ML17328A388
| ML17328A388 | |
| Person / Time | |
|---|---|
| Site: | Cook |
| Issue date: | 08/22/1990 |
| From: | Koltay P, Konklin J, Lanning W Office of Nuclear Reactor Regulation |
| To: | |
| Shared Package | |
| ML17328A387 | List: |
| References | |
| 50-315-90-201, 50-316-90-201, GL-89-04, NUDOCS 9008270005 | |
| Download: ML17328A388 (50) | |
See also: IR 05000315/1990201
Text
U.S ~
NUCLEAR REGULATORY COMMISSION
OFFICE
OF
NUCLEAR REACTOR REGULATION
NRC Inspection Report Nos:
50-315/90-201
50-316/90-201
Docket Nos.:
50-315
and 50-316
Licensee:
American Electric Power Service Corporation
Company
1 Riverside Plaza
Columbus,
OH
43216
License Nos.:
DPR-74
Facility Name:
Donald C.
Cook Nuclear Power Plant, Units
1 and
2
Inspection at:
Donald C.
Cook Site,
Bridgman,
MI and
AEPSC Headquarters,
Columbus,
OH
Inspection
Conducted:
June
11 through June
22 and July
9 through July 13,
1990
Inspection
Team:
NRC Consultants:
Approved by:
Peter
S. Koltay, Team Leader,
S. V. Athavale, Discipline Lead,
Melanic A. Miller, Operations
Engineer,
Gregory
M. Nejfelt, Reactor Engineer,
Region III
Hershell A. Walker, Reactor Engineer,
Region III
John
D. Wilcox, Senior Operations
Engineer,
Harban Singh,
AECL (Atomic Energy of Canada,
Ltd.)
Mahesh Singla,
AECL
Donald A. Beckman,
AECL
David B. Waters,
AECL
Lo
. nley
AECL
4( / l1o
eter
.
o tay,
earn
ead
Team Inspection Section
A
Special
Inspection
Branch
Division of Reactor Inspection
and Safeguards
Office of Nuclear Reactor Regulation
at
Approved by:
Approved by:
arne
.
on
n,
se
Team
nspection
Section
A
Special
Inspection
Branch
Division of Reactor Inspection
and Safeguards
Office of Nuclear Reactor Regulation
(
ayn
.
anni ng,
ve
Speci
1 Inspection
Branch
Division of Reactor Inspection
and Safeguards
Office of Nuclear Reactor Regulation
9008270005
900822
ADOCK 050003l5
9
at
g/'zz
Po
a e
TABLE OF
CONTENTS
PAGE
EXECUTIVE SUMMARY..~ ~ ~ ~ ~ ~ ~ ~ . ~ ~ ~ ~
~ ~ ~ ~ ~ ~ ~ ~ . ~ ~ . ~ ~ . ~ ~ ~ ~ ~ ~ ~ ....
~ ~ ~ ~ ~ ~ ~ . ~ ~ ~
1.0
INSPECTION OBJECTIVE AND SCOPE.
~.... ~..... ~...... ~ . ~...
~ ~ .. ~.....
2.0
INSPECTION DETAIL ... ~ . ~ . ~ . ~ . ~ ~ . ~ ..
~ . ~". ~ ~.;"~ . ~"'. ~ ~ ~ ~ ~ ~
2.1
Design Review...............................................
2.1.1
Design Control and Independent
Design Verification...
2.1.2
Electrical Systems...................................
2.1.3
Mechanical
Systems
and Components....................
2.1.4
Instrumentation
and Control..........................
2
3
5
7
2.2 Operations............"..""..'-.".""".-""- -"
~ ~ ~
2.2.1
Procedures.........................
2.2.2
Control
Room Drawings..............
2.2.3
Material Condition of Equipment....
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
~ ~ ~ ~ ~ ~ 1 ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
9
10
11
2.3 Haintenance.................-"""-"-"-.-"".-"- "."
2.3.1
Procedures
and Vendor Manuals......
2.3.2
System/Component History...........
2.3.3
Spare Parts
and Material Control...
2.3.4
Engineer ing Support................
2.3.5
Drawing Updates....................
2.3.6
Root-Cause Analysis................
~ ~ ~ 1 ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
12
13,
14
15
15
16
2.4
guality Assurance..........................................
2.4.1
Onsite
Review Committee.............................
2.5
Surveillance
and Inservice Testing.........................
16
17
17
2.5.1
Surveillance
Test Procedures.......
2.5.2
Station Battery Testing............
2.5.3
Inservice Testing (IST)............
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
17
19
20
3'
CONCLUSIONS ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
~ ~ ~ ~ ~ ~ ~ ~ ~ ~
20
4 0
UNRESOLVED
ITEHS ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
~ ~ ~ ~ ~ ~ ~ ~ ~ ~
21
5.0
EXIT MEETING..... ~ . ~~...~.....................
~ .~...
~ ~ ~ .
~ .
21
APPENDIX A - Summary of Inspection Findings.........
APPENDIX
B - Personnel
in Attendance at Exit Meeting
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
A-1
B-1
EXECUTIVE SUMMARY
A Nuclear Regulatory
Commission
(NRC) inspection
team conducted this safety
system functional inspection
(SSFI) from June ll through June
22 and July
9
through July 13, 1990, to assess
the operational
readiness
of the essential
(ESW) system.
The SSFI
team focused
on the licensee's ability to
integrate
systems
and components within the functional areas of design,
design
control, operations,
maintenance,
and surveillance
and testing into cohesive
programs that support operational
readiness
of safety systems.
The SSFI team determined that the
ESW system
had an adequate
design capacity to
perform its required safety functions.
Nevertheless,
problems requiring
management
attention were identified in the areas of design control, surveil-
lance
and testing,
procedural
adherence,
and corrective actions.
The team was particularly concerned with the licensee's
failure to implement an
effective independent
design verification program.
The absence
of a design
verification program was recognized
by the licensee
in 1987
and was again
identified in a 1989
NRC inspection report.
The team identified several
examples of design deficiencies that were the result of an ineffective inde-
pendent
design verification program.
These
included under sized electrical
cables
and circuit breaker current interrupting capacity for the 4-kV buses,
improper inverter voltage qualification, and wrong relief valve settings for
the service water system.
Although the individual findings did not affect safe plant operations,
the team
was concerned that not all existing designs
were supported
by acceptable
calculations
because
of the significant number of deficiencies it had
identified in the calculations
reviewed.
The team identified numerous
minor deficiencies
which could be attributed to a
general
lack of attention to procedural
requirements.
Examples
included the
improper use of limitorque motor mounting bolts by the maintenance
personnel
and the improper use of locked valve procedures
by the operations staff.
The
team also identified procedural
inadequacies
in the areas
of surveillance
and
testing.
Other weaknesses
identified by the team included the lack of a
comprehensive
root-cause
analysis
program,
inadequate
control over the list of
safety class
equipment,
and inadequate
coordination
between engineering
design
groups'he
team determined that, although
concerns
in the areas of independent
design
verifications, station battery testing,
drawing controls,
emergency
diesel
generator
loading calculations,
and setpoint calculations
had been identified
to the cognizant engineers
through previous
NRC and licensee audits,
both engi-
neering
and operations
personnel
had failed, in some cases,
to recognize the
safety significance of the concerns,
and that consequently,
licensee
manage-
ment had failed to take prompt corrective actions.
ln
I
1.0
INSPECTION OBJECTIYE AND SCOPE
The Nuclear Regulatory
Commission
(NRC) staff performed
an announced
safety
system functional inspection
(SSFI) to verify the functionality of the
emergency
(ESW) system at the D. C. Cook Nuclear Power Plant,
Units I and 2.
The primary objective of the SSFI
was to assess
the operational
readiness
of
the
ESW system
and other interacting
systems
by determining whether:
The systems
were capable of performing the safety functions required
by
their design bases.
Surveillance testing
was adequate
to demonstrate
that the systems
would
perform their required safety functions.
System maintenance
(with emphasis
on pumps
and valves)
was adequate
to
ensure
system operability under accident conditions.
Training was adequate
to ensure that technicians
could proper ly operate
and maintain the systems.
Management controls were adequate
to ensure that the safety
systems
would
fulfillthe safety functions required
by their design bases.
Procedures
provided adequate
guidance to ensure
proper system operation
under normal
and accident conditions.
The SSFI team reviewed system descriptions;
the Updatea
Final Safety Analysis
Report; equipment sizing calculations;
documentatior, pertaining to system
protection, controls,
and interlocks; equipment specifications;
modification
packages;
related test
and operating
procedures;
and one-line
and elementary
diagrams
and equipment layout drawings.
In addition, the team reviewed operating
and administrative control procedures,
selected
operator
status
logs,
and control room system files; performed
walkdowns of systems
and plant areas;
and interviewed licensed
and non-licensed
operators,
and instrumentation
and control personnel
arid system engineers
with
regard to the
ESW system.
2.0
INSPECTION DETAIL
The
ESW system
was
common to Units I and
2 and provided cooling water to compo-
nent cooling heat exchangers,
containment
spray heat exchangers,
emergency
diesel generators,
and control room air conditioners.
In addition
the
system
served
as
a backup water source to the auxiliary feedwater
tAFW) pumps
when the condensate
storage tank, which was the normal supply for the
system, is either empty or otherwise lost.
The system consisted of four
pumps, fuur duplex strainers,
and associated
piping and valves.
System piping
was arranged
in two independent
each serving certain
components of
each unit.
2.1
Design Review
The design portion of the inspection
was conducted at the corporate
headquar-
ters of American Electr ic Power Service Corporation
(AEPSC) in Columbus,
Ohio.
The team evaluated
the technical
adequacy
of the design,
compliance with
regulations
and licensing
commitments,
and the effectiveness
of the design
controls.
The evaluation
was accomplished
by review of drawings, specifica-
tions, calculations,
engineering
and design control procedures,
modification
packages,
and interviews with the licensee
engineering staff and all levels of
licensee
management.
The team reviewed in detail approximately
5 engineering
calculations
in the electrical discipline,
20 in the mechanical discipline,
and
10 in the instrumentation
and control (I&C) discipline.
In addition to reviewing various diagrams,
calculations,
engineering
proce--
dures,
and design modification packages,
the team evaluated
the engineering
organization
and experience,
interdiscipline coordination,
and engineering
--.
support for operation-related activities.
The engineering
and technical
support to the operating staff was adequate.
2.1.1
Design Control and Independent
Design Verification
The team found that independent
design verifications were either not performed
or were performed inadequately
for original plant design calculations, test
reports
and drawings,
and design
documents resulting from design
changes
and
design activities subsequent
to plant licensing.
The
NRC staff had identified the absence
of independent
design verification
during
a 1989 inspection.
A licensee-sponsored
SSFI inspection of the Unit 1
(AFW) system in 1987
had resulted in the
same finding.
In
response
to the finding, the licensee instituted
a program for independent
design verification in 1989.
The team found that the program -properly incorpo-
rated the requirements
of 10 CFR Part 50, Appendix B, and the American National
Standards
Institute (ANSI) Standard
N45.2.11-1974
but that the licensee
had not
effectively implemented the program.
Calculations
performed after the
new program was implemented in both electrical
and mechanical
designs either did not receive
an independent
design verifica-
tion or received
an improperly performed verification.
In addition, verifica-
tion of many post-1988 calculations
were accomplished
by the verifier stating
not applicable
(N/A) for each of the verification items
on the independent
verification forms.
Some of the verification questions
noted
as
N/A related to
the correctness
of the calculation inputs, application of proper codes to the
calculations,
and the validity of information relating to design
and environ-
mental conditions.
Hany of the calculations
the team reviewed
had been
based
on unverified assumptions,
and the licensee
did not have
a program to track
these
assumptions
to ensure verification before declaring the affected safety
system(s)
operational.
Although previous inspections
had indicated that the independent
design verifi-
cation program was deficient, the licensee failed to correct this problem and
to implement an effective verification program.
Title 10 CFR 50, Appendix B,
Criterion XVI, required that measures
be established
to ensure that conditions
adverse to quality are promptly identified and corrected in a manner to
preclude repetition
(see Appendix A, Unresolved Item 90-201-01).
Several
examples
where inadequate
design verification contributed to design
deficiencies
are listed below with reference to subsequent
report sections
in
which each is discussed
in more detail:
Undersized
4-kV electrical cables
(Section 2.1.2);
Undersized
4-kV circuit breaker current interrupting capacity
(Section 2.1.2);
Improper inverter voltage qualification (Section 2.1.2);
Incorrect service water system relief valve settings
(Section 2.1.3);
and
Inadequate
setpoint
program (Section 2.1.4).
The following examples of original calculations that did not receive
indepen-
aent design verification but were subsequently
verified by the liceiisee during
the inspection period are discussed
in Section 2.1.3:
Essential
service water flow requirements
during a fire scenario,
calcula-
tion No. HXP890720AF;
.
Essential
pump potential runout, calculation
No. HXP900613;
and
Essential
pump room temperature
calculation
No.
DCCHV12ES.
The lack of traceability and validation of design input, the lack of design
document control, and lack of independent
design verification indicated weak-
nesses
in the licensee's
capability to maintain design control for the plant.
The team concluded that the quality assurance
requirements for the design of
nuclear
power plant structures,
systems,
arid components
as delineated
in 10 CFR Part 50, Appendix B, and ANSI N45.2.11-1974
were not properly implemented in
the plant design
and design
change activities in accordance
with licensee
commitrrents.
Title 10 CFR 50, Appendix B, Criterion III, requires that the
adequacy of designs
be verified by the performance of design reviews,
by use of
alternate or simplified calculations,
or by testing
(see Appendix A, Unresolved
Item 90-201-02).
2.1.2
Electr i ca 1 Systems
The team reviewed the
power
source
and distribution system for the
ESW system
as well as design documentation for motors,
loads,.and circuit breakers
needed
for the operation of the
ESW system equipment.
The team identified deficien-
cies in the design basis calculations.
The subject calculations
were indica-
tive of inadequate
design verification as described
in Section 2.1.1 of this
report.
However, these deficiencies
did not affect the operability of the
system.
Specific concerns with the electrical
system design are described
below.
The neutral
ground for the emergency
diesel
generator
(EDG) was grounded
through
a 6-ohm resistor
equipped with a ground detector relay.
This relay
I
~ I
would trip the
EDG output breaker if a ground fault occurred;
however, the trip
function is required to be bypassed
following initiation signals for either
a
loss-of-coolant accident
(LOCA) or a loss-of-offsite-power
(LOOP) cond)tion.
A
ground fault under either of these conditions could result in a fault current
of 400 amps or about
960
kW (about
27 percent of the nominal
EDG rating), with
no protective action until the resistor failed, interrupting the current.
Under the most conservative
condition this would result in an additional
load
of 48
kW.
The initial 1CD
EDG sizing calculation
was unconservative
because
low service
factors were assigned
to cyclic loads such
as the boric acid tank heaters
and
the boric acid heat trace
and load center transformer efficiencies were
omitted.
The licensee
performed another calculation for EDG sizing during
this inspection which accounted for transformer losses,
cyclic loads
and
increased
loading of approximately
48
kW as
a result of an undetected
ground
fault.
The result of this calculation indicated that the load for the
1CD
was approximately
3590
kW, thus exceeding
the continuous rating of 3500
kW, but
below its 2,000 hour0 days <br />0 hours <br />0 weeks <br />0 months <br /> rating of 3650
kM during
LOCA and
LOOP conaitions.
8ecause
the latest calculation
was conservative
in its use of assumptions,
the
team a9reed that the
EDG would meet its maximum load demands.
However, the
team noted that the licensee
had not performed
dynamic analysis to determine
actual fluctuations of EDG loads.
The licensee
stated that
EDG dynamic
analysis
would be performed.
The specifications for Class
1E vital instrument
power inverters stated that
the inverters were qualified to operate at a minimum of 210 Vdc at the input
terminals.
The team found that the end-of-life voltage at the battery termi-
nals would be about 210 Y; therefore,
a lower voltage would exist at the
inverter input terminals
due to the line loss between the battery
and the
inverter.
The licensee
performed calculations
during the inspection,
but the
new calculations
used
an incorrect battery charger output voltage
(250 V) as
an
initial battery condition, even though the battery
charger
would be unavailable
during
LOCA and
LOOP conditions.
The licensee
was reevaluating
the analysis at
the close of the inspection
and expected to obtain confirmation from the
inverter vendor that the units were qualified to operate at the lower,
end-of-life voltage of approximately
200 V.
The licensee
stated that
a
calculation will be performed to show inverter qualification to 200 Vdc (see
Appendix A, Urresolved Item 90-201-03).
As a result of voltage drop considerations for the inverters,
the team reviewed
a voltage drop calculation for the'cable that feeds
dc power to the steam-
driven
AFW pump feedwater inlet valve motor to assess
the adequacy of the motor
terminal voltage.
The worst-case
terminal voltage at the motor was
178 Vdc.
Valve vendor technical information only provided
a single nominal value of
250
V for the terminal voltage.
The licensee
could not substantiate
the
adequacy
of the lower voltages to the valve motor.
The team was concerned with
the operability of the
AFW pump inlet valve during the battery end-of-life
period.
Since the batteries
were installed in 1986,
no immediate safety
concern existed.
However, Technical Specification Section 3.7.12 required that
the turbine-driven
AFW pump be operable while the plant was in modes 1, 2,
and 3.
The team considered this to be an unresolved
item (see Appendix A,
Unresolved
Item 90-201-04).
Cable sizing calculations did not verify the capability of the
ESW pump feeder
cable to withstand effects of short circuit currents until these currents
were
interrupted
by the upstream breaker.
The licensee's
short circuit calculation
indicated that, if a short circuit occurred at the motor terminals,
the value
of the fault current could be 20,940
Amps.
Using an alternate
method
(ICEA
Publication
page 32-382, "Short Circuit Characteristics
of Insulated
Cables" ),
the team estimated that, for a fault at the motor terminals,
cable conductor
temperature
could rise to damaging
levels before the upstream
breaker
opened
the circuit.
This appeared
to be
a generic design
problem for all of the
safety-related
cables.
However, the team verified that
a single failure due to
a short circuit would result in the loss of a single piece of equipment,
and that redundant
equipment would not be damaged.
Therefore,
no immediate
safety concern existed.
However, the licensee
agreed to review this issue.
Short circuit calculations
had not been performed for the 4160-Y Class lE
buses.
As a result of this inspection,
the licensee
per formed the calcu-
lations.
The calculations indicated that the breakers for the safety-related
and nonsafety-related
4-kV buses
were undersized.
For the 4160-V safety-
related buses,
the maximum calculated short circuit duty was found to be about
69,000
Amps, but the installed breakers
were rated for a maximum of 60,000
Amps.
The calculation did not consider the short circuit contribution from the
EDG or higher
(5 percent)
operating voltages,
which could result in short
circuit currents of almost 75,000
Amps, and possible breaker destruction or the
melting and fusing of contacts.
Although the licensee
was aware of the
undersized
breakers, it had not analyzed the effects of such breaker failures.
The team verified that the loss of a breaker would not affect redundant
equipment.
Therefore,
no immediate safety
concern existed.
However, the
licensee
agreed to review this issue.
2.1.3
Mechanical
Systems
and Components
The team evaluated
calculations
and design documentation
associated
with the
ESW system.
The calculations
indicated
inadequate
design verification as
described
in Section 2.1.1 of this report.
Specific concerns with the mechani-
cal engineering
and design
documents
are described
below.
The design documentation
indicated that the thermal relief valves
on the
component
cooling water heat exchangers,
diesel
generator
heat exchangers,
and
containment
spray heat exchangers
had been set at 150 psig while the piping
system design pressure
was
105 psig.
This was inconsistent with the American
Society of Hechanical
Engineers,
Boiler and Pressure
Vessel
Code
(ASNE Code),
Section III, Article ND7000, which required that the set pressure
of the relief
valves
be at, or lower than, the design pressure.
The licensee
stated that the
relief valve setpoints
would be lowered to 105 psig.
No documented
basis
was available to substantiate
the, values for ESW system
design pressure.
The
ESW system description
(SD-DCC-HP102, Revision 9)
provided the design pressure for the duplex strainers
as
125 psig.
The vendor
specification sheets for the heat exchangers
provided the design pressures
for
the heat exchangers
as
150 psig,
and the piping material specification
(DDC PV112 gCN, Revision 0) specified the piping design pressure
as
105 psig.
The
ESW pump performance
curve calculation
(TC-1774 dated September
23,
1971)
showed the
pump shutoff head
as
245 feet (approximately
106 psig).
On the
~I
~
basis of the measured
pump shutoff head of 245 feet,
and considering
the
allowances for the instrument calibration errors in the
pump head measurements,
the piping'design
had little or no calculated
margin.
However, the
ESW system
piping wall thickness
was based
on the standard
weight pipe wall thickness,
which can withstand
much higher pressures
than the
ESW pump shutoff head and,
as noted above,
the system
components
other
than piping were designed for
higher pressures,
so the team considered that no significant safety
concern
existed.
Two inconsistencies
were found between the piping material specification
DCC PY112 gCN, Revision 0, and the system flow diagram 1-5113-30,
Revision 30.
First, the system flow diagram
showed that all the safety-related
piping for
the
ESW system
was piping Class A-12.
However, the piping material specifica-
tion iaentified only the containment
spray heat exchanger
piping, the
cross-connecting
piping, and component cooling water heat exchanger
piping as
Class A-12.
Second,
the system flow diagram
showed that the maximum discharge
pressure
of the
pump was
120 psig.
However, the piping material specifica-
tion showed the maximum design pressure
of the piping as
105 psig.
The
licensee
agreed to resolve the inconsistencies.
Three different seismic analysis reports were found to be applicable for the
same
ESW pump.
Two of these reports
were apparently
prepared
by the
pump
vendor at the time of procurement,
and the third report was prepared
in 1976 by
a licensee contractor.
None of the analyses
had been annotated
to indicate
which was effective.
The licensee
committed to resolve this discrepancy
by
maintaining the
1976 seismic analysis report as the design-controlled
document.
The design calculation for ESW flow under normal operating conditions (dated
September
11, 1972)
showed that the flow through the system using
one
ESW pump
per unit was less
than the required flow.
The licensee
had taken
no action to
resolve this concern before plant licensing.
During this inspection,
the
licensee
performed
a new design calculation
(HXP900627), using the system
resistances
as calculated
in 1984 for calculation
HXP841106,
and demonstrated
that the
pump could supply adequate
system flow.
The team identified a number of additional calculational
weaknesses
attributed
to an inadequate
design verification program.
In each
case,
the licensee
was
able to perform a supplemental
calculation during the inspection to show design
adequacy.
Calculation
HXP890720AF was performed to determine whether
one
pump could
supply the
ESW flow requirements
during a scenario with a fire in one unit
and with the opposite unit maintaining the capability to shut
down
The calculation did not consider the effect of
full ESW pump lift, the effect of pressure
drop across
the strainer,
and
the full component cooling water
design flow to the residual
heat
exchangers.
The licensee
performed supplementary
calculation
HXP900628
to consider these
issues
and concluded that one
pump could supply
ESW flow requirements.
Because of questions
about the boundaries
of different piping classes,
the
team questioned
whether
ESW pump runout could occur if a nonsafety-related
Class
A-31 pipe broke at the point where it interfaces with safety-related
Class A-12 piping.
The licensee
performed
a
new calculation
(HXP900613AF)
assuming
a break
on the return piping at the exit to the turbine building
and concluded that the
pump would not run out.
~I
~ r
o
To determine the
ESW pump room temperature,
calculation
DCCHV12ES02N
assumed
the screen
house
maximum temperature
tu be 104'F based
on
operational
experience.
However, the licensee
could not provide documen-
tation of the operational
experience
and subsequently
performed
a supple-
mentary calculation to justify the assumption.
Calculation
HXP841106 demonstrated
the capability of the
ESW system to
meet flow requirements for one unit at full power while a
LOCA was occur-
ring in the other unit.
However, the calculation did not consider
the
effect of full ESW
pump lift and pressure
drop across
the strainer.
The
licensee
performed supplementary
calculation
HXP900626AF during the
inspection
and the results,
although not verified or approved,
were found
to be acceptable.
2.1.4
Instrumentation
and Control
The SSFI
team reviewed the
ESW system electrical
schematic
diagrams,
instrument
calibration and setpoint records,
automatic controls, indication, alarms,
protective relaying and interlocks,
and power supplies for motors
and control
circuits.
The team identified weaknesses
in setpoint calculation methodology
and in the control of installation and maintenance
of safety-related
com-
ponents.
However, these
weaknesses
did not affect the operabi lity of the
system.
The team's
review of instrument setpoint calculations
involving the
ESW system,
reactor
protection system,
and component cooling water system indicated that
existing setpoint values
were within acceptable
values.
However, the estimated
accuracy
was not provided or
was incompletely modeled in most instances.
Procedures
employed since
1973 for the format, content,
and control of the
calculations
appeared
to be inadequate
to produce
a technically complete
and
comprehensive
instrument setpuint calculation for safety-related
instrument
application because
they contained insufficient guidance for the instrumenta-
tion and control (IhC) engineer.
Consequently,
the team found the following
inadequacies
in the setpoint calculations:
Setpoint accuracy
tolerances
either did not exist or had
no basis stated.
None of the calculations
accounted for the effect of a seismic event
on
the setpoint
and its tolerance.
None of the calculations
considered
the effect of radiation
on setpoint
tolerances,
where appropriate.
Over half of the calculations aid.not contain
a value for anticipated
instrument drift.
Approximately one-half the calculations did not address
the amount of
hysteresis
between
a trip setpoint
and the subsequent
reset value.
None of the calculations
contained stated
assumptions
that would normally
be subject to confirmation from operating plant tests or vendor tests.
Most of the calculations
were deficient in identifying the method used for
verification and on the actual
implementation of the independent
design
verification process.
Approximately half of the calculations did not use the Westinghouse
methodology
and the alternative
method for the calculation
was not ident)-
fied or justified.
No specific setpoint errors in plant systems
were identified'y the team.
The
licensee
stated that the setpoint calculation procedure will-be improved using
the guidance of Regulatory
Guide 1.105, "Instrument Setpoints for, Safety-
Related Systems,"
Revision 2, February
1986.
During the review of applicable drawings
and specifications
the team identified
instances
where nonsafety-related
components
were installed in safety.-related
applications of the
ESW system.
In order to assess
the extent to which
nonsafety-related
components
were installed in safety-related
systems
other
than the
ESW system,
the team expanded its review to the instrumentation
and
control components
of the safety injection system accumulator tanks. =-Subse=
quently, the team identified solenoid valves installed in the air-operated
control valves associated
with the fill, vent,
and drain line of the=accumu-
lators which may not have met the environmental qualification requirements for
their specific application.
The team also noted
one example where the equip-
ment, in this case thermostats,
was purchased
and installed
as safety-related
equipment,
however,
no maintenance
and surveillance testing
had been performed
on the equipment for approximately
15 years.
The team verified that the misuse
of components
in the subject
examples
did not impact the safe operation of the
affected equipment.
However, the team was concerned with the licensee's
ability to control the purchase,
installation,
ana maintenance of components in
safety-related
applications.
The following specific examples of improper
designation of components
were identified by the team.
Pressure
indicators
(1-WPI-707, 1-WPI-705, 2-WPI-708, 2-WPI-706) were replaced
on each of the
ESW pump discharge
in the
ESW pump tunnel during late
1989.
The replacements
were classified
as nonsafety-related
instruments.
The
instrument root valves
between the instruments
and the safety-related
piping were maintained in an open position.
An internal
AEPSC letter dated
August 21, 1989, stated that these
pressure
indicators
had no safety function.
AEPSC subsequently
developed
a calculation
(HXP900613PDC)
showing that follow-
ing a pipe failure at the interface
between the instruments
and the
the leakage into the pipe tunnel would be 120 gpm.
The team determined that
the
120
gpm leakage
would not degrade
the safety function of the
ESW system.
The elementary
diagram for the
pump and discharge strainer controls
and
interlocks indicated that electrically operated
solenoid valves that control
instrument air for control valves in the strainer
backwash circuit were not
identified as safety related.
These solenoid valves were connected directly to
a Class lE safety-related circuit.
Failure of these
a
result of shorted windings would cause
a series of 8 Amp fuses to open, dis-
abling both manual
and automatic
backwash of the strainers.
The team verified
that the failure of the fuses would not affect the operability of the
100 percent capacity,
redundant,
standby
ESW pumps.
Accumulator tank solenoid valves associated
with tank fill, drain,
and ventila-
tion valves
IRV-100, IRV-ill, IRV-112, and GRV-341 were designated
as not
safety related in the facility data
base
(FDB) and were assumed
to reposition
to their normally closed, fail-safe state
on loss of air or electric power.
However,
such solenoid valves located within the containment are subject to a
postulated
cordon-mode failure from either
a seismic event or a small-break or
large-break
LOCA.
Unqualified solenoid valves under these
environmental
conditions could be postulated to fail open,
causing the concurrent
loss of all
safety injection accumulator
tanks for both units.
Although the team consid-
ered this nonmechanistic multiple failure to be of low probability, the
requirements
of 10 CFR 50.49 regarding the qualification of nonsafety-grade
electrical
components
need to be evaluated
by the licensee.
Two thermostatically controlled venti lation fans were provided in each
ESW pump
room to provide cooling of the
pump motors.
The design basis
maximum ambient
temperature for the
pump motor was determined to be 125'F per calculation
DCCHY12ES02N, the normal fans at 90'F rising temperature
and the backup fans
at 95'F.
Each
ESW pump room also
had
a high temperature
alarm set at 105'F
for temperature
switches
VTA-701, VTA-703, VTA-705, and VTA-707, respectively.
Licensee
Problem Report 90-621
(Hay 22, 1990), identified that fan temperature
switches,
which had been
purchased
as safety related,
had not had preventive
maintenance
or periodic calibration performed since they were installed.
The
eight temperature
switches
were calibrated
on June 4, 1990:
one was in a
failed state
and six others
were outside the acceptable
calibration band.
During the inspection,
the licensee
prepared
documentation to establish
a
24-M nth calibration interval for the fan temperature
switches.
During the inspection,
the team noted that a significant number of components
in the
ESW system
(such
as pressure
indicators
and electrical solenoid valves)
were incorrectly designated
as not safety related in the
FDB (9-List).
The
licensee
had earlier identified the incorrect classification of the
ESW venti-
lation temperature
switches
and subsequently
provided several
other examples
where they had detected
and corrected similar FDB errors over the past several
years.
2.2 Operations
The team assessed
the
ESW system operations
to evaluate
the adequacy of proce-
dures,
equipment,
and training available to plant operations
personnel
to
ensure
the operability and reliability of the
ESW system.
2.2.1
Procedures
During its review cf the operating,
abnormal,
emergency
operating
and
response
procedures
that pertained to the
ESW system,
the team
conducted control
room ana field walkdowns of procedure activities.
The team
identified minor procedural
weaknesses,
and the licensee,
in all instances,
a9reed to initiate corrective actions.
Several
procedural
discrepancies
were
corrected before the close of the inspection.
The weaknesses
described
below were found as
a result of the review:
The
ESW system description
and Section 9.8.3.2 of the
FSAR referenced
the
capability to open motor-operated
sluice gates
and provide additional
capability to access
Lake Michigan and to ensure
continued operation of
the
ESW system should the screen
house forebay, which is supplied
by three
intake pipes,
be isolated from the lake.
However, this mode of operation
was not incorporated into existing plant procedures.
Procedure
10HP4024.104,
"Annunciator ¹104 Response:
Essential
Service
and
Component Cooling, Drops
55 and 65," Revision 7, did not identify partial
misalignment of the strainer inlet and outlet gates
as
a cause of the high
differential pressure
alarm.
The following weaknesses
were identified in procedures
associated
with the
plant alternate
shutdown capability.
These
procedures
responded
to the require-
ments of 10 CFR Part 50, Appendix R, Fire protection,
and will be evaluated
as
part of an upcoming regionally based
inspection effort.
Procedure
120HP4023.001.001,
"Emergency
Remote Shutdown," Revision 8,
contained instructions
and responses
for an alternate
method of achieving
safe
shutdown in the event that equipment
could not be controlled from
the control room or hot shutdown
panel
because
of fire or other event.
However, there
was
a discrepancy
between Attachment R-4 (Section R-4-1
and R-4-2, restore
ESW pumps) of this procedure
and Procedure
120HP4021.019.001,
"Operation of the Essential
Service Water System,"
Revision 8, with regard to the discharge
valve position before
pump start.
In addition, the availability of tools and equipment to conduct modifica-
tions to restore
the
ESW pump room exhaust
fans to service
and perform
modifications to enable local control of individual
EDGs were not speci-
fied in the procedure.
The licensee
agreed to review the procedure
and
make the necessary
corrections.
Procedures
120HP4023.032.002
and .003,
"AB Diesel Generator
Local Control," and
"CD Diesel Generator
Local Control," Revision 0, Sheet
2 contained
instructions to establish
local control of individual
EDGs in the event of
a fire in the cable spreading
room.
However, the procedure did not
adequately
relate the procedure entry conditions to the emergency
remote
shutdown procedure.
The licensee
indicated that the emergency
remote
shutdown procedure
should take precedence
in the event of a cable spreaa-
ing room fire and stated that the entry conditions would be corrected.
2.2.2
Control
Room Drawings
Operations
personnel
used the drawing records maintained in the Unit 1 and
Unit 2 control rooms.
The drawing files were maintained
as microfiche cards
rather than hardcopy prints and reader/printers
were available for the opera-
tors'se.
The Shift Supervisor's office contained
the
same type of drawing
files outside th~ control room complex.
Full-size, hardcopy prints were
available only from the document control area.
10
The team noted that the microfiche cards
and the copies obtained from the cards
were difficult to read in some instances.
Improved reader/printers
were
installed in the control rooms for both units during the inspection period.
The inspectors verified that the
new equipment
enhanced
the quality of the
prints.
2.2.3
Haterial Condition of Equipment
The
ESW pump rooms and areas
containing equipment cooled by
ESW were found to
have
good housekeeping,
except for a few isolated instances.
Equipment
material conditions, for the
ESW and adjacent safety-related
systems
were found
to be adequately
maintained.
Equipment labeling was especially
good and the
team considered this a licensee
strength.
Although several
instances
of
missing or inadequate
bolts or screws,
clogged floor drains,
and
loose sensing
line supports
were observed,
the licensee
promptly initiated
corrective action in the form of maintenance
job orders for these
items.
During the tour of the motor-driven and turbine-driven
AFW pump rooms, the team
noted that six
ESW system Cell-tale valves
(ESM-110,
ESW-116,
ESW-140,
ESW-146,
1-ESM-244 and 2-ESW-244)
had locks and metal chains
as opposed to seals
and
plastic chains or cables
as specified
by procedure
120HP4030.STP.035,
"Cori-
trolled Valve Position Logging,."
The licensee
replaced
the metal chains
although its evaluation of the safety significance of using the metal chains
and locks was not adverse to safety.
Valves 2-ESW-140
and 2-ESW-146 in the
pump rooms
and valve 2-ESW-171S,
associated
with the control room air con-
ditioning system were improperly chained
and locked such that the intent of the
locking device could have been defeated
by removing the chain.
The licensee
took prompt corrective action by properly locking the valve operators.
During the tour of the component cooling water
(CCM) heat exchanger
areas for
both units, the team noted several
instances
where bolts used to attach
the
Limitorque valve operators to the butterfly valve yokes for
ESM inlet and
outlet valves to the
CCW heat exchangers
(valves
WMO-731 through -738),
appeared
tu have inadequate
thread
engagement.
In addition, the bolts used for
valves
1 Mtt0-731, 1-MN0-733, and 2-MYi0-734 had
an incorrect head configuration
for use with the valve yoke flange.
The licensee initiated job orders to
correct the deficient conditions.
On the basis of this finding, the licensee
performed
a review of other motor-operated butterfly valves in the
ESW and the
CCW systems
and found additional instances
of inadequate
thread
engagement for
operator-mounting bolts.
Engineering evaluations of the as-found conditions
concluded that safety functions of the valves would not be compromised.
A
definition of adequate
thread
engagement for threaded
fasteners
was not con-
tained in maintenance
procedures
or other plant documentation.
The licensee
stated that
a procedure detailing bolting practices will be prepared
and
provided to maintenance
personnel.
2.3
Haintenance
The team assessed
the adequacy of ESM system maintenance
to ensure
system
operability under accident conditions
by system walkdowns and observations
of
maintenance
in progress.
The team also reviewed maintenance
procedures,
vendor
manuals,
and the preventive maintenance
program and activities as they applied
to the system parts,
and material control, post-maintenance
testing, engi-
neering
and technical
support,
personnel training,
and maintenance
program
documentation.
~ ~
I
2.3.1
Procedures
and Vendor Manuals
The programs for administrative
and technical
procedures
in the maintenance
area
were described
in Plant Manager Instruction (PNI)-2010, "Plant Manager
and
Department
Head Instructions,
Procedures,
and Associated
Indexes,"
Revision 16,
and in various maintenance
department
procedures
and instructions.
The
licensee
had established
both equipment-specific
and generic maintenance
and
repair instructions for the major
ESW system
components.
However, the
NRC
and licensee
reviews of maintenance
had found that these
procedures
required
significant improvement in technical
content
and ergonomics to meet current
inaustry standards.
In 1989, the licensee initiated a major procedure
upgrade
program to rewrite existing maintenance
procedures
to address
human factors,
vendor requirements
and recommendations,
quality attributes,
and deficiency
identification.
The program was recently initiated and the writer's guide,
policy instructions,
and administrative procedures
were still in unapproved
form.
The licensee
had
a 1992 completion target date for the program.
Maintenance
Head Instruction (NHI)-5030, "Preventive Maintenance
Program
and
Environmental gualification Program," Revision 12, was being replaced
by a
long-term reliability-centered maintenance
(RCM) program scheduled for comple-
tion in the next
2 to 5 years.
The team reviewed the maintenance
head procedures
(NHPs) and instrument
head
procedures
(IHPs) which provided both administrative
and work instructions for
the
kSW pumps,
power-operated
valves,
ESW. system instrumentation
and controls, motor control centers,
4-kV circuit breakers,
EDGs, station
~
~
batteries,
and completed job orders
and tests.
While major programmatic
improvements
were being
implemented in all areas of maintenance,
the team found
that the following procedural
weaknesses
existed:
Procedure
12NHP5021.032.026,
"Emer gency Diesel
Engine Inlet and Exhaust
Hydraulic Valve Lifters Inspection
and Testing," Revision 1, provided
instructions for a "leakdown" test of the hydraulic lifters'nternal
check valves with an acceptance
criterion of 12 to 120 seconds.
This
criterion deviated from the requirement of a maximum 35-second
leakdown
time stated in the Worthington Company's Instruction Manual for Type
SWB-VEE Diesel Engine, Hydraulic Valve Lifters section
(page 28).
When advised of this technical
manual discrepancy,
the licensee
produced
a vendor letter dated
March 19,
1984, which authorized the
120-second criterion.
This letter was not included in the controlled
vendor information/manual file, which was contrary to Procedure
12PNP2030
VICS.001, "Control of Vendor Documents,"
Revision 2.
This
procedure established
a vendor information control system
(VICS), and
Section 5.0 of that procedure required that all vendor information,
including bulletins, letters,
vendor manuals or revisions,
be processed
and controlled to ensure their proper availability and use under the
licensee's
document control system.
Procedure
12NHP5021.032.025,
"Emergency Diesel
Engine Timing and Balanc-
ing," Revision 1, provided instructions for adjusting exhaust
temperatures
and for obtaining measurements
and adjustments
in compression
and
combus-
tion pressures.
During testing
on June
13,
1990 of the lAB EDG following
replacement of cylinder 3R valve lifters, the procedure
was not available
12
at the job location and was not used to connect or use the drum-type
cylinder pressure
indicator.
PMI-2010, "Plant Manager
and Department
Head
Instructions,
Procedures,
and Associated
Indexes,"
Revfsion 16, Section
3.1.1, required that procedures
having
a double-asterisk
designation
such
as procedure
12HHP5021.032.025
be present
and used at the job site.
The licensee's failure to follow procedures
did not meet the requirements
of
10 CFR 50, Appendix B, Criterion V.
Criterion
V required that activities
affecting quality be accomplished
fn accordance
with appropriate
proceaures
(see Appendix A, Unresolved
Item 90-201-05).
2.3.2
System/Component
History
The team noted several
adverse
trends involving repetitive maintenance
on
spring-loaded
check valve maintenance,
butterfly valve maintenance,
and
pump.
In each
case the licensee
was responsive
and demonstrated
that remedial
action was either complete or in progress.
The licensee
had not fully imple-
mented
a root-cause
analysis
program;
as
a result, the licensee's
actions
were
largely responsive
to equipment
symptoms rather than cause.
Maintenance history for the
ESW inlet and outlet valves to the
CCW heat
exchangers
for Units
1 and
2 showed that six out of the eight valves
(1/2-WMO-
731 through 738) were 16-inch butterfly valves manufactured
by Henry Pratt
Company.
These
were replacement
valves for the six valves originally installed
and manufactured
by Center line.
The other two valves were Centerline valves,
one of which had been replacea with a new Centerline valve in 1982.
Job Order (JO) 728163
was performed fn June
1989 to replace the Centerline
valve in position 1-WHO-735 with a Pratt valve.
The
JO documentation
showed
that one and possibly all of the pipe flange bolt holes were enlarged
from
1 1/8 to
1 3/16 inches to achieve alignment with the valve bolt holes.
No
indication of engineering
review or evaluation of this modification was evi-
denced in the
JO documentation,
and the licensee
could not find arly documented
follow-up of this change.
The team was concerned that changes
in plant config-
uration of safety-related
equipment could be performed
by maintenance
personnel
without evaluation of the safety significance of the change
by supervision or
engineering.
The team observed that the replacement
of a Centerline
Company butterfly valve
with a valve manufactured
by the Henry Pratt
Company
on the
ESW inlet to the
Unit 1 west
CCW heat exchanger
had been performed
as
a maintenance
JO rather
than
a design
change
JO.
The licensee
had received
a Notice of Violation fn
1988 for replacing parts
and components
with those from another manufacturer
without designating
the work as
a minor modification and performing
a safety
evaluation in accordance
with PMP5040MOD.002,
"Minor Modifications," Revision 2.
JO 728163
was initiated in August 1987 but the physical valve replacement
was
not performed until June
1989.
Thus, the valve replacement
under
a maintenance
JO constituted
an apparent
repeat violation.
The licensee's
continued failure
to properly designate
and evaluate
minor modif'ications in accordance
with the
requirements
of the subject procedure is another
example of lack of prompt cor-
rective action of a deficiency adverse to quality (see Appendix A, Unresolved
Item 90-201-01).
13
IKC calibrations of
ESW instruments
had repeatedly
found instruments
out of
calibration with as-found errors of 4.5 to 11 times the allowable tolerances.
No evaluation of as-found instrument drift conditions
and no adjustment to
calibration frequencies
were made
by the licensee.
Specific examples
included:
The
pressure
switch,
1-WPS-701,
had an as-found error of
4.5 percent (high) versus
1 percent allowable during
a February
1989
calibration.
The pressure
switch was used for starting-of the standby
pump on low header
pressure
and
had
a nominal 48-month calibration fre-
quency.
The instrument
was recalibrated without further evaluation.
Similarly, the setpoint for the
ESW strainer differential pressure
alarm,
1-WDA-701, had
an as-found setpoint
10 percent over the required
maximum
allowable setpofnt.
The calibration tolerance
was
1 percent.
Thl's
instrument provided
an alarm when the strainer
had fouled and backwash--had
failed.
Similar out-of-tolerance
data were found for instruments
1-WPA=701,
2-WPI-708, 2-WFI-712, 2-WFA-706, and 1-WFA-703.
Data for ESW-safety-
related
instruments
indicated that a significant fraction (20 to 25 percent)
had been fourid out of tolerance for two or more of their most- recent
calibrations.
The licensee's
current calibration program as described
by procedure
12IHP6030IMP.044,
"Instrument Data System Preventive
Maintenance
Program,"
Revision 15,
became effective in early 1989.
The procedure
provided for
tracking the acceptability of as-found instrument data
and for adjusting the
frequency of testing if those instruments
had been found unacceptable for
three consecutive calibrations.
8ecause
the program did not incorporate the
pre-1989 calibration data,
no adjustments will be made until at least three
calibration intervals of 4 years
each
(a total of 12 years from 1989-90)
have
elapsed.
Although the licensee
indicated that these considerations
were
included in the planned reliabi lity-centered maintenance
program, there were
no
immediate plans to evaluate
the instrument performance
tracked
by this proce-
dure, which was considered
a weakness
in the licensee's
control of
safety-related
instr'uments.
2.3.3
Spare Parts
and Mater ial Control
The team reviewed the licensee's
methods of controlling material
used in
safety-related
applications,
focusing on the control
and replacement of fuses
in safety-related
circuits, use of all-thread stock as threaded fasteners,
and
storage of weld rod.
The licensee
maintained
segregated
areas for certified
and open stock stores
items within the plant area.
Storage of larger items fn
remote warehouses
was well-controlled with clear designation of safety-related
versus nonsafety-related
items.
However, the supply of fuses maintained
by
operations
were riot traceable
to certification documentation.
The team
revfewea several circuits that use fuses,
including 4-kV and smaller circuit
breakers
and circuits for containment isolation valves.
The diesel generator
test
bank breakers
contained
a mixture of controlled and open stock fuse types
in the control circuitry, while the containment isolation valve circuitry
contained
a large
number of certified fuses,
but of a type that could be replaced
with open stock fuses.
During the inspection,
the licensee
established tighter
controls
on fuse replacements
by operators
to ensure that only certified fuses
would be placed in safety-related circuits.
14
2.3.4
Engineering Support
Plant engineering
support
was centered
in two groups within the plant organiza-
tion within the past year.
The plant engineering
group, under the Technical
Support Manager,
was responsible for all plant engineering activities,
such
as
system engineering,
predictive maintenance/performance
testing, reactor engi-
neering,
and engineering
support functions.
The project engineering
group,
under the Projects
Manager,
was responsible for coordinating all outage activi-
ties
and design
change activities,
such
as requests for change,
minor modifica-
tions,
and plant modifications.
The system engineering
positions were about
50 percent staffed at the time of the inspection
by existing plant personnel
that had been assigned
to specific systems
in early 1990.
The goals
and res-
ponsibilities set forth for the system engineers
were oriented to safe, effic-
ient,
and reliable functionality of the assigned
systems
as opposed to design-
related functions.
As such, the system engineering
program appeared
to be
consistent with programs established
by other utilities.
In practice,
the
system engineers
appeared
to rely heavily on the input of the corporate engi-
neering organization for design-related
questions.
The team also noted that
the system engineering
group was not yet functioning at the desired maturity
level and was not performing all the intended functions efficiently.
The
AEPSC Nuclear Design Group had
a representative
organization
on site, the
site design organization.
This organization
served
as liaison between the
plant site and the corporate
design
group with regard to design questions
and
concerns
and design
change activities involving the
AEPSC organizations.
The
site design organization also coordinated the updating
and revision of opera-
tions series
drawings to ensure that these
drawings were properly revised
before design
changes
were turned over to operations
personnel.
This organiza-
tion has
been available
on site for several years
and appeared
to be function-
ing well.
2.3.5
Drawing Updates
The team noted that while the control room drawings were maintained
up to
date,
the engineering
organization
had
a backlog of approximately
2000 drawings
that required updating to incorporate
design
changes that had been
implemented
in the field.
Most of these
drawings were associated
with balance-of-plant
systems rather than safety-related
systems
and equipment.
The licensee
stated
that the backlog of pre-1990 drawing changes
(some extending
as far back as
1984) would be eliminated
by January
1991
and
a 60-day turnaround
on all
drawing revisions would be achieved
by January
1992.
Priority will be given to
safety-related
drawings affected by design
changes
to ensure
updated
design
information was employed
by design engineers.
Maintenance craft and other plant personnel
assumed
that the latest controlled
drawing revision reflected as-built plant conditions when, in fact, the drawing
could be affected
by one or more implemented
design
changes
that had not yet
been incorporated into the arawing.
Out of the
36 drawings reviewed in the
satellite maintenance
library, 6 were not the latest revisions.
The licensee's failure to maintain the latest revision of drawings in the
maintenance
drawing library was contrary to the requirements
of procedure
PMI-2030, "Document Control," Revision
11 and to 10 CFR Part 50, Appendix B,
15
~I
e
0
Criterion VI, which requires
measures
to be established
to control changes
to drawings that prescribe activities affecting quality.
(see Appendix A,
Unresc 1ved Item 90-201-06).
2.3.6
Root-Cause
Analysis
AEPSC general
procedure
(GP) 15.1, "Corrective Action," Revision 5, and
PHI-7030, "Condition Reports
and Plant Reporting," Revision 14, provided the
vehicles for identifying deficiencies
and processing
them with or without
root-cause
investigation.
Both procedures
required
the. use of investigations
but neither procedure
provided root-cause
investigation methodologies.
Little
evidence of formal application of disciplined root-cause
investigations
was
observed in the problem reports
and other deficiency documentation (e.g.,
JOs,
audits,
and surveillances)
reviewed
by the team.
The procedures
required that a
condition report be prepared
when
a potential
problem or condition adverse to
quality.
Several
cases
were identified in which apparent
problems meeting the
criteria of the procedures
did riot result in the preparation
of a condition
report or performance of a root-cause
investigation.
Procedure
20HP4030.STP.038,
"Leak Rate Test of Liquid Systems,"
Revision 4,
identified unacceptable
leakage in the containment
spray
system during
performance of the test in April 1988.
Job orders were apparently
com-
pleted for the repairs but the post-repair testing
was not documented
on
the sheets
as required,
and the testing for valve 2-IHO-212 (JO 37595)
was
not completed correctly.
The procedure
was repeated
in February
1989 as
a
result of the extended
Unit 2 outage
and coincidentally retested
the
subject areas
although specific inspections of repairs
were not separately
documented.
The procedure
was signed off as acceptable
by the plant staff
without recognition of the omissions.
Following the team's review,
a
condition report was issued
on June 20, 1990.
Job Orders
B020648 and
B013903 involved check valve removal from the
20-inch, Schedule
40,
ESM pump discharge
piping for the Unit 2 west
pump.
Both JOs were annotated
by the mechanics
indicating that abnormal
"pipe
strain" (piping deformation)
caused
substantial difficulty in valve
reinstallation.
Although the JOs were signed off as complete in
December
1987 and April 1990, the pipe strain condition apparently
had not
been identified for engineer ing evaluation.
Six cf the butterfly-type Pratt valves
had been replaced
since
1982 with
new or reworked valves
as
a result of rubber seal or other undocumented
failures.
The licensee
had not conducted
a root-cause
analysis to deter-
mine the cause of the failures, nor had it evaluated
the potential for
affecting the safety function of the valves during accident conditions.
Further examples of lack of initiation of condition reports are discussed
in
Section 2.5.1 of this report.
The team verified that site staff training in
root-cause
analysis
techniques
had been initiated by the licensee.
2.4
Quality Assurance
The team reviewed the licensee's
Quality Assurance
(QA) audits
arid surveillances
of plant activities for identifying problems
and problem areas.
Audits by
design were broad in scope
and addressed
overall control and methods of per-
forming activities rather that addressing
specific systems.
Surveillances,
16
however,
were narrow in scope
and covered specific activities.
In all cases,
application of the activities and controls to the
ESW system
was evident.
gA
surveillances
were conducted to supplement audits
and were limited to specific
activities such as repair of specific components
or systems.
2.4.1
Onsite Review Committee
The Plant Nuclear
Safety
Revie~ Committee
(PNSRC)
performed the onsite review
function.
The technical specification requirements
were appro~riately
addressed
in procedure
PMI-1040, "Plant Nuclear Safety
Review Committee, 'evision 9.
The
procedure
appeared
to be adequate.
PNSRC meetings
were required to be held
monthly but were usually held weekly with special
meetings
held as needed.
During the review,
nc issues
were discussea
involving the
ESW system.
2.5
Surveillance
and Inservice Testing
The team reviewed the surveillance
and inservice test program for the
system io verify that the surveillance
procedures
would confirm the required
ESW system function.
The team conducted
a technical
review of the survei llance
procedures
for the
ESW system
and electrical support
systems
and observed
the
performance of three
ESW surveillance
procedures
as well as two surveillances
associated
with the reactor protection system
and steam generator
instrumenta-
tion.
In addition, the team reviewed the results of surveillance tests per-
formed recently
on the
ESW system
and assessed
the implementation of inservice
testing
program requirements.
The team concluded that surveillance test procedures,
with the exception of the
18-month surveillance test procedure for battery
emergency
load arid the
inservice testing
program requirements for the diesel generator
and the
ESW pump discharge
were adequate
to ver ify that
safety-related
equipment
and systems
could accomplish their intended functions.
2.5.1
Surveillance Test Procedures
The team evaluated
the licensee's
biennial procedure
review program as it
applied to the
ESW surveillance
procedures.
The team had concerns
regarding
the timeliness
and effectiveness
of the licensee's
biennial reviews.
The
review of procedure
1THP4030.STP.068,
"Essential
Service Water Liquid Process
Monitor (R-20) Surveillance Test," was overdue
because it should
have been
performed in January
1990.
The latest biennial review for procedure
2THP4030.STP.175,
"Essential
Service Water Liquid Process
Monitor (R-28) Test,"
was late when performed in July 1989.
The failure to perform timely biennial
reviews was inconsistent with PMI-2010, "Plant Manager
and Department
Head
Instructions,
Procedures
and Associated
Indexes."
Further,
paragraph
3.14.1.A
of this procedure required that those
procedures
whose biennial review cycle was
exceeded
should be marked to ensure
they were not used before
an appropriate
review was accomplished.
Procedure
1THP4030.STP.068,
performed June 21, 1990,
was not so marked.
Additionally, some of the biennial reviews conducted
had been ineffective.
For
example,
the last biennial review of procedure
1THP6030.IMP.012,
"Radiation
Monitoring System Calibration:
Air/Liquid/Gas," was performed in January
1990.
On June 21, 1990, the team observed that four change notices
were required
to be issued in order to accomplish the tasks detailed in procedure
ll'HP6030.IMP.012.
None of the problems that required
change
sheets
during its
17
I 4 ~
I J
P
implementation were identified during the biennial review of the procedure.
The form used to document the reviews was found to be ambiguous
and unclear in
its questions
and required responses,
contributing further to the ineffective-
ness
of the biennial review.
The team identified the following additional
examples
where licensee
personnel
failed to adhere to procedural
requirements.
During completion of procedure
1THP6030. IMP.012, the technicians
did not perform independent verification as
required.
The technicians'ailure
to observe
independent verification
requirements
and the need for generating
change
sheets
to accomplish
a sur-
veillance required the issuance of condition reports in accordance
with
PM1-7030, "Condition Reports
and Plant Reporting."
In both instances,
condi-
tion reports were not initiated by the staff until the team identified the
deficiency.
The lack of condition reports prohibited management
from being
informed of problems
and prevented effective and timely assessment.
The team noted through direct observation
and review of completed procedures,
that the technicians
did not utilize the tolerance
allowed by procedure
1THP4030.STP.068.
This procedure
required setting
and reading the meter for
the liquid process
monitot
between
a target value and -.25 decade
less than
this target value.
However, the technicians routinely attempted to set the
meter at the target value.
The team observed that this was not always possible
and that the meter
may actually be set at more than the target value.
The review of completed surveillances identified numerous
instances
where
recorded
data fell outside the acceptable
range identified in the procedure.
For example, for the four liquid process radiation monitor surveillance
proce-
dures
(27 completed surveillances
reviewed), the counts-per-minute
range
was
exceeded five times,
and counts-per-minute
values
were not recorded for an
additional four times.
In addition, Step 7.10 (the calibration of the low
level alarm) of procedure
1THP4030.STP.068
was exceeded
by a full decade
on
March 30, 1990.
Procedure
10HP4030.STP.022E,
"East Essential
Service Mater
System Test," conducted
on December
18, 1989, did not show an acceptable
flow
through valve 1-ESW-113.
In each of the instances
noted above, neither the personnel
conducting the
surveillance
nor the supervisor reviewing the results
noted the procedural
deviations.
The large number of instances
associated
with the radiation
monitor surveil'lances
indicated
a lack of understanding
of procedural require-
ments
and an inability of IEC technicians to properly implement these
procedures.
In addition, the lack of acceptance
criteria in the
IKC surveillance
procedures
for the liquid process
radiation monitors contributed to uncertainty
as to when
the surveillance test failed.
Numerous other discrepancies
in completed surveillances
were identified by the
team including missing dates
and serial
numbers,
incomplete review sheets,
and
sloppy data taking.
In total, these
inadequacies
with the data of completed
surveillance
procedures
inaicates
a lack of attention to detail
and
a recurrent
lack of adherence
to procedures.
The examples of lack of procedural
adherence
discussed
above did not meet the
requirements
of 10 CFR Part 50, Appendix B, Criter ion V, which requires that activi-
ties affecting quality be accomplished
according to procedures
(see Appendix A,
Unresolved
Item 90-201-07).
18
2.5.2
Station Battery Testing
Battery sizing documents
prepared
by the utility engineers
during 1984
and
1985, in preparation for the purchase of replacement batteries,
showed that the
battery
load profile developed
by the engineers
exceeded
the identified load
profile of the technical specification
by 35 to 65 percent.
Following the
installation of the
new batteries
in 1986, the licensee failed to incorporate
the new battery capacity
and test profile into existing test procedures
(2NHP4030.STP.034,
2MHP4030.STP.022,
and IHHP4030.STP.044),
and the 18-month
surveillance
procedures for 2AB, 2CD, and IAB battery
emergency
load discharge
and battery charger tests.
Therefore,
the technicians
continued to test the
new station batteries to a load profile that was
up to 65 percent
below the
calculated
emergency
loads.
The licensee,
by not incorporating the 1984
battery
load profile into the applicable battery capacity test, did not meet
the requirements
of 10 CFR Part 50, Appendix B, Criterion XI.
This criterion
required
a test program to demonstrate
that components will perform satisfacto-
rily in service in accordance
with written test procedures
that incorporate the
requirements
and acceptance
limits contained in applicable design
documents
(see Appendix A, Unresolved
Item 90-201-08).
To date only one out of the four station batteries
(LCD) had been tested against
the
new battery load profile.
That test
was successfully
completed in Hay 1989.
The team questioned
the operability of the remaining three station batteries.
The licensee
provided the team with a justification for continued operation for
the improperly tested batteries.
It considered
the aging, testing history,
and
overall capacity of the batteries.
Further, the licensee
expected to test both
Unit 2 batteries
during
a refueling outage that began during the inspection.
The Unit 1 batteries
were to be tested
during the planned October
1990 outage.
The team reviewed additional calculations of the battery duty cycle preparea
for the 1990 station blackout
(SBO) engineering
studies.
These calculations of
a 4-hour
SBO duty cycle were not intended to replace the 1984-85 8-hour duty
cycles for technical specification surveillance
purposes,
but the newer calcu-
lations appeared
to identify battery
loads previously not considered.
These
loads could increase initial battery discharge
rates (e.g.,
EDG field flash
current, initial switchgear
control power demand during engineered
safeguards
sequencing,
and related loads).
The team considered
the newly identified loads
to be potentially significant with regard to near end-of-life battery
conditions.
The licensee
stated that such
loads will be considered for
inclusion into the battery capacity test procedures.
The team evaluated
the effects of battery end-of-life operating
temperatures
on
the battery sizing calculations for the station batteries installed in 1986.
Review of battery
room temperature
monitoring data indicated that the battery
'oom
temperatures
were monitored weekly by an informal program established
by
the system engineer.
The
1AB and
2AB battery
rooms
had intermittently been
below the end-of-life design limits by as
much as
12 to 15 degrees
Fahrenheit.
On the basis of information contained in the battery vendor
manuals,
the
battery capacity degradation
as
a result of temperature
variations
appeared
minor except for end-of-life conditions.
The licensee
stated that
a program to
monitor and control battery
room temperatures
within acceptable
ranges
would
be established.
19
2.5.3
Inservice Testing (IST)
The appropriate
ESW valves were included in the
IST program,
and program
requirements
were properly reflected in procedures
with the exception of diesel
generator
ESM-111 to -114 (Unit 1) and
ESW-141 to -144 (Unit 2)
and
ESM pump discharge
ESW-101E
and -101M (Unit 1) and
ESM-102E
and
-102W (Unit 2).
The licensee
planed to test the forward-flow capability of
each valve but not the checking capability.
These valves perform a safety function in the checked position for certain
scenarios.
The four check valves
on each aiesel
generator
cooling supply are
each in series with a motor-operated
valve.
The four motor-operated
valves
open simultaneously
on a diesel generator start signal
and, in so -doi~n
,
interconnect
the two
Therefore,-should
an-ESW
pump fail or a line break occur upstream of the diesel generator
branch stop
valves,
ESM-111 to -114 and
ESW-141 to -144 would be called. upon.
to perform a checking function.
Likewise, check valves
ESM-101E,
-101W, -102E,
and
-102W would perform a
checking function should
an
pump become idle. If a
pump becomes--idle,
the
standby
pump on the
same
header will start.
8ecause
the motor-operated
valve
on the discharge of the idle pump (in series with the check valve)'nd the four
crosstie
valves would be open, the check valve woula be required to
close
so that the operating
pump on that header
does not feed the idle pump
rather
than the system
loads.
This scenario,
in effect,
leads to two lost
pumps.
Closure of the motor-operated
discharge
valves to terminate the
backflow would require operator action.
Section XI of the
ASME Code requires that check valves of this type, which per-
form a safety function in the closed position,
be tested in .a,,manner
which proves
that the disk travels to the seat promptly on cessation
or reversal of flow.
This requirement for Category
C check valves (valves that are self-actuated
in
response
to a system requirement)
had been reiterated in Generic Letter 89-04,
"Guidance
on Developing Acceptable Inservice Testing Programs."
The licensee's
IST program,
as currently written, did not provide for testing this function
for the
12 valves noted above.
(See Appendix A, Unresolved
Item 90-201-09).
3.0
CONCLUSION
The team concluded that based
on design
conservatisms
such
as redundancy
and
pipe sizing, the
ESW system
was capable of performing its required safety
functions.
However, the team identified weaknesses
in the licensee's
program
to maintain operational
readiness
of the'SW and other safety-related
systems,
although the identified weaknesses
did not compromise the safe operation of the
systems.
The licensee's
ineffectiveness
in recognizing deficiencies
and
initiating prompt corrective actions
was particularly evident in the areas of
independent
design verification, engineering
evaluation of the
ESM system
relief valve settings,
and the development of appropriate battery capacity
tests.
The lack of an effective independent
design verification program was
involved in the engineering
department's
failure to implement the necessary
engineering practices.
This was evident in all of the calculations
reviewed
by
the team.
However, the team noted that the licensee's
engineers
were pro-
fessionally qualified and experienced
in their respective fields of engineering.
20
The team was also concerned with the number of procedural
inadequacies
identi-
c
~
fied in the areas of maintenance
and surveillance.
While the deficiencies
were
generally minor, in total they were indicative of poor procedures
and lack of
procedural
adherence.
The team verified that corrective actions to improve
procedure quality had been recently initiated.
However,
improvements in
procedural
usage
and adherence
were not evident to the team.
4'
UNRESOLVED ITEMS
Unresolved
items are matters
which require
more information to determine whether
they are acceptable,
deviations
or violations.
Unresolved
items identified are
listed in Appendix A of this report.
5.0
EXIT MEETING
The team conducted
an exit nieeting
on July 13,
1990 at the D. C. Cook Nuclear
Power Plant.
NRC management
from NRR and Region III arid licensee
representa-
tives
who attended this meeting are identified in Appendix B.
During the exit
meeting,
the
NRC inspectors
summarized
the scope
and findings of the inspection.
21
~
~
~ ~. I
APPENDIX A
Summar
of Ins ection Findin s
UNRESOLVED ITEN 90-201-01
FINDING TITLE:
Inadequate
Corrective Action
DESCRIPTION
OF CONDITION:
The team identified the following instances
in which the licensee failed to
recognize the significance of events
and to initiate prompt corrective actions:
1.
The lack of independent
design verification was identified by the licensee
in 1987
and by the
NRC in 1989.
At the time of this inspection,
an
effective design verification program had not been
implemented
by the
licensee
(see also Unresolved
Item 90-200-02).
2.
In 1984, the licensee recalculated
the station battery load profiles and
found that the
new load profile exceeded
the existing battery test profile
by up to 65 percent.
No attempt
was
made by the licensee to test the
station batteries
to the
new profile until 1989
(see also Unresolved
Item 90-201-09).
The licensee's failure to conduct
component
replacement
in accordance
with
procedure
PI1P5040.NOD.002,
"Minor Modifications," was identified by the
NRC in 1988.
In June
1989,
a Centerline
Company valve in the component
cooling water heat exchanger inlet line was replaced with a valve manufac-
tured by the Henry Pratt
Company without implementing the requirements
of
the subject procedure.
RE( UIREt~ENT:
10 CFR Part 50, Appendix B, Criterion XVI requires that measures
be established
to assure that conditions adverse to quality are promptly identified and cor-
rected in a manner that would preclude repetition.
REFERENCES:
1.
NRC inspection reports,
50-315/88-28
and 50-316/88-32
dated
Hay 1, 1989.
2.
Job Order 728163,
datea
August 18, 1987.
I ~ ~
I
~I
~
UNRESOLVED ITEM 90-201-02
FINDING TITLE:
Independent
Design Verification
DESCRIPTION
OF CONDITION:
The team noted that design of nuclear
power plant structures
and systems
was
not verified by an independent verification process. as delineated
in 10 CFR Part 50, Appendix
B and the ANSI N45.2.11 standard.
Documentation for indepen-
dent design verification for pre-1988 calculations, test reports,
and drawings
was missing.
This weakness
had been identified by Region III during an inspec-
tion in 1989 and had also been identified in 1987 by an independent
contractor
to the licensee
during an in-house
SSFI inspection of the auxiliary feedwater
system.
In response
to the Region III findings, the licensee
had initiated a
program for independent
design verification in 1989.
The team reviewed proce-
dures
and forms relating to this program and noted that, although the program
incorporated
requirements
of 10 CFR Part 50, Appendix
B and ANSI N45.2.11, the
lice~see
engineers
were not effectively implementing the program.
Calculations
which were performed after the
new program was implemented either received
no
independent
design verification or an adequate
one.
The team concluded that
the licensee's staff implementing the verification program lacked experience
and
was not adequately
trained.
REQUIREMENT:
10 CFR Part 50, Appendix B, Criterion III requires that the design control
measures
shall
be provided for verifying or checking the adequacy of the design
including an "independent
design verification" of each of the design
documents
for systems
important to safety.
REFERENCES:
1.
"Quality Assurance
Requirements for the Design of
Nuclear Power Plants."
2.
NRC inspection reports,
50-315/88-28
and 50-316/88-32
dated
May 1, 1989.
A-2
UNRESOLVED ITEN 90-201-03
FINDING TITLE:
Inadequate
Terminal Voltage at Class
lE Inverter Terminals
DESCRIPTION
OF CONDITION:
The team reviewed specifications for Class
1E 250 volts dc to 120 volts ac
instrument
power inverters
and noted that the inverters
were qualified to
operate at a minimum of 210 volts dc at their input terminals.
Because
the
end-of-life (EOL) voltage at the station battery terminals
was calculated to be
210 volts, inverter terminal voltage during battery
EOL would always
be less
than 210 volts due to feeder voltage drop.
Therefore,
the inverter would not
be operational.
This condition could result in an inadequate
power supply to
plant instrumentation
during a loss of ac power supply.
During the inspection
the licensee initiated actions to requalify these inverters for a minimum input
voltage of 200 volts dc.
REQUIREMENT:
10 CFR Part 50, Appendix A, General
Design Criterion 17, requires that the
electric distribution system
be available during accident mitigation.
REFERENCES'.
Licensee's
voltage drop calculations,
dated July 1990.
2.
Inverter Specification sheets.
A-3
~ ~a
~
s
~
g
~
~
tl
~ ~ ~
~ ~
UNRESOLVED ITEM 90-201-04
FINDING TITLE:
Inadequate
Terminal Voltage at Steam-Driven
Inlet Valve
DESCRIPTION OF CONDITION:
The voltage drop calculation for the dc power feed cable to the steam-driven
AFW pump feedwater inlet valve motor indicated that the worst-case
terminal
voltage at the motor was
178 Vdc.
This condition could occur during a loss of
ac power, with the station batteries at their end-of-life condition.
The team
could riot determine if the 178 Vdc was sufficient for the valve to perform its
required design function which is to control
AFW flow.
The team verified that
vendor specification
sheets of the valve only provided
a single value of
terminal voltage equal to 250 Vdc.
Under these conditions the operability of
the subject valve could not be verified.
RE(UIREMENT:
Technical Specification 3.7.12 requires that the turbine-driven auxiliary
pump be operable while the plant is in Modes 1, 2, and 3.
REFERENCES:
.
Attachments
1 and
2
"DC Motor Cable Sizing" to AEP's response
to
SER 25-88, dated
November 29, 1988.
"guality Assurance
Requirements for the Design of
Nuclear Power Plants."
< qc
J
~
~
e
~ '
0
~
~
UNRESOLVED ITEM 90-201-05
FINDING TITLE:
Failure to Follow Procedures
in Maintenance Activities
DESCRIPTION
OF CONDITION:
12MHP5021.03?..025,
"Emergency Diesel Engine Timing and Balancing,"-Revision
1,
provided instructions for adjusting exhaust
temperatures
and-.for obtaining
measurements
and adjustments
in compression
and combustion pressures.
During
testing
on June
13,
1990 of the lAB EDG following replacement of cylinder
3R
valve lifters, the procedure
was not available at the job location and was not
used to connect
and use the drum type cylinder pressure
indicator or to docu-
ment the readings obtained.
Procedure
12PMP2030.VICS.001,
"Control of Vendor Documents,"
Revision-2
established
a vendor information control system
(VICS).
Section 5.0 -of=that
procedure
required that all vendor information including bulletins, letters,
vendor manuals or revisions
be processed
and controlled to ensure their proper
availability, and use under the licensee's
document control system.--The
licensee failed to identify and include
a March 19,
1984 vendor lettei'regard-
ing the diesel
bleeddown test acceptance
criteria in the vendor file for the
RE)UIREMENTS:
10 CFR Part 50, Appendix B, Criterion V, requires that activities affecting
quality be accomplishea
in accordance
with approved
procedures.
A
Procedure
PMI-2010, "Plant Manager
and Department
Head Instructions,
Proce-
dures,
and Associated
Indexes,"
Revision 16, Section 3.1.1 requires that
procedures
having
a double-asterisk
(**) designation
be present
and used at the
job site.
Procedure
12PMP2030.VICS.001,
"Control of Vendor Documents,"
Revision 2,
requires that all vendor information fs incorporated into applicable
procedures.
REFERENCES:
2.
3.
Procedure
12MHP5021.032.025,
"Emergency Diesel
Engine Timing and Balanc-
ing," Revision 1.
Procedure
12MHP5021.032.026,
"Emergency Diesel
Engine Inlet and Exhaust
Hydraulic Valve Lifters Inspection
and Testing," Revision 1.
VICS File Nos.
385 and 388, "Instruction Manua1 for Type SWB-YEE Diesel
Engine."
A-5
~
e
~ ~ i
1>
UNRESOLVED ITEN 90-201-06
FINDING TITLE:
Inadequate
Dra~ing Control
DESCRIPTION
OF CONDITION:
Six out of 36 controlled aperture
cards
checked
by the inspection
team and
located in the Maintenance Library were out of date.
In addition,
2 out
of the
36 aperture
cards
checked
had both the correct and out-of-date
revisions in the controlled set.
The drawing numbers which were out-of-date
were:
PS2-94208-4;
PS2-94208-15;
PS1-94208-14;
PS2-94209-9.
PSl-94209-8
and
IKH2-94208-13.
The drawing numbers
which had both the current
and out-of-date
drawings in the controlled file were:
PS2-94206-2,
-4; 1094202-14,
-17.
I'ver
2,000 plant drawings
had not been
updated to incorporate all design
changes,
some of which had been
implemented in 1984.
While many of these
drawings were associated
with nonsafety-related
systems,
some were associated
with safety-related
systems.
The maintenance
organization did not review
drawings obtained
from the controlled drawing file to determine if there were
outstanding modifications that would impact the configuration of the affected
component.
REQUIREMENTS:
PHI-2030,
"Document Control," Revision ll, paragraph
3.5.1 states that "Con-
trolled documents shall
be filea in a timely manner consistent with the
document
used in controlling activity important to nuclear safety.
Superseded
documents
are to be destroyea."
10 CFR Part 50, Appendix B, Criterion VI, states
"Measures shall
be established
to control the issuance
of documents,
such
as instructions,
procedures,
and
drawings, including changes thereto,
which prescribe all activities affecting
quality."
REFERENCE'.
PNI-2030,
"Document Control," Revision 11.
A-6
'E pl
'
UNRESOLVED ITEM 90-201-07
FINDING TITLE:
Failure to Follow Procedures
in Surveillance Activities
DESCRIPTION
OF CONDITION:
l.
Independent verification of a step
was not performed
as required during
implementation of procedure
1THP6030.IMP.012,
"Radiation Monitoring System
Calibration: Air/Liquid/Gas," on June 21, 1990.
2.
Following licensee
recognition of the missed
independent verification,
a
condition report as required
by procedure
PMI-7030, "Condition Reports
and
Plant Reporting,"
was not initiated.
3.
Four change
sheets
were required in order to conduct procedure
1THP6030.IMP.012
on June 21, 1990.
Per PMI-7030,
a condition report would
be required for a procedure
which had been
conducted previously without
the change
sheet.
However,
a condition report was not initiated.
4.
PMI-2010, "Plant Manager
and Department
Head Instructions,
Procedures
and
Associated
Indexes," requires that procedures
performed more frequently
than every two years receive biennial reviews.
Contrary to this proced-
ural requirement,
procedure
1THP6030.STP.068,
"Essential
Liquid Process
Monitor (R-20) Surveillance Test," was
due to have
a
biennial review in January
1990,
and the latest biennial review for
2THP4030.STP.175,
"Essential
Service Water Liquid Process
Monitor (R-28)
Test," was late when performed in July 1989.
5.
PMI-2010 requires that those
procedures
whose biennial review cycle is
exceeded
are required to be marked to ensure that they are not used prior
to an appropriate
review.
Contrary to this procedural
requirement,
procedure
1THP6030.STP.068
was not marked to indicate that the review
cycle had been
exceeded
and was not reviewed prior to its being performed
on June 21,
1990.
6.
Recorded
Data Outside of Values in Procedures
Procedure
10HP4030.STP.022E,
"East Essential
Service Water System
Test," conducted
on December
18,
1989 did not show an acceptable
flow
through valve 1-ESW-113.
Procedure
1THP4030.STP.068,
"Essential
Service Water Liquid Process
Monitor (R-20) Surveillance Test," conducted
March 30,
1990
showed
the calibration of the low level alarm exceeding
the required value.
Of 27 completed survei llances
reviewed of the 4 liquid process
radiation monitor surveillance
procedures,
the
cpm range identified
by Step 7.12.3.2
was exceeded
5 times (see Section 2.4.1).
A-7
RE(UIREHENTS:
10 CFR Part 50, Appendix B, Criterion V, requires that activities affecting
quality be accomplished
in accordance
with appropriate
procedures.
PHI-2010, "Plant Hanger
and Department
Head Inst'ctions,
Procedures,
and
Associated
Indexes," requires biennial reviews of certain procedures
and
marking of those
procedures
when the review cycle is exceeded.
PM1-7030, "Condition Reports
and Plant Reporting," requires preparation of a
condition report upon identification of certain conditions adverse to quality.
REFERENCES:
2.
3.
4,
5 ~
6.
Procedure
1THP6030. IMP.012, "Radiation Monitoring System Calibration:
Air/Liquid/Gas," conducted
June 21, 1990.
Procedure
1THP6030.STP.068,
"Essential
Service
Water Liquid Process
Hr,nitor (R-20) Surveillance Test."
Procedure
10HP4030.STP.022E,
"East Essential
Water System Test."
Procedure
1THP4030.STP.075,
"Essential
Service Water Liquid Process
Monitor (R-28) Surveillance Test."
Procedure
2THP4030.STP.168,
"Essential
Service
Water Liquid Process
Monitor (2R-20) Surveillance Test."
Procedure
2THP4030.STP.175,
Essential
Service Water Liquid Process
t'lonitor (R-28) Test."
A-8
UNRESOLVED ITEM 90<<201-08
FINDING TITLE:
Inadequate
Battery Surveillance Testing
REQUIREMENTS:
Surveillance test procedures
2MHP4030.STP.034,
2MHP4030.STP.022,
and
1MHP4030.STP.044,
which were performed for the 2AB, 2CD, and lAB plant batter-
ies in October
1988 and February
1989, failed to adequately verify battery
capacity to maintain emergency
loads operable in that the test procedures
did
not contain quantitative criteria necessary
to assure that the required
capacity
was present.
Inadequate
battery testing
methods
and criteria were identified during
1984-1985 but action to correct the deficiencies
and adequately test the
batteries
remained
incomplete
as of July 13, 1990, in that:
l.
Only the
1CD plant battery of four plant batteries
had been tested
using
corrected test methods,
and
2.
Additional loads identified in 1989-90 engineering
calculations
haa not
been incorporated into the testing requirements
and acceptance
limits for
any of the batteries.
REQUIREMENTS:~
~
~
~
Technical Specification 4.8.3.2.d requires,
in part, that the batteries
be
tested
once per 18 months
by "verifying that the battery capacity is
adequate
to supply
and maintain in OPERABLE status
the emergency
loads for the
times specified in Table 4.8-1A with the battery charger disconnected."
10 CFR Part 50, Appendix B, Criterion XI, requires that "a test program shall
be established
to demonstrate
that structures,
systems,
and components will
perform satisfactorily in service ... in accordance
with written test proce-
dures which incorporate the requirements
and acceptance
limits contained in
applicable design documents."
10 CFR Part 50, Appendix B, Criterion XVI, requires that measures
be estab-
lished to assure that conditions adverse to quality are promptly identified ana
corrected.
REFERENCES:
2.
3.
Procedure
2MHP4030.STP.034,
Plant
2AB Battery Emergency
Procedure
2MHP4030.STP.022,
Plant
2CD Battery Emergency
Procedure
1MHP4030.STP.044,
Train Battery."
"18-Month Surveillance Test Procedure for
Load Discharge Test
and Battery Charger Test."
"18-Month Surveillance Test Procedure for
Load Discharge Test and Battery Charger Test."
"Quarterly Surveillance Test Procedure for In
A-9
~,Wa .
~
~
4'NRESOLVED ITEN 90-201-09
FINDING TITLE:
Lack of Inclusion of Certain
ESW Check Valves Into IST Program
DESCRIPTION
OF CONDITION:
Check valves in the
ESW system
(ESW-111 to -114, -141 to -144, -101E,
-101W,
-102E,
and -102W) are required to perform a reverse flow closure function for
certain scenarios
where backflow may occur through the cross-connect
valves
between unit headers.
However, testing of this function was not included in
the licensee's
IST program.
REQUIREMENTS:
requires
compliance with Secti'on XI of the
ASME Boiler and
Pressure
Vessel
Code.
Technical Specification 4.0.5 requires
compliance with 10 CFR 50.55a(g).
REFERENCES:
2.
D. C. Cook Inservice Testing
Program for Valves - Unit 1, Revision 3,
February 5, 1990.
D. C. Cook Inservice Testing
Program for Valves - Unit 2, Revision 3,
February 5, 1990.
A-10
k
4
APPENDIX
B
Personnel
In Attendance at Exit Heetin
American Electric Power Service
Cor oration
Name
~ar
Ackerman
Hilton Alexich
Tom Argenta
Steve
Brewer
Jim Kobyra
Bryan P.
Lauzau
Patrick H. YicCarty
Paul
G. Schoepf
Rod Simms
Chuck Swenson
Indiana Hichi an
Power
Com an
Or anization
uc eai
a ety and Licensing Engineer
Vice President-Nuclear
Operations
Nuclear Engineer
Nuclear Safety
and Licensing Hanager
Group Hanager Nuclear Design
Nuclear Safety
and Licensing
Site guality Assurance
Nuclear Engineering
Department
NOS
Nuclear
Engineering
Department
Name
~ban Blind
John Allard
Ken Baker
Terry Beilman
Doug Burris
Steve
DeLong
Jim Droste
I. D. Fleetwood
Robert
M. Hennen
Ken Johnson
John
Kauffman
Yern Kincheloe
Hark Lester
Lewis Hatthias
Hark Hitch
William A. Nichols
Terry Postlewait
Roy Russell
Jack Rutgowski
John
Sampson
Tom Shane
Hark Stark
Russ Stephens
Lec VanGinhoven
Denny Willemin
Jim Wojcik
Or anization
ant
1anager
Computer Science Supt.
Assistant Plant Hanager-Production
Haintenance
Superintendent
Operations
Department
Project Engineer Supervisor
Plant Engineering Supt.
Operations
Department
Plant Engineering/Sys.
Eng. Supervisor
Haintenance
Super visor
Construction
Hanager
Training Superintenaent
ESW System Engineer
Administration Superintendent
Plant Engineering
Operations Training Superintendent
Project Engineer Superintendent
Project Engineering
Assistant Plant Hanager - Technical
Operations
Superintendent
I&C/Senior Technician
Plant Engineer /System Engineer
Sup.
Operations
Department
Site Design
Operations,
Training
Technical Physical
Science Superintendent
Nuclear
Re ulator
Commission
~
~
Name
. Athavale
Don Beckrran
Tim Colburn
Bruce L. Jorgensen
Peter Koltay
James
E. Konklin
Wayne Lanning
B. D. Liaw
Hubert Miller
Melanic Miller
Greg Nejfelt
David Passehl
Robert Pierson
Tim Rowell
Harban Singh
Mahesh Singla
Loren Stanley
Dave Waters
J.
D. Wilcox, Jr.
Or anization
sc
p
ne
ead/DRIS
NRC Consultant
Project Manager
Senior Resident
Inspector
Team Leader/DRIS
Section Chief/RSIB
Branch Chief/RSIB
Deputy Director/DRIS
Director DRS/Region III
Operations
Engineer/DRIS
Reactor Engineer/Reg)on III
Resident
Inspector
Director
PD III-I
Technical Intern
NRC Consultant
NRC Consultant
NRC Consultant
NRC Consultant
Operations
Engineer/DRIS
~~~,~
a