Forwards Insp Repts 50-250/90-30 & 50-251/90-30 on 900804-31 & Notice of Violation
ML17348A584
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 09/21/1990
From: Sinkule M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Goldberg J
FLORIDA POWER & LIGHT CO.
Shared Package
ML17348A585 List:
References
NUDOCS 9010120030
Download: ML17348A584 (7)


See also: IR 05000250/1990030

Text

OFFICIAL COPY

Docket Hos.

50-250,

50-251

License

Nos.

DPR-31,

DPR-41

Florida Power

and Light Company

ATTN: 'r.'.

H. 'Goldberg

President - Nuclear D'ivision

Nuclear Energy Department

P. 0.

Box 14000

Juno

Beach,

FL

33408-0420

Gentlemen:

SUBJECT:

NOTICE OF VIOLATION

(NRC INSPECTION

REPORT

NOS. 50-250/90-30

and 50-251/90-30)

This refers

to the inspection

conducted

by

R.

C. Butcher of this office on

August

4 through

August

31,

1990.

The

inspection

included

a review of

activities authorized for your Turkey Point facility.

At the conclusion of the

inspection,

the findings

were

discussed

with those

members

of your staff

identified in the enclosed report.

Areas

examined

during

the inspection

are identified in the report.

Within

these

areas,

the inspection

consisted

of selected

examinations

of procedures

and

representative

records,

interviews with personnel,

and observation

of

activities in progress.

The inspection

findings indicate that certain activities appeared

to violate

NRC requirements.

The violation, with pertinent references

and elements

to be

included in your response,

are described

in the enclosed

Notice.

You are required to respond

to this letter

and should follow the instructions

specified

in the

enclosed

Notice

when

preparing

your response.

In your

response,

you should

document

the specific actions

taken

and

any additional

actions

you plan to prevent

recurrence.

After reviewing your response

to this

Notice, including your proposed

corrective

actions

and the results

of future

inspections,

the

NRC will determine

whether further

NRC enforcement

action is

necessary

to ensure

compliance with NRC regulatory requirements.

In accordance

with Section

2.790 of the

NRC's

"Rules of Practice,"

a copy of

this letter

and its enclosures will be placed in the

NRC Public Document

Room.

The responses

directed

by this letter

and the enclosed

Notice are not subject

to the clearance

procedures

of the Office of Management

and Budget

as required

by the Paperwork

Reduction Act of 1980,

Pub.

L. No. 96.511.

Florida Power

and Light Company

gr-> 81 3990

Should you have

any questions

concerning this letter,

please

contact us.

Sincerely,

.Enclosures;

1.

Notice of Violation

2.

NRC Inspection

Report

,cc w/encls:

K. N. Harris, Senior Vice President

Nuclear Operations

P. 0.

Box 029100

Miami, Fl

33102

L.

W. Pearce,

Plant Manager

Turkey Point Nuclear Plant

P. 0.

Box 029100

Miami, Fl

33102

L.

W. Bl adow,

equal

ity Manager

Turkey Point Nuclear Plant

P. 0.

Box 029'100

Miami, Fl

33102

ORlQWAL SIGNED

HY

tACV)N V. SINKULE

Marvin V. Sinkule, Chief

Reactor Projects

Branch

2

Division of,Reactor

Projects

a

D. Powell, Superintendent,

Plant Licensing

Turkey Point Nuclear Plant

P. 0.

Box 029100

Miami, Fl

33102

Harold F. Reis,

Esq.

Newman

and Holtzinger,

P.C.

1615

L Street,

NW

Washington,

D.

C.

20036

John T. Butler,

Esq.

Steel,

Hector

and Davis

4000 Southeast

Financial

Center

Miami, Fl

33131-2398

Attorney General

Department of Legal Affairs

The Capitol

Tallahassee,

Fl

32304

(cc w/encls cont'd

page

3)

0

Florida Power

and Light Company

(cc w/encls cont'd)

Jacob

Daniel

Nash

Office of Radiation Control

Department of Health

and

Rehabilitative

Services

1317 Winewood Boulevard

Tallahassee,

Fl

32399-0700

Jack Shreve

Office of the Public Counsel

Room 4, Holland Building

.Tallahassee,

Fl

32304'dministrator

Department of Environmental

Regulation

Power Plant Siting Section

State of Florida

Twin Towers

2600 Blair Stone

Road

Tallahassee,

Fl

32301

Joaquin

Avino

County Manager of Metropolitan

Dade County

111

NW 1st Street,

29th Floor

Miami, Fl

33128

Inter governmental

Coordination

and Review

Office of Planning

and Budget

Executive Office of the Governor

The Capitol Building

Tallahassee,

Fl

32301

State of Florida

bcc w/encls:

G.

E. Edison,

NRR

LPM

Document Control

Desk

DRP Section Chief

NRC Resident

Inspector

U.S. Nuclear Regulatory

Commission

P.O.

Box 1448

Homestead,

Fl

33090

RI

DRP

R chin

09/ ~i/90

RII:DRS

..'"

LWatson

j'9/;;/90

RQI: DQS

TPeebles

09/ ;/90

RI

D

RC lenjak

09~ (/90

ENCLOSURE

1

NOTICE OF VIOLATION

Florida Power and Light Company

Turkey Point Urlits 3 and

4

Docket Nos. 50-250,

50-251

License

Nos'.

DPR-31,

DPR-41-

During

an

NRC inspection

conducted

on August

4 through August 31,

1990,

a

violation of

NRC requirements

was identified.

In accordance

with the "General

Statement

of Policy and Procedure

for NRC Enforcement Actions,"

10

CFR Part. 2,

Appendix

C (1990), the violation is listed below:

TS 6.8. 1 requires

that written procedures

and administrative

policies

shall

be established,

implemented,

and maintained that meet or exceed

the

requirements

and

recommendations

of Appendix

A of USNRC Regulatory

Guide

1.33

and Sections

5. 1

and 5.3 of ANSI N18.7-1972.

Section

5. 1 of ANSI

N18.7-1972Property "ANSI code" (as page type) with input value "ANSI</br></br>N18.7-1972" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process.

requires

that administrative policies

be provided to control

the

issuance

of documents,

including changes,

that prescribe activities

affecting safety-related

structures,

systems,

or components.

Contrary

to the

above,

administrative policies

were not established

to

control

changes

to the master

instrument calibration data

sheet for Unit 4

CCW

pump automatic start

pressure

switch,

PC-4-611,

in that

procedures

did not address

changes

to the

instrument calibration data

sheets.

In

January,

1988, the required

and actual

setpoints for PC-3-611

and PC-4-611

were

changed

from 75.0

+ 1.5 psig to 60.0

+ 1.5 psig but the related

instrument

calibration

data

sheets

were

not

changed.

Subsequently,

PC-4-611

was

moved

and then improperly calibrated

to 75.0

+ 1.5 psig using

the instrument calibration

data sheets.

As

a result,

on July 26,

1990,

the Unit

4A

CCW

pump improperly automatically started

due to pressure

switch PC-4-611

being set at the wrong value.

This is

a Severity Level

IV Violation (Supplement

1).

Pursuant

to the provisions of 10 CFR 2.201, Florida Power

and Light Company is

hereby

required

to submit

a written statement

or explanation

to the Nuclear

Regulatory Coomission,

ATTN:

Document Control

Desk, Washington,

DC 20555; with

a copy to the Regional Administrator,

Region II, and if applicable,

a copy to

the

NRC

Resident

Inspector,

within

30

days

of the

date

of the letter

transmitting this Notice.

This reply should

be clearly marked

as

a "Reply to a

Notice of Violation" and should include for each violation:

( 1) the reason for

the violation, or, if contested,

the basis for disputing the violation, (2) the

corrective

steps

that

have

been

taken

and

the results

achieved,

(3)

the

corrective

steps

that will be taken to avoid further violations,

and

(4) the

date

when full compliance will be

achieved.

If an

adequate

reply is not

received within the time specified in this Notice,

an order

may be issued to

Florida

Power

and Light Company

2

~

Turkey Point Units

3 and

4

Docket Nos. 50-250,

50-251

License

Nos.

DPR-31,

DPR-41

show cause

why the license

should not be modified,

suspended,

or revoked,

or

why such other action

as

may

be proper should not

be taken.

Where

good cause

is shown, consideration will be given to extending

the response

time.

FOR THE NUCLEAR REGULATORY COMMISSION

Dated at Atlanta, Georgia

this 21st

day of September

1990

Vce

Marvin V. Sinkule, Chief

Reactor Projects

Branch

2

Division of Reactor Projects