ML17319B045

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-315/81-19 & 50-316/81-22 on 810810-12. Noncompliance Noted:Walkdown Hanger Deficiencies Such as Bent Rod & Missing U-bolts Not Being Identified by Insp Personnel Per IE Bulletin 79-14
ML17319B045
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 08/27/1981
From: Danielson D, Yin I
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17319B043 List:
References
50-315-81-19, 50-316-81-22, IEB-79-14, NUDOCS 8109150301
Download: ML17319B045 (18)


See also: IR 05000315/1981019

Text

U.S.

NUCLEAR REGULATOR COMMISSION

OFFICE

OF INSPECTION AND ENFORCEMENT

REGION III

Reports

No. 50-315/81-19;

50-316/81-22

Docket Nos. 50-315; 50-316

Licenses

No. DPR-58;

DPR-74

Licensee:

American Electric Power Service Corporation

Indiana

and Michigan Power

Company

2 Broadway

New York, NY

10004

Facility Name:

D. C.

Cook Nuclear, Plant,, Units

1 and

2

Inspection At:

American Electric Power Service Corporation,

New York, NY

Inspection

Conducted:

August 10-12,

1981

Inspector:

I. T. Yin

Z a7Z/

Approved By:

D. H.=Danielson,

Chief

Materials and Processes

Section

Ins ection

Summar

Ins ection on Au ust 10-12

1981

(Re orts No. 50-315/81-19

50-316/81-22)

Areas Ins ected:

Licensee actions relative to IE Bulletin No. 79-14; re-

view of LER corrective actions.

The inspection involved 23 inspector-hours

at the corporate

engineers office by one

NRC inspector.

Results:

Of the areas

inspected,

two apparent violations were identified.

~pailure to follow design calculation verification procedures

paragraph

6.c.(1); failure to report events

as required by Technical Specifications-

Paragraphs

6.a.(4)

and 6.d.(l)).

'

( 8i09i5030i Bi083i

PDR

ADOCK 050003i5

'. 9

PDR

'E

~

'L

)

4

Nl

M

I

I

E

P

> a'

4

'

Persons

Contacted

DETAILS

American Electric Power Service

Cor oration

(AEP)

"T.

  • J

+K.

~'G.

"R

'S.

"T

'>S.

~H.

"H

J.

R. Satyan-Sharma,

Nuclear Safety

and Licensing

I. Castresana,

Safety and Licensing Section Manager

H. Vehstedt, Nuclear Safety and Licensing

P. Field,

AVP and Chief Design Engineer

F. Kroeger,

Manager of (}A

H. Steinhart,

Mechanical Engineering

W. Baker, Mechanical Engineering

PSV Section Manager

Sun, Mechanical Design

Ulan, Mechanical Design

Sobol, Nuclear Engineering

T. Sinclair, Design Staff

L. Williams, Section Manager,

Mechanical Design

"-Denotes those

who attended

the exit interview.

Functional or Pro

ram Areas Ins ected

Status of S stem Evaluation

and Modifications (IE Bulletin No. 79-14)

Engineering evaluation for all safety related piping systems in both

Units

1 and

2 is completed.

Hardware modifications had been completed based

on the results of

393 computer calculations.

At the time of this visit, there were 24

computer calculations

which required site modification.

The original Class

1 piping systems

design

and analysis responsibili-

ties were as follows:

D~esi n

Seismic Anal sis

Primary Coolant Loop

MS from SG to Containment Penetration

FW from Containment Penetration

to,SG

All other Class

1 Piping

SSL

AEP

AEP

AEP

W

SSL

SSL

EDS,S.F.

The

was

IE Bulle'tin No. 79-14 computer Class

1 piping systems

analysis

work

assigned

as follows:

EDS,NY-33 calculations

Associated Technologies,

Inc. (ATI) - 32 calculations

Harstead - 4 calculations

Teledyne Engineering Service

(TES) - 2 calculations

AEP - 13 calculations

'

P a

~

~

2.

Review of Licensee Evaluation Criteria

a.

The original piping design loading conditions

and stress limits

documented in CESAR Volume IV, Appendix B, Table

2 stated:

Upset Conditions:

(a)

Pm < 1.2S

(including OBE)

(b)

Pm (or Pl) + Pb< 1.2S

Emergency Conditions:

(a)

Pm < 1.2S

(Including DBE)

(b)

Pm (or Pl) + Pb< 1.8S

Where:

Pm = primary general

membrane stress

Pl = primary local membrane

stress

Pb = primary bending stress

S = allowable stress

from USASI B31.1,

Code for Pressure

Piping

In discussion with the licensee, it was stated that the original

calculation methods

employed were as follows:

Large Bore Piping Systems:

Class

1 - Computer analysis

(2

~pl>

and larger)

Class

2 - Both computer analysis

and static coefficient

Class

3 - Mostly static coefficient

analysis

Small Bore Piping Systems:

All classes

were based

on static

(2" and smaller)

coefficient analysis

The computer programs

used during the original design were the

programs established

by W, S&L, and

EDS.

The static coefficient

analysis

was based

on EDS Procedure,

"Alternative Piping Analysis

Criteria for Earthquake

and Gravity Ioads for Donald C.

Cook

Nuclear Plant," dated

September

1971.

The IE Bulletin No. 79-14

computer seismic analyses

were performed by EDS, ATI, AEP and other

companies

using their own computer programs.

The static analysis

is still based

on the September

1971

EDS procedure.

b.

The D.

C.

Cook FSAR does not address

piping component

support design

and analysis criteria.

The design requirements

are addressed

in AEP

Specification

No.

DCCPM402QCN, "Pipe Supports,

Special Requirements

for Seismic Class I, II, and Quality Ievel

5 Systems,"

Revision 2,

dated April 20,

1970.

The IE Bulletin No. 79-14 hanger design

evaluations

are also based

on this specification.

In discussions

with the

AEP engineering staff, it was,stated

that

the system discrepancy evaluation operability criteria under the

DBE conditions is the

same

as the original Code stress criteria.

- 3-

)I

'II

No items of noncompliance

or deviations

were identified as

a

result of the review.

The EDS static coefficient analysis

procedure,

and the

AEP pipe hanger design specification will

be reviewed in detail during

a future inspection.

3.

Review of En ineerin

Evaluation Procedures

The following AEP evaluation procedures

per IE Bulletin No. 79-14

requirements

were either revised or added to the program since the

inspector's last visit in September

1979

(Region III Inspection

Reports

No. 50-315/79-22;

50-316/79-19):

79-14-1-S, "Structural Design Procedure,"

Revision 1, dated

October

16,

1979.

79-14-4,

"Method of Document Comparison to Evaluate Exiting

Erected Configurations," Revision 2, dated October

16,

1979.

79-1'4-5,

"Procedure for Seismic Evaluation of Discrepancy Data,"

Revision 4, dated January 6,

1981.

79-14-7,

"Procedure for Up-Dating Drawings and Documents Relating

to IE Bulletin No. 79-14,",Revision 2, dated November

17,

1980.

79-14-8, "Close-out Procedure

for. Handling Storage

and Reproduction

of Documentation for NRC IE Bulletin No. 79-14", Revision 1, dated

October 31,

1981.

The inspector

reviewed these procedures.

No items of noncompliance

or

deviations

were identified.

4.

Review of Field Xns ection Walkdown Procedures

During the site inspection performed

on August 29,

1979

(Region XII

Inspection Reports

No. 50-315/79-20;

50-316/79-17)

the inspector re-

viewed Procedure

No.

12-gHP-SP.002,

"Seismic Class I Piping System

Field Inspection for Conformity with Design Documentation of .Seismic

Analyses," Revision 0, dated August 6,

1979,

and had several

comments.

During this visit, the inspector

reviewed Revision

1 of the procedure

dated August 29,

1979, together with a letter from AEP to Region IIX,

AEP:NRC:

00238B,

dated

September

14,

1979,

where

a description of the

field inspection methods being employed is given.

The inspector

con-

siders

the intent of the subject matter has

been met,

and stated that

he has

no further questions.

5.

Followu

Resident

Ins ector (RI) Identified Problems

On April 15,

1981, the Region XII RI while observing the SI and blackout

surveillance,

heard unusual vibration from Support

2GESW-R38 of the Diesel

Enginer Aftercooler System in the Unit 2 diesel generator

area.

This and

other supports in the area

were found loose,

some not supporting the

pipinq system.

He also found that the Unit 2 supports differ from those

in Uni;t l.

A number of hanger detail sheets

were furnished by the RI for

4-

-

the inspector's

followup review and evaluation in conjunction with the

review of licensee's

implementation of IE Bulletin No. 79-14 requirements.

The following hangers in question

were reviewed by the inspector:

Calculation 2-006 - Diesel Generator

(DG) 2AB and

2CD Iso.

No.

2-GESW-34 and

2GESW-42.

The hangers in

question

were R41, R40, R39,

and R38.

Calculation 2-005 - DG 2AB and

2CD Iso. No.

2-GESW-36

and

2-GESW-38.

The hangers in question

were

R44,

V45, V42, and V43.

Calculation 1-005 - DG lAB and

1CD Iso.

No.

1-GESW-35

and

1-GESW-37.

The hangers in question were

R14, R15, R12,

and R13.

Calculation 1-006 - DG lAB and

1CD Iso. No.

1-GESW-33

and

1-GESW-41.

The hangers in question were

R14, R15, R12,

and R13.

The problems identified by the RI included:

(1) hanger locations

were

changed

from pipe runs to pipe elbows,

(2) where variable spring hangers

were called for on design details, rigid hangers

were installed,

and (3)

during the IE Bulletin No. 79-14 walkdown hanger deficiencies,

such

as

bend rod, missing U-bolts,

and clearances

between trapeze

type pipe

supports

and the bottom of the pipe were apparently not being identified

by the site inspection staff.

Relative to problems

(1) and (2) above,

the inspector

reviewed

some of

the site inspection

and corporate engineering evaluation packages

and

found that discrepancies

on V45, V43, R44,

and V42, R38, F39, F40,

and

R41 had been identified during the September

28,

1979 system walkdown;

and the discrepancies

on R8, R9, V10, and Vll had been identified dur-

ing the August 29,

1979

and November 8,

1979 walkdown inspections.

The

inspector

reviewed the stress

analysis

'packages

and concurred with the

licensee that the existing arrangement

does not present

any safety

problem.

This was based

on the fact that the system temperature

is

below 100 F, there was,a high system natural frequency

(some

exceeded

0

33 cps at first mode),

and both primary and secondary

stresses

including

OBE and

DBE are very small in comparison with the

Code allowables.

Relative to (3) above,

the missing U-bolt was determined to be

a mis-

interpretation deficiency on the part of the field walkdown group and

did not represent

a safety problem.

However,

the problems involving

the

damaged

component, i.e., bent hanger

rods

and improper hanger 'in-

stallation, including gaps between supports

and pipes will be followed

up by the inspector during

a future site inspection to assess

whether

or not these

are isolated

cases

or a generic problem.

This is con-

sidered

an unresolved

item (315/81-19-01;

316/81-22-01).

lp

~

~

6.

Review of IE Bulletin No. 79-14 Evaluation Packa

es

A number of the subject packages

were selected

by the inspector for

review.

The review findings are

as follows:

a.

EDS Calculation No. 2-215,

"Chemical and Volume Control,

1-CCS-5,

3" and 4" CS Line From CPN-37," Revision 1, dated October

18,

1980.

(1)

The inspector

reviewed the

EDS Nuclear Inc. Project Instruc-

tions,

"D. C.

Cook Nuclear Plant - NRC Bulletin No. 79-14

Reanalysis",

Revision 1, dated August 13,

1980,

and had no

adverse

comment.

(2)

Valves

QCM-250 and SV-50, the weights modeled in the computer,

were based

on values

from the manufacture

drawing.

(3)

Maximum DBE XY Quake Stress

of 28,749 psi at

C16 pipe elbow

was 99.8'/ of Code allowable (28,800,psi).

In view the fact

that the

SV discharge thrust loads

and the loads

due to the

attached non-safety related discharge

pipe section

had not

been included in the calculation,

the adequacy of design in

terms of meeting the

Code requirements

remained to be ques-

tionable.

Insufficient evaluation of SV discharge piping loads

and the

dynamic effect of secondary piping is,a problem that has been

identified at several facilities.

This matter will be for-

warded to IE Headquarters

for evaluation

as

a potentially

generic problem,

(4)

In review of Revision

0 of the calculation,

dated October

14,

1980, the following stresses

were found:

XY OBE 21,924 psi, which is 114.2g, of Code allowable

(19,200 psi) at C22 pipe elbow, Joint No. 77.

XY DBE 42,515 psi, which is 147.6/ of Code allowable

(28,800 psi) at C22 pipe elbow, Joint No. 77.

ZY DBE 34,342 psi, which 119.2/ of Code allowable

(28,800 psi) at C09 elbow, Joint No.. 23.

In order to correct these overstress

conditions

an X-stop

was added at Joint No. 52A (called 2-GCS-R-608A)

and support

2-BCS-R-610 at Joint No.

74 was modified from a Y-stop to

a

.Y-stop and

a lateral.

The design

was forwarded to the site

on March 6,

1981,

and installation was completed

on April 10,

1981.

An IER was not issued informing Region III that the

piping was overstressed.

b.

ATI Calculation 1-220,

"10" Line From Accumulators

No.

2 and

No.

3 to CPS-17

and

CPS-21 (1-CSI-3)", Revision 0.

I

l

Y

t

h

k

(1)

Check Valve 51CN08XX, the weight modeled in the computer

was based

on valves

from the manufacturer

drawing.

The water

weight inside the valve was included in the calculation.

(2)

Pipe penetration Fl. El. was marked 601'-3/8" but in fact,

it should be Fl. EL. 608'",

However, this did not affect

the computer input.

In discussion with the President of ATI,

it was stated that computer input deck was verified prior to

run,

and

some outputs

were graphically plotted by computer.

The inspector noted that the verification measures

did not

appear to be applied systematically.

A more detailed procedural

review relative to computer

calculation 'verification methods will be conducted by the

inspector during

a future inspection.

This is an unresolved

item (315/81-19-02;

316/81-22-02)

~

c.

AEP Calculation

2 -258,

"From Pump 2-RC-20 to Excess

Ietdown Heat

Exchanger,

2-CS-670",

dated

December

3,

1979.

(1)

There

was

no documented

evidence that the computer calculation

was verified by a checker.

(2)

X-restraint

(20GCS-I-852)

was added to the system to reduce

the seismic stress

to meet the

Code allowable valve.

A

hanger drawing was issued

on December

14,

1979,

and sent to

the site on .December

15,

1979.

The restraint

was installed

on December

21,

1979.

A Licensee

Event Report

(LER) was

forwarded to Region III.

d.

TES Calculation 2-178, "Technical Report,

TR-4128-2, Stress

Analysis of Essential

Service Water to Axuiliary Feed

Pump

Piping (2-ESW-5) for D.

C.

Cook Nuclear Power Plant," dated

January

8,

1980.

(1)

In Paragraph

2 it stated,

"Conclusion, that Analysis of the

system as-built condition showed failure at Nodes

53 through

57.

To correct this condition,

a

Z direction (rigid) re-

straint was added at Node 48 and an X direction (rigid)

restraint

was

added at Node 5013."

Modified 2GESW-R-120

(the Z-restraint) - The drawing

was sent to the site on January

24,

1980.

Added 2AESW-I,-120A (the X-restraint) - The drawing was

sent to the site on January

17,

1980.

The installation of these restraints

was completed

on

February 25,

1980.

No LER was sent to Region III.

Subsequent

to the review, the inspector

determined:

1

l

+ ~

V

Item 6.c.(1) are in noncompliance with the

AEP Design Division

Organization

and Procedures

Manual, General Design Procedure

No. 8,

Revision

2 dated October 31, '1980, "Calculations," "Computer Calcula-

tions", Paragraph

2 states,

"The engineer or designer

responsible for

the problem shall stamp the first sheet of output containing the input

data

and review it for accuracy, against the input data

and review or

for accuracy against the input data. 'he'assigned

"Checker" shall" also

check the input data in the

same manner.

After checking,

the originator

and checker shall sign and date the stamp."

This is an apparent viola-

tion identified in Appendix A (315/81-19-03;

316/81-22-03).

Items 6.a.(4)

and 6.d.(1) were in noncompliance with the Technical Specification 6.9.1.8.

The D.

C.

Cook Nuclear Plant, Units

1 and 2,

Technical Specification,

Amendment No. 23, "Prompt Notification with

Written Followup" Section 6.9.1.8 states

that,

"The types of events

listed below shall be reported within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> by telephone

and

confirmed by telegraph,

mailgram, or facsimile transmission

to the

Director of the Regional Office, or his designate

no later than the

first working day following the event, with a written followup report

within 14 days.

The written followup report shall include,

as

a

minimum,

a completed

copy of a licensee

event report form.

Information

provided on the licensee

event report form shall be supplemented,

as

needed,

by additional narrative material to provide complete explanation

of the circumstances

surrounding the event."

Section 6.9.1.8.i states,

"Performance of structures,

systems,

or components

that, require remedial

action or corrective measures

to prevent operation in a manner less

conservative

than assumed in the accident analyses in the safety

analysis report or technical specification bases;

or discovery during

unit life of conditions not specifically considered in the safety

analysis report or technical specifications that require- remedial

action or corrective measures

to prevent the existence

or development

of an unsafe condition."

During the review, the inspector

was presented

the following LERs

relative to problems identified as

a result of the IE Bulletin

No. 79-14 evaluations;

however,

none of them described

the above

problem areas:

LER No. R079-050/OIT-O, reported

on January

11,

1980

IER No. R079-065/OIT-O,

reported

on January

17,

1980

IER No. R079=049/OIT-O,

reported

on December

21,

1979

This is an apparent violation identified in Appendix A (315/81-19-4;

316/81-22-04).

Reactor Coolant

Pum

(RCP) Restraint

Problem

The licensee reported to Region III on July 29,

1981 that the shim pack

retaining bolts

on the

RCP No.

12 (Unit 1,

Pump No. 2) were sheared off,

allowing the shim pack to fall from its installed location.

The re-

straint was located at RCP support,

column No.

2 away from the reactor

vessel.

The shim pack (with Gap

C) was designed

to receive

loa'ds

normal to the cold leg during LOCA conditions.

Licensee

engineers

- 8-

E

I

E

~

I

~

~

I

f'

i

stated that the slightly offset gap

was based

on pipe thermal expansion

and contraction

movements

and (1) blackout condition of 620 F, (2) hot

functional of 547 F, (3) hot leg reactor full load at 599 F, and (4)

cold leg reactor full load of 540 F.

Subsequent

to the discussion with

the

AEP nuclear licensing

and design staff, the inspector determined:

a

~

AEP engineers

stated that the failure was considered

to be in-

cidental because

the previous

60 plus system transient

cycles

did not have similar problems.

They stated that site personnel

had inspected all other restraint settings at the

RCPs

and the

steam generators

and found no abnormal conditions.

A subsequent

review of IER RO 81-026/99T-0 noted that it did not mention the

steam generator

gaps being checked.

This is an unresolved item

(315/81-19-05;

316/81-22-05).

b.

The original Westinghouse

(Q) restraint

gap setting at hot func-

tional temperature

of 547

F was 0<'nd 1/32".

The AEP design

department

revised the settings to 1/16" with a tolerance of +1/32"

and -0".

Documentation indicating

W engineering

had concurred with

this revised setting

was not available.

The licensee

stated

they

would obtain the necessary

documentation.

This is an unresolved

item (315/81-19-06;

316/81-22-06).

Unresolved Items

Unresolved items are matters

about which. more information is required in

order to ascertain

whether they are a'cceptable

items,

items of noncompliance,

or deviations.

Three unresolved

items disclosed

during the inspection are

discussed in Paragraphs

5, 6.b.(2),

7.a

and 7.b.

Exit Interview

The inspector

met with licensee

representatives

prior to the conclusion of

the inspection.

The inspector

summarized

the scope

and findings of the

inspection.

The licensee

acknowledged

the findings reported herein.

J

~

~

I

L