ML17319B436

From kanterella
Jump to navigation Jump to search
Proposed Tech Spec Changes Re Installation of post-accident Monitoring Sys,Per NUREG-0737,Item II.F.1
ML17319B436
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 07/13/1982
From:
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
To:
Shared Package
ML17319B435 List:
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.F.1, TASK-TM AEP:NRC-0699, AEP:NRC-699, NUDOCS 8207200403
Download: ML17319B436 (23)


Text

ATTACHMENT NO.

1 TO AEP:NRC:0699 DESCRIPTION OF PROPOSED TECHNICAL SPECIFICATION CHANGES FOR D. C.

COOK UNIT NOS.

1 AND 2 8>072pp~p3pnppp315 agp713 00C~

p p

Chan e No.

1 Unit 1; Page'/4 6-17, 18, 19, and 20; Section 3/4.6.3, Table 3.6-1 Unit 2; Page 3/4 6-18, 19, 20, 21, 22, 23, 24, and 25; Section 3/4.6.3, Table 3.6-1 The changes in the valves listed in Table 3.6-1 are the result of two different items.

First, the installation of the post accident monitoring system as required by Item No.II.F.l of NUREG-0737 twas caused the addition of three valves to the table (this applies to item Nos.

9 to 11 in section B of the table).

Second, due to excessive
leakage, 14 of the existing check valves in the Non-Essential Service Water System are being replaced with valves of superior closing characteristics (this applies to item Nos.

28 to 31, 48, 50, 52, 54, 56, 58,i60, 62, 64, 66 in section B of the table).

Lastly, valves ECR-416, 417,)496,

497, 535, 536 were added to this table as part of a previous submittal, AEP:NRC:0591.

These additions are being resubmitted here for ease of processing.

Additional revisions to the table under this change are renumbering changes only.

These changes shall become effective after each unit's 1982 refueling outage.

Chan e No.

2 Unit 1; Page 3/4 6-21, and 22; Section 3/4.6.3 Table 3.6-1 Unit 2; Page 3/4 6-29, 30, and 31; Section 3/4.6.3 Table 3.6-1 The revisions to Table 3.6-1 are due to the replacement of the locked closed manual valves on the demineralized water supply for the refueling cavity, with remote air operated valves.

Valves QCR-919,

-920 are replacing valves DW-200, 210 in Unit 1 and DW-211, -212 in Unit 2.

AEPSC had committed to make this change in a letter from Mr. W. G. Smith, Jr.'s, Cook Plant Manager to Mr. J.

G. Keppler of NRC Region III, dated March ll, 1982.

Additional revisions to the table under this change are renumbering changes only.

These changes shall become effective after each unit's 1982 refueling outage.

r

ATTACHMENT NO.

2 TO AEP:NRC:0699 REVISED TECHNICAL SPECIFICATION PAGES FOR D. C.

COOK UNIT NO.

1

TABLE 3.6-1 (Continued)

VALVE NUMBER FUNCTION TESTABLE DURING PLANT OPERATION ISOLATION TIME IN SECONDS A.

PHASE "A" ISOLATION (Continued n

OOO pq I

H 27.

28.

29.

30.

31.

32.

33.

34.

35.

36.

37.

38.

39.

40.

41.

42.

43.

44.

45.

46.

47.

48.

49.

50.

51.

52.

53.

54.

55.

56.

57.

58.

59.

60.

61.

62.

ECR-10 ECR-11 ECR-12 ECR-13 ECR-14 ECR-15 ECR-16 ECR-17 ECR-18 ECR-19 ECR-.20 ECR-21 ECR-22 ECR-23 ECR-24 ECR-25 ECR-26 ECR-27 ECR-28 ECR-29 ECR-416 ECR-417 ECR-496 ECR-497 ECR-535 ECR-536 GCR-301 GCR-314 ICR-5 ICR-6 MCR-251 MCR-252 MCR-253 MCR-254 NCR-105 NCR-106 Cont.

H2 Sample Return Cont.

H2 Sample Air to Rec.

E Cont.

H2 Sample Air from Rec.

E Cont.

H2 Sample Low. Cont. Vol.

Cont.

H2 Sample Low. Cont. Vol.

Cont.

H2 Sample Up Cont. Vol.

Cont.

H2 Sample Up Cont. Vol.

Cont.

H2 Sample Air to Rec.

W Cont.

H2 Sample Air from Rec.

W Cont.

H2 Sample Cont.

Dome Vol.

Cont.

H2 Sample Return Cont.

H2 Sample Air to Rec.

E.

Cont.

H2 Sample Air fr. Rec.

E Cont.

H2 Sample Low Cont. Vol.

Cont.

H2 Sample Low Cont. Vol.

Cont.

H2 Sample Up Cont. Vol.

Cont.

H2 Sample Up Cont. Vol.

Cont.

H2 Sample Air to Rec.

W.

Cont.

H2 Sample Air Fr. Rec.

W.

Cont.

H2 Sample Cont.

Dome Vol.

PAS Containment Sump Sample PAS Containment Sump Sample PAS Waste Liquid and Gas Return PAS Waste Liquid and Gas Return PAS Containment Gas Sample PAS Containment Gas Sample N

Supply to Pressurizer Relief Tank N2 Supply to Accumulators Accumulators Sample Accumulators Sample Sample Line from Steam Gen. Outlet 81 Sample Line from Steam Gen. Outlet 82 Sample Line from Steam Gen. Outlet /f3 Sample Line form Steam Gen. Outlet

!/4 Hot Leg Sample Hot Leg Sample Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes 10 1A 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 ln 10 10 10 10 10 10 10

TABLE 3.6-1 (continued)

VALVE NASSER FUNCTION TESTABLE DURING ISOLATION TIME PLANT OPERATION IN SECONDS A

OO I

63.

64.

65.

66.

67.

68.

69.

70.

71.

72.

73.

74.

75.

76.

77.

78.

79.

80.

81.

82.

83.

PHASE "A" ISOLATION NCR-107 NCR-108 NCR-109 NCR-110 NCR-252 QCM-250 QCM-350 QCR-300 QCR-301 QCR-919 QCR-920 RCR-100 RCR-101 VCR-10 VCR-11 VCR-20 VCR-21 XCR-100 XCR-101 XCR-102 XCR-103 Continued)

PRZ Liquid Sample PRZ Liquid Sample PRZ Steam Sample PRZ Steam Sample Primary Water to Pressure Relief Tank RCP Seal Water Discharge RCP Seal Water Discharge Letdown to Letdown Hx.

Letdown to Letdown Hx.

Demineralized Water Supply for Refueling Demineralized Water Supply for Refueling PRZ Relief Tank to Gas Anal.

PRZ Relief Tank to Gas Anal.

Glycol Supply to Fan Cooler Glycol Supply to Fan Cooler Glycol Supply from Fan Cooler Glycol Supply from Fan Cooler Control Air to Containment Control Air to Containment Isolation Control Air to Containment Isolation Control Air to Containment Cavity Cavity Yes Yes Yes Yes Yes No No No No Yes Yes Yes Yes Yes Yes Yes Yes No No No No 10 10 10 10 10 15 15 10 10 10 10 10 10 10 10 10 10 10 10 10 10 BE PHASE "B" ISOLATION l.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

CCM-451 CCM-452 CCM-453 CCM-454 CCM-458 CCM-459 ECR-31 ECR-32 ECR-33 ECR-35 ECR-36 CCW from RCP Oil Coolers CCW from RCP Oil Coolers CCW from RCP Thermal Barrier CCW from RCP Thermal Barrier CCW to RCP Oil Coolers

& Thermal Barrier CCW to RCP Oil Coolers

& Thermal Barrier Containment Airborne Radiation Monitor Containment Airborne Radiation Monitor Containment Airborne Radiation Monitor Containment Airborne Radiation Monitor Containment Airborne Radiation Monitor No No No No No No No No No No No 60 60 30 30 60 60 10 10 10 10 10

VALVE NUMBER FUNCTION TABLE 3.6-1 (Continued)

TESTABLE DURING ISOLATION.TIME PLANT OPERATION IN SECONDS nOO PC I

B.

12.

13.

14.

15.

16.

17.

18.

19.

20.

21.

22.

23.

24.

25.

26.

27.

28.

29.

30.

31.

32.

33.

34.

35.

36.

37.

38.

39.

40.

41.

42.

43.

PHASE "B" WCR-901 WCR-903 WCR-905 WCR-907 WCR-909 WCR-911 WCR-913 WCR-915 WCR-921 WCR-923 WCR-925 WCR-927 WCR-929 WCR-931 WCR-933 WCR-935 WCR-941 WCR-942 WCR-943 WCR-944 WCR-945 WCR-946 WCR-947 WCR-948 WCR-951 WCR-952 WCR-953 WCR-954 WCR-955 WCR-956 WCR-957 WCR-958 ISOLATION Continued)

NESW to Low Containment Vent //1 NESW from Low Containment Vent //1 NESW to Low Containment Vent !/2 NESW from Low Containment Vent //2 NESW to Low Containment Vent //3 NESW from Low Containment Vent //3 NESW to Low Containment Vent 84 NESW from Low Containment Vent 84 NESW to Up Containment Vent //1 NESW from Up Containment Vent 81 NESW to Up Containment Vent //2 NESW from Up Containment Vent (/2 NESW to Up Containment Vent 83 NESW from Up Containment Vent f/3 NESW to Up Containment Vent !l4 NESW from Up Containment Vent 84 NESW to RCP Motor Air Cooler NESW to RCP Motor Air Cooler NESW to RCP Motor Air Cooler NESW to RCP Motor Air Cooler NESW from RCP Motor Air Cooler NESW from RCP Motor Air Cooler NESW from RCP Motor Air Cooler NESW from RCP Motor Air Cooler NESW to RCP Motor Air Cooler Vent //1 NESW to RCP Motor Air Cooler Vent //2 NESW to RCP Motor Air Cooler Vent //3 NESW to RCP Motor Air Cooler Vent //4 NESW from RCP Motor Air Cooler Vent //1 NESW from RCP Motor Air Cooler Vent 82 NESW from RCP Motor Air Cooler Vent //3 NESW from RCP Motor Air Cooler Vent //4 Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes yes Yes Yes Yes Yes Yes Yes Yes Yes Yes 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10

VALVE NUMBER FUNCTION TABLE 3.6-1 (Continued)

TESTABLE DURING PLANT OPERATION ISOLATION TIME IN SECONDS B.

PHASE "B" ISOLATION Continued n

A OO I

t~

44, 45.

46.

47.

48.

49.

50.

51.

52.

53.

54.

55.

56.

57.

58.

59.

60.

61.

62.

63.

64.

65.

66.

67.

WCR-961 WCR-963 WCR-965 WCR-967 WCR-900 WCR-902 WCR-904 WCR-906 WCR-908 WCR-910 WCR-912 WCR-914 WCR-920 WCR-922 WCR-924 WCR-926 WCR-928 WCR-930 WCR-932 WCR-934 WCR-960 WCR-962 WCR-964 WCR-966 NESW NESW

=NESW

-NESW NESW NESW NESW NESW NESW NESW NESW NESW NESW NESW NESW NESW NESW NESW NESW NESW

-NESW NESW NESW NESW to Instr.

Rm. East Vent from Instr.

Rm. West Vent to Instr.

Rm. East Vent from Instr.

Rm. West Vent to RCP Lower Containment Vent 81 from Lower Containment Vent 81 to RCP Lower Containment Vent 82 from Lower Containment Vent 82 to RCP Lower Containment Vent 83 from Lower Containment Vent /f3 to RCP Lower Containment Vent //4 from Lour Containment Vent //4 to RCP Upper Containment Vent Pl from Upper Containment Vent 81 to RCP Upper Containment Vent 82 from Upper Containment Vent 82 to RCP Upper Containment Vent 83 from Upper Containment Vent 83 to RCP Upper Containment Vent 84 from Upper Containment Vent 84 to Instrument Room East Vent from Instrument Room East Vent to Instrument Room West Vent from Instrument Room West Vent Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 C.

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

CONTAINMENT VCR-101 VCR-102 VCR-103 VCR-104 VCR-105 VCR-106 VCR-107 VCR-201 VCR-202 VCR-203 VCR-204 PURGE AND EXHAUST Instr.

Room Purge Air Inlet Instr.

Room Purge Air Outlet Lower Comp. Purge Air Inlet Lower Comp. Purge Air Outlet Upper Comp. Purge Air Inlet Upper Comp. Purge Air Outlet Cont. Press.

Relief Fan Isolation Instr.

Room Purge Air Inlet Instr.

Room Purge Air Outlet Lower Comp. Purge Air Inlet Lower Comp. Purge Air Outlet Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes

TABLE 3.6-1 (Continued)

VALVE NUMBER FUNCTION TESTABLE DURING PLANT OPERATION ISOLATION TIME IN SECONDS AoO I

M 12.

VCR-205 13.

VCR-206 14.

VCR-207 Upper Comp. Purge Air Inlet Upper Comp. Purge Air Outlet Cont. Press Relief Fan Isolation C.

CONTAINMENT PURGE EXHAUST (Continued Yes Yes Yes D. MANUAL ISOLATION VALVES 1.

ICM-111 2.

ICM-129 3.

ICM-250 4.

ICM-251 5.

ICM-260 6.

ICM-265 7.

ICM-305 8.

ICM-306 9.

ICM-311 10.

ICM-321 11.

NPX 151 VI 12.

PA 145 13.

SF-151 14.

SF-153 15.

SF-159 16.

SF-160 17.

SI-171 18.

SI-172 RHR to RC Cold Legs RHR Inlet to Pumps Boron Injection Inlet Boron Injection Inlet Safety Injection Inlet Safety Injection Inlet

.RHR Suction from Sump RHR Suction from Sump RHR to RC Hot Legs RHR to RC Hot Legs Dead Weight Tester Containment Service Air Refueling Water Supply Refueling Water Supply Refueling Cavity Drain to Purification System Refueling Cavity Drain to Purification System Safety Injection Test Line Accumulator Test Line Yes No Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes Yes Yes Yes Yes NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA

TABLE 3.6-1 (Continued)

VALVE NUMBER FUNCTION TESTABLE DURING PLANT OPERATION ISOLATION TIME IN SECONDS D. MANUAL ISOLATION VALVES (Continued)

(1) 19.

CCR-440 20.

CCR-441 21.

MCM-221 22.

HCM-231 23.

CCM-430 24.

CCH-431 25.

CCM-432 26.

CCM-433 27.

SM-8*

28.

SH-10*

29.

SH-4*

30.

SM-6*

CCW from Main Steam Penetration CCW from Main Steam Penetration Hain Steam to Auxiliary Feed Pump Hain Steam to Auxiliary Feed Pump CCW to East Pressure Equalization Fan CCW from East Pressure Equalization Fan CCW to West Pressure Equalization Fan CCW from West Pressure Equalization Fan Upper Containment Sample Upper Containment Sample Instrument Room Sample Instrument Room Sample Yes Yes No No Yes Yes Yes Yes Yes Yes Yes Yes NA NA NA NA NA NA NA NA NA NA NA NA NA Manual Valve-Isolation time not applicable.

(1)

Includes motor operated valves which do not isolate automatically.

May be opened on an intermittent basis under administrative control.

ATTACDKNT NO.

3 TO AEP:NRC:0699 REVISED TECHNICAL SPECIFICATION PAGES FOR D. C.

COOK UNIT NO.

2

TABLE 3.6-1 Continued)

CONTAINMENT ISOLATION VALVES VALVE NUMBFR FUNCTION ISOLATION TIME IN SECONDS A.

PHASE "A" ISOLATION (Continued) 37.

ECR-20 38.

ECR-21 39.

ECR-22 40.

ECR-23 41.

ECR-24 42.

ECR-25 43.

ECR-26 44.

ECR-27 45.

ECR-28 46.

ECR-29 Cont.

H2,Sample-Return Cont.

H2 Sample - Air to Rec.

E.

Cont.

H2 Sample Air Fr. Rec.

E.

Cont.

H2 Sample

<< Lou. Cont. Vol.

Cont.

H2 Sample Lov.-Cont. Vol.

Cont.

H2 Sample Up. Cont. Vol.

Cont.

H2 Sample Up. Cont. Vol.

Cont.

H2 Sample Air to Rec.

W.

Cont.

H2 Sample - Air Fr. Rec.

R.

Cont.

H2 Sample - Cont.

Dome Vol.

c10 c10 410 clO clO

<10 c10

<10 c10 cl0 47.

48.

49.

50.

51.

52.

53.

54.

ECR-416 ECR-417 ECR-496 ECR-497 ECR-535 ECR-536 GCR-301 GCR-314 PAS Containment Sump Sample PAS Containment Sump Sample PAS Waste Liquid and Gas Return PAS Waste Liquid and Gas Return PAS Containment Gas Sample PAS Containment Gas Sample N2 Supply to Pressurizer Relief Tank N2 Supply to Accumulators clO clO c10

<10 c10 c10 c10

<10

TAHLE 3.6-1

{Continued)

- COHTAIflMEHT ISOLATION VALVES VALVE NUMBER FUHCTION ISOLATION TIME IN SECONDS A.

PHASE "A" ISOLATION (Continued)

. 55.

56.

1CR-5 1CR-6 Accumulators Sample Accumulators Sample

< 10

< 10 58.

t1CR-2510-MCR-2528 5'9.

lfCR-2531 60.

ttCR-2540 61.

HCR-105 62 ~

ttCR-106:

63 'CR-107 64.

HCR-108 65.

NCR-109 66.

HCR-110 Sample Line from Steam Gen. Outlet 81 Sample Line from Steam Gen. Outlet 81 Sample Line from Steam Gen. Outlet II3 Sample Line'rom Steam Gen. Outlet P4

-Hot Leg Sample Hot Leg Sample PRZ Liquid Sample PRZ Liquid Sample PRZ Steam Sample PRZ Steam Sample

< 10.

< 10

< 10

< 10

< 10

< 10

< 10

< 10

< 10

< 10

TABLE 3.6-1 (Continued)

CONTAINlfENT ISOLATION VALVES VALVE NUHBER FUNCTION ISOLATION TIIK IN SECONDS A

OO I

K4H O

A.

PHASE "A" ISOLATION (Continued) 67.

NCR-252 68.

QCH-250 69.

QCH-350 70.

QCR-300 71.

QCR-301 72.

QCR-919 73.

QCR-920 74.

RCR-100 75.

RCR-101 76.

VCR-10 77.

VCR-11 78.

VCR-20 79.

VCR-21 80.

XCR-100 81.

XCR-101 Letdown to Letdown Hx.

Demin Wtr. Supply for Refueling Cavity Demin Wtr. Supply for Refueling Cavity PRZ Relief Tank to Gas Anal.

PRZ Relief Tank to Gas Anal.

Glycol Supply to Fan Cooler Glycol Supply to Fan Cooler Glycol Supply from Fan Cooler Glycol Supply from Fan Cooler Control Air to Containment Control Air to Containment Isolation Primary Water to Pressurizer Relief Tank RCP Seal Water Discharge RCP Seal Water Discharge Letdown to Letdown Hx.

<15

<10

>10 410

<10

~10

~10

~10 4-10 410

TABLE 3.6-1 (Continued)

CONTAINMENT ISOLATION VALVES VALVE NUMBER FUNCTION ISOLATION TIME IN SECONDS CjOO I

t~

A.

PHASE "A" ISOLATION (Continued) 83.

XCR-103 Control Air to Containment B.

PHASE "B" ISOLATION 1.

CCM-451 CCW from RCP Oil Coolers 2.

CCM-452 3.

CCM-453 4.

CCM-454 5.

CCM-458 6.

CCM-459 7.

ECR-31 8.

ECR-32 9.

ECR-33 10.

ECR-35 11.

ECR-36 CCW from RCP Oil Coolers CCW from RCP Thermal Barrier CCW from RCP Thermal Barrier CCW to RCP Oil Coolers

& Thermal Barrier CCW to RCP Oil Coolers

& Thermal Barrier Containment Airborne Rad Monitor Containment Airborne Rad Monitor Containment Airborne Rad Monitor Containment Airborne Rad Monitor Containment Airborne Rad Monitor 82.

XCR-102 Control Air to Containment Isolation

&10 Z io 460

~60

~30 M30 M60 M60

~10 M10 Aio

~10

~10

TABLE 3.6-1 (Continued CONTAINSKNT ISOLATION VALVES VALVE NUMBER FUNCTION ISOLATION TIME IN SECONDS OoO B.

PHASE "B" ISOLATION (Continued 410 12.

WCR-901 13.

WCR-903 14.

WCR-905 15.

WCR-907 16.

WCR-909 17.

WCR-911 18.

WCR-913 19.

WCR-915 20.

WCR-921 21.

WCR-923 22.

WCR-925 23.

WCR-927 NESW to Low. Containment Vent 81 NESW from Low. Containment Vent II1 NESW to Low. Containment Vent II2 NESW from Low. Containment Vent 82 NESW to Low. Containment Vent II3 NESW from Low. Containment Vent f/3 NESW to Low. Containment Vent t'I4 NESW from Low Containment Vent f14 NESW to Up. Containment Vent I/1 NESW from Up. Containment Vent 81 NESW to Up. to Containment Vent 82 NESW from Up. Containment Vent 82 410 410 410

%10 410 410 cJ.O MO 410 410

TABLE 3.6-1 (Continued CONTAINMENT ISOLATION VALVES VALVE NUMBER FUNCTION ISOLATION TIME IN SECONDS AoO I

M B. PIIASE "B" ISOLATION (Continued) 24.

WCR-929 25.

WCR-931 26.

WCR-933 27.

WCR"935 28.

WCR-941 29.

WCR-942 30.

WCR-943 31.

WCR-944 32.

WCR-945 33.

WCR-946 34.

WCR-947 35.

WCR-948 36.

WCR-951 37.

WCR-952 38.

WCR-953 39.

WCR-954 NESW NESW to Up. Containment Vent 83 from Up. Containment Vent f/3 NESW to Up. Containment Vent /f4 NESW from Up. Containment Vent II4 NESW to RCP Motor Air Cooler NESW to RCP Motor Air Cooler NESW to RCP Motor Air Cooler NESW to RCP Motor Air Cooler NESW from RCP Motor Air Cooler NESW from RCP Motor Air Cooler NESW from RCP Motor Air Cooler NESW from RCP Motor Air Cooler NESW to RCP Motor Air Cooler Vent 81 NESW to RCP Hotor Air Cooler Vent II2 NESW to RCP Motor Air Cooler Vent II3 NESW to RCP Motor Air Cooler Vent 84 C 10

+10 410

<10

<10 410

<10

. 410

<10

<10 K10

<10 zoo

<10 410

TABLE 3.6-1 (Continued)

CONTAIN1KNT ISOLATION VALVES a

VALVE NUHBER FUNCTION ISOLATION TIME IN SECONDS n

B.

PHASE "B" ISOLATION (Continued)

A OO 40.

WCR-955 41.

MCR-956 42.

MCR-957 43.

WCR-958 44.

WCR-961 45.

WCR-963 46.

WCR-965 47.

WCR-967 48.

WCR-900 49.

MCR-902 50.

WCR-904 51.

WCR-906 52.

WCR-908 53.

WCR-910 54.

MCR-912 55.

MCR-914 NESW from RCP Motor Air Cooler Vent 81 NESW from RCP Motor Air Cooler Vent f12 NESW from RCP Motor Air Cooler Vent 83 NESW from RCP Motor Air Cooler Vent 84 NESW to Instr.

Rm. East Vent NESW from Instr.

Rm. West Vent NESW to Instr.

Rm. East Vent NESW from Instr.

Rm. West Vent NESW to RCP Lower Containment Vent 81 NESW from Lower Containment Vent ftl NESW to RCP Lower Containment Vent 82 NESW from Lower Containment Vent 82 NESW to RCP Lower Containment Vent I/3 NESW from Lower Containment Vent f/3 NESW to RCP Lower Containment Vent 84 NESW from Lower Containment Vent 84

<10

<10

<10 410

<10 a 10

<10

<10

TABLE 3.6-1 (Continued)

CONTAIN'KNT ISOLATION VALVES VALVE NUMBER FUNCTION ISOLATION TIME IN SECOND B.

PHASE "B" ISOLATION Continued AoO 56.

WCR-920 57.

WCR-922 58.

WCR-924 59.

WCR-926 60.

WCR-928 61.

WCR-930 62.

WCR-932 63.

WCR-934 64.

WCR-960 65.

WCR-962 66.

WCR-964 67.

WCR-966 NESW to RCP Upper Containment Vent 81 NESW from Upper Containment Vent 81 NESW to RCP Upper Containment Vent f/2 NESW from Upper Containment Vent f/2 NESW to RCP Upper Containment Vent 83 NESW from Upper Containment Vent 83 NESW to RCP Upper Containment Vent //4 NESW from Upper Containment Vent 84 NESW to Instrument Room East Vent NESW from Instrument Room East Vent NESW to Instrument Room West Vent NESW from Instrument Room West Vent

<10

<10

@10 (10 C.

CONTAINMENT PURGE AND EXHAUST 1.

VCR-101 2.

VCR-102 3.

VCR-103 4.

VCR-104 5.

VCR-105 Instr.

Room Purge Air Inlet Instr.

Room Purge Air Outlet Lower Comp. Purge Air Inlet Lower Comp. Purge Air Outlet Upper Comp. Purge Air Inlet c5 (5

c5

TABLE 3.6-1 (Continued)

CONTAI&KNT ISOLATION VALVES n

AoO I

VALVL'UMBER E.

OTHER Continued 18.

PA-243 19.

NPX-151 VI 20.

N-160 21.

SM-1 22.

N-102 23.

SI-171 24.

SI-172 25.

SI-194 26.

PW-275 27.

CS-321 FUNCTION Service Air to Containment Dead Weight Calibrator N2 to R. C. Drain Tank Air Particle/Radio Gas Detect Return N2 To Accumulators Safety Injection Test Line Safety Injection Test Line Safety Injection*Test Line Primary Wtr. to Pre. Relief Tank R.C.S.

Charging ISOLATION TIME IN SECONDS NA NA NA NA NA NA NA NA

a A

OO I

VALVE NUMBER TABLE 3.6-1 (Continued)

CONTAINMENT ISOLATION VALVES FUNCTION ISOLATION TIME IN SECONDS E.

OTHER (Continued 28.

SF-152 29.

SF-154 30.

SF-159 31.

SF-160 32.

NSW-417-3 33.

NSW-417-4 34.

N-159 35.

CCW-135 36.

CA-181-N 37.

CA-181-S 38.

SM-8 39.

SM-10 Refueling Wtr. to Refuel. Cavity Refueling Wtr. to Refuel. Cavity Refueling Cavity Drain Refueling Cavity Drain NESW to Instr.

Rm. Vent

'W'ESW to Instr.

Rm. Vent

'E'2 to Prz. Relief Tank CCW to Reactor Supports Weld Channel Supply Air Weld Channel Supply Air Upper Cont. Grab Sample Upper Cont.

Grab Sample NA NA NA NA NA NA NA NA NA NA NA

AO, 0

VALVE NUMBER TABLE 3.6-1 (Continued)

CONTAIAKNT ISOLATION VALVES FUNCTION ISOLATION TIME IN SECONDS E.

OTHER (Continued 40.

PPP-300 41.

PPP-301 42.

PPP-302 43.

PPP-303 Instrument Penetration Instrument Penetration Instrument Penetration Instrument Penetration NA NA NA NA 44.

PPA-310 and PPA-311 Instrument Penetration NA 45.

PPA-312 and PPA-313 46.

Blind Flange 47.

Blind Flange 48.

Blind Flange 49.

Blind Flange 50.

Blind Flange Instrument Penetration Fuel Transf er Penetration Service Air to Containment Ice Condenser Ice Supply Ice Condenser Ice Return In-Core Flux Thimble Access NA NA NA NA NA