TABLE 4.1-2 (SHEET 2 OF 3)
MINIMUM FREQUENCIES FOR EQUIPMENT AND SAMPLING TESTS 11.
Reactor Coolant System Leakage 12.
Diesel Fuel Supply 13.
Spent Fuel Pit 14.
Secondary Coolant'5.
Vent Gas 5 Particulates.
16.
Fire Protection Pump 5
~
Power Supply 17.
Turbine Stop and Control Valves, Reheater Stop and Intercept Valves Evaluate Fuel inventory Boron Concentration I-131 Concentration
~ I-131 5 Particulate Activity Operable Cl osure Daily Monthly
. 45 Monthly***
Meekly 10 Prior to refueling NA Meekly' 10
~ Meekly* -
-10 18.
LP Turbine Rotor Inspector (w/o rotor disassembly) 19.
Spent Fuel Cask Crane Interlocks V,MT,PT Functioning Every 5 Years Mithin 7 days 6 Years 7 days when crane is being used to maneuver spent fuel cask 8211010295 821022 PDR ADOCK 05000250 P'DR.
Am ndments 87 E 81
h r
t
'tt t
h'Cjt
4
~
5.
TMO residual heat removal pumps shall be operable.
6-TMO residual. heat exchangers shall be operable.
7.
Al.l valves, interlocks and piping assoicated with the above components and required for post accident operation, shall be operable.
except-valves that are positioned and locked.
Yalves 864-A, B, 862-A,B, 865-A, B, C; 866-A, B shall have power removed from their motor operators by locking"'pen the circuit breakers at the Motor Control Centers.
The air supply to valve 758 shall be shut off to the valve operator.
b.
During power operation, the requirements of 3.4.1a may be
" modified to allow one of'he following components to be inoperable (including associated valves and piping) at any one time except for the cases stated in 3.4.1.b.2.
-'- If-the systen-is not restored to meet the requirenents of 3.4.1a within the time period specified.
the reactor shall be placed in the hot shutdown condition.
If the requirements of 3.4.la are not satisfied within an additional 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> the reactor shall be placed in the cold shutdown condition.
Specification 3.0.1 applies to 3.4.l.b.
1.
ONE accumulator may be out of service for a period of up to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.
'\\
2.:ONE of FOUR safety injection pumps may be out of service for 30 days.
A second safety injection pump may be out of service, provided the pump is restored to operable status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
TMO of the FOUR safety injection pumps shall be tested to demonstrate operability before initiating maintenance of the inoperable pumps.
3.
ONE channel of heat tracing on the flow path may be out of service for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.*
4 ~
ONE residual heat removal pump may be out of service, piovided the pump is restored to operable status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
In addition the other residual heat removal pump shall be tested to demonstrate operability prior to initiating maintenance of the inoperable pump;
<<See reference (11) on page B.3.'4-2 3.4 2
Amendments 87 E