ML17312A896

From kanterella
Jump to navigation Jump to search
Insp Repts 50-528/96-11,50-529/96-11 & 50-530/96-11 on 960602-0713.Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maintenance & Plant Support
ML17312A896
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 07/26/1996
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML17312A893 List:
References
50-528-96-11, 50-529-96-11, 50-530-96-11, NUDOCS 9608060114
Download: ML17312A896 (37)


See also: IR 05000528/1996011

Text

ENCLOSURE

2

U.S.

NUCLEAR REGULATORY COMMISSION

REGION IV

Docket Nos.:

License Nos.:

Report No.:

Licensee:

Facility:

Location:

Dates:

Inspectors:

Approved By:

50-528

50-529

50-530

NPF-41

NPF-51

NPF-74

50-528/9611

50-529/9611

50-530/9611

Arizona Public Service

Company

Palo Verde Nuclear Generating

Station,

Units 1,

2,

and

3

5951

S. Wintersburg

Road

Tonopah,

Arizona

June

2 through July 13,

1996

K. Johnston,

Senior Resident

Inspector

J.

Kramer,

Resident

Inspector

D. Garcia,

Resident

Inspector

D. Carter,

Resident

Inspector

D.

F. Kirsch, Chief, Reactor Projects

Branch

F

ATTACHMENTS:

Attachment

1:

Partial List of Persons

Contacted

List of Inspection

Procedures

Used

List of Items Opened,

Closed,

and Discussed

List of Acronyms

9608060ii4 960726

PDR

ADOCK 05000528

6

PDR

I

f

I

EXECUTIVE SUMMARY

Palo Verde Nuclear Generating Station,

Units 1, 2,

and

3

NRC Inspection

Report 50-528/9611;

50-529/9611;

50-530/9611

This integrated

inspection

included aspects

of licensee

operations,

engineering,

maintenance,

and plant support.

The report covers

a 6-week

period of resident

inspections.

~0erations

~

Operators

exhibited strong performance

in response

to

a main turbine

electro-hydraulic control

(EHC) fluid leak

and in the subsequent

restart

of the main turbine.

The reactor operator dedicated

to board monitoring

was well focused during the turbine startup.

Additionally, there

was

good management

and nuclear

assurance

oversight of startup activities

(Section 01.2).

A Unit

1 Auxiliary Operator

(AO) was observed

during routine rounds

conduc'ting thorough checks of plant equipment,

appropriate

reviews of

equipment clearances,

and demonstrated

excellent

knowledge of plant

radiological conditions

(Section 01.3).

Unit 2 operations'ad

not demonstrated

an adequate

understanding

and

ownership of the Qualified Safety Parameter

Display System

(QSPDS)

(Section

04. 1).

Maintenance

Maintenance

personnel

responded

promptly and thoroughly in their

evaluation of an

EHC line leak in Unit 3.

Additionally, the licensee

initiated appropriate

corrective actions

aFter vibration monitoring data

collection efforts inadvertently

caused

a turbine control valve to close

(Section M1.3).

~

Mechanical

maintenance

personnel

demonstrated

excellent maintenance

and

radiological protection practices

during the performance of work on the

Unit 3 high pressure

safety injection (HPSI) system

(Section M1.4).

En ineerin

~

Instrumentation

and Controls

(I&C) maintenance

engineering

had not

developed

a comprehensive

plan to address

longstanding

QSPDS

deficiencies.

As

a result,

communications

with other organizations

was

weak

and available resources

were not adequately

focussed

to resolve the

problem (Section

M6. 1).

~

A violation was identified concerning

the failure of I&C maintenance

engineering

to follow procedures

for the performance of a

10 CFR 50.59

f

screening

evaluation for a plant change.

Maintenance

engineering

had

not recognized that

a change

made to the

(ISPDS involved

a change

to the

facility as described

in the licensing basis

(Section

E3. 1).

Plant

Su

ort

~

Radiation protection

(RP) staff demonstrated

very good performance

in

their support of maintenance

activities conducted

on the Unit 3 Train A

HPSI system

(Section

R4. 1).

~

A violation was identified concerning

the failure to perform

a search of

personnel

and

hand carried

items using screening

equipment prior to

being allowed access

to the protected

area

(PA) (Section Sl. 1).

I

N

i

Re ort Details

Summar

of Plant Status

Unit

1 began

the inspection period at

100 percent

power.

On July 4, the unit

reduced

power to 88 percent to perForm maintenance

on turbine Control Valve 4.

The unit returned to

100 percent

power the

same

day

and operated

at

essentially

100 percent

power for the duration of the inspection period.

Unit 2 operated

at essentially

100 percent

power for the duration of the

inspection period.

Unit 3 began

the inspection period at

100 percent

power.

On June

10, the

operators

reduced

power to 30 percent

and manually tripped the turbine due to

an

EHC oil leak

on Control Valve 4.

On June

11, the unit returned to

100 percent

power.

On June

25, operators

manually tripped the turbine from

essentially

100 percent

power 'due to another

EHC oil leak in the

same vicinity

as the previous leak.

On June

27, the unit returned to 100 percent

power

and

remained

at essentially

100 percent

power for the duration of the inspection

period.

Ol

Conduct of Operations

01.1

General

Comments

71707

4

Using Insp'ection

Procedure

71707,

the inspectors

conducted

frequent

reviews of ongoing plant operations.

In general,

the conduct of

operations

was professional

and safety conscious.

Specific events

and

noteworthy observations

are. detailed

in the sections

below.

In

particular,

the inspectors

noted that the philosophy of a dedicated

board monitor, free from the distractions of ongoing surveillance

and

maintenance

support activities,

had

been

applied consistently

in all

units.

01.2

0 erator

Performance

Durin

Hain Turbine Transient

Unit 3

, a.

Ins ection

Sco

e

71707

and

92703

On June

25, Unit 3 experienced

a

EHC oil leak and

a manual turbine trip.

The inspectors'esponded

to the control

room to access

the plant

and

operator

response.

On June

26, the inspectors

observed

the Unit 3

operators

perform the startup of the main turbine.

b.

Observations

and Findin

s

On June

25, operators

received

a low EHC level alarm in the control

room

and dispatched

an

AO to investigate.

The

AO reported

a large leak in

turbine Control Valve

4 and

no oil level indication in the

EHC tank.

Control

Room operators initiated

a manual trip of the turbine

and

stabilized the plant at approximately

30 percent

power.

e

'C)

e

On June

26, the inspectors

observed

the Unit 3 operators

perform the

startup of the main turbine

and observed

good communications

and

procedure

compliance.

Appropriate management

and nuclear assurance

oversite

was evident during the startup.

The reactor

operator dedicated

to board monitoring remained

focused

on the monitoring and

was not

distracted

by the turbine startup activities.

The shift supervision

limited the activities in the control

room.

C.

Conclusions

01.3

a.

Operators

exhibited strong performance

in response

to the main turbine

EHC fluid leak

and in the subsequent

start of the main turbine.

The

reactor operator dedicated

to board monitoring was well focused during

turbine startup,

Additionally, there

was

good management

and nuclear

assurance

oversight of startup activities.

Ins ection

Sco

e

71707

b.

On July 2, the inspectors

accompanied

an area operator during the

performance of Procedure

40DP-90PA3,

"Area 3 Operator

Logs,

Modes 1-4,"

Revision 8.

In addition,

the inspectors

observed

the

AO perform

clearances

and perform

a charging

pump start in accordance

with

410P-ICH01,

"CVCS Normal Operations,"

Revision

21.

Observations

and Findin

s

The inspectors

observed

the

AO performance

entering the radiological

controlled area

and noted that the

AO was very knowledgeable of the

plant radiological conditions of the auxiliary building.

The

AO

properly performed the equipment

checks

required

by

Procedure

40DP-90PA3.

During the plant tour, the

AO performed

additional

checks of the plant equipment in the areas

and documented

equipment discrepancies.

The

AO utilized closed

loop communications

when conversing with the control

room.

The

AO properly verified the

position clearance

components

using multiple indications

and correctly

used

Procedure

410P-1CH01 to perform the charging

pump prestart

and

after-start

checks'onclusions

The

AO conducted

thorough

checks of plant equipment,

appropriate

reviews

of equipment clearances,

and demonstrated

excellent

knowledge of plant

radiological conditions.

e

(

i

I

e

04

Operator

Knowledge

and Performance

04.1

0 erations

Understandin

and Ownershi

of

SPDS

Problems

Unit 2

71707

Unit 2 operations

had not demonstrated

adequate

understanding

and

ownership of gSPDS.

Operations

management

responded

aggressively

to

resolve

the associated

issues.

Further aspects

of this issue

are

discussed

in Section

H6. 1.

-68

Miscellaneous

Operations

Issues

08. 1

Review of Institute of Nuclear

Power

0 erations

INPO

Evaluation

71707

The inspectors

reviewed the March,

1996

INPO evaluation report which

covered

a site evaluation

performed in October,

1995.

The inspectors

found that the evaluation

was consistent

with recent

NRC perception of

the licensee's

performance

and did not identify any areas

which

substantially

deviated

from NRC perceptions.

II.

Maintenance

Hl

Conduct of Maintenance

Ml. 1

General

Comments

on Maintenance Activities

a.

Ins ection

Sco

e

62703

The inspectors

observed all or portions of the following work

activities:

WO 737994

WO 755569

Clean

and Inspect Essential

Spray

Pond

Pump

A Sliding

Screen

(Unit 2)

Replace

the

9R Emergency

Diesel

Generator

Injection

Pump Delivery Valve (Unit 1)

b.

Observations

and Findin

s

The inspectors

found these

work activities were performed in accordance

with procedures.

In addition,

see the specific discussions

of

maintenance

observed

under Sections

H1.3

and H1.4.

I

H1.2

General

Comments

on Surveillance Activities

a.

Ins ection

Sco

e

61726

The inspectors

observed all or portions of the following surveillance

activities:

41ST-IDG01,

Revision 25, Diesel

Generator

A Test (Unit 1)

72ST-9RX02,

Revision 9, Moderator Temperature

Coefficient at

Power

(Unit 2)

73ST-9CL03',

Revision 8, Containment

Personnel

Air Lock Seal

Leak

Rate Testing (Unit 3)

b." Observations

and Findin

s

The inspectors

found these

surveillances

were performed

as specified

by

applicable

procedures.

Hl.3

Troubleshootin

of EHC Line Failures

Unit 3

a.

Ins ection

Sco

e

62703

The inspectors

reviewed the licensee

repairs of the

EHC oil leaks

and

corrective actions.

b.

Observations

and Findin

s

On June

9,

a crack developed

in the

EHC piping for turbine Control

Valve 4.

The licensee initiated corrective actions to repair the

cracked

EHC piping and

a condition report/disposition report

(CRDR) to

evaluate

the

EHC piping for potential cyclic fatigue failure.

On

June

25,

a crack occurred in the

same vicinity as

a previous

EHC piping

leak.

The licensee initiated another

CRDR to identify the root cause of

the cracking to prevent reoccurrence.

The licensee

sent the failed

section of

EHC piping offsite for analysis to determine

the failure

mechanism.

In addition,

the licensee

replaced

several

servo-control

and

logic cards for Control Valve 4 in an attempt to reduce the vibrations

generated

by the valve.

The inspectors

found these corrective actions

to be appropriate.

On July 1,

as part of the corrective actions,

a vibration technician

used

a magnetic

probe to obtain readings

on the Control Valve

4 servo,

causing

the control valve to shut for approximately

35 seconds.

The

control valve closing induced

a power oscillation of approximately

5 percent.

The licensee initiated

a

CRDR to evaluate

the event.

The

licensee

advised other vibration technicians of the event

and planned to

issue

a

"NEWS FLASH" to inform all employees of the effect of using

magnets

near servos.

The Maintenance

Director stated that the magnetic

effect

on servos

was not well understood

throughout the industry

and

that

he planned to forward information on this event to industry.

The

inspectors

found these corrective actions to be appropriate.

c.

Conclusions

Maintenance

personnel

responded

promptly and thoroughly in their

evaluation of an

EHC line leak in Unit 3.

Additionally, the licensee

initiated appropriate corrective actions after vibration monitoring data

collection efforts inadvertently

caused

a turbine control valve to

close.

Ml.4 "Corrective Maintenance

Performed

on Train

A HPSI

S stem

Unit 3

a,

Ins ection

Sco

e

62703

On July 10, the inspectors

observed

the portions of the following work

activities involving the Train A HPSI.

~

WO 743571

Rework and Replacement

of Valve SIA-HV-0698 Stem

and

Bonnet

~

WO 730319

Removal

and Engineering

Inspection of Flow Orifice

SIA-P02

~

WO 752525

Sampling of Oil and the Installation of Oil Sample

Ports for the Motor Bearings

In addition,

the inspectors

discussed

the work activities with

maintenance

technicians

and

RP personnel.

b.

Observations

and Findin

s

The inspectors

obse'rved that the maintenance

activities were performed

with the work packages

present

and in active use.

The maintenance

technicians

exhibited detailed

knowledge of the valve's construction

and

repair.

The technicians

demonstrated

good radiation worker practices

during all aspects

of the job.

Maintenance

supervisors

frequently

monitor the job progress.

During the installation of an oil sample port, the

head of the old oil

plug broke off.

The maintenance

technician

stopped

the activity and

discussed

the problem with supervision.

The technician properly

obtained

an

amendment

to the work package

to remove the

damaged

plug and

complete the job.

e

RP technicians

demonstrated

very good supervision

oF radiological

controls throughout the job.

They ensured

face shields

were worn when

required

and allowed the technicians

to remove the shields

when

contamination levels decreased.

RP technicians

performed air samples of

the work area during packing

removal

and

when the system

was breached,

and ensured

the work area

remained wetted to prevent contamination

from

becoming airborne.

RP te'chnicians

ensured

that tools were wiped clean

throughout the job and that torque wrenches

were prewrapped

to prevent

the spread of contamination.

Conclusions

Mechanical

maintenance

personnel

demonstrated

excellent maintenance

and

RP practices

during the performance of work on the Unit 3 HPSI system.

Maintenance

Organization

and Administration

I&C Maintenance

Troubleshootin

of

SPDS

Problems

Unit 2

Ins ection

Sco

e

62703

During the inspection period,

I&C maintenance

performed troubleshooting

of the Unit 2 Channel

A gSPDS.

The inspectors

reviewed the operating

history of the Channel

A gSPDS,

discussed

troubleshooting efforts with

I&C maintenance

and Unit 2 operations,

and reviewed associated

work

documentation.

Observations

and Findin

s

~Back round

The inspectors

reviewed the system description

manual

and the design

basis

manual for the

gSPDS.

The

gSPDS consists

of two redundant

Class

IE channels,

seismically qualified, electrically and physically

independent for the continuous display of safety parameters

which

provide indication of the thermal-hydraulic states within the reactor

pressure

vessel

during the approach to, the existence of,

and the

recovery from inadequate

core cooling (ICC).

The

ICC signals

are

processed

by system microprocessors

into three parameters:

~

margin to saturation

(subcooled

margin)

~

reactor vessel

water level

~

reactor core exit temperature

Each

gSPDS

channel

is comprised of three chassis

containing

ICC

instrumentation.

The

ICC instrumentation

consi'sts of hot-leg

and

cold-leg resistance, temperature

detectors,

pressurizer

pressure

sensors,

core exit thermocouples

(CETs)

and reactor vessel

level monitoring

system

(RVLMS) probes

employing the heated junction thermocouple

heater

Il

I

~t

L

I

t

f

(

i

controllers.

Each channel of QSPDS receives

two sets of CET data,

one

which is directly fed to the main

QSPDS computer

and the other which is

processed

through

a fiber optic isolation device.

Together both

channels of QSPDS process

a total of 61

CET temperatures.

The inspectors

determined that for the past year,

the Unit 2 Channel

A

QSPDS

had sporadically displayed

suspect

and out-of-range data for

some

or all of the

CETs in Channel

A.

Additionally, the Channel

A QSPDS

would periodically lock up, requiring manual

operator action to reset

the system.

IKC technicians

established

that the most likely source of these

problems was,'rom the Chassis

C, which provides

16 optically isolated

CET inputs to the Channel

A QSPDS.

On Hay 31,

1996,

as part of the

troubleshooting efforts,

ISC technicians

removed the field inputs from

Chassis

C and operated

the Channel

A QSPDS without 16

CET inputs.

On

June

4,

18C technicians

installed

a spare

chassis

in place of Chassis

C

in order to determine if the problem was isolated to the installed

Chassis

C.

The spare

chassis

was mounted

on

a cart

and

was not

-considered

to meet seismic

and quality requirements.

Between

June

4-June

21,

ILC technicians

placed the spare/test

chassis

in service

on Tuesdays

and disconnected it on Fridays'hile the spare

chassis

was

in service,

operators

considered

that Channel

A of QSPDS

was inoperable.

On June

21, operations

performed

an operability determination

which

considered all of the Channel

A QSPDS operable,

with the exception of

its

CET functions,

when the spare

chassis

was in service.

Technical Specification (TS) 3.3.3.6,

"Post-Accident Monitoring

Instrumentation,"

Table 3.3-10,, provided requirements for QSPDS

instrumentation.

The table required four operable

CETs per core

quadrant

as the limiting condition for operation

(LCO).

The licensee

considered

that this

LCO was met during the troubleshooting efforts

on

the Channel

A QSPDS since .the

30

CET inputs to the Channel

B QSPDS

provided at least four operable

CETs per core quadrant.

Action 29 of Table 3.3-10,

which applied to all the postaccident

monitoring instrumentation with the exception of RVLHS, established

a

7-day allotted out-of-service limit, with a subsequent

shutdown action,

if one channel

was inoperable.

With two channels

out of service,

Action

30 of Table 3.3-10 reduced

the allowed out-of-service limit to 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />.

Actions 31

and

32 of Table 3.3-10 applied to

RVLMS and included similar

allowed out-of-service limits.

However, the subsequent

action

was

limited to

a report to the Commission.

TS

Com liance

and Unit Lo

Entries

The inspectors

reviewed the TS, unit log entries,

and discussed

the

QSPDS configuration with operations

personnel.

On June

14, the

inspectors

noted that the licensee

had entered

Action 29 of Table 3.3-10

and questioned

the reason with the Unit 2 control

room supervisor

(CRS).

~

~

The

CRS stated that

he was not'lear

why the action

had

been entered.

The

CRS noted that the

TS action statement

For the minimum number of

CET's required

had not been affected

and stated that the entry into

Action 29 appeared

to have

been

a conservative

interpretation.

The

CRS

did not recognize that the entire

Channel

A of gSPDS

was considered

inoperable with the test chassis

installed, requiring entry into both

Action 29 and

31 of TS Table 3.3-10,

The inspectors

found that the

CRS

did not have

a clear understanding

of the

gSPDS configuration

and the

impact it had

on applicable

TS actions.

During subsequent

reviews,

the inspectors

noted that, with the test

chassis

placed in service

and the Channel

A gSPDS inoperable,

operations

personnel

had consistently

entered

TS Table 3.3-10, Action 29'he

inspectors

questioned

a Unit 2 shift supervisor regarding whether

any

other

TS Table 3.3-10 instrumentation

was affected with the Channel

A

gSPDS inoperable.

The shift supervisor

reviewed the configuration

and

the

TS requirements

and determined that Action 31,

as it pertained

to

the

RVLMS instrumentation,

was also applicable.

The inspectors

performed

a review of the Unit 2 control

room log from

May 27 through June

18.

The'nspectors

determined that during this

period, operation

crews

had not consistently

logged the entry of Action

31 when Channel

A of gSPDS

was

made inoperable.

The inspectors

determined that the inconsistencies

were the result of operators

having

a weak understanding

of the

TS action statements

applicable to gSPDS.

The inspectors

noted that in al,l cases,

the more conservative

Action 29

was entered

and

an out-of-service limit was never exceeded.

The inspectors

also found that the Unit 2 log entries

were not

adequately descriptive

and the inadequacies

in the log entries

made it

difficult to assess

the system configuration,

given the fact that the

test chassis

had

been installed

and

removed several

times.

Th'e

TS action entries

and inconsistent

log entries

were discussed

with

the Unit 2 operations

department

leader.

The department

leader stated

that the log entries

had not met his management's

expectations.

The

department

leader stated that operators

in all units would be provided

additional

guidance

on expectations

for logkeeping

and the operation of

gSPDS.

Based

on these findings, the inspectors

concluded that Unit 2 operations

had not demonstrated

adequate

understanding

and ownership of the

gSPDS.

However, operations

management

responded

aggressively

to the

inspectors'oncerns.

In addition, operations

identified weaknesses

in their action

to reset

the

gSPDS

and that the system

had not been alarming for system

malfunctions

as described

in the design basis.

IKC Maintenance

Mana ement of

SPDS

Problems

4

During the week of June

18, operations

requested

that

I&C maintenance

engineering

leave the test chassis

in continued service

and develop the

basis to allow Channel

A gSPDS to be declared

operable.

With technical

input from I&C maintenance

engineering,

operations

developed

an

operability determination

and,

on June

21, declared

Channel

A gSPDS

operable with the test chassis

installed.

The inspectors

reviewed the

operability determination

and noted that it relied

on the following

factors:

The link between

Chassis

C and the

gSPDS computer

was through

a

fiber optic modem link which acted

as

an isolation device.

The Channel

A CET data

and information derived from the data would

not be used

and

was not necessary

for operability.

I&C maintenance

engineering

had performed

a

10 CFR 50.59

evaluation.

The inspectors

reviewed the

10 CFR 50.59 screening

and evaluation

performed

by I&C maintenance

engineerin'g

on June

21,

and determined that

the screening failed to identify this

as

change to the facility as

described

in the licensing basis.

Combustion

Engineering

Standard

Safety Analysis Report,

Chapter

17,

Appendix B, "Address of Three Nile Island Action Plan Requirements,"

Table 3-2, "Evaluation of ICC Detection Instrumentation,"

stated that

the plant design

had

61

CETs

and that, together,

both channels

of gSPDS

could display all

CET temperatures.

The inspectors

determined that,

with the test chassis

installed,

only 45

CETs were displayed

and that

this was

a change to the facility as described

in the licensing basis.

As

a result,

the

I&C maintenance

engineering

had not performed

a review

sufficient to determine if the change

involved an unreviewed safety

question

as required

by 10 CFR 50.59 for changes

to the facility

described

in the safety analysis report.

The failure to follow

procedures

for 10 CFR 50.59 screenings

is

a violation (50-529/96011-01).

The inspectors

discussed

the

10 CFR 50.59 screening with the

I&C

maintenance

engineering

section leader.

The section leader

agreed with

the inspectors'onclusion

and stated that the

10 CFR 50.59 screening

and evaluation

would be performed.

On June

25, the inspectors

determined that

I&C maintenance

engineering

had not completed

the additional

10 CFR 50.59 evaluation.

Therefore,

from June

21-25, operations

had not been

aware that the

10 CFR 50.59

evaluation,

that

had

been the basis for the Channel

A gSPDS operability

evaluation,

was not valid.

I&C maintenance

engineering

subsequently

completed

the evaluation

and determined that the change

had not involved

an unreviewed safety question.

The inspectors

discussed

this example of

weak interorganizational

communications

with both the Unit 2 operations

0

r

f

0

-10-

C.

department

leader

and the

I&C maintenance

department

leader.

The

licensee

subsequently

initiated

a

CRDR and

an evaluation of I&C

maintenance

engineering

performance.

The

I&C maintenance

department

leader recognized that the

gSPDS

has

had

multiple problems

impacting both the reliability and availability of the

system.

The department

leader

noted that

I&C maintenance

had

experienced

problems resolving

system design

issues

with the system

vendor

and that considerable

time and

I&C department

resources

had

been

expended

on the Unit 2 Channel

A gSPDS

problems.

This issue

had not

been'ocumented

in the form of a

CRDR or in any other way to ensure site

attention,

such

as including it as

an engineering

issue or as department

"Level

1" action.

The"inspectors

concluded that this

may have

impacted

the quality of communications

between organizations

and contributed to

the issues

discussed

in this report.

Subsequently,

I&C maintenance

initiated

a department

"Level

1" action'o

address

the performance of the Unit 2 gSPDS.

In addition,

I&C

maintenance

established

frequent meetings

between operations,

computer

services,

I&C maintenance,

and the engineering

organization to develop

and implement

a troubleshooting

plan.

The inspectors

found these

planned actions to be appropriate.

Conclusions

A violation was identified concerning

the failure of I&C maintenance

engineering

to follow procedures

for the performance of a

10 CFR 50.59

screening

evaluation for a plant change.

Naintenance

engineering

had

not recognized that

a change

made to the

gSPDS involved

a change to the

facility as described

in the licensing basis.

I&C maintenance

had not

developed

a comprehensive

plan to address

longstanding

gSPDS

deficiencies.

As

a result,

communications with other organizations

were

weak

and available resources

had not been

focused to resolving the

problem.

Unit 2 operations

had not demonstrated

adequate

understanding

and ownership of gSPDS troubleshooting efforts.

Operations

management

responded

aggressively

to the inspectors'oncerns.

III.

En ineerin

E3

E3.1

Engineering

Procedures

and Documentation

Facilit

Chan

e Performed Without Performin

Unreviewed Safet

uestion

Review

37551

A violation was identified concerning the failure of I&C maintenance

engineering

to follow procedures

for the performance of a

10 CFR 50.59

screening

evaluation for a plant change.

Maintenance

engineering

had

not recognized that

a change

made to the

gSPDS involved

a change to the

facility as described

in the licensing basis.

Further aspects

of this

issue

are discussed

in Section

H6. 1.

e

-11-

E8

E8.1

Miscellaneous

Engineering

Issues

(92903)

Closed

Unresolved

Item 50-528 95021-02:

accident condition identified

puts auxiliary feedwater

beyond

component level design basis.

The

licensee

completed

the evaluation of this item and issued

Licensee

Event

Report 50-528/95-13,

dated

December

31,

1995, to describe

the

significance,

cause,

and corrective actions for the item.

Followup

inspection for the licensee

event report will resolve

any outstanding

issue

associated

with this item.

IV.

Plant

Su

ort

R4

R4.1

Staff Knowledge

and Performance

in Radiological Protection

and Chemistry

RP Staff Performance

Durin

Maintenance Activities

71750

On July 10, the inspectors

observed

the

RP staff during work activities

involving the Unit 3 HPSI system.

The

RP staff demonstrated

very good

performance

in their support of the maintenance activities.

Further

aspects

of the maintenance activities

and

RP practices

are discussed

in

Section

M1.4.

S1

0

si.i

Conduct of Security

and Safeguards

Activities

Material Enterin

the

PA Without Pro er Search

a

~

Ins ection

Sco

e

71750

b.

On July 3,

1996, the inspectors

observed

an individual

and the

hand

carried

items,

proceed

into the

PA without

a search.

The inspectors

discussed

these

observations

with the security force

and with security

management.

Ob'servations

and Findin

s

The licensee's

security search train at the main personnel

access

for

entry to the

PA consisted

of metal detectors for personnel,

x-ray

machines for hand carried items,

and nitrate detectors

for both.

On

July 3, the inspectors

observed

a janitor proceed

from inside the

PA,

through the search train area,

to

a waste container outside the search

train.

The janitor then collected the waste liner and its contents

and

proceeded

back inside the

PA without processing either herself or the

waste through

search train equipment.

The inspectors

asked

a security officer, who had

been

posted

nearby -the

waste container, if he

had observed

the janitor's actions

and if these

actions

were appropriate.

The security officer confirmed the

inspectors'bservations.

The security officer indicated that the

container

had, within the past

10 minutes,

been

moved from a location

under the x-ray machine to

a location outside the search train.

The

't

-12-

security ofFicer also noted that the waste container

had

been

under his

observation

and

was able to itemize the contents.

The security officer

indicated that the actions of the janitor to bypass

the search train

when collecting waste

was

a

common practice

and did not see it as

inappropriate.

The inspectors

discussed

this observation with the security shift

sergeant.

The security shift sergeant

also noted that what had

been

observed

was standard

practice.

The sergeant

concluded,

however, that

it would have

been appropriate

to either

have the contents

screened

or

to have

a janitor remove waste inside security headquarters

to directly

outside the

PA.

In response

to the inspectors'oncerns.

that material

could

be introduced into the

PA without a proper search,

the security

shift sergeant

initiated action to have the waste containers

emptied to

outside the

PA.

The inspectors

subsequently

determined,

through interviews with security

and janitorial personnel,

that it was standard

practice for the

janitorial staff to process

through the search train equipment prior to

initial entry into the

PA.

The janitorial staff would then proceed to

a

supply closet in the

PA portion of the security headquarters

building to

collect cleaning supplies,

then proceed

out of the

PA onto the floor of

the search train,

and perform cleaning activities.

The janitorial staff

would then reenter

the

PA without

a search of themselves

or hand carried

cleaning supplies,

Security management

had established

the position

that while the janitorial staff was in the search train area they were

under the direct observation of security officers and, therefore,

did

not require

a search prior to reentry into the

PA.

The inspectors

reviewed the security plan

and security procedures.

Both

the security plan, in paragraph

5.3.2

and 5.3.7;

and

PA ingress

Procedure

20DP-OSK22,

Revision 8, in Paragraph

3.2. 1.4, required that

personnel

and

hand carried

items

be properly searched

through the search

train equipment prior to admittance to the

PA.

The inspectors

determined that the janitor had not complied with these

requirements.

The inspectors

discussed

this determination with the Director of Site

Security.

The Director of Site Security stated that it was the

licensee's

position that both the janitor and the waste container

had.

been

under constant

observation

by security personnel

and that this was

a standard

practice.

The director indicated that this practice

was

consistent

with the security plan exemption of a search of a vehicle

reentering

the

PA if it had

been

accompanied

by an

armed security

officer.

The inspectors

were concerned that Security management's

position that

the janitorial staff would be under constant

observation while cleaning

the search train could detract

from the principal duties of the security

officers to monitor ingress

screening.

Conversely, if the security

officer was distracted

by his/her principal duties,

an opportunity was

0

-13-

created for items to be introduced into the

PA undetected

on the person

of the janitorial staff or. their equipment.

The inspectors

agreed

that

the security plan provided

a few specific exemptions

to

a search prior

to entry into the

PA.

These

exemptions

were specific

and highlighted

special

circumstances.

The practice

employed for the janitorial staff

was not discussed,

either specifically or in general,

in the security

plan or security procedures.

The failure of the janitor to follow

security procedures

for searches

prior to entering the

PA is

a violation

(50-528;529;530/96011-02).

c.

Conclusions

A violation was identified concerning

the failure to perform

a search of

personnel

and

hand carried

items using screening

equipment prior to

being allowed access

to the

PA.

V. Nana

ement Heetin

s

'l

Exit meeting

Summary

The inspectors

presented

the inspection results

to members of licensee

management

at the conclusion of the inspection

on July ll, 1996.

The licensee

acknowledged

the findings,presented.

The inspectors

asked

the licensee

whether

any materials

examined during the

inspection

should

be considered

proprietary.

Ho proprietary inFormation

was

identified.

e

'e

ATTACHMENT I

PARTIAL LIST OF

PERSONS

CONTACTED

Licensee

T. Cannon,

Department

Leader,

Engineering

R. Flood, Department

Leader,

System Engineering

D. Gouge,

Department

Leader,

Maintenance

Services

B. Grabo,

Section

Leader,

Nuclear Regulatory Affairs

J.

Hesser,

Director, Nuclear Engineering

L. Houghtey, Director, Security

W. Ide, Director, Operations

A. Krainik, Department

Leader,

Nuclear Regulatory Affairs

J.

Levine, Vice President,

Nuclear Production

D. Mauldin, Director, Maintenance

R. Myrick, Department

Leader,

I&C Maintenance

G. Overbeck,

Vice President,

Nuclear Support

C.

Seaman,

Director, Nuclear Assurance

W. Stewart,

Executive Vice President

fi

e

e

IP 37551:

IP 61726:

IP 62703:

IP 71707:

IP 71750:

IP 92703:

IP 92903:

~0ened

INSPECTION

PROCEDURES

USED

Onsite Engineering

Surveillance

Observations

Maintenance

Observations

Plant Operations

Plant Support Activities

Followup of Confirmatory Action Letters

Followup - Engineering

ITEMS OPENED

CLOSED

AND DISCUSSED

50-529/96011-01

VIO

failure to follow 10 CFR 50.59 screening

procedures

50-528;529;530/96011-02,VIO

failure of a janitor to follow security

procedures

Cl osed

50-528/95021-02

URI

condition potentially outside design

basis

which

could lead to turbine driven

AFW pump tripping

on'verspeed

E

AO

CESSAR

CET

CRDR

CRS

EHC

HPSI

IKC

ICC

INPO

LCO

PA

gSPDS

RP

RVLNS

TS

LIST OF ACRONYHS USED

Auxiliary Operator

Combustion

Engineering

Standard

Safety Analysis Report

Core Exit Thermocouples

Condition Report/Disposition

Request

Control

Room Supervisor

Electro-hydraulic Control

High Pressure

Safety Injection

Instrumentation

and Controls

Inadequate

Core Cooling

Institute of Nuclear

Power Operations

Limiting Condition for Operation

Protected

Area

gualified Safety Parameter

Display System

Radiation Protection

Reactor

Vessel

Level Monitoring System

Technical Specifications