ML17333A725

From kanterella
Jump to navigation Jump to search
Insp Repts 50-315/96-12 & 50-316/96-12 on 961021-25. Violations Noted.Major Areas Inspected:Engineering
ML17333A725
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 12/27/1996
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17333A722 List:
References
50-315-96-12, 50-316-96-12, NUDOCS 9701030236
Download: ML17333A725 (26)


See also: IR 05000315/1996012

Text

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Docket Nos:

License Nos:

4

50-315; 50-316

DPR-58; DPR-74

Report Nos:

50-31 5/9601 2(DRS):

50-31 6/9601 2(DRS)

Licensee:

Indiana Michigan Power Company

Facility:

Donald C. Cook Nuclear Generating Plant

Location:

7700 Red Arrow Highway

Stevensville, Ml 49127

Dates:

October 21-25, 1996, and December 5, 1996

Inspectors:

A. Dunlop, Reactor Inspector

J. Guzman, Reactor Inspector

R. Cain, Engineering Specialist, INEL

Approved By:

W. Kropp, Chief

Engineering Specialist Branch

1

970i030236 96i227

PDR

ADOCK 050003i5

8

PDR

f )

EXECUTIVE SUMMARY

~En ineerin

~

This close-out inspection of NRC's review of Generic Letter (GL) 89-10,

"Safety-Related Motor-Operated Valve (MOV) Testing and Surveillance," determined

that the MOV program and implementation at D. C. Cook was not sufficiently

complete to close-out the NRC's program review. Although a number of areas have

been sufficiently addressed,

the inspectors could not conclude that the licensee had

completed verifying all GL 89-10 program MOVs would perform the intended safety

functions under design-basis

conditions.

Specific issues that remain to be resolved

are described

in sections E1.1.b.10; E1.1.b.1.5; E1.1.b.1.9(a); E1.1.b.1.9(b);

E1.1.b.1.9(c); E1.1.b.5; E1.1.b.1.6;

and E1.1.b.1.9(d) of this report.

~

A condition report was not initiated and a prompt operability assessment

was not

made when a potentially adverse condition was identified for the PORV block

valves. (Section E1.1.b.1.3)

4

The licensee made significant progress

on the GL 89-10 program with respect to

previous NRC MOV inspections.

(Section E1.1.b.1)

~

The number of GL 89-10 valves dynamically tested and diagnostically testing

additional plant MOV's was considered

a positive management

position.

(Section

E1.1.b.2)

~

The licensee's

GL 89-10 Closure Summary Reports were well detailed and

contained useful information in determining the MOV's design-basis

capability.

(Section E1.1.b.1)

Safe

Assessmen

Qualit

Verification

~

The recent self-assessment

in the MOV area, although limited in scope, provided

some good technical findings to prepare the MOV program for closure.

The use of

an outside technical MOV expert was also viewed as a positive aspect to provide

additional insights into this highly technical program.

(Section E7.1)

Re ort Details

Summar

of Plan

S atus

Unit 1 was operating at 90 percent power and Unit 2 was operating at 100 percent power

during this inspection period.

III. En ineerin

E1

Conduct of Engineering

E1.1

Generic Le

er 89-10 Pro ram Im lemen a ion

Ins ection Sco

e Tl 2515 109

This inspection evaluated the process for qualifying the design-basis

capability of

MOVs and closure of NRC's review of GL 89-10.

The inspection concentrated

on

MOVs that were tested under static or low differential pressure

(dp) conditions.

A

valve sample that included several program closure m'ethods used by the licensee

was selected to verify design-basis

capability. The inspectors reviewed design-

basis documents, thrust calculations, test packages,

and engineering evaluations for

the following MOVs:

1-FMO-202

Steam Generator (SG) OME-3-2 Feedwater Shutoff (S/0) Valve

1-QMO-226

East Component Cooling Pump IViini-flowto Reactor Coolant Pump

Seal Water Heat Exchanger S/0 Valve

2-IMO-256

Boron Injection Tank Train Inlet S/0 Valve

2-IMO-91 0

Refueling Water Storage Tank to Chemical and Volume Control

System (CVCS) Pump Suction Header Train "A" S/0 Valve

2-FMO-21 1

Turbine-Driven Auxiliary Feedwater

(AFW) Pump PP-4 Discharge to

SG Control Valve

2-NMO-252

Pressurizer

Power-Operated

Relief Valve (PORV) Block Valve

2-IMO-270

Safety Injection (Sl) Pumps Discharge Crosstie Train S/0 Valve

2-IMO-326

West Residual Hear Removal (RHR) and South Sl to Reactor Coolant

System (RCS) Loops 2 5. 3 Cold Legs S/0 Valve

The inspectors also reviewed other licensee documentation

used to justify program

assumptions,

such as stem friction coefficients and load sensitive behavior.

Further, the inspectors reviewed documentation

related to program issues, such as

periodic verification, post-maintenance

testing, and program audits.

b.

Observations

and Findin s

MOV Desi n-Basis Ca abilit

Verification

The inspectors noted that the licensee's

GL 89-10 Closure Summary Reports were

well detailed and contained useful information in determining the MOV's design-

basis capability.

The licensee had made significant progress

on the GL 89-10

program with respect to previous NRC MOV inspections.

In general, the licensee's

design-basis

calculations to verify valve capability were considered adequate.

However, the justifications for several assumptions

used for certain valves or valve

group calculations were not adequately supported.

Based on these concerns, the

inspectors were not able to conclude that the licensee had completed verifying all

GL 89-10 MOVs were capable to meet the design-basis

requirements.

As a result,

the NRC's review of the licensee's

GL 89-10 MOV program will remain open

pending additional support information.

b.1.1

MOV Sizin

and Switch Settin

s

The licensee's thrust calculations utilized the industry's standard thrust equation to

determine thrust requirements for rising stem gate and globe valves.

The applied

stem friction coefficient (SFC) was either the measured

value recorded during a

static test, or 0.174 when the stem factor was not measured.

If the static test

value was less than 0.15, it was generally increased to 0.15.

These values were

used to convert thrust into torque when torque was not measured.

Applied valve

factors were based on licensee testing or best available industry data, such as data

from other utilities and the Electric Power Research Institute's (EPRI) Performance

Prediction Methodology (PPM). A factor of 15% was added to the closed target

thrust to account for the effects of load sensitive behavior and 5% to account for

degradation of stem factors.

Equipment er.ors, such as torque switch repeatability

and diagnostic system accuracies,

were combined in a square root sum of the

squares methodology and used to adjust the upper and lower required thrust, where

appropriate.

Overall, the design basis capabilities of the GL 89-10 valves were

acceptable,

except as noted in the following paragraphs.

b.1.2

Valve Fac ors

The licensee Valve Factor (VF) Technical Paper divided MOVs into 24 groups.

The

grouping was based

on valve type, size, manufacturer,

and pressure

class.

The

licensee used in plant-testing, industry data, the EPRI PPM, or a combination of all

of these to justify the VF applied to the valves in a particular group.

Industry data

was further screened

for flow, temperature,

and pressure to ensure the data would

be applicable to the licensee's

MOVs.

Generaily, if the valves in a group could not be practicably tested, the licensee

would use the thrust obtained from application of the EPRI PPM to back calculate a

VF. Further, the licensee reviewed several industry data points to confirm the EPRI

PPM results.

Once this review was complete, the licensee used the more

conservative of the two methods.

Overall, for the majority of valve groups, the

assumed

VF was adequately justified. There were several valve groups, however,

that had minimal justification for the applied VF. These are discussed

below and in

paragraph E1.1.b.1.3 of this report.

(a)

Valve group "BAAC"was 8" Aloyco 300¹ ball-socket gate valves,

which used a VF of 0.71 based on a single industry test data point.

The inspectors stated that a single data point was insufficient to

justify the VF for the entire group.

The lowest thrust margin for the

valve group in the open safety direction, however, was 178 percent.

The inspectors considered the large calculated margin to be adequate

for program closure.

(b)

Valve groups GL10 and GL11 were 4" Rockwell and Conval 1500¹ Y-Globe

valves, which used a VF of 1.1 based on EPRI testing that indicated VFs

between 0.9 and 1.1 for globe valves.

The inspectors stated that other

globe valves tested in the industry had indicated valve factors higher than

1.1.

Valve group GL11 had 47 percent available margin in the closed

direction and could support an available VF of 1.65, which was considered

adequate

for program closure.

However, in valve group GL10, the most

limiting MOV had a 6 percent available margin in the closed direction and

could only support an available VF of 1.17.

The inspectors con"!dered the

margin for these MOVs to be low. However, based on use of a guide-based

area term that was used to calculate required thrust, the settings for the

group were considered adequate

for program closure.

The licensee indicated they would attempt to find additional data to support the use

of the applied VFs for these valve groups.

b.1.3

0 erabilit

of he Power-0

crated Relief Valve

PORV Block Valves

The inspectors were concerned with the operability of four pressurizer

PORV block

valves based on the use of a 0.4 VF while two PORV block valves were using a

0.51 VF. The licensee has 6 PORV block valves, three for each unit, which were

3" Velan 1500¹ flex-wedge gate valves.

The licensee had applied the EPRI PPM in

October 1996 and back calculated

a required VF of 0.51.

The 0.51 VF was

considered

by the licensee to be conservative

because

EPRI Velan Valve ¹13,

tested under similar conditions (blowdown, hign temperature), showed

a VF of 0.34

in the closed direction. Two MOVs on Unit 2 (2-NMO-152 and -153), which were

modified during the last refuel outage, could support the 0.51 VF. The modification

was not performed on the third Unit 2 valve due to lack of parts during the outage.

However, MOVs 1-NM0-151, -152, -153, and 2-NMO-151 used a VF of 0.40 that

the licensee considered adequate

based on the EPRI test results.

The inspectors had the following concerns with this justification. Ir.formation from

the NRC Safety Evaluation (SE), dated March 15, 1996, of the EPRI Topical Report

TR-103237, "EPRI Motor-Operated Valve Performance Prediction Program,"

Sections II.B.2.a (page 9) and II.B.2.c (page 17), discussed that EPRI did not

precondition the valves tested in-situ and that guide rails in two valves

manufactured

by Velan experienced plastic bending under the high flow conditions.

Based on the SE information and the lack of specific in-plant dynamic test data, the

EPRI PPM information should have been considered the best applicable data once

the licensee had performed the EPRI PPM runs.

As a result of the inspectors'oncerns,

the licensee recalculated the required

thrusts for four unmodified MOVs based on current torque settings and a 0.51 VF.

The revised calculations determined MOV 2-NMO-151 was capable of supporting

the 0.51 VF. MOVs 1-NMO-151 and -153 could only support the 0.51 VF when

rate of loading (ROL) and stem tube degradation were reduced or removed from the

calculation.

This condition was documented

on a condition report (CR) with an

associated

operability determination.

The inspectors reviewed the operability

determination and considered it acceptable until the valves could be modified at the

soonest available opportunity.

MOV 1-NMO-152, however, could not support a VF

of 0.51 with the current torque switch setting.

Based on the results of these

calculations and discussions with the inspectors, the licensee declared MOV

1-NMO-152 inoperable and initiated a CR. The licensee performed the required

Technical Specifications (TS) actions when the MOV was declared inoperable.

Based on the inspectors'eview

of this issue, the licensee should have addressed

the 0.51 VF from the EPRI PPM for the PORV block valves with respect to valve

operability.

Plant Managers Instruction (PMI) 7030, "Corrective Action,"

Revision 22, was the licensee's primary mechanism by which degraded

and

potentially nonconforming conditions were evaluated.

PMI-7030 required the

originator to initiate a CR for known or susPected

adverse conditions or events

(step 6.9.a).

PMI-7030 also defined an adverse condition/event as "A non-

conformance, deficiency, deviation, discrepancy,

or adverse trend of items, services

and/or administrative systems that, if left uncorrected,

could adversely impact

safety, quality, or operability" (step 5.1). The failure to initiate a CR and perform a

prompt operability assessment

following the identification of a potentially adverse

condition from the EPRI PPM information is considered

a violation (50-315/96012-

01(DRS);

50-316/96012-01(DRS))

of TS 6.8.1.

The licensee stated that the three'PORV block valves for Unit

1 were scheduled for

modifications in the upcoming February 1997 outage to verify the valves'esign-

basis capabilities.

The Unit 2 MOV was scheduled for the same modification during

the Fall 1997 refueling outage.

The licensee also stated the'modifications would be

added to the forced outage list if an outage of sufficient duration occurred prior to

the refuel outages.

The licensee stated these modifications would allow the valves

to support the use of a 0.51 VF with sufficient margin.

This will be considered

an

inspection followup item (IFI) (50-315/96012-02(DRS))

pending completion of the

Unit

1 modifications and inspector review of the obtained margins.

b.1.4

Load Sensitive Behavior

The inspectors reviewed the licensee's Technical Report 0012-00204-R02,

"Rate

Of Loading," Revision 0, which was used to perform a statistical analysis of load

sensitive behavior (LSB). The statistical evaluation was performed for three data

sets; gate and globe valves combined, gate valves only, and globe valves only. The

LSB mean plus 2 standard deviations results were 20.1%, 20.8%, and 18.7%,

respectively.

The licensee used

a 15% bias margin for LSB and added

a 5% bias margin for stern

factor degradation.

These were added directly to increase the minimum required

thrust.

Equipment accuracies

and torque switch repeatability were combined in a

square root sum of the squares methodology and then used to increase the

minimum required thrust.

The licensee compared this methodology to the

methodology of adding the statistical LSB bias and the 5% bias for stem factor

degradation with the random LSB combined in a square root sum of the squares

methodology with torque switch repeatability and diagnostic accuracies.

The

licensee's methodology bounded all cases except when the value of torque switch

repeatability was 5% and diagnostic accuracies were less than 7%.

In this case,

the licensee used a 16% direct bias for LSB to hound these values.

Based on the

licensee's test data, the LSB values used in the design-basis

calculations were

considered acceptable.

b.1.5

Stem Friction Coefficien

The inspectors reviewed Technical Report 0012-00204-R01,

"As-Left Stem/Stem

Nut Coefficient Of Friction," Revision 0, which was a statistical study of the

stem/stem nut coefficient of friction (SFC) for static test data.

The licensee

performed two studies, one which included all the test data and one which

excluded those values less than 0.04 (which were considered suspect compared to

industry experience).

The study, which included all the data, resulted in a mean

value of 0.097 and a mean value with 2 standard deviations of 0.178.

The study,

which excluded the values below 0.04, had a mean value of 0.102 and a mean

value with 2 standard deviation of 0.174.

The licensee used the measured static

SFC, generally rounded up to 0.15, if the measured

value was less than 0.15.

For

those MOVs where torque was not measured,

a value of 0.174 was used for the

SFC.

The inspectors had two concerns with the licensee's methodology.

Industry and

NRC sponsored test data has shown that dynamic SFC values (measured at flow

isolation) were generally higher than the values measured

during static testing.

The

licensee performed a second statistical evaluation using the dynamic torque and

thrust values from torque switch trip. The SFC values for this study indicated a

mean of 0.104 and a mean value with 2 standard deviations of 0.174.

The

inspectors discussed with the licensee that the values of SFC may still be higher at

flow isolation verses torque switch trip values.

The inspectors noted that changes

in SFC from static values to dynamic values should be accounted for in the closing

direction by the licensee's

LSB margin.

The inspectors'econd

concern was related to the potential change in SFC in the

open direction due to dynamic conditions.

In this direction, there was no added

LSB margin to account for the change in SFC.

The licensee performed an

evaluation for the inspectors which compared the motor operator open capability to

the minimum required thrust using the measured

SFC and a 15% direct bias for

LSB. No operability concerns were identified at this time, since the MOVs appeared

to have sufficient margin using this methodology.

Based on several issues concerning open motor capability values with respect to

SFC, further licensee review and subsequent

evaluation by the NRC will be required

for program closure.

The licensee needs to: provide the methodology and

justification to address

open motor capability when the appropriate SFC is taken

into account; for all valves with an open safety function, provide the valves

capability margin using the proposed methodology; and provide assurance

that this

issue will continue to be addressed

during the periodic verification program (i.e.,

program or procedure revision).

b.1.6

0 en Un ea in

Forces

During an April 1996 MOV inspection, inspectors identified that the open unseating

force was not accounted for and compared to the operator's capability or structural

limits. Subsequent

to this inspection, the licensee had compared the static

unseating forces to operator thrust and valve structural limits and to the dynamic

test data for MOV open capability (at degraded voltage and high ambient

temperature,

as appropriate).

No concerns were noted with these evaluations.

The

inspectors noted, however, that the licensee had not completed the review of the

static unseating forces compared to the operator's torque capability.

Based on this

finding, the licensee compared the static open unseating force to the operator's

thrust capability and identified MOVs 2-QIVIO-451 and -452 (volume control tank to

CVCS pumps isolation valves) had a potential overtorque condition.

These valves

have high speed actuators and with an unseating torque which would slightly

exceed the motor capabilities torque if the valves were opened at degraded voltage.

Since these MOVs do not have an open safety function, there was not an

operability concern.

The resolution of the potential overtorque condition was being

addressed

by CR-1780.

Although the licensee had modified the dynamic test procedure acceptance

criteria,

the static test procedure acceptance

criteria was not modified to address open

unseating forces.

A revision to the static test acceptance

criteria to address the

MOVs unseating force versus the operator and valve structural limits, and operator

capability needs to be completed prior to program review closure.

b.1.7

Linear Extra ola ion

The inspectors reviewed Technical Report 0012-00192-R02,

"Justification For

Linear Extrapolation Of Gate and Globe Valve Dynamic Test Data," Revision 0. The

licensee used the EPRI study and data to justify the position of linear extrapolation

from 30 percent dp to 100 percent design-basis

dp, with the exception of

blowdown conditions.

The inspectors noted that the lowest percent dp

extrapolated was 61 percent of design-basis

dp.

Further, the licensee noted that dp

loads less than 3000 Ib-force may yield VFs that were inaccurate and misleading.

The Technical Report, however, did not mention a minimum allowed value of dp (an

absolute value, not a percentage) to ensure that all linear extrapolations would be

meaningful.

This was a minor procedure issue that the licensee stated would be

corrected.

The inspectors considered the licensee's

linear extrapolation

methodology to be acceptable.

b.1.8

Tor ue Switch Re eatabili

The licensee's application of margin for torque switch repeatability was acceptable

for program review closure.

Torque switch repeatability values of 5%, 10% and

20% based on torque switch setting and actuator torque were appropriately applied

following Limitorque guidance.

b.1.9

Butterfl

Valve Tes in

Approximately two-thirds of all program butterfly valves (43 out of 66) had been

dynamically tested.

Based on this test information, the licensee's verification of

design basis capability of butterfly valves was near completion, pending completion

of analyses adjusting butterfly valve structural limits. While the majority of the

licensee's butterfly valves exhibited substantial capability margin, several

assumptions

used in the capability verification equations could not be verified by

the inspectors and close-out of GL 89-10 program review was pending submittal of

additional information and NRC review of the following issues:

(a)

To allow a means of comparing valves and determining a dynamic effect

load to apply to static test results, the licensee used a seating/unseating

factor which was based on the bearing equation described in EPRI's

Application Guide for Motor-Operated Butterfly Valves.

Essentially, the

seating/unseating

factors were determined by solving for the bearing y

described

in the Application Guide.

These seating/unseating

factors were

used the same way as valve factors are used for gates and globe valves.

For non-dp tested valves, the seat/unseat

factors were based on the

seat/unseat

factors obtained from dp tested valves in the same group.

However, as discussed

in the section II.B.4.b of the NRC's SE of the EPRI

MOV PPM Topical Report, EPRI testing revealed several areas whero the

Application Guide needed improvement or correction.

EPRI was revising the

Application Guide and plans to include new information on various issues,

including the treatment of bearing torque.

During the ir.spection, the NRC

inspectors were informed that based on discussions with engineers involved

with the Application Guide revision, the planned changes to the Application

Guide did not affect the methodology.

In view of the uncompleted revision

to the Application Guide, the NRC requested

a formal response

on the

impact of the changes

on the bearing equation and whether any proposed

changes impacted the methodology.

(b)

For symmetrical butterfly valves, the licensee assumed

closing hydrodynamic

loads were negligible, and therefore, were not included when comparing

actuator capability verse required seating torque.

The basis for this

assumption was based on the January 1993 EPRI Application Guide, page

3-47.

However, the NRC could not confirm whether information generated

during development of the EPRI butterfly valve model consistently supported

this assumption and requested

a formal response

on this issue.

(c)

The NRC also requested,

upon completion of the ongoing analyses,

a

summary tabulation detailing the structural and weak link margins for all

program butterfly valves.

0

I

4

(d)

The licensee's method for extrapolating tested torque to design basis

conditions used a linear method based on differential pressure if the peak

dynamic torque occurred at less then 15 degree open disc angle.

If the peak

dynamic torque occurs at greater than a 15 degree open disc angle,

extrapolation was performed based on flow rate squared.

The review of the

white paper justifying this position will be completed with review of the

submittals discussed

above.

The inspectors requested that the licensee submit information on items (a)-(c)

above, for NRC review.

The inspectors informed the licensee that the NRC's GL 89-10 program review closure will be contingent upon receipt and NRC review of

these p!ans.

b.1.10

Mar inal Valves

The inspectors noted that a number of valves in the GL 89-10 program were

considered

marginal based on design-basis

calculations.

In view of evolving

industry issues, such as the use of run versus pullout efficiencies, the inspectors

were concerned with the adequacy of several of the licensee's MOVs with less than

10 percent margin.

Although 16 valves were scheduled for margin improving

modifications, there were no established

plans for the other marginal valves.

The

inspectors requested that prior to program closure, the licensee submit any plans to

address the licensee's marginal valves.

b.2

Pro ram Sco

Chan

e

A total of 34 valves were removed from the program since the Part 2 inspection.

Thirty-two were removed based on Supplement

7 to GL-89-10, mispositioning.

The

remaining two were balance-of-plant

(BOP) valves that were not required to be in

the program scope.

Although removed from the program, these valves had been

diagnostically tested, and in some cases were scheduled for a design change to

increase the valves'apability.

With the removal of these valves, the program scope for both units consisted of

220 MOVs: 104 gates, 50 globes, and 66 quarter-turn (butterfly) valves.

Included

in the scope were 12 BOP valves, which was considered

a positive aspect of the

MOV program.

From this scope, the licensee was able to dynamically test 120

MOVs, which was considered

a program strength.

An additional positive aspect

was the position to perform diagnostic testing of MOVs not included in the

GL 89-10 program.

b.3

Periodic Verifica ion

PV of Desi n-Basis Ca abili

The licensee planned to statically test all program MOVs on an initial 3 fuel cycle

period with increased frequencies for valves in high ambient temperatures

or in

harsh environments.

Dynamic testing of program valves that are testable and

meaningful was planned taking into consideration margin and risk. However, as of

the date of the inspection, the licensee did not have a schedule or actual numbers

of valves to be dynamically tested.

10

The NRC staff will review the PV program in greater detail following the licensee's

submittals in response to GL 96-05, "Periodic Verification of Design-Basis

Capability of Safety-Related Motor-Operated Valves." As stated in the Generic

Letter, consideration of the benefits (such as identification of decreased

thrust

output and increased thrust requirements)

and potential adverse effects (such as

accelerated

aging or valve damage) when determining appropriate PV testing for

each program valve needs to be considered.

b.4

Post-Maintenance

Verifica ion

es in

PMT

Post-maintenance

verification/testing requirements documented

in Section 6 of the

Motor-Operated Valve Program Description, Revision 5, were reviewed and found

acceptable for program closure by the inspectors.

One program revision was

required to resolve the IFI discussed

in Section E8.1 of this report concerning

testing requirements after valve packing adjustments.

The licensee adequately

established static and dynamic test requirements following MOV maintenance

and

modifications.

b.5

MOV Trendin

and Correc ive Ac ions

The inspectors determined that the licensee's trending program appeared

capable of

tracking and evaluating data to maintain MOV design-basis

capability.

The

licensee's

MOV coordinator maintained

a database that contained baseline

diagnostic test results that would be used to evaluate valve performance during the

PV program.

The licensee's condition report process and the maintenance

rule will

assist the tracking and trending of repetitive problems or to initiate reviews of other

MOVs for similar problems.

Overall, the reviewed MOV-related CRs generated

over the last two years indicated

that MOV failures were appropriately reviewed and dispositioned.

However, the

inspectors were concerned that actions had not been completed on the resolution

of potential MOV overloading due to handwheel operation.

Recent industry MOV

failures, as well as a CR for MOV 2-ICM-311, reemphasized

that certain MOVs,

such as those with SMB-00 operators with a 4.38:1 handwheel ratio, can develop

manual loads that readily approach valve or operator limits. Although guidance to

evaluate MOV handwheel loads was given in Limitorque SEL-11 and EPRI

Application Guide NP-6660-D, the licensee had not fully addressed

this issue.

CR 96-0687 was generated

in April 1996 as a result of licensee identification that

Operations had manually "hand wheeled" MOV 2-ICM-311 into the seat with

enough force to exceed the torque switch settings.

The inspectors reviewed the

CR and determined that, besides identification of susceptible

MOVs, little progress

had been made in resolution of the CR.

Further, the existing procedural

requirements, which require that excessive force not be used during manual

operation, were insufficient. Of concern to the inspectors were the many valves in

the preliminary revie~ that indicated maximum handwheel rim pull forces as low as

10 pounds.

Additionally, the CR investigation due date had been extended twice

and was overdue by three months as of the week of the inspection.

The inspectors requested that the licensee submit plans on resolution of this issue

for NRC review.

The inspectors informed the licensee that the NRC's GL 89-10

program review closure will be contingent upon receipt and NRC review of these

plans.

b.6

NRC Informa ion Notice

IN 92-18

"Poten ial for Loss of Remote Shu down

Ca abili

Durin

a Control Room Fire"

IN 92-18 identified the potential for loss of remote shutdown capability during a

control room fire. Due to potential hot shorts caused

by a control room fire, various

MOVs controlled from the remote shutdown panel could go to a stall condition,

since the control signal would not be available to stop power to the motor.

This

could cause valve and/or operator degradation that could result in the loss of safe

shutdown capability.

'he

MOV control circuits use a double break scheme around the open/close valve

contact.

In most cases this was provided by both limit/torque switch contacts and

remote/alternate

transfer switch contacts.

For the above, two hot shorts of the

correct polarity and conductors must occur to operate

a valve.

The licensee's

response to IN 92-18 was recently reviewed by regional engineering inspectors and

is discussed

in Inspection Report No. 50-315/96010;

50-316/ 96010.

The

inspectors had reviewed the electrical design of the Appendix R valves for both

units and concluded that the licensee met the intent of the IN.

Conclusions

The failure to perform an operability determination on the PORV block valves when

new information became available was considered

a violation for failure to

document

a potentially adverse condition and perform an operability determination.

This was a significant concern, considering the previous issues identified by the

NRC in this area.

Although a majority of the significant issues related to the MOV program have been

resolved, a number of issues relating to the design-basis

capability of program

valves remain open.

Therefore, the NRC's GL 89-10 program review will remain

open pending completion and submittal of these open issues as discussed

in the

details of this report.

Aspects of the program adequately completed for program

review closure included program scope, requirements for post maintenance testing,

trending, and corrective action program.

E7

Quality Assurance in Engineering Activities

E7.1

Licensee Self-Assessment

Activities

The inspectors reviewed a recent MOV self-assessment.

Although narrow in scope,

the self assessment

identified several good technical issues.

The use of an outside

MOV expert was considered

beneficial to improving the MOV program.

12

I

III'

ES

Miscellaneous Engineering Issues (92902)

E8.1

Closed

Ins ec ion Followu

I em 50-315 93006-04

50-316 93006-04:

Packing

adjustment PMT requirements did not include diagnostic verification to confirm that

assumed

packing thrust design loads were not exceeded.

The licensee's position

had been that if the original packing gland nut torque was not exceeded

during the

packing adjustment, the packing load would not exceed the value which had been

determined to be acceptable

during the previous diagnostic test.

Although various

tests had been conducted in an attempt to validate this position, the relatively small

amount of data did not support use of this position across all program MOVs.

Further, the position was weakened with on-site examples of increased

packing

loads due to improper maintenance that had resulted in cocked packing glands

resulting in higher packing loads (the nuts had been retorqued to the original

torque).

In view of this, the licensee committed to revise the process and, for all

program MOVs, will diagnostically verify, subsequent

to packing adjustments, that

packing loads did not adversely affect thrust requirements.

This item is closed.

E9

Updated Final Safety Analysis Report (UFSAR) Commitments

E9.1

Review of UFSAR Commi ments

The inspectors reviewed the applicable sections of the UFSAR that related to the

inspection areas discussed

in this report.

The inspectors verified that the UFSAR

wording was consistent with the observed plant practices, procedures and/or

parameters.

V. Mana ement Meetin s

X1

Exit Meeting Summary

The inspectors presented the inspection results to members of licensee

management at the conclusion of the inspection on October 25, 1996.

The

inspectors re-exited with members of licensee management

on December 5, 1996.

The licensee acknowledged the findings presented.

The inspectors asked the

licensee whether any materials examined during the inspection should be

considered

proprietary.

No proprietary information was identified.

13

PARTIAL LIST OF PERSONS CONTACTED

Licensee

¹ "A. Blind, Site Vice President

¹"J. Sampson,

Plant Manager

¹

K. Baker, Assistant Plant Manager

"D. Hafer, Nuclear Engineering

¹"F. Pisarsky, Nuclear Engineering

¹ "D. Powell, Nuclear Engineering

¹ S. Steinhart, Nuclear Engineering

"L. Demaizco, Nuclear Engineering

¹ "A. Gort, Nuclear Engineering-MOV Coordinator

¹"K. Toth, Licensing

"L. Smart, Licensing

R. Ptacek, Nuclear Safety 5. Assessment

Duke En ineerin

& Services

L. Lutz, MOV Engineer

S. Korn, MOV Engineer

NRC

. Kropp, Chief, Engineering Specialists Branch

1

¹ "B. Bartlett, Senior Resident Inspector

"B. Fuller, Resident Inspector

¹ J. Maven, Resident Inspector

INSPECTION PROCEDURE USED

TI 2515/109

Safety-Related

Motor-Operated Valve (MOV) Testing and Surveillance

ITEMS OPENED and CLOSED

~Oened

50-31 5/9601 2-01 (DRS);

50-31 6/9601 2-01 (DRS)

VIO

Failure to initiate a condition report and perform a

prompt operability determination for the PORV block

valves

50-31 5/9601 2-02(DRS);

50-31 6/9601 2-02(DRS)

IFI

Modifications not completed for the PORV block valves

Closed

50-31 5/93006-04;

50-31 6/93006-04

IFI

PMT requirements following packing adjustments

LIST OF ACRONYMS USED

AFW

BOP

COF

CR

CVCS

dp

EPRI

GL

HPCI

IFI

IN

INEL

LER

LCO

LSB

MOV

NRC

NRR

P&.ID

PDR

PMI

PMT

PORV

PPM

PV

RCP

RCS

RHR

ROL

S/0

SE

SFC

SG

SI

SSC

Tl

TS

UFSAR

URI

VF

VIO

Auxiliary Feedwater

Balance-of-Plant

Coefficient of Friction

Condition Report

Chemical and Volume Control System

Differential Pressure

Electric Power Research Institute

Generic Letter

High Pressure

Coolant Injection

Inspector Followup Item

Information Notice

Idaho National Engineering Laboratory

Licensee Event Report

Limiting Condition for Operation

Load Sensitive Behavior

Motor Operated Valve

Nuclear Regulatory Commission

Office of Nuclear Reactor Regulation

Piping 5. Instrumentation Diagram

Public Document Room

Plant Manager Instruction

Post Maintenance Testing

Power-Operated

Relief Valve

Performance Prediction Methodology

Periodic Verification

Reactor Coolant Pump

Reactor Coolant System

Residual Hear Removal

Rate of Loading

Shutoff

Safety Evaluation

Stem Friction Coefficient

Steam Generator

Safety Injection

Structure, System, or Component

Temporary Instruction

Technical Specification

Updated Final Safety Analysis Report

Unresolved Item

Valve Factor

Violation

15

ll

1I