.
Pump Testing
(73756)
The inspectors
reviewed
IST for three
CVCS/SI
pumps (3) and two boric acid
transfer
pumps
to
determine if periodic
testing
was
performed
in
accordance
with Section
XI, Subsection
IWP requirements.
The following
CVCS/SI
pump implementing procedures
and .test results for the previous
two
year period were reviewed:
ISI-203,
Rev.
6,
ASME Section
XI Pump
and Valve Program
Plan
ISI-800,
Rev.
2, Inservice Testing of Pumps
OST-1007,
Rev.
3,
CVCS/SI System Operability quarterly Interval,
Modes 1-2-3-4
OST-1106,
Rev.
2,
CVCS/SI System Operability Quarterly Interval,
Nodes 4-5-6
OST-1505,
Rev.
1, Boric Acid Flow Path
Check Valve ISI Test
Quarterly Interval,
Mode
5
The inspectors
verified that the
above test procedures
incorporated
Code
requirements
concerning
acceptance
criteria,
test
frequency
and
duration,
calibration
of instrumentation,
time allowed for analysis
of
test results,
and action to be taken if the measured
pump test quantities
fell within the alert or required action range.
The review of test data
indicated that
acceptance
criteria were being
met
and both the
CVCS/SI
pumps
and boric acid
pumps
measured
test quantities
remained within the-
acceptable
range.
Within the areas
inspected,
no violations or deviations
were identified.
5.
Power Operated
Valve IST (73756)
The inspectors
reviewed
IST for the following MOVs and
AOYs in the
CVCS:
CS-480
CS-9
CS-470
CS-746
CS-214
CS-217
CS-165
CS-170
CS-492
CS-341
CS-472
CS-752
CS-182
CS-218
CS-166
CS-171
CS-7
CS-11
CS-382
CS-235
CS-210
CS-219
CS-168
CS-291
CS-8
CS-238
CS 423
CS-231
CS-196
CS-220
CS-169
CS-292
The
inspectors
interviewed
licensee
personnel
regarding
the
general
methods
used
to stroke
time
power operated
valves.
The inspectors
also
reviewed
appropriate
relief
requests,
and
reviewed
the
following
implementing procedures
for IST of the previously listed valves:
ISI-801,
Rev.
2, Inservice Testing of Valves
OST-1106,
Rev.
2,
CVCS/SI System Operability Quarterly Interval,
Modes 4-5-6
OST-1072,
Rev.
0,
CVCS/SI
Remote Position Indication Test
Criteria for IST power operated
valves is contained
in Subsections
IWV
3412,
3413,
3415,
and
3417 of the
ASME Code.
These
Subsections
specify
stroke
timing, fail-safe testing,
and corrective
action
requirements.
Subsection
IWV-3300 addresses
valve position indicator verification which
requires
checking
remote
position
indication
once
every
two years
to
verify that
valve
operation
is accurately
indicated.
The
inspectors
verified that testing
was performed in accordance
with code requirements,
and that testing data
and subsequent
corrective actions
were satisfactory.
The inspectors
raised
a concern
regarding
the
performance
of the
Remote
Position
Indication Surveillance
Test
(OST-1072) prior to performing the
stroke
time testing of these
valves
(OST-1106).
This practice
has
the
r
potential
for
masking
deficiencies
in
valve
performance
and
valve
degradation.
The licensee
stated
that these
tests
are usually performed
concurrently,
thus the valve is only stroked
once to satisfy stroke timing
and position indication requirements.
However,
the inspectors
review of
previous
testing
noted
that
the
remote
position
indication test
was
'erformed
the
day before
the
stroke
time testing.
To correct
this
weakness
in valve stroke timing, the licensee
agreed to revi se OST-1072 to
notify operators
of the
need to perform OST-1072 concurrently or after the
performance
of OST-1106.
The inspectors
also
reviewed
the stroke time testing results for all IST
valves
in the
CVCS performed
during the
past
three
years,
as
well
as
maximum,
alert,
and
increased
test
frequency
values.
In addition,
maintenance
work requests
were
reviewed
for selected
valves,
including
post-maintenance
testing
requirements
and
acceptance
criteria.
The
results within these
areas
of review were satisfactory.
During
a review of systems
which interface with the
CVCS, the inspectors
questioned
the
licensee
on the
need
to fail-safe test
valves
RH-20
and
RH-5S.
These
valves
are
power operated
valves
(AOVs), which control
the
RHR heat exchanger
bypass
flow, and
have
a fail-safe position.
Subsection
IWV-3415 provides
the
requirements
for testing
valves
with fail-safe
actuators.
Valves
RH-20 and
RH-58 were not in the licensee's
IST Program,
thus
no
IST was
being
performed.
The
licensee
stated
that
the
normal
position .of these
valves is the failed position,
and
as
such,
do not have
to change position to fulfillthei r safety
function.
Valves that
do not
have
to
change
position
to fulfill their
function
are classified
as
passive
valves,
which have
no exercising requirements'n
addition,
the
licensee
stated that during plant conditions
where
these
valves
may
be
open
(such
as during
Mode
4 when the
RHR system is in operation),
they are
not required to mitigate the consequences
of an -accident or shut the plant
down to the cold shutdown condition.
Thus,
the licensee
considers
these
valves to be outside
the
scope of Sect'ion
XI testing.
During normal at-power operation,
the
RHR system is available
in stand-by,
and
the position
of these
valves
(closed)
is the
same
as
the fail-safe
position.
These
valves
are
opened during normal
RHR system operation,
as
stated
in procedure
Rev.
4,
Residual
Heat
Removal
System,
to
initially prevent thermal
shock to the
RHR heat exchangers,
and to control
and maintain
cooldown
such
as during Mode 4.
Thus,
the normal position is
not always closed.
Failure of these
valves to close
on demand
once they
are
open,
whether
as part of the
system
control
or inadvertently,
could result
in
a majority of the
pump flow bypassing
the
RHR heat
exchanger.
The heat
exchanger
would be bypassed
due to the pressure
drop
across
the vertical
U-Tube heat
exchanger,
and the fact that the bypass
line (nominal eight inch diameter)
is approximately
the
same
diameter
as
the
RHR heat
exchanger
flow path (ten inch nominal diameter).
Bypassing
the
RHR heat
exchanger
would substantially
reduce
the ability to remove
residual
heat
by the
normal
method
of utilizing the
system.
In
addition,
FSAR Table 5.4.7-3 contains
a Failure
Mode and Effects Analysis
on
the
active
components
of
the
system
during
plant
cooldown
operation.
The Table
states
that
a failure of the
RHR bypass
valve to
close, on
demand
would have
no effect
on safety for system operation,
in
that the heat
exchanger
discharge
flow control valve can
be throttled and
the redundant,
RHR train can control cooldown.
However,
since the
RHR heat
exchanger
bypass
flow control valves are
common to each train and both are
not fail-safe tested, it cannot
be assumed
that the other
RHR train could
be used to control cooldown.
The inspectors
consider
the
RHR heat exchanger
bypass
flow control valves
to
be power-operated
valves with
a fail-safe position.
IWV-1100 defines
the
scope for IST in terms of valves
which
are
required
to perform
a
specific
function
in
shutting
down
a
reactor
to
the
'cold
shutdown
condition
or
in mitigating the
consequences
of an accident., Failure of
these
valves to close
on demand
would preclude
the safety function of the
RHR system,
which is
needed
to bring the reactor
to cold
shutdown
and
mitigate
the
consequences
of
an
accident.
In addition,
GL 89-04 also
provides
guidance
specifically in the
area
of testing
the fail-safe
function of control valves,
and in the area of reviewing
IST programs to
ensure
adequate
scope.
Based
on the above,
the inspectors
concluded
that
failure to fail-safe test these
valves is
a violation of IWV-3415, and is
identified as Part
C to violation 50-400/89-35-01,
Failure to Perform
on Valves
RH-20 and
RH-58.
Within the
areas
inspected,
one
example
of
the
IST violation
was
identified.
6.
Safety
and Relief Valve IST (73756)
The inspectors
reviewed
IST for the following safety
and relief valves in
the
CVCS and
RCS systems:
RC-123
RC-125
CS-10
CS-744
CS-127
CS-310
The inspectors
interviewed
licensee
personnel
regarding
the methods
used
to test relief valves
and
reviewed
the following implementing
procedures
for IST of the previously listed valve's:
EST-211,
Rev.
4, Auxiliary Relief Valve Testing
Crosby Test Procedure
T-16548,
Rev.
0, Testing of HB-BP-86 Style
Pressurizer
Safety Valves with Flexi-Disc Seating
for Carolina
Power
and Light Company
WYLE Laboratories
Test Procedure
1032,
Rev.
A, Dresser/Crosby
Pressurizer
Safety Relief Valve Non-Elevated
Temperature
Test
The criteria for
IST of relief valves
and safety
valves is contained
in
ANSI/ASME OM-1-1981,
Requirements
for Inservice
Performance
Testing
of
Nuclear
Power Plant
Pressure
Relief Devices.
specifies
a
PSV
setpoint
tolerance
of 2485
plus/minus
one
percent
PSIG.
Results of this
review indicated
that all testing
was
accomplished
in accordance
with
ANS I/ASME OM-1-1981.
SHNPP
PSVs
are installed
on unisulated
During the
1988
one
PSV
was
removed
and
sent
to
WYLE Laboratories
for setpoint testing,
and
a spare
PSV
was installed.
Prior to installation of the
spare
PSV,
the valve was sent to Crosby
and setpoint tested.
Crosby setpoint tested
the
PSV utilizing air at
70 plus/minus
10'F
as
the test
medium,
then
tested
with water at 250'F with ambient temperature
maintained at 130'F;
the valve was allowed to cool
and then retested
using air at 70 plus/minus
10'F.
No adjustments
were
made to change
setpoint.
The guide
and nozzle
rings were adjusted
to obtain crisper
pops.
The results
of the
Crosby
setpoint testing
were
as follows:
Test
Medium
Po
in
Pressure
Air
Air
Air
Water
Water
Air
Air
Air
2500
2488
2499
2469
2465
2489
2497
2483
The
PSV that was
removed
and sent to
WYLE Laboratories
during the
1988
was setpoint tested
with steam
at
650
F as
the test
medium.
During the
steam testing,
valve
body temperature
was
510'F
and
ambient
temperature
was 140'F.
Following the
steam tests
the valve
was
allowed to cool
and
then tested
with water at
130'F as the test
medium.
During this testing
ambient temperature
was maintained at
115~F.
The results
were
as follows:
Test
Medium
Steam
Steam
Steam
Water
Water
2492
2488
2502
2509
2507
During the
1989
a
Results of this testing
Test
Medium
PSV
was
removed
and
sent to
WYLE Laboratories.
were:
Set oint PSIG
Steam
Steam
Steam
Water
Water
2456
2453
2475
2477
2494
Both Crosby
and
>/YLE test results
indicated that higher valve temperatures
result in lower valve setpoints.
The inspectors
also
reviewed
the test
methods
and test
r'esults
of
valves
previously
listed
at
the
beginning
of this
paragraph.
The
inspectors
suggested
that the licensee
develop
a correlation
between water
at ambient temperature
and 290'F for valve CS-10.
CS-10
was
with water at ambient
temperature;
however,
during
nominal
oper'ation
the
valve
is
exposed
to water
at
approximately
290~F.
This
temperature
difference
may effect the setpoint.
This
item
was
discussed
with the
licensee.
Within the areas
inspected,
no violations or deviation were identified.
7..
Complex Surveillance
(61701)
TS Surveillance
Requirements
4.4.4.1.b
and 4.4.9.4.1.b
require that each
pressurizer
PORV be demonstrated
at least
once every
18 months
by
performing
a
channel
calibration.
The inspectors
reviewed
the following
procedures
that accompli sh tni s surveillance
requirement:
Rev.
1,
Reactor
Coolant
System
Cold Overpressure
Protection
Loop, P-0440,
Opera.ional
Test
Rev.
2,
System
Cold Overpressure
Protection
Loop, P-0440, Calibration
Rev.
2
Reactor
Coolant
Loop Hot Leg Temperature,
T-413,
Calibration
Rev.
1,
Pressurizer
Pressure
and
PORV Loop, P-0445,
Calibration
Rev.
1,
Reactor
Coolant
Loop
2 Cold Leg Temperature,
T-402, Protective
Set II Calibration
Pressurizer
channel
calibrations're
accomplished
by performing
a
series of overlapping procedures.
Results of the inspectors
review of the
PORV channel
calibration
procedures
was that with the exception
of the
K710 contacts
and associated
wiring, all components
in the channels
were
properly tested.
The
K710 contacts
operate
in
response
to the
safety
injection unblock pressure
signal,
P11.
Above 2000
PSIG the
K710 contacts
are closed which completes
the circuit to allow automatic
PORV operation
if a high pressurizer
pressure
condition existed.
Below 2000
PSIG,
the
K710 contacts
open to prevent
automatic
PORV actuation.
The
inspectors'oncern
was that if the
K710 'contacts
failed to close at 2000
PSIG with
increasing
pressurizer
pressure,
then
the
automatic
function
for
the
associated
PORV would be disabled.
The fact that the
K710 contacts failed
to close
and disabled
the associated
PORV automatic function, would not be
detected
unless
a high pressurizer
condition existed
and the
PORV failed
to open.
The licensee
stated that per
TS Table 4-3-2,
Engineered
Safety
Features
Actuation
System
Instrumentation
Surveillance
Requirements,
the
K710 contacts
were
not required
to
be tested.
Item 10.a of Table 4-3-2
states
that Pll actuation
logic testing,
master
relay testing,
and slave
relay testing is not required.
The licensee
stated that there is no built
10
in test circuit that would allow the
K710 contact to be easily tested.
In
order to resolve
the
issue
of the
K710 contacts
having to
be tested
as
part of a channel calibration,
Region II will request
NRR assi stance.
The
issue of testing the
K710 contacts
and associated
circuitry was identified
as
URI 50-400/89-35-02,
Testing of PORV channel.
While reviewing the
PORV channel
calibration
procedures,
the inspectors
were informed by the licensee
that the
PORVs were required to
be capable
of being
manually
opened
and closed
to
be considered
and that
the
automatic
functioning
of
these
valves
was
not
an
operability
requirement.
This policy was
documented
in
a licensee
internal
document
as
TS Interpretation
Number 89-001.
The
inspectors
disagreed
with the
licensee's
interpretation
of
TS
3'.4.4.
The
inspectors
interpreted
TS 3.4.4 to require
PORV automatic
function
be available
in order for the
valves
to
be operable.
Per
TS bases,
Section 3/4.4.4,
operation
of the
PORYs minimize the undesirable
opening of the spring-loaded
pressurizer
code
safety
valves.
The
inspectors
consider
that in order to prevent
opening
of the
PSVs,
the
PORV automatic
function is
required
to
be
If the
automatic
function
of
one
or
more
is
not
available,
then per the licensees
interpretation
of T/S 3.4.4,
the block
valves
could
be
shut
and
the
plant
operated
indefinitely.
Per
the
inspectors
interpretation,
the plant would
be required to
be
shut
down.
The inspector's
interpreta-'.ion
is also
based
on
a
NRC memorandum
from NRR
to Region II concerning
a similar'ssue
with respect
to this
TS.
This
memorandum,
provided
as
Enclosure
3 to this report,
documents
the staff
interpretation
of
the surveillance
requirement,
and
states
that
the
automatic
function of the
must
be
assured
except
for cases
of
excessive
seat
leakage.
At the exit interview the
licensee
was
informed that
the
inspectors
disagreed
with their
interpretation
of
Within the areas
inspected,
one unresolved
item was identified.
IE Bulletin Followup (92701)
(Closed)
50-400/85-BU-03,
Motor Operated
Yal ve
Common
Mode
Failure During Plant Transients
Due to Improper Switch Settings.
The
purpose
of this Bulletin is to require
licensees
to develop
and
implement
a
program
to
ensure
that, switch settings
for high
pressure
coolant injection
and
emergency
system
MOVs subject to testing
for operational
readiness
in accordance
with 10 CFR 50.55a(g)
are properly
set,
selected,
and maintained.
The licensee's
program
was previously discussed
in
NRC
Inspection
Report
50-400/88-10.
With the
exception
of addressing
operation
at
degraded
voltages
and re-testing
MOYs
under differential
pressure
following major maintenance,
all the findings discussed
in
NRC
Inspection
Report
50-400/88-10
were satisfactorily
completed.
However,
11
further review of the licensee's
program during this
inspection
'identified significant weaknesses
in the areas
of establishing
closed
limit switch 'ettings,
balancing
switches,
and
post
maintenance
testing.
NRC Inspection
Report
50-400/88-10
identifi'ed that operation
of
MOVs at
degraded
voltages
was
not addressed
in the
licensee's
responses
to
Licensee
correspondence
with Limitorque
Corporation
verified that IE Bulletin 85-03
MOVs were
sized for operation
at
reduced
voltages
of 80 percent
and
86 percent.
There
was
a conflict, in that,
Section 8.3. 1.2.3 of the
FSAR states
that the
EDGs voltage output wi 11 not
decrease
to less
than
75 percent of nominal during
sequencing
of loads.
Oper ation at degraded
voltages is still under evaluation
by the licensee.
Also discussed
in
NRC Inspection
Report
50-400/88-10
was
the
need
to
retest
MOVs at accident differential pressures
following major maintenance
in order to verify that adequate
thrust
was available.
Review of work
histories
for IE Bulletin 85-03 valves
indicated that the actuator
for
valve
CS-752
was
disassembled
and
reassembled
after it was differential
pressure
tested
to meet
requirements.
Following this
maintenance,
testing
was
not
performed
to
ensure
that,
the
actuator
developed
adequate
thrust to cycle against
accident differential pressure.
In order to assure operability, the inspectors
consider that it is prudent
to test
IE Bulle.',n
85-03 valves
following major maintenance
to verify
adequate
thrust
is
available.
Testing
at differential
pressure
or
diagnostic testing would accomplish this objective.
It was the licensee's
policy that only stroke timing, valve cycling,
and measuring
motor current
was required.
Additional
significant
weaknesses
noted
by
the
inspectors
include the following:
SHNPP
MOVs that operate
in response
to
a .containment isolation or SI
signal
have
the
thermal
overload;
switch,
and torque
switch
bypass
switches
bypassed.
Therefore,
the
open or closed limit switch
deenergizes
the actuator
motor following valve operation.
For the SI
mode of operation
the licensee
normally sets
the closed limit switch
to actuate
at 96 percent of full valve stroke.
The inspectors
were
concerned
that
96 percent of full valve stroke
may not be adequate
to
ensure
the valve is fully shut.
After the
motor
stops,
valve
and
actuator
momentum will continue
to drive the valve disk.
This is
referred to as "coastdown".
The amount of coastdown
is dependent
on
a
number
of factors
and
varies
from valve
to valve.
If, for
a
particular valve, little or no coastdown exists,
then the valve would
be four percent
open after the limi.t switch deenergizes
the motor.
In
some
instances
for the containment
isolation
mode of operation,
the
licensee
may
set
the
closed limit switch to actuate
at zero
percent
of valve
stroke.
The
inspectors
were
concerned
that
coastdown
may
the
valve
and/or
actuator
by exerting
excessive
force
when
driving
the
valve
disk
into
the
seat.
Overthrusting
the
valve
or actuator
in this
manner
could
lead to
12
eventual
valve and/o'r actuator failure.
The concerns
involving valve
limit switch settings
not only include
IE Bulletin 85-03 valves,
but
al l
- SI
and
containment
i sol ation
valves
that
get
a
signal
to
automatically shut.
Procedure
CN-.1002,
Revision
3,
Calibration
and
Stroking, provides instructions for replacing
switches.
This
procedure
did not require
SNB-000 torque switches to be checked for
balancing prior to ins.allation.
Balancing
a torque
switch involves
making adjustments
so that both the
open
and closed
switch contacts
open at
a given set.ing after the
same
amount of torque
switch
arm
travel.
An. unbalanced
switch
does
not
provide
a
true
correlation
between
the
selected
switch setting'nd
the
corresponding
actuator output.
SHNPP
does
not
perform diagnostic
testing.
Following packing
and
switch
maintenance
the
licensee
stroke
tests
the
and
measures
motor
current.
-Stroking
and
measuring
current
provides
useful
information regarding
valve. operability;
however,
diagnostic
testing
provides
a
significant
amount
of additional
information
regarding
valve operability.
Because
the licensee
does
not perform
diagnostic
testing
following packing
and torque
switch maintenance
the
inspect.ors
concluded
the
SHNPP
lags
behind
the
rest
of the
nuclear industry in this area.
These findings were discussed
with the licensee.
The licensee
stated that
problems currently exist with presert diagnostic test
systems
which needed
to be resolved prior to utilizing diagnostic test equipment.
The licensee
also stated that in order to satisfy Generic Letter 89-10, Safety-Related
Notor-Operated
Valve Testing
and Surveillance,
diagnostic testing would be
required,
and that after incorporation of GL 89-10 the inspector
concerns
raised during the inspection
would be resolved.
Action on Previous
Inspection
Findings (92701,
92702)
a.
(Closed)
URI 50-400/88-10-01,
Setpoint Test
Frequency of Pressurizer
Safety Valves
This item 'was discussed
in detai
1 in paragraph
6 of this Inspection
Report.
Since
one
PSV was tested
during
each of the
1988
and
1989
RFOs, all ANSI/ASME ON-1-1981 Test frequency requirements
were met.
b.
(Closed)
IFI 50-400/88-26-03,
Kerotest Valves Installed Backwards
on
Leakoff Lines for RC107
and
RC103.
This item involved inspector
concerns
for
a Kerotest
Y type globe
valve in the leak off collection
system for pressurizer
spray valve
RC-103.
The inspector
observed that the Kerotest valve was installed
in opposition
to
the
normal
direction
of
leak off flow.
The
0
~
13
inspector
was
concerned
that
the
Kerotest
valve
was
installed
improperly and with sufficient design flow above the seat,
the valve
'ould close
and cause
the collector shield to become part of the
pressure
boundary.
The
licensee
provided
the
inspector
a
copy
of design
drawing
2166-G-171
Rev.
5, Valve Stem Leakoff Piping
Containment Building
Unit 1.
The drawing included
a note "Leakoff inclined stem valves -to
be installed with flow above
seat."
The inspector
noted that this
required
the Kerotest
valves
to
be installed in opposition
to the
direction of normal
leakoff flow.
Although this demonstrated
that
the valves were installed
as designed, it still did not resolve
the
inspectors
concern regarding
the adequacy of the leak off design.
In order to address
the inspectors
concerns,
the licensee's
technical
support
group performed
several
tests
to determine
the flow required
to induce
valve closure with an identical valve connected
to
a test
setup with flow over the seat.
The test concluded that the Kerotest
valve would not exhibit flow induced closure until greater
than
18.6
gpm.
Shearon
Harris Technical Specification limit identified leal age
is
10
gpm which is less
than
the test
value
average
of 18.6
gpm.
Therefore,
the
TS value is the limiting value
of
maximum
leakage
allowed without entering
the
TS action statement.
The inspector
has
no other
concerns.
(Closed)
Inspector
Followup
Item
50-400/88-36-01,
Revision
of
Procedure
MPT-M0045 to Clarify Jacket.
Water
Heat
Exchanger
Divider
Plate Bolting Configuration
The
inspectors
reviewed
the revision of MPT-M0045,,which included
clarification for final positioning of jam nuts
on the outlet
head
studs,
and
compression
of the
packed joint of the tubesheet
when
at
operating
temperatures'.
The
inspectors
consider
the
licensee's
actions to be satisfactory.
(Closed)
Inspector
Followup
Item
50-400/86-77-05,
Painting
of
Restricted
Embeds
The inspectors verified that Plant
Change
Requests
2879,
2880,
2881,
2882,
2883,
2884,
2910,
3533,
3564,
and
3565
had been
completed.
The
inspectors
,consider
the
licensee's
actions
for this
item to
be
satisfactory.
Within the areas
inspected,
no violations. or deviations
were identified.
10.
Exit Interview
The inspection
scope
and results
were
summarized
on December
8,
1989, with
those
persons
indicated
in
paragraph
1.
The
inspectors
described
the
areas
inspected
and
discussed
in detail
the
inspection
results
listed
above.
Proprietary
information
is
not
contained
in this
report.
14
Dissenting
comments
were
received
from the
li'censee
in the
areas
of
. fail-safe -esting
the
RHR heat exchanger
bypass
valves,
(RH-20 and
RH-58)
and
NRC identified
MOV weaknesses.
The licensee
stated that the
RHR heat
. exchanger
bypass
valves
were
not within the
scope of Section
XI testing,
and
as
such
IST was
not required.
With regard
to the identified
weaknesses,
the
licensee
commented
that
problems
and
inaccuracies
currently existed with present diagnostic testing
systems,
and until
such
problems
are
corrected,
only" limited usefulness
could
be
attained
in
identifying
problems.
In
addition,
the
licensee
stated
that
. implementation
of
requirements
would resolve
the
MOV concerns
raised
during
the
inspection.
The
licensee
was
informed
that
their
interpretation
of
did
not
agree
with
the
NRC position
on
operability of PORVs
when the automatic function is not available.
Item Number
Descri tion and Reference
50-400/89-35-01,
Part
A
Violation - Failure to Perform
IST on
Check
Valves
CS-775,
CS-776,
and
CS-525.
50-400/89-35-01,
Par
B
.50-400/89-35-01,
Part
C
Violation - Failure to Adequately
Perform
on
Check
Valves
CS-179,
CS-207,
and CS-193
Violation - Failure to Perform
IST on
Valves
RH-20 and
RH-58
50-400/89-35-02
Unresolved
Item - Testing of PORV
Channel
Licensee
management
was informed that the following items were closed:
paragraph
8
URI 50-400/88-10-01,
paragraph
9
IFI 50-400/88-26-03,
paragraph
9
IFI 50-400/88-36-01,
paragraph
9
IFI 50-400/86-77-05,
paragraph
9
11.
Acronyms and Abbreviations
ANSI
CFR
CSIP
American National
Standard Institute
Air Operated
Valve
American Society of Mechanical
Engineers
Code of Federal
Regulations
Corrective Maintenance
Charging Safety -Injection
Pump
Chemical
and
Volume Control
System
Emergency
Core Cooling Systems
Emergency
Diesel Generator
Engineered
Safety
Features
Actuation Signal
15
EST
OF
GL
GPM
IFI
MPT
NRC
OP
OST
PSV
Rev.
SHNPP
TS
Engineering Surveillance
Tes-
Final Safety Analysis Report,
Degrees
Fahrenheit
Generic Letter
Gallons Per Minutes
Inspector
Followup Item
Inservice Inspection
Inservice Testing
Loss of Coolant Accident
Motor Operated
Valve
Maintenance
Periodic Test
Maintenance
Surveillance
Test
Nuclear Regulatory
Commission
Nuclear Reactor Regulation
Operations
Procedure
Operation'Surveillance
Test
Power Operated
Relief Valve
Pounds
per Square
Inch,
Gage
Pressurizer
Safety Valve
Revision
Residual
Heat
Removal
Refueling Outage
Relief Request
Refueling Water Storage
Tank
Safety Evaluation
Report
Safety Injection
Shearon
Harris Nuclear
Power Plant
Technical Specifications
Unre so 1 ved. Itern