Monthly Operating Rept for Aug 1992 for DC Cook Unit 2
ML17329A608
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 08/31/1992
From: Doreen Turner
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
To:
Shared Package
ML17329A606 List:
References
NUDOCS 9209150076
Download: ML17329A608 (5)


Text

N.R.C.

OPERATING DATA REPORT DOCKET NO.

50-316 DATE 03-Sep-92 COMPLETED BY DG Turner TELEPHONE 616-465-5901 OPERATING STATUS

1. Unit Name D.

C.

Cook Unit 2

2. Reporting Period August 92
3. Licensed Thermal Power (MWt) 3411 4.

Name Plate Rating (Gross MWe) 1133

5. Design Electrical Rating (Net MWe) 1090 6.

Maximum Dependable Capacity (GROSS MWe) 1100 7.

Maximum Dependable Capacity (Net MWe) 1060 notes

8. If Changes Occur in Capacity Ratings (Items no.

3 through 7) Since Last Report Give Reasons 9.

Power Level To Which Restricted. If Any (Net MWe) 10.

Reasons For Restrfctions. If Any:

11. Hours in Reporting Period 12.

No. of Hrs. Reactor Was Critical

13. Reactor Reserve Shutdown Hours
14. Hours Generator on Line
15. Unit Reserve Shutdown Hours
16. Gross Therm.

Energy Gen.

(MWH)

17. Gross Elect.

Energy Gen.

(MWH)

18. Net Elect.

Energy Gen.

(MWH)

19. Unit Service Factor
20. Unit Availability Factor
21. Unit Capacity Factor (MDC Net)
22. Unit Capacity Factor (DER Net)
23. Unit Forced Outage Rate 24.

Shutdowns Scheduled over Next Six This Mo.

Yr.

744.0 242 '0.0 0 ~ 0 0.0 29234 0

0 0.0 0.0 0.0 0.0 100.0 Months (Type, to Date 5856.0 2194.4 0 '

1266.0 0.0 3772061 1163670 1120154 21.6 21.6 18.0 17.4 53 '

Date,and Cumm o 128568. 0 85382.5 0.0 82866.1 0.0 256466694 83431820 80365026 65.6 65.6 60.0 58 '

14.3 Duration):

25. If Shut Down At End of Report Period, Estimated Date of Startup:

The unit was aralleled to t e s

tern ri on 2

2 at our

26. Units in Test Status (Prior to Commercial Operation):

Forcast INITIALCRITICALITY INITIALELECTRICITY COMMERCIAL OPERATION Achieved 920915007b 920904 PDR 'DOCK 0500031b P,DR

AVERAGE DAILY POWER LEVEL (MWe-Net)

DOCKET NO.

50-316 UNIT TWO DATE 03-Sep-92 COMPLETED BY DG Turner TELEPHONE 616-465-5901 DAY 1

2 3

4 5

6 7

8 9

10 11 12 13 14 15 16 MONTH AVERAGE DAILY POWER LEVEL August 92 DAY 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 AVERAGE DAILY POWER LEVEL

UNIT SHUTDOWNS AND PONER REDJCZIONS REPORT MONIH:

August 1992 DOCKEZ NO:

UNIT NAME DATE COMPLI"TED BY:

TE XI'0-316 D.C.

COOK UNIT 2 Septe11lber 5,

1992 G.J. Costello (616) 465-5901 METHOD OF SHUTPING LI:CENSEE IXRATION IXNN EVENT NO DATE TYPE HOURS REASON REACIOR3 REPORT NO.

SYSTEM CCMjK5ZKZ CAUSE AND CORRECZXVE ACTION TO CODE CODE5 PREVENT REQ3RIKNCE 224 920701 F

Cont'd 744 N/A N/A N/A The unit renained shutdown for the C't lov pressure turbine and main generator inspection.

The repairs of the pressurizer manway steam leak were completed, and the RCS was returned to rated pressure and temperature.

'Ihe reactor was returned to pmer and the turbine has been rolled for vibration evaluation and balancing.

No conclusive cause for the turbine vibration problem was found 1

F:

S 2

Forced Reason:

Scheduled A:

Equipment Failure (Explain)

B:

Maintenance or Test C:

Refueling D:

Regulatory Restriction E:

Operator Training and License Rcamination F:

Administrative G:

Operational Error (Explain)

H:

Other (Explain) 3 Method 1:

Manual 2:

Manual Scram 3:

Automatic Scram 4:

Other (Explain) 4 5

Exhibit G Instructions Exhibit I:

Same Source for preperation of data entry sheets for Licensee Event Report (LER) File (NUREG 0161)

DOCKET NO:

UNIT NAME:

COMPLETED BY:

TELEPHONE:

DATE PAGE:

50-316 D.C.

Cook Unit 2 G.J. Costello (616) 465-5901 September 5,

1992 1 of 1 MONTHLY OPERATING ACTIVITIES AUGUST 1992 HIGHLIGHTS The unit entered this reporting period with the RCS in Mode 3

preparing for cooldown to Mode 5 for corrective maintenance on the pressurizer steam space manway in parallel with the disassembly and inspection of the "C" low pressure turbine and the inspection of the main generator.

The unit ended the reporting period in Mode 2 with the reactor critical and reactor power being maintained as required to support the turbine generator vibration evaluation and balancing efforts.

There were no challenges to the pressurizer safety valves or power operated relief valves.

Gross electrical generation for the month of August was 0

MWH.

DETAILS 8-1-92 0405 1236 2156 8-18-92 0837 0915 8-20-92 0422 8-21-92 1759 8-25-92 2033 2147 Commenced RCS cooldown to Mode 5.

The RCS is in Mode 4.

The RCS is in Mode 5.

Commenced RCS heatup.

The RCS is in Mode 4.

The RCS is in Mode 3.

The reactor is critical.

The reactor entered Mode 1.

Rolled the main turbine.

Between 8-25-92 and 8-31-92 reactor power was changed as required to support the main turbine vibration evaluation and balancing efforts.

~

e

~ r DOCKET N UNIT NAME:

COMPLETED BY'ELEPHONE:

DATE:

PAGE:

50-316 D.C.

Cook Unit 2 E. C. Schimmel (616) 465-5901 September 4,

1992 1 of 1 MAJOR SAFETY-RELATED MAINTENANCE Au ust 1992 There vere no ma)or safety-related maintenance items during the month of August.