ML17318A623

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-315/79-28 on 791211-14.Noncompliance Noted: Failure to Update Plant Technical Data Book
ML17318A623
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 01/08/1980
From: Chow E, Little W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17318A621 List:
References
50-315-79-28, NUDOCS 8002200336
Download: ML17318A623 (7)


See also: IR 05000315/1979028

Text

U.S.

NUCLEAR REGULATORY COMMISSION

OFFICE

OF INSPECTION AND ENFORCEMENT

REGION III

Report No. 50-315/79-28

Docket No. 50-315

I,icense

No. DPR-58

Licensee:

American Electric Power Service Corporation

Indiana

and Michigan Power

Company

2 Broadway,

N.Y. 10004

Facility Name:

Donald

C.

Cook Nuclear Plant Unit 1

Inspection At:

Donald

C.

Cook Site,

Bridgman,

MI

Inspection Conducted:

December ll thru 14,

1979

Nuclear Support Section

1

Ins ection

Summar

Ins ection on December ll thru 14

1979

(Re ort No. 50-315/79-28)

Areas Ins ected:

Routine,

announced

inspection of shutdown margin deter-

mination; isothermal temperature

coefficient; power coefficient of reacti-

vity measurement;

target axial flux difference; reactivitiy anomalies.

The inspection involved 22 inspector

hours onsite by one

NRC inspector.

Results:

Of the five areas

inspected,

no Items of Noncompliance

or Devia-

tions were identified in four areas.

One Item of Noncompliance

was identi-

fied in one area.

(Deficiency - failure to update the plant technical data

book - Paragraph

7).

soossoo

DETAILS

Persons

Contacted

.*V.

  • E

%J

  • T.

"E.

"D

~R.

Ho, Performance

Engineer

Vanderburg,

Nuclear Engineer

Smarrella,

Technical 'Superintendent

Stietzel,

QA Supervisor

Beilman, Senior

QA Auditor

Townley, Assistant Plant Manager

Shaller, Plant Manager

Masse,

Resident Inspector,

NRC, RIII

  • Denotes those present

during the exit interview.

2.

Verification of Conduct of Startu

Ph sics Testin

The inspector

reviewed the startup physics testing

and verified that

the licensee

conducted

the following:

a

~

b.

c

~

d.

e.f.

g

h.

J

~

Rod Drive and Rod Position Indication Checks

Core Power Distribution Limits

Incore/Excore Calibration

Core Thermal Power Evaluation

Determination of Shutdown Margin

Isothermal Temperature Coefficient

Power Coefficient of Reactivity Measurement

Control Rod Worth Measurement

Target Axial Flux Difference Calculation

Determination of Reactivity Anomalies

3.

Shutdown Mar in Determination

The inspector

reviewed information relating to Cycle 4 shutdown

margin determination

as described in Appendix B, "Shutdown Margin

Verification," of Procedure

12 THP 6040

PER .059, Revision 2, "Zero

Power and Power Ascension Tests,"

dated

May 8,

1979.

The inspector noted that the calculated

shutdown margin with the

most reactive

rod F 14 stuck out of the core

was

4689

pcm which met

the Technical Specification requirement of 1750 pcm.

The inspector noted that only the worths of control banks were

measured

and the worths of shutdown banks

were not measured

but cal-

culated by assuming that the ratio of the measured

control bank worth

P

~

0

to the predicted control bank worth was the

same

as the ratio of

the measured

shutdown bank worth to the predicted

shutdown bank

worth.

The licensee

agreed that the assumption of using the

same

ratio to calculate

shutdown bank worth might not be conservative

and would review the procedure.

This Unresolved

Item (315/79-28-01)

will be reviewed in a subsequent

inspection.

No items of noncompliance

or deviations

were identified.

4.

Isothermal

Tem erature Coefficient

The inspector

reviewed information relating to Cycle 4 determination

of isothermal temperature

coefficient as described in Procedure

12

THP 6040 PER.

050, Revision 2, "Isothermal Temperature

Coefficient

Measurement,"

dated July 9,

1979.

The licensee's

acceptance

criterion requires that the measured

isothermal temperature

coefficient be within +3 pcm/ F of the pre-

dicted value.

The inspector determined that this requirement

was

satisfied.

The isothermal

temperature

coefficient measured

during

heatup

was

.2048 pcm/ F and the coefficients

measured

during two

cooldowns were

.2621 pcm/ F and

.2125 pcm/ F.

No items of noncompliance

or deviations

were identified.

5.

Power Coefficient of Reactivit

Measurement

The inspector

revs.ewed

xnformatxon relating to the Cycle 4 determin-

ation of power coefficient of reactivity as described in Procedure

THP 6040 PER.054, Revision 2, "Determination of the Doppler Power

and Total Power Coefficients,"

and Procedure

12 THP 4030 STP.307,

"Moderator Temperature Coefficient Determination."

The inspector noted that the power coefficient was calculated

from

the measurements

of Doppler and moderator temperature

coefficients.

The inspector

reviewed the results of power coefficient tests at

50'j of rated power on July 22,

1979

and at 90'j of rated power on

July 25,

1979.

The review criterion was that the power coefficient

obtained

from the measurements

be within + 30'j of the design value.

The inspector noted that the predicted

power coefficient was -12.22

pcm// power and the power coefficient obtained

from measurements

was

-9.177 pcm/g power.

The inspector

concluded that the review criterion

was met,

No items of noncompliance

or deviations

were identified.

4

6.

Tar et Axial Flux Difference

The inspector

reviewed information relating to the Cycle 4 deter-

mination of target axial flux difference

as described in Procedure

12 THP 4030 STP.372,

Revision 3, "Target Flux Difference Update."

The inspector noted that the Technical Specification requires that

. the indicated axial flux difference

be maintained within a +5/ target

band about the target flux difference,

and

a new target band will be

issued if the measured

or updated target value is more than 1/ dif-

ferent from the present target value.

The inspector

reviewed the

flux map taken

on November

16,

1979

and noted that

a new target value

was calculated

and the related target band

was issued.

The inspector

further noted that the target flux difference

was measured

at least

once per 92 effective full power days

(EFPD)

and

was updated at least

once per

31 EFPD.

No items of noncompliance

or deviations

were identified.

7 ~

Reactivit

Anomal

Determination

The inspector

reviewed information relating to the Cycle 4 deter-

mination of reactivity anomaly

as described in Procedure

1-THP

4030 STP.308,

Revision 2, "Boron Curve Update," dated January 4,

1979.

The inspector noted that,

based

on the boron endpoint

and

rod worth measurements,

the measured differential boron worth was

about 20/ higher than the Exxon design value.

The inspector noted

that the determination of reactivity anomaly using either the mea-

sured differential boron worth or the predicted value satisfied

Technical Specification requirement.

Plant Manager Instruction PMI 4060 requires

the licensee

to forward

only properly prepared,

reviewed

and approved technical data for

entry in technical data books.

The inspector noted that Unit

1 Cycle 4 Physics Test Data

Summary

stated that the values for'he differential boron worth used in the

plant technical data book have been scaled up'o reflect the true

boron worth in the core.

Contrary to the above,

the differential boron worth curves in the

technical

data books have not been scaled

up to reflect the dis-

crepancy

between the predicted

and the measured differential boron

worths.

This is considered

to be an item of noncompliance of the

Deficiency level.

The licensee

stated that Exxon had acknowledged

the discrepancy in

boron worth and also discovered

the similar problem at another nuclear

power plant.

This Unresolved

Item (315/79-28-02) will be reviewed in

a subsequent

inspection.

8.

Unresolved

Items

Unresolved

Items are matters

about which more information is re-

quired in order to ascertain

whether they are acceptable

items,

Items of Noncompliance,

or Deviations.

Two Unresolved

Items dis"

closed during the inspection were discussed

in Paragraph

3 and 7.

9.

Exit Interview

The inspector

met with licensee

representatives

(denoted in Paragraph

1) at the conclusion of the inspection

on December

14,

1979.

The

inspector

summarized

the purpose

and the scope of the inspection

and

the findings.