Forwards IE Insp Rept 50-315/79-28 on 791211-14 & Notice of Violation
ML17318A620
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 01/09/1980
From: Heishnan R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Dolan J
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
Shared Package
ML17318A621 List:
References
NUDOCS 8002200331
Download: ML17318A620 (3)


See also: IR 05000315/1979028

Text

I

~8 RED

I

ClO

0

v

4~

~0

++*++

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

799 ROOSEVELT ROAD

GLEN ELLYN,ILLINOIS60137

JAN 9

l380

CENTR@,gjil+

Docket No. 50-315

American Electric Power Service

Corporation

Indiana

and Michigan Power

Company

ATTN:

Mr. John E. Dolan, Vice

Chairman, Engineering

2 Broadway

New York, NY

10004

Gentlemen:

This refers to the inspection

conducted

by Mr. E. T.

Chow of this office

on December

11-14,

1979, of activities at the D.

C.

Cook Nuclear Power

Station, Unit 1, authorized

by NRC Operating License

No. DPR-58 and to the

discussion of our findings with Mr. D. Shaller at the conclusion of the

inspection.

The enclosed

copy of our inspection report identifies areas

examined dur-

ing the inspection.

Within these

areas,

the inspection consisted

of a

selective examination of procedures

and representative

records,

observa-

tions,

and interviews with personnel.

During this inspection,

certain of your. activities appeared

to be in non-

compliance with NRC requirements,

as described in the enclosed

Appendix A.

This notice is sent to you pursuant to the provisions of Section 2.201 of

the NRC's "Rules of Practice," Part 2, Title 10,

Code of Federal Regula-

tions.

Section 2.201 requires

you to submit to this office within twenty

days of your receipt of this notice

a written statement

or explanation in

reply, including for each item of noncompliance:

(1) corrective action

taken

and the results

achieved;

(2) corrective action to be taken to avoid

further noncompliance;

and (3) the date

when full compliance will be achieved.

In accordance

with Section 2.790 of the NRC's "Rules of Practice," Part 2,

Title 10'ode of Federal Regulations,

a copy of this letter and the en-

closed inspection report will be placed in the NRC's Public Document

Room,

except

as follows. If this report contains information that you or your

contractors

believe to be proprietary,

you must apply in writing to this

office, within twenty days of your receipt of this letter, to withhold

such information from public disclosure.

The application must include

a

t

American Electric Power

Service Corporation

JP.f) o

]99)

full statement

of the reasons

for which the information is considered

pro-

prietary,

and should be prepared

so that proprietary information identi-

fied. in the application is contained in an enclosure

to- the application.

We will gladly discuss

any questions

you have'oncerning

this inspection.

Sincerely,

R. F. Heishman,

Chief

Reactor Operations

and Nuclear

Support Branch

Enclosures:

l.

Appendix A, Notice

of Violation

2.

IE Inspection Rpt

No. 50-315/79-28

cc w/encl:

D. V. Shaller, Plant Manager

Central Files

Reproduction Unit NRC 20b

PDR

Local

PDR

NSIC

TIC

Ronald Callen, Michigan Public

Service

Commission

RIII

4<c

Chow/jp

1/6/80