ML17305A510

From kanterella
Jump to navigation Jump to search
Insp Repts 50-528/89-50,50-529/89-50 & 50-530/89-50 on 891113-1217.Violations Noted.Major Areas Inspected:Esf Sys Walkdowns,Plant Activities,Previously Identified Items, Monthly Surveillance Testing & Monthly Plant Maint
ML17305A510
Person / Time
Site: Palo Verde  
Issue date: 01/19/1990
From: Wong H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML17305A508 List:
References
50-528-89-50, 50-529-89-50, 50-530-89-50, NUDOCS 9002140011
Download: ML17305A510 (56)


See also: IR 05000528/1989050

Text

U.

S.

NUCLEAR REGULATORY COMMISSION

REGION V

Re ort Nos.

Docket Nos.

License

Nos.

Licensee:

Facilit

Name:

50-528/89-50,

50-529/89-50,

50-530/89-50

50-528,

50-529,

50-530

NPF-41,

NPF""51,

NPF-74

Arizona Nuclear Power Project

P.

0.

Box 52034

Phoenix,

AZ, 85072-2034

Palo Verde Nuclear Generating Station

Units 1, 28

3

Ins ection Conducted:

November

13 through

December

17,

1989

Inspectors:

Approved By:

T. Polich, Senior Resident Inspector

D.

Coe,

Resident

Inspector

J.

Ringwald, -Resident Inspector

J.

Sloan,

Resident

Inspector

W. Wagner,

Reactor Inspector

T. Meadows,

License

Examiner

W. Ang,

roject Inspector

ong,

ie

Reactor Projects

Section II

/ /$~

a

e

igne

Ins ection

Summar

Ins ection on November

13 throu

h December

17

1989

(Re ort Nos.

an

Areas Ins ected:

Routine, onsite,

regular

and backshift inspection

by the

our ress

en

inspectors.

Areas inspected

included: previously identified

items; review of plant activities; engineered

safety feature

system walkdowns;

monthly surveillance testing;

monthly plant maintenance;

sign-offs not made

as

maintenance

was performed - Unit 1; misplacement of fuel assembly

event - Unit

1; stuck fuel assembly - Unit 1; wrong assembly

grappled=and lifted in the

spent fuel pool - Unit 1; unofficial procedure

change - Unit 1; incorrect

clearance

- Unit 1; reactor- coolant system

heatup rate limit exceeded

- Unit

2

refueling water tank makeup water spills - Unit 2; reactor startup - Unit

2; auxiliary feedwater

pump pressure

pulsations - Unit 3; missing handwheels

on downcomer feedwater isolation valves - Unit 3; allegation followup; review

of licensee

event reports - Units 1,

2 and 3; and review of periodic and

special

reports - Units 1,

2 and 3.

During this inspection the following Inspection

Procedures

were utilized;

30702,

30703,

40500,

60705,

60710,

61726,

62703,

71707,

71720,

92700,

92701,

and 93702.

Safet

Issues

Mana ement

S stem

(SIMS

Items:

NONE

Results:

Of the nineteen

areas

inspected,

two violations were identified.

Tfie 7>rst violation is for failure to follow procedures.

Electricians

performing work, with a equality Control inspector in attendance,

failed to

signoff work order steps

during the conduct of maintenance

at Unit 1.

The

second violation is for issuing directions for core reload which contained

an

error

and resulted in placing a new fuel assembly into other than its analyzed

location.

General

Conclusions

and

S ecific Findin s:

Si nificant Safet

Matters:

NONE

Summar

of Violations:

Summar

of Deviations:

0 en Items

Summar

TWO violations

NONE

8 items closed

and

2 new items opened.

DETAILS

V

Persons

Contacted:

The below listed technical

and supervisory personnel

were

among those

contacted:

Arizona Nuclear Power Pro ect

ANPP

  • R.

J.

J.

B.

H.

T.

Ap

kp

AW

  • D

p.

W.

J.

J.

J.

+W.

  • T

Adney,

Al 1 en,

Bailey,

Ballard,

Bieling,

Bradish,

Brandjes

Caudill,

Conway,

Heinicke

Hughes,

Ide,

Kirby,

Levine,

LoCicero

Marsh,

Cogbur n,

Rouse,

Russo,

Shell,

Shriver,

Sowers,

Taufiq,

Willsey,

Younger,

  • R.

C.

G.

T.

  • G
  • A.

)kN

R.

J

Plant Manager, Unit 3

Engineering

8 Construction Director

Vice President,

Nuclear Safety

8 Licensing

equality Assurance

Director

Emergency Plan/Fire Protection

Manager

Compliance Supervisor

Central

Maintenance

Manager

Site Services Director

Executive Vice President - Nuclear

Plant Manager,

Unit 2

Radiation Protection

8 Chemistry Manager

Plant Manager,

Unit 1

Nuclear Production Support Director

Vice President,

Nuclear Power Production

Independent

Safety Engineering

Manager

Plant Director

(Acting) Standard

and Tech.

Support Director

Lead Compliance

Engineer

Assistant

equality Assurance

Director

equality Systems

Manager

Compliance

Manager

Engineering Evaluations

Manager

Independent

Safety Engineering Senior Engineer

(Acting) Emergency

Planning

and Fire Protection

Plant Standards

and Control Manager

Manager

The inspectors

also talked with other licensee

and contractor personnel

during the course of the inspection.

Attended the Exit meeting held with NRC Resident

Inspectors

on

December 27,

1989.

Previousl

Identified Items - Units 1

2

and

3 (92701

92702)

a,

(Closed

Information Notice

IN-88-47: "Slower Than

Ex ected

Rod

ro

>mes.

The inspector

reviewed licensee

procedure

73ST-9RXOl,

"CEA Drop

Time," with respect to the licensee's

commitment, per

NRC Inspection

Report 528/89-36, to account for the increase

in CEA drop time due

to the testing methodology.

The inspector

noted the acceptance

criteria had been adjusted

accordingly

and observed

the performance

of a portion of the surveillance test,

the results of which appeared

'I

b.

to meet the

new criteria,

based

on preliminary review.

The

inspector

had

no further questions-.

This item is closed.

Closed

Unresolved

Item (528/89-49-03

"Remote

Shutdown

Room

ommunsca

sons

evince

oun

sn

.

The inspector discussed

applicable

seismic criteria regarding the

radios in question

and determined that the criteria had been met.

This item >s closed.

3.

Review of Plant Activities (60705

71707

71710

93702)

a 0

C.

Unit 1

Unit 1 remained .in Mode

6 throughout this inspection period.

Refueling operations

continued,

however several

problems

were

encountered

during refueling operations

(see Sections

8,

9 and 10).

Unit 2

Unit 2 entered the inspection period in Mode 5, performing

corrective maintenance

on nuclear cooling water, essential

cooling

water,

and auxiliary feedwater valves.

The Unit began

a heatup

on

November 21,

1989.

Shortly after entering

Mode 4 on that date,

the

heatup

was terminated

due to exceeding

the reactor coolant system

heatup rate limit.

As a conservative

measure,

the Unit was cooled

down to Mode 5

(COLD SHUTDOWN) on November 22,

1989.

A heatup to

Mode 3 (HOT STANDBY) was performed

on November 23, where the unit

stabilized to perform maintenance

on an auxiliary feedwater

valve.

The reactor

was started

up on November 30, 1989, but the power

increase

was halted in Mode 2 due to indications of a potential

control element drive mechanism coil ground.

The Unit borated to

subcriticality on December

1,

1989 (see Section 15).

The reactor

was started

again

and entered

Mode 1 on December 2, 1989.

The-plant

was synchronized to the grid on December

2, 1989 and reached

lOOX

power on December

5.

The plant operated at essentially

100X power

for the remainder of the inspection period.

Unit 3

I

Unit 3 began this report period in Mode 5,

and was nearing

completion of its first refueling outage.

As post-outage

maintenance

and testing were completed

and required prerequisites

were met, Unit 3 heated

up to Mode 4 and then achieved

Mode 3 on

November 30,

1989.

During steam testing of the turbine-driven

auxiliary feedwater

pump, the licensee

determined that operability

questions

associated

with pump discharge

pressure

oscillations

and

throttle valve gland leakage

required

pump disassembly

(see Section

17).

Thus, Unit 3 was returned to Mode 4 in compliance with

technical specification (T/S) requirements

for Auxiliary Feedwater

System operability.

Following pump reassembly,

the Unit was retur ned to Mode

3 and

remained in Mode 3 through the end of the inspection period.

tI

d.

Plant Tours

The following plant areas

at Units 1,

2 and

3 were toured by the

inspector during the inspection:

Auxiliary Building

Containment Build)ng

Control Complex Building

Diesel Generator Building

.Radwaste

Building

Technical

Support Center

Turbine Building

Yard Area and Perimeter

Central

and Secondary

Alarm Stations

The

2.

3.

5.

7.

8.

9.

following areas

were observed

during the tours:

0 eratin

Lo s and Records - Records

were reviewed against

ec n)ca

pec>>ca

)on and administrative control procedure

requirements.

Monitorin

Instrumentation - Process

instruments

were observed

or corre at)on

etween

c annels

and for conformance with

Technical Specification requirements.

Shift Mannin

- Control

room and shift manning were observed

or con ormance with 10

CFR 50.54(k), Technical Specifications,

and administrative

procedures.

E ui ment Lineu

s - Various valves

and electrical

breakers

were

ver) )e

o

e )n the position or condition required

by

Technical Specifications

and administrative

procedures

for the

applicable plant mode.

E ui ment Ta

in

- Selected

equipment, for which tagging

reques

s

a

een initiated,

was observed to verify that tags

were in place

and the equipment

was in the condition specified.

General

Plant

E ui ment Conditions - Plant equipment

was

o serve

or )n )ca )ons

o

sys

em leakage,

improper

lubrication, or other conditions that would prevent the systems

from fulfillingtheir functional requirements.

Fire Protection - Fire fighting equipment

and controls were

'f

ithT hi

1SP if'i

d

administrative procedures.

Plant Chemistr

- Chemical analysis results

were reviewed for

con ormance w)th Technical Specifications

and.administrative

control procedures.

~Securit

Activities observed for conformance with regulatory

requ)rements,

implementation of the site security plan,

and

administrative procedures

included vehicle and personnel

access,

and protected

and vital area integrity.

The Central- Alarm Station

and Secondary

Alarm Station were

included in plant tours.

The inspector raised

concerns

regarding

compensatory

posts

which were discussed

with NRC

security personnel'ollowup

on these

items will be performed

by Region

V based Security Inspectors.

10.

Plant Housekee

in

- .Plant conditions

and material/equipment

s orage

were

o served'to

determine

the general

state of

cleanliness

and housekeeping.

Housekeeping

in the

radiologically controlled areas

was evaluated with respect to

'ontrolling

the spread of surface

and airborne contamination.

11.

Radiation Protection Controls - Areas observed

included control

po>n

opera

>on, recor

s

o

icensee

surveys within the

radiologicalIy controlled areas,

postinq of radiation

and high

radiation areas,

compliance with Radiation Exposure Permits,

personnel

monitoring devices

being properly worn,

and personnel

frisking practices.

The inspector

noted

one isolated=occurrence

of an apparent

improper transfer of material

across

a posted

contaminated

area

barrier

on Unit 2, which could have resulted in a personnel

contamination,

although

none actually occurred.

This was

discussed

with and acknowledged

by the appropriate

management.

No violations of NRC requirements

or deviations

were identified.

4.

En ineered Safet

Feature

S stem Malkdowns - Units 1

2 and

3

Selected

engineered

safety feature

systems

(and systems

important to

safety)

were walked

down by the inspector to confirm that the systems

were aligned in accordance

with plant procedures.

During the walkdown of

the systems,

items such

as hangers,

supports,

electrical

cabinets

and

cables,

were inspected

to determine that they were operable,

and in a

condition to perform their required functions.

Accessible portions of

the following systems

were walked

down during this inspection period:

Unit 1

o

Containment Recirculation

Sumps

and Tri-Sodium Phosphate

Baskets.

Unit 2

o

"A" and "B" Emergency Diesel Generators.

Unit 3

o

Containment Recirculation

Sumps

and Tri-Sodium Phosphate

Baskets.

0

Condensate

Storage

Tank.

No violations of NRC requirements

or deviations

were identified.

5.

Monthl

Surveillance Testin

- Units 1

2 and

3

61726

Selected

surveillance tests

required to be performed by the

Technica'l Specifications

(T/S) were reviewed

on a sampling basis to

verify that:

1) the surveillance tests

were correctly included

on

the facility schedule;

2)

a technically adequate

procedure

existed

for performance. of the surveillance tests;

3) the surveillance

tests

had been performed at the frequency specified in the T/S; and 4)

test results satisfied

acceptance

criteria or were properly

dispositioned.

Specifically, portions of the following surveillances

were observed

by the inspector during this inspection period:

Unit 1

Procedure

o 41ST-1ZZ08

Unit 2

Procedure

o 36ST-2SE02

Unit 3

Descri tion

Containment

Bui 1 ding Atmospheri c Penetrati ons

~oi ti

Excore Linear Calibration,

Channel

"A"

C.

Procedure

D~iti

o 43ST-3SG03

Atmospheric

Dump Va1ve Testing in Mode

3

The inspector

was

made

aware that

a System Engineering

Lead Engineer

had written a memorandum to the System Engineering

Manager

expressing

concern that

some completed surveillance test packages

were being reviewed

and signed

by system engineers

who were not

properly qualified in accordance

with ANSI 3. 1.

The inspector

contacted

the Lead Engineer to determine the content of the-

memorandum.

Based

on this discussion,

the inspector confirmed that

the

Lead Engineer

had written a memorandum to the System Engineering

Manager;

however, the memorandum

described

the lack of a program to

document engineer qualifications.

A copy of this memorandum

could

not be located

by the

Lead Engineer or System Engineering

Manager.

The Lead Engineer

had

no concern

regardinq

improper signatures

on

surveillance

packages.

The inspector

reviewed the licensee's

procedure for tracking the

ANSI qualifications of Evaluation

I Engineering

Department personnel

that perform surveillance t'est

procedures.

This procedure,

70DP-OTR01, "gualification and Training

Requirements for Engineering Evaluations Department,"

which was

issued

on September

1, 1989, is currently under revision and three

separate

procedures will be issued.

These will be for the system

engineers,

reactor engineers,

and technical

support engineers.

The

inspector determined

the current procedure

and the proposed

revisions are sufficient to document the qualification status of

Evaluation Engineering

Department

personnel

provided the procedures

are fully implemented.

No violations of NRC requirements

or deviations

were identified.

6.

Monthl

Plant Maintenance - Units 1

2 and

3 (60710

62703)

a.

b.

During the inspection period, the inspector observed

and reviewed

selected

documentation

associated

with maintenance

and problem

investigation activities listed below to verify compliance with

regulatory requirements,

compliance with administrative

and

maintenance

procedures,

required guality Assurance/guality

Control

(gA/gC) involvement, proper use of safety tags,

proper equipment

alignment and use of jumpers,

personnel

qualifications,

and proper

retesting.

The inspector verified that reportability for these

activities was correct.

Specifically, the inspector witnessed portions of the following

maintenance activities:

Unit 1

o

Core Reloading Activities

o

Stuck Fuel Assembly Recovery

o

Installation of Fuel Assembly Restraining

Device

o

Control Element Drive Mechanism Lift Coi] De-stacking

and

Inspection

o

Fuel'uilding Upender Hydraulic Power Unit Repair

o

Troubleshooting the "B" Channel

Plant Protection

System

Parameter

13 Bypass Light Failure

Unit 2

o

Electrical

Reassembly

of Valve AF-V31

o

Troubleshooting

a Control Board Annunciator

o

Removal of Lagging from valves

PC-V024 and

CH-V124

Unit 3

o

Pressure

switch- calibration

on MSIV 180

o

Troubleshooting

Steam

Bypass

Control Valve 1008

o

Troubleshooting Auxiliary Feedwater

Pump "A"

No violations of NRC requirements

or deviations

were identified.

0

Si n-offs Not Made As Maintenance

Was Performed - Unit 1 (62703

The inspector

observed

maintenance

being performed

on the Unit 1 "B"

containment

spray

pump motor on November 14, 1989.

The inspector

reviewed Work Order

(WO) 362320 at the work location and observed that

none of the work steps

contained in the work instructions

had been

initialed, even though the job had proceeded to the point that power

cables

were being reassembled.

The

gC inspectoi

present

explained the

work instructions

and indicated that step 4.5 was in progress.

The

NRC inspector

asked the electrician

how the completion of each step

of the procedure

was assured

and was told that it was

done by memory and

documented

on the official copy when the job was completed.

When asked

if this was the way work was normally done, it was indicated that check

marks were sometimes

placed

on the "field copy" as work progressed.

The

gC inspector

showed the

NRC inspector his notebook,

which contained

a

list of steps

completed

where

gC hold points were included.

The inspector reviewed

a copy of the

WO in the electrical

shop

and

observed that it also did not contain initials indicating completion of

prerequisites

or initial notifications.

Similar failures to perform

WO

signoffs

as the work was completed

were identified at Unit 2 in

Inspection

Reports

50-529/88-28,

Section

12,

and 50-529/88-31,

Section

10

and for Unit 3 in Inspection

Report 50-530/89-28.

This 'was the subject

of Notice of. Violation Items 529/88-31-01

and 530/89-28-09.

Arizona Nuclear Power Plant

(ANPP) procedure

30DP-9MP01,

"Conduct of

Maintenance,"

step 3.8.6 states,

"Work instruction steps,

sections of

steps

and data sheets

shall

be properly documented at the time of

performing the step or soon thereafter if conditions

do not permit."

The

failure to follow procedures

is a violation of Technical Specification 6.8. 1(a)

and is an example of management

expectations

not being fully

implemented at the working level in both the maintenance

and quality

control areas

(528/89-50-01).

The

NRC inspector discussed

the incident with both Unit 1 and

gC

management.

The electricians

and

gC inspector involved in this situation

have

been instructed

on management's

expectations

in their respective

areas

and disciplinary action was taken to reinforce management's

intentions.

The

WO was

amended

and the work was reperformed

satisfactorily.

Mis lacement of a Fuel

Assembl

Event - Unit 1 (40500

60705

60710

During the Unit 1 core reload, at approximately 9:35

PM on November 16,

1989,

a new fuel assembly

was grappled

from the wrong spent fuel pool

location and was almost fully inserted into the wrong core location

before the error was discovered

by the on-shift Reactor

Engineer.

I

I

k

Pre aration of the Transfer

Forms

The error occurred

because

the fuel transfer

form which specifies

the transfer

sequence,

serial

numbers,

and locations incorrectly

specified spent fuel pool location

P38 where location

P28 should

have

been specified.

These

forms are partially printed, then

. handwritten to fill in fuel assembly serial

numbers,

spent fuel pool

locations

and core locations.

The completed

forms consist of

several

hundred line entries.

The Reactor Engineering Technician

who made the error prepared.-the

entire core load transfer

form but

did not sign it.

The Reactor Engineer

who signed the form as

preparer

said that approximately

75K of the form had been reviewed

line by line prior to signing.

The 'Reactor Engineer

who signed

as

approver signed without a line by line review.

There

was

no

requirement for the Reactor Engineering Supervisor to review the

transfer form prior to use.

The procedure

which governs

the

reparation of the transfer

forms,

72AC-9NF01, "Control of SNM

ransfer

and Inventory," did not specify who is to sign the form as

preparer or approver other than

on the signature

page,

Appendix

C of

this procedure<

which simply identifies the signer in both cases

as

a "Rx Eng Rep."

This procedure

also did not specify what these

reviews should entail.

Failure to have

an adequate

procedure

appropriate to the circumstance

is

a violation of NRC requirements

(528/89-50-02)

and highlights the need to improve the performance

engineering

and technical

work.

The inspector also noted that

approximately six weeks elapsed

between

the preparation

review of

these transfer forms,

and their actual

use,

thereby giving ample

time for a thorough review.

The licensee

responded

by changing procedure

72AC-9NF01, "Control of

SNM Transfer

and Inventory," to change

the second

approval

signature

to an "Independently Verified and Approved For Use" signature with

procedural

steps defining what the two transfer form signatures

represent.

The independent

review signature

was defined to be "...

a 100'erification of all information on the

MBA Transfer Form...."

The licensee

also revised the Unit j. Core Reloading procedure,

72IC-lRÃ03, to: 1) clarify what the refueling Senior Reactor

Operator's

(SRO) function is and where the

SRO is to be stationed

during core alteration,

2) define what fuel assembly

intermediate

storage

locations

should

be used,

in order of preference,

as well as

defining the criteria for using in-core locations for intermediate

storage

locations

and,

3) using visual verification of assembly

seating

as

each

assembly is seated

where practical.

Procedure

72AC-9NF01 is generic to all three units at Palo Verde.

There is a

separate

core off-loading and core re-loading procedure for each

unit,

a total of six procedures.

The license

subsequently

revised

these

procedures.

Immediate Actions

After the error was discovered,

the on-shift Reactor Engineer

documented

the error in the Reactor

Engineer Test

Log portion of

72IC-lRX03, "Core Reloading," but did not include

a full description

of pertinent information in that

he did not specify

how far the

assembly

had been inserted

into the core prior to the discovery of

the error.

Core reloading

was halted for about five and one-half

hour s while the remainder of the transfer form was verified to be

correct.

After this review was complete core reloading continued at

3: 12

AM.

Later that morning, the Operations

Supervisor

was

appraised

of the error but was assured .that the error was detected

before the incorrect assembly

reached

the core.

Since the

Operations

Supervisor

understood that the assembly

was never placed

into the core, the event

was not considered to have major importance

and was, therefore,

not communicated to higher management.

The

significance of this event was finally app'arent to higher

management

the following week durin'g the investigation of the subsequent

stuck

fuel event (see paragraph

9).

The inspector stated to management

his opinion that it is important

'for abnormal

events to be fully evaluated

by appropriate

levels of

management

and for all pertinent

lessons

learned to be implemented

prior to continuing the activity which did not proceed

as expected.

The inspector

noted that core loading was halted for five and

one-half hours while the transfer

form was reviewed.

The licensee

further noted that the Shift Supervisor

was the most senior

management

representative

who was

aware of the event until the

following morning after refueling,had

continued.

The inspector further noted that it was

a communication error that

led the Operations

Supervisor to not appreciate

the significance of

the event

and not raise the issue

higher until after the

investigation of the stuck fuel event uncovered this event three

days later.

The licensee

responded

by reviewing the remainder of the transfer

form and by having the fuel vendor evaluate

the effect of this event

and the mis-positioning of the four most reactive

assemblies

in the

four most reactive core locations.

The results of these analysis

were that both configurations resulted in a shutdown margin well

within the Technical Specification requirements.

Mana ement Control of Plant Activities

The inspector

concluded that with regard to this event,

management

failed to define the threshold for raising problems

beyond the Shift

Supervisor in a timely fashion,

and core alterations

continued

before

management

was provided the opportunity to review the event

to ensure that lessons

learned

were appropriately

implemented.

Inaccurate

communication of the details of this event also

contributed to the failure to appraise

management

of the situation.

The inspector

concluded that additional

management

attention is

necessary

in these

areas.

10

9.

One apparent violation of NRC requirements

was identified.

Stuck Fuel

Assembl

- Unit 1

40500

93702

While reloading the core,

the Refueling Senior Reactor Operator

(SRO) was

unable to fully lower the fuel assembly'nto

core location L-17 (the last

'ocation

in that core row).

After discussion with the on-shift Reactor

Engineer,

the refueling team

assumed that the assembly in L-17 was

bowed,

and caused

the difficulty in fully seating

L-17.

The team decided to

move the fuel assembly

in L-17 to an intermediate

storage

location,

move

the assembly in L-16 to an intermediate

storage location, place the

assembly for location M-17, and then try to place .the assembly for

location L-17.

This was accomplished

successfully.

The refueling team

then tried to seat the assembly for location L-16 which could not be

fully seated

but was obstructed further into the core than L-17 had been.

This seemed to confirm the theory that L-17 was

bowed toward L-16.

The

team .then decided to repeat this process

by moving the assemblies

in L-16

and L-15 to intermediate

storage locations,

then to fully seat

L-16.

This was also accomplished

successfully.

When they then tried to seat

L-15, it could not be fully seated

but was obstructed

even further into

the core than L-16 had been.

When the team attempted to repeat this

sequence

of "backing down the row" they were unable to remove the

assembly at L-15 and were forced to stop the core reload

so they could

decide

how to move the assembly at L-15.

A subsequent

inspection

using lights suspended

into the core basket

and

binoculars

revealed that the assembly at L-17 was not significantly

bowed, but that the assembly in L-14 was

bowed sufficiently to not be

seated at all.

The bottom nozzle of the L-14 assembly

straddled

the core

basket pins, which are normally shared

by assemblies

of L-14 and L-15 and

was obstructing about half of L-15's bottom seating

area.

The assembly

in L-15 was stuck about 40 inches

above the core bottom and the bottom

nozzle of the assembly

in L-15 was compressing

the fuel pins of L-14

inward.

~

The Resident

Inspectors verified containment integrity and evaluated

and

confirmed that existing

FSAR analyses

bounded the worst case

event

associated

with the stuck assembly.

The inspector also visually verified

the position of the stuck assembly,

determined that the refueling machine

did have

a secure grip on the assembly

and was supporting the stuck

assembly's

weight,

and evaluated

the location and reason for the location

of all other assemblies

not in the spent fuel pool. It was during this

verification that the inspector

learned that the event addressed

in

paragraph

8 of this report occurred.

The inspector also evaluated

the

increased

chemistry

and radiological sampling/surveys

which were

instituted

as

a result of the stuck assembly

and

had

no further questions

regarding sampling/surveys.

The inspector

noted that the Unit 1 Plant

Manager directed core alterations

and any attempts

to free the stuck

assembly to be halted

as

soon

as

he was notified of the problem on

November 19, 1989,

so the, situation could be fully evaluated

and recovery

efforts proceed in a well-controlled manner.

During the following week

the licensee

had numerous

conversations

with the Resident

Inspectors,

Region

V and the

NRR Licensing Project Manager,

to clarify various

technical

and licensing issues.

~I

Two of these technical

issues

related to Radiological Controls.'he

first was

a reappraisal

of the radiation exposure

levels at the refueling

bridge and at the reactor vessel

flange due to the stuck spent assembly

protruding 40 inches

above the .top of the core in the event of a cavity

seal failure.

The second

was

an evaluation of the expected

airborne

concentration

should

one fuel pin rupture.

The first issue

had not been evaluated

when the inspector questioned

the

Unit 1 Radiological Protection

Manager

on November 20, 1989,

two days

after the assembly

was stuck.

The following day the licensee

determined

an estimated

dose rate at the reactor vessel

flange.

The inspector

concluded that the licensee

required prompting to consider the possible

radiological effects of this incident assuming

a concurrent incident,

such

as cavity seal failure, for which licensee

established

procedures

were available,

but which assumed normal;initial conditions.

The second

issue associated

with expected

airborne concentrations

from

the rupture of one. fuel pin resulted in a calculation which was reviewed

and passed

to Region

V based

inspectors.

The result which was initially

passed

to

NRC Region

V was

a factor of 1,000 higher that the correct

calculation

due to an error which was not discovered

during the

licensee's

review.

When Region

V inspectors

questioned

and performed

independent calculations,

the error was discovered.

The licensee

acknowledged their error when questioned

by the Region

V inspector.

The

inspector

considers it important for technical

data to be accurate,

especially during abnormal-situations-

when people or organizations

are

likely to act

on this information.

The licensee

responded

by correcting

the calculation

and acknowledging the inspector's

concern.

This point

was also emphasized

during the exit meeting for Region

V inspection

report 89-51.

The licensee

prepared

the detailed designs

to fabricate temporary devices

to restrain the assembly at L-14 prior to attempting to move the assembly

in L-15.

As a parallel activity, the licensee

wrote procedure

720P-9RX07,

"Fuel Assembly Recovery," which required

a 10

CFR 50.59

review concluding that this activity did not present

an unreviewed safety

question.

The inspector

reviewed this procedure

and the

10

CFR 50. 59

review and concluded it was adequate.

Once the procedure

was approved

and the restraining

devices

were in

place,

the licensee

recovered

the assembly

by exerting approximately

1630

pounds of force to begin moving the assembly,

then approximately

1750

pounds of force to free the assembly grid straps

when they first

interlocked.

The assembly

was then inspected

and seated

in an incore

intermediate

storage

location.

The inspector

observed

the assembly

recovery from containment

and noted that the recovery

was carefully

planned

and executed with appropriate

controls

and contingency plans.

Several

days of subsequent

fuel inspections

ensued

which resulted in the

licensee

deciding to reconstitute

the

bowed assembly in L-14 and attempt

reconstitution

on the

new assembly in L-16.

The remainder of the core

was loaded

and locations

L-14, L-15, L-16 and L-17 remained

empty pending

reconstitution at the

end of this inspect'ion period.

12

The licensee's

response

to this event

was closely intertwined with their

response

to the fuel misalignment event since

management

beyond the Shift

Supervisor

was not fully aware of the mis-fueling event until this stuck

assemble

event recovery

was underway.

Beyond the procedural

enhancements,

the refueling

SRO drafted

a

memo to Fuel

Load Teams

documenting the problems

and the procedui al enhancements

desiqned to

eliminate these

problems.

The licensee's

response

to the radiological

concerns

raised

by the

NRC are discussed

above.

The inspector concluded that the. licensee

proceeded

in the face of

uncertainty

when the assemblies

in core locations

L-17 and L-16 would not

fully insert and was not identified to supervision

beyond the Shift

Supervisor until after the assembly in L-15 was stuck.

The licensee's

response

to use

a light to verify the seating of each

assembly

as it is

loaded into the core where practical indicates

the ease

by which the

operators

could have stopped to ensure'hat

they fully understood

the

problem before proceeding to a stuck assembly.

In addition, the inspector

concluded that the licensee

subsequently

failed to rapidly and accurately anticipate

the potential radiological

consequences

of this abnormal

event

and its bounding events.

No violation of NRC requirements

or deviations

were identified.

Mron

Assembl

Gra

led and Lifted in the

S ent Fuel

Pool - Unit 1

1

After the stuck fuel assembly

was freed

and core reloading continued,

the

Spent

Fuel

Pool

(SFP) machine operator grappled the fuel assembly at

SFP

location

N31 and raised it approximately

3 inches (to ensure it was

grappled)

before the Reactor

Engineer discover ed it was the wrong

assembly

and stopped its movement.

The

SFP operator

had just moved the

assembly in SFP location A29 to containment.

The next location assembly

to be moved was AA29.

The

SFP operator misread the sheet,

thought the

AA29 assembly

had been

moved, turned the page

and grappled the next

assembly to be moved at

SFP location N31.

The refueling team

had been directed to contact the Unit 1 Operations

Manager if anything abnormal

occurred during the continuation of core

loading.

This did not occur,

and the refueling team reseated

the

assembly inadvertently lifted at location N31, and proceeded

with core

load.

The Unit 1 Operations

Manager

was not appraised

of the error,

until questioned

by the

NRC Resident

Inspector at which point refueling

was immediately halted.

An investigation

ensued

and another

change

was

made to procedure

72IC-lRX03, "Core Re-Loading," to define specific

communications

requirements

designed to catch this and other fuel

handling errors.

The licensee

revised the "Core Re-Loading"

and "Core

Off-Loading" procedures

to incorporate

these

communications

requirements

prior to recommencing

fuel movement.

The inspector considers it important for fuel movement to be

a very

carefully controlled evolution so errors are minimized if not eliminated.

The inspector

concluded that even in light of the recent fuel handling

problems,

management's

expectations

for communicating problems to

13

management

so the problems

can

be resolved

and lessons

learned

be

implemented prior to proceeding

has still not effectively been

communicated to the working level.

No violation of NRC requirements

or deviations

were identified.

Unofficial Procedure

Chan

e - Unit 1 (61726)

During the. performance of 41ST-lZZ08, "Containment Building Atmospheric

Penetrations,"

the Chemistry Effluent Technician

used Unit 1 Chemistry

Standing Guideline 1-EFF-89-006:-'0,

"Channel

and Channel

Functional

Checks

on RU-37 and RU-38" in lieu of Steps 6.4.4.3, 6.4.4.4

and 6.4.4.5 of

procedure

75RP-9ZZ92,

"Gaseous

Radioactive

Release

Permits

and Offsite

Dose Assessment."

This Chemistry Standing Guideline was developed

on

October 20, 1989, in response

to

HPES Evaluation 89-021 when

a Unit 3

Chemistry Effluent Technician inadvertently r'estored

10 times the

required high alarm setpoint during a weekly channel

check.

This was

an

interim measure while a new surveillance

procedure

was being developed to

standardize

the details

on operating the radiation monitor keyboard.

The

inspector discussed

this with the Chemistry Effluent Supervisor

and

Chemistry Manager

and noted that management's

endorsement

of this lack of

formality in the performance of activities associated

with surveillance

testing is contrary to conservative plant operation.

The licensee

agreed

that -this is not the message

that management

should

be

be communicating

to plant workers

and coincidentally learned that the

new procedure

would

be completed

near the end of this inspection period.

The inspector

had

no further questions

on this issue.

No violations of NRC requirements

or deviations

were identified.

Incorrect Clearance - Unit 1 (93702)

The clearance

to repair/rework 1-1/2 inch sealtite

and fittings for

instrument rack 01JRCEA01A required opening breaker

52-D-1202, which

removed power from the Reactor Coolant System

(RCS) and Chemical

and

Volume Control System

(CVCS) process

instrumentation.

When this

clearance

was performed

a large

number of RCS and

CVCS instruments lost

power.

Among these

was Volume Control Tank (VCT) level.

When the

VCT

level instrument lost power, the charging

pump suctions

were

automatically realigned

from the

VCT to the Boric Acid Hakeup

Pump

(BANP).

Since the Refueling Water Tank was below 73X for refueling, the

BANP did not start

and the charging

pump tripped on low suction pressure.

When the operators

realized what had happened

they restored

power to the

RCS and

CVCS instrumentation

by shutting breaker

52-D-1202

and restored

charging flow.

This incident was caused

by inattention to the

preparation

and review of the clearance.

The licensee

stated that the

involved individuals

had been counseled.

No violations of NRC requirements

or deviations

were identified.

Reactor Coolant

S stem Heatu

Rate .Exceeded - Unit 2 {93702)

During a reactor coolant system

(RCS) heatup

on November

21,

1989, the

RCS heatup rate limit was exceeded.

The heatup started at 12:45

PH from

an

RCS cold leg temperature

(Tc) of 190 degrees

F, with three reactor

coolant

pumps

(RCP's)

and Shutdown Cooling (SDC) in operation.

At least

one Reactor Operator

(RO) had expressed

anxiety regarding the status of

the

Mode 5 to Mode 4 change checklist,

which was believed to expire at

1:30

PH.

The Shift Supervisor

had assured

the

ROs that the checklist

had

been completed within the required

24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period,

and that

no time

constraint existed for performing the actual

mode change.

Mode 4 would

be entered

when Tc reached

210 degrees

F.

At 1: 15 PH, Tc was 208 degrees

F,

and at 1:45

PM, Tc was

232 degrees

F.

During the hour ending at 1:45

PH, Tc had in'creased

by 42 degrees

F,

exceeding

the 40 degrees

F per hour limit specified in Technical

Specification (T/S) Limiting Condition for Operation 3.4.8.1(a).

The

action statement

was entered at 1:45

PM, and all requirements

of the

action statement

were performed.

At 2: 15

PM, Tc was

252 degrees

F,

resulting in a maximum one hour heatup

.of 44 degrees

F, however, the

heatup rate for that half hour was 40 degrees

F per hour, which is within

the T/S limits and is in compliance with the action statement.

At approximately 4:45

PM, the inspector

asked what time

SDC had been

secured.

As no entry had been

made in the control

room logs, the

operators

determined that the

Low Pressure

Safety Injection (LPSI) pump

had been stopped at 2:25

PH, but that

SDC had effectively been

secured at

some previous

undetermined

time by bypassing

the

SDC heat exchanger.

Subsequent

investigation determined that the

SDC heat exchanger

had been

bypassed

immediately prior to the start of the heatup.

After the absence

of information in the control

room logs regarding the securing of SDC was

pointed out by the inspector to the RO's,

a late entry was

made

indicating the stopping of the

LPSI pump and completion of terminating

SDC.

The inspector

concluded that insufficient attention

had been given to

controlling the heatup

by the Control

Room operators

and their

super vision.

The inspector

reviewed procedure

420P-2ZZOl,

"Cold Shutdown

to Hot Standby,

Mode 5 to Mode 3," and determined that procedure

guidance

for monitoring the heatup

had been met.

The inspector

concluded that the

guidance in this procedure

was inadequate.

Additionally, the inspector

concluded that the Control

Room logs did not contain adequate

information

regarding the major evolutions involved in the heatup.

The licensee

independently

concluded that procedure

420P-2ZZ01 should be

enhanced

to provide more guidance

on monitoring heatup rate

and

a

procedure

change

was

made.

The inspector

observed

the first briefing

given to operators

on these

changes,

and considered

the briefings

satisfactory.

Also, in response

to a refueling water tank makeup water

spill on November 26, 1989,

more specific guidance

was being developed

on

maintaining adequate

operator

loqs (see

paraqraph

14).

Additionally, the

Assistant Shift Supervisor

on shift at the time has

been relieved of

control

room duties pending

a management

evalution of his.ability to

fulfillhis responsibilities

in overseeing plant evolutions.

The

inspector

concluded that these

actions

appeared

adequate.

No violations of NRC requirements

or deviations

were identified.

15

14."

Refuelin

Mater Tank

RMT) Makeu

Mater

S ills - Unit 2 (93702)

On November 26, 1989, while performing procedure

42ST-2RC02,

"RCS Mater

Inventory Balance,"

two spills of slightly contaminated

water occurred.

One spill was in the vicinity of the Boric Acid Batch Tank (BABT), and

the other was next to the

RMT, outside the Auxiliary Building but'nside

the Radiologically Controlled Area (RCA).

The spills:resulted

from two

valves,

CHN-V649 (BABT eductor inlet valve), and

CHN-V126 (BABT eductor

outlet valve), being open after their manipulation during a boric acid

, addition to the

RMT on November.

9., 1989.

Additionally, the

body-to-bonnet bolts

on CHN-V126 and

PCN-V024 were insufficiently

torqued,

such that they would not withstand their normal design pressure

without leaking.

During the performance of 42ST-2RC02, with both a Boric Acid Makeup

Pump

(BAMP) and

a Reactor Mater Makeup

Pump

(RWMP) in service,

the makeup

mode

selector switch was taken to manual.

This causes

closure of CHN-V510,

and resulted in a pressure

spike, estimated at 191 psig.

Because of the

inadvertently

open valves, this pressure

was exerted

on portions of the

RMT makeup piping not normally exposed to this pressure.

Mhile this

pressure

is less that the design pressure

of the system, it was

sufficient to unseat the bonnets

on CHN-V126 and PCN-V024, resulting in

the spills.

After closing

CHN-V126 failed to stop the spill, CHN-V649

was closed

and the spill was terminated.

The spill from CHN-V126 covered most of the floor on the west side of the

120 foot elevation of the Auxiliary Building.

The area

was immediately

posted

as

a contaminated

area,

and the spill was cleaned

up.

The valve

diaphragm

was replaced

and the bonnet bolts retorqued.

During the repair of CHN-V126, it was noted that the heat tracing went

over the bonnet.

After the valve manufacturer indicated that the heat

tracing could damage the bonnet,

the licensee initiated work orders to

check all diaphragm valves to ensure

the heat tracing did not go over the

bonnets.

The spill from PCN-V024 was estimated to be about

50 gallons,

and was

limited to the concrete

surfaced

area

immediately around the valve.

After the area dried, it was covered with stripable paint.

The valve

diaphragm

was replaced

and the bonnet bolts retorqued.

Decontamination

efforts were not complete at the end of this report period.

Two significant problems

were identified during the course of the

licensee

s investigation.

First, since two valves were apparently left

open inadvertently,

the licensee failed to maintain adequate

control of

system status.

Since

no other explanation

could be determined,

the

licensee

believes

the valves

may have

been left open following the last

boric acid addition.

Second,

operator

logs contained insufficient

information regarding the manipulation of valves

and equipment to allow

determination of the sequence

of events

leading

up to this event.

Letters providing interim guidance

on these

subjects

have

been

issued

and

reviewed with each operating shift.

Once refined, the licensee

committed

to incorporate this guidance into appropriate

procedures.

16

No violations of NRC requirements

or deviations

were identified.

Reactor Startu

- Unit 2 (71707

On November 30, 1989, the Unit 2 reactor

was started,

going critical at

5:25

PM.

At 10:59

PM, with the reactor at 1/2 percent power, while

withdrawing Group 4 and Group

5 Control Element Assemblies '(CEAs), full

scale deflection of the Control Element Drive Mechanism

(CEDM) control

system

ground detector indication occurred.

Procedure

42TP-2SF01,

"CEA

Operation

While Monitoring for Ground Faults," prohibits motion of any

CEA with a known ground while in Modes

1 and 2,

and requires

a reactor

shutdown

by boratson if ground. indication is observed

on any

CEA coil in

regulating groups 3, 4,

5 or P.

Boration was

commenced at 2:42 AM, on

December',

1989,

and the reactor

was subcritical at 3:40 AM.

After extensive monitoring of approximately 1,000

CEDM steps

on both

groups

4 and 5, the licensee

determined that the ground indication was

not reproducible

and

no grounded

CEDM coils were identified.

The reactor

was brought to criticality on December

2, 1989, at 4:41

PM, and

Mode 1

was entered at 10:48

PM.

The unit was paralleled to the grid on December

3, 1989,

and reached

100 percent

power at 5:13

AM on December

5, 1989.

No violations of NRC requirements

or deviations

were identified.

One violation of NRC requirements

was identified.

Auxiliar

Feedwater

Pum

Pressure

Pulsations - Unit 3

62703

92700

and

On December

4, 1989 during performance of surveillance test 43ST-3AF02

on

the turbine-driven auxiliary feedwater

pump,

a discharge

pressure

of 100

psi higher than the previous baseline

readings for miniflow recirculation

was observed.

Pulsations

were also observed

on pressure

instrumentation

and heard

by the system engineer.

These pressure

pulsations

were similar

to problems

encountered

during initial startup testing of the auxiliary

feedwater

pumps.

The initial cause of the pressure

pulsations

was believed to be the

impeller assembly or a blocked flow orifice.

The impeller had been

replaced during the refueling outage to correct

an unrelated

problem.

The licensee

did not find any obstruction in the orifice, the rotating

assembly

was replaced

and surveillance test 43ST-3AF02

was reperformed

on

December

12,

1989.

High discharge

pressure

and pressure

pulations

were

again present with the

new rotating assembly.

The licensee

continued troubleshooting efforts by changing out the

miniflow recirculation orifice from Unit 1.

The Unit 1 flow orifice also

failed to correct the problem.

The licensee

was in the process

of

further troubleshooting at the end of this inspection report period which

consisted of a proposed microflow line in addition to the miniflow

recirculation orifice.

The licensee

consulted

the

pump vendor

and concluded that the

pump was

operable,

however the long-term effects of the pulsations is currently

under -investigation

by an independent

pump expert..

No violations of NRC requirements

of deviations

were identified.

Missin

Handwheels

on Downcomer Feedwater Isolation Valves - Unit 3

10

During a Unit 3 plant tour on December

5, 1989, the inspector

noted that

handwheels

on Downcomer Feedwat'er Isolation valves

SGA-UV-175 and

SGA-UV-172 appeared

to be missing.

The licensee

stated that these

valves

are immediately adjacent to identical redundant

valves

such that the

handwheels

would interfere with each other if both were mounted.

The

licensee further stated that the handwheels

mounted

on the adjacent

valves could be removed

and placed

on valves

SGA-UV-175 or -172 if

needed.

The inspector

noted that the operations

procedure

which governs local

manual operation of these valves,

43DP-30P01

made

no mention of the

need

to share

one

handwheel

between

two valves.

also, this condition existed

in Units 2 and 3, but not in Unit 1 where

a slightly modified handwheel

was used to avoid interference.

Finally, a system engineer

had noted

this discrepancy

in Unit 2 on November 5, 1989 and

had initiated a work

request

(¹347089) to replace the missing handwheels.

The work request

had not been entered into the work control computer

system

(SIMS) as of

one month later.

The safety significance of these

valves is that the only available

flowpath for one of three auxiliary feedwater

pumps

(AFN-P03) required

by

Technical Specifications is through these

valves.

The valves are

remotely operated

and held open by instrument air with a nitrogen

accumulator

backup.

The

FSAR (10.4.7.1.1)

requires that these

valves

continue to f'unction remotely for 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> following a loss of offsite

ower (LOOP).

Local manual operation capability is not required by the

icensing basis,

although it is highly advisable

as

was

shown by the

need

to manually operate

ADV s following the Unit 3 Parch 3, 1989 reactor trip

event.

In fact, the licensee's

valve equipment

and operating procedures

provide for this capability.

In summary,

the inspectors

stated

the following concerns.

Procedural

guidance

was not available to auxiliary operators

which described

the

need to transfer

handwheels

between adjacent

valves for manual

valve

operation.

Further,

although this discrepancy

was identified by a system

engineer in Unit 2, the work request

only addressed

the Unit 2 condition

and was not in the work planning system

one month after it had been

written.

The difference which exists

between Unit 1 and Units 2/3 is an

indication of a divergence of systems

and procedures

between the three

units that

may be taking place.

Finally, Unit 3 routine operations

tours

failed to identify this discrepancy.

At the resident inspector exit meeting for this inspection,

'licensee

management

stated that the handwheels

would be made consistent

among the

three Units.

Responsible

engineering

management

later indicated that the

previously initiated work request for Unit 2, pIus

a similar one for Unit

3, would provide handwheels

where they were missing.

No violations of NRC requirements

of deviations

were identified.

18.

Al le

A.

~ B.

C.

ation Follow-u

- ATS NO. RV-88-A-055

Characterization

uality Assurance

is not following up on Corrective Action Requests

~

~

CARs).

Im lied Si nificance to Desi

n

Construction or 0 eration

Failure to verify the adequacy of corrective actions

could challenge

safe operation of the plant.

Assessment

of Safet

Si nificance

The following six CAR's were reviewed by the inspector to verify

that

QA was actively following-up in accordance

with the licensee's

QA program.

These six CAR's are part of a total of eleven

identified by the alleger; the other five CAR's were previously

reviewed

and documented in NRC Report Nos. 50-528/89-12,

50-529/89-12

and 50-530/89-12.

CP87-0111 - This

CAR was

opened

by Vendor Quality to Cooper Energy

Zervices

Group

(ESG)

on December

15,

1987 for not initiating a

Request for Drawing Action (RFDA) prior to making drawing changes.

This

CAR was

one of eleven

CARs issued

as the result of the Vendor

Quality Assurance

Audit conducted at

ESG on November 16-19,

1987.

The initial response

was

due by January

14,

1988 and

on January

12,

1988

ESG requested

an extension to February 29, 1988.

The Manager

of Procurement Quality informed

ESG on January

22,

1988 that the

extension

would be granted to February

15,

1988 on a one-time basis

only.

ESG responded

on February 2, 1988.

On February 29,

1988 the

Director Corporate

QA/QC sent

a letter to

ESG expressing their

disappointment

in the lack of effort ESG was putting forth regarding

all eleven

CARS.

On March 23,

1988 the Director Corporate

QA/QC

sent

a letter to

ESG thanking them for their cooperation with two

Vendor Quality representatives

in resolving the outstanding

issues

regarding the deficiencies

described

in the

CARs.

These

same

two

Vendor Quality representatives

visited the

ESG facility to assess

the status

of Correct Action Commitments which were

due by April 30,

1988.

This visit was documented

in a letter from the Director

Corporate

QA/QC to

ESG dated

May 17, 1988; this letter also included

additional actions

by

ESG to resolve the deficiencies.

Vendor

Quality again visited

ESG the week of September

12,

1988 to evaluate

the progress

completed to resolve the issues

addressed

in all eleven

CARs.

Vendor Quality returned to the

ESG facility the week of

September

26,

1988 to assess

completion of the open items

and to

assist

ESG in achieving those

means.

The results of the September

visits by Vendor Quality was sent to

ESG on a letter dated October

6, 1988.

The director Corporate

QA/QC sent

a letter to

ESG on

19

October

25,

1988 regarding

Vendor Quality's evaluation of their

responses

which incl,uded

CAR CP87-0111.

Final verification of

corrective actions

was performed by Vendor Quality during an audit

conducted

on December 14-16,

1988.

This

CAR was closed

on January

3, 1989.

CP88-0002 - This

CAR was issued

by Vendor Quality to Borg-Warner

~nustr)al

on January

12,

1988 for failure to implement design

changes.

Specifically,

as described

in LER No.87-003,

two Unit 3

shutdown cooling isolation,valves

did not have the required bolting

for the yoke to adaptor plate

as specified

on the applicable

revision of the valve assembly

drawing.

QA was involved in meetings

held at Borg-Marner facilities during

October,and

December of 1987 concerning the subject valves resulting

in several

unanswered

concerns, which initiated this

CAR with an

initial response

due by February 4, 1988.

The Borg-Marner response

is documented

in a letter to the Procurement Quality Department

dated January

29, 1988.

Two Vendor Quality Engineers,

following-up

on this response,

notified Borg-Marner that their response

was

acceptable

and corrective action verification was scheduled

the week

of March- 21,

1988.

Borg-Warner's

QA manager

requested

an extension

for the verification scheduled

on March 17, 1988, which was granted

by Procurement Quality and extended to April 15,

1988.

The licensee

received

and evaluated

Borg-Warner responses

addressed

in letters

dated

May 25,

1988 and July 1, 1988.

This review

prompted

a letter,

dated July 20, 1988,

from the Director, Corporate

QA/QC to Borg-Warner dated July 20,

1988 requesting

the performance

of additional actions

and

a response

addressing

root causes

and

actions taken to prevent occurrence

be submitted

by August 19,

1988.

This response

was issued

by Borg-Marner on August 15,

1988.

This

CAR was left opened

pending Engineering's

closing of EER 88-118

which was accomplished

on August 30,

1989.

On September

28,

1989

Vendor Quality performed

an audit at Borg-Marner to assist

Engineering in review of design

documents.

On September

29, 1987,

the issuance

date of LER No.87-003,

the licensee

imposed

Note 14 on

Borg-Marner.

Note 14,

a supplement to the Approved Vendors List, is

'ssentially

a restriction

on the release

of any items from the

Borg-Marner facility without prior licensee

approval.

As of this

inspection this restriction is still applicable.

Final verification

of the corrective actions

taken

was completed

by October 6, 1989 and

CAR CP88-002

was closed

by Vendor Quality on October 9, 1989.

CE 88-0005 - This

CAR, issued to the Central

Maintenance

I8C Rework

panes

s y,

was opened

on February 3, 1988, with an initial response

due by March 7,

1988.

This

CAR identified numerous

rework orders

that were not processed

through the warehouse/material

control

process.

That is, the storage,

issuance

and disposition of material

by the

I&C Rework Facility'as not in accordance

with approved

procedures.

Central Maintenance's

response

of February

18,

1988

denied the existence

of any conditions adverse

to quality and

therefore,

concluded that the

recommended

corrective actions

were

not required.

QA soundly rejected this response

and

on June

3,

1988

20

issued

a letter to Central

Maintenance stating this along with the

reasons

for their rejection.

Central

Maintenance

provided

gA with

an additional

response

on June

27,

1988 complete with action items

and projected completion dates.

This response

was evaluated

as

acceptable

by gA on July 15, 1988; it was noted at this time that it

would take several

months for implementation of all the corrective

actions.

The following additional

gA letters associated

with CAR

CE-88-0005

were issued

on the following dates:

August 4, 1988

(Status of Act'ion Items), August 17,

1988 (Commitment Extension

Request),

September

14,

1988 (Corrective Actions), October 17,

1988

(Corrective Action Verifications), March 27,

1989 (Verification),

March 31,

1989

(Reworked Items Awaiting MRS into Warehouse

Inventory), April 13,

1989 (Corrective Action Verification and

Status of Remaining Actions), July 7,

1989 (Verification of

Corrective Actions).

CAR CE 88-005

was closed

by gA on August 4,

1989.

~

~

~

~

~

C

88-0007 - This

CAR, issued to Unit 3 Operations/Radwaste

to

a

ress valve leakage

in the gaseous

radwaste

system,

was opened

on

January

21,

1988 with an initial response

due by February 12,

1988.

The response

was submitted

on February 9, 1988.

gA evaluated

the

response

and found it acceptable

on February 23,'988.

Interim

corrective action verification was found satisfactorily completed

as

documented

in a gA letter issued to Unit 3 Operations

on April 8,

1988.

This letter'escribes

gA's review of a draft procedure that

was revised to incorporate

proper controls

when. valve leakage is

suspected

and torque is to be checked.

The

CAR remained

opened at

this time pending final approval

and implementation/effective

date

being verified.

gA follow-up verification and

CAR closure

was

completed

on May 17,

1988.

CA 88-0084 - This

CAR, issued to Nuclear Engineering,

was opened

on

~co)er TI, 1988 with an initial response

date of November 10,

1988.

The adverse

condition reported

concerned

the review and approval of

vendor manuals.

The initial response

of November 15,

1988 was late

even though

gA reminded Engineering

on November 7, 1988 of the due

date.

Scheduled

completion dates for verification by gA of

corrective actions

taken were rescheduled

with gA approval.

gA

corrective action verification was partially completed

on April 15,

1989 with two items remaining

open pending resolution of a Vendor

Document

Review (VDR) checklist from EED and

PSEC.

gA follow-up was

scheduled for April 18,

1989.

On April 3, 1989,

gA sent

a letter to

Engineering Evaluation Department

(EED) regarding this

CAR

emphasizing

the importance of their direct involvement to resolve

the deficiency.

This April 3,

1989 letter also requested

a response

by April 17,

1989.

gA notified EED on April 17,

1989 that their

response

was not received;

EED subsequently

sent their response

on

April 21,

1989.

The

PS8C response

of April 26,

1989 was also late.

On April 27,

1989

gA approved the corrective actions identified by

EED

8

PS8C.

Corrective action verification was completed

on June

30, 1989;

gA closure of this

CAR was

on July 31,

1989.

The licensee

corrective action procedure,

60GB-O(01, in effect at the time of the

CAR required the Managers/Supervisors

of site organizations

to

respond to gA/gC on or before established

due dates.

Since the

CAR

21

package

status

sheet indicated

QA's awareness

of Engineering not

being in compliance with this procedure,

the inspector interviewed

QA management

about their plans to correct the problem.

This

interview revealed that

QA management

provided appropriate

corrective actions

by revising their program requirements

as

follows:

1)

Procedure

60AC-OQQ02 entitled "Corrective Actions" was revised

to read in Section

3. 1.3 that "Lack of corrective action to

identified nonconformances

is

a significant violation of the

QA

Program.

Overdue corr'ective action responses

and/or corrective

action implementation shall

be brought to the attention of

higher management

in accordance

with the escalation

program

defined in 60AC-OQ04,

Management

Escalation

Program for

Quality/Nuclear Safety Related

Issues

and Deficiencies".

2)

A new procedure,

60AC-OQ04,

was issued with the purpose

being

to establish

the method to sequentially escalate

resolution of

quality/nuclear safety-related

issues

and deficiencies to

higher levels of management

when either responses

to or

completion of actions for resolution are not timely.

This

procedure

was drafted

and issued for review on August 22,- 1989

and received final

QA approval,

along with procedure

60-AC-OQQ02,

on October 6, 1989.

The'inspector

did not issue

a citation for failure of Nuclear

Engineering to follow procedures=- because

the licensee's

QA

department

was aware of the problem and took proper corrective

actions to assure. that late responses will be resolved at

higher levels of management.

CE 88-0103 - This

CAR was issued

by Quality Engineering to the

nglneersng

Evaluations

Department

(EED) on December

6,

1988 with an

initial response

due by January

6, 1989.

This

CAR addressed

a

programmatic deficiency in the Engineering Evaluation

Request

(EER)

process.

The

EED response

of January

6, 1989 was determined

by QA

to be unacceptable;

a

new response

due date of February 2,

1989 was

established.

EED's response

was evaluated

by QA on February 18,

1989 and found acceptable

based

on the contingency that the

identified deficiencies

would be corrected

on or before

June 1,

1989.

This

CAR package

shows that although the

EED response

letter was

dated January

6, 1989, it was not received

by QA until January

9,

1989.

However,

on January

9, 1989 and prior to receiving EED's

response,

QA issued

an Overdue Notice to,EED.

Also,

EED did not

meet the June 1,

1989 contingency for revising procedure

73

AC-OZZ29.

This is expressed

in a

QA letter to

EED on July 18,

1989

which states that the

EED commitment was not addressed

in subsequent

revisions of 73 AC-OZZ29.

QA's letter further states

that

"Consequently,

the subject

CAR cannot

be closed

and is in a

delinquent status

since all of the corrective actions

were not

completed

by June 1,

1989 as committed."

EED's response

was

22

subsequently

submitted

and verified as acceptable

by gA thus closing

this

CAR on August 11, 1989.

D.

Conclusions

and Staff Positions

Review of documentation

indicated that gA was in constant

communications with the applicable organizations

responsible for

correcting adverse

conditions.

From review of the

CARs, it was

evident that the

gA follow-up actions

were adequate

to assure that

corrective actions

were adequate

and properly implemented in a

timely manner consistent with the seriousness

and complexity of the

adverse

condition.

E.

~Ati

R

i

d

None

19.

Review of Licensee

Event

Re orts - Units 1

2 and

3 (90712

and 92700)

The followinq LERs were reviewed by the Resident

Inspectors.

Based

on

the information provided in the report, it was concluded that reporting

requirements

had been met, root causes

had been identified,

and

corrective actions

were appropriate.

The below listed

LERs are

considered

closed:

Unit 2

TIMBER

89-09-LO +

89-09-L1

~ll

i ti

"Reactor Trip Due to Partial

Loss of Forced Flow."

In addition, the following LERs and special-reports

were reviewed

and

closed.

A.

(Closed)

LER 529/89-04-LO - Missed T/S Action Statement - 4. 16

KV

us

The licensee

reported that on June

17,

1989, the operability and

action requirements

of Technical Specification 3.8. 1. 1 had not been

met as

a result of the onsite class lE distribution system not being

supplied by two physically independent circuits.

The occurrence

resulted

from each of the two 1E buses

being transferred

from their

normal

power supplies to the

same alternate

startup transformer for

maintenance

on consecutive

days.

The transfer to the alternate

power supplies

were performed in accordance

with existing

procedures.

The following day, the condition was discovered,

the

affected

bus declared

inoperable,

bus

2E-NAN-S06 shifted back to its

normal

power supply and the T/S action statement

was exited.

Licensee corrective actions for the

LER were reviewed.

Personnel

involved in the event were counseled

by the licensee

and

a night

order issued in Unit 2 to enhance

operator

awareness

ot correct

electrical

bus alignment.

Yellow caution tags

were placed

on the

applicable control panel

breaker controls to emphasize

the

23

requirements

of T/S 3.8.1.1.

Operating

Procedure

420P-2NA01 - 13.2

KV Electrical

System

(NA), was revised to add

a precaution that

reiterates

the requirements

of T/S 3.8. 1. 1.

The equiva1ent

procedures

for the other two units were also

ch'anged.

Based

on the

review of the changes,

the

NRC inspectors

determined that the

procedures still allowed the reported condition to occur without

adequate verification to preclude the occurrence.

The, lice'nsee

responded

by stating that they would further change the affected

procedures

by adding 'a signature verification step that would

require verification of compliance with T/S 3.8.1. 1 prior to

shifting class

1E electrical

busses

from their normal

p'ower

supplies.

The licensee

committed to complete this action by

December 8, 1989.

The licensee

evaluations

and committed corrective

actions

appeared

to adequately

resolve

and preclude the reported

condition.

.The

LER was closed.

(Closed

LER 530/89-06-LO - Missed Surveillances

The licensee

reported that on June 6, 1989, while in a refueling

outage,

survei11ances

performed

once

each shift for the spent fuel

pool area monitor (RU-31) channel

check

and verification that Steam

Generator

pressure

was within the T/S limits were not performed

within the required interval.

Upon discovery, the licensee

performed the surveil'1ances

and verified compliance with applicable

action requirements

of the

T/ST

The action requirement for T/S

3. 7. 2 was met since the Steam Generator pressure

did not exceed the

specified limit.

The action requirement for T/S 3.3.3.1

was met

since

no fuel movement or crane operation

over the storage

pool were

in progress.

The licensee corrective actions

were reviewed.

-The cause of the

event

was attributed to personnel

error by responsible

operations

personnel.

In addition to completion of the required surveillances,

the licensee

issued

a night order to remind operations

personnel

of

the importance of completing T/S surveillances within the specified

time limits.

The licensee

also revised the Control

Room data sheets

to require time dependent

sign-offs for surveillances

performed

each

shift.

The licensee is also performing an incident investigation to

further eva1uate

human performance

concerns.

The licensee

evaluation

and corrective actions

appeared

to adequately

provide for

the correction

and prec1usion of repetition of the reported

condition.

The

LER was closed.

(Closed)

LERs 530/89-07-LO

and 530/89-07-Ll - Potter Brumfield

e

a

a

unc

>ons

On May 3, 1989, the licensee

determined that deficiencies

discovered

during the installation of Potter

and Brumfield relays were

reportable

under both 10

CFR Part 21 and

10

CFR 50.73.

On August 3,

1988, the licensee

reported

a defect in Potter

and Brumfield MDR

series

relays being utilized at

PVNGS, in LER 528/88-18-LO.

As

corrective action to that reported

defect,

the licensee

and Potter

and Brumfield designed

replacement

MDR series

relays to be installed

during each refueling outage.

The redesigned

reIays were

24

subsequently

installed in Unit 3.

During post installation testing

of the 42 relays tested in Unit 3,

5 seized

and .5 operated

slowly.

The malfunctioning relays were installed in the "B" train

NSSS

Engineered

Safety Features

Actuation System.

Licensee evaluation

and corrective action

had been previously

inspected

by the

NRC and those inspections

were documented

in

inspection reports 50-528/88-39,

50-529/88-39,

50-530/88-37,

50-528,

50-529,

50-530/89-21,

50-528,

50-529,

50-530/89-37

and 50-528,

50-529, 50-530/89-41.

During the current inspection,

previous

NRC

inspection

documentation

were reviewed with the licensee.

In

addition, licensee corrective actions

were again reviewed.

The

licensee

and the vendor

had determined that the malfunctions of the

relays observed

during post-installation testing resulted

from a

manufacturing process

deficiency whereby epoxy was

used to touch

up

parts of the relay without being subsequently

cured.

The uncured

epoxy flowed onto the rotor and stator mating surfaces

and was

subsequently

cured by normal heat

when the relays

were energized.

This resulted in binding the relays in the energized position.

The

affected relays

were

removed from Unit 3.

The manufacturer

corrected the manufacturing process

deficiency,

and relays

manufactured

using the corrected

process

were installed

and were

being tested in Unit 3.

The licensee

evaluation -and corrective

actions

appeared

to adequately correct

and preclude the identified

condition.

The'ER

was closed.

D.

(Closed)

10

CFR Part

21

Re ort 89-02P - Limitor ue Motor 0 erators

an

-

or ue

w) c

a> ures

On November 3, 1988, Limitorque Corporation notified the

NRC and

ANPP of two types of defects associated

with SMB-000 and

SMB-00

actuators.

The first defect related to post-mold shrinkage of

Melamine torque switches

and

recommended

replacement with

environmentally qualified Fibrite torque switches.

The second

defect identified that RH-insulated motors

may not develop full

rated starting torque at elevated

ambient temperatures.

The licensee

evaluated

the reported defect regarding

Melamine torque

switches in Engineering Action Request

(EAR) 89-0448.

The

EAR

determined that the noted condition was previously addressed

by

Design

Change

Package

(DCP) lOJ/20J/30J-SI-052.

The

DCP required

walkdowns of all safety-related

motor operated

valves

and

replacement

of Melamine torque switches with Fibrite and Durez

torque switches.

During discussion

of the corrective action between

the

NRC inspector

and the licensee,

the licensee

was unable to

readily show the acceptability of the Durez torque switches.

The

licensee

subsequently

contacted

Limitorque Corporation

and obtained

a letter on November 30,

1989 stating that the defect noted with

Melamine torque switches

was not identified for Durez-type switches

and that it had different material characteristics.

The letter

fur ther stated that Limitorque stopped manufacturing

Durez type

switches in approximately

1981 because

the production

volume did not

justify manufacturing

switches

using both Melamine and Durez

25

materials.

The licensee

concluded that the reported

discrep'ancy did

not apply to Durez material torque switches.

The licensee

evaluated

the reported defect regarding RH-insulated

motors for Limitorque motor operators

in Engineering Evaluation

Report 88-XE-015.

In this evaluation,

the licensee

determined

the

applications

where RH-insulated motors were used

and the design

temperature

conditions they were exposed to. In its report;

Limitorque had provided the maximum ambient temperature

at which

full rated torque could be developed for var'ious motors.

The

licensee

compared the Limitorque data with the design data for the

affected motors

and determined that the applications in which they

were using the motors in question

were still within the temperature

limitations identified by Limitorque.

The inspector

reviewed the licensee

evaluations

and corrective

actions

and discussed

them with the licensee.

The licensee

evaluations

and corrective action appeared

to adequately

provide for

the deficient conditions reported

by Limitorque Corporation in its

November 3, 1988,

10

CFR Part 21 report.

This item was closed.

(Closed)

10

CFR Part 21

Re ort 89-04P - Coo er Ener

Services

es>

n

ass>>cat>on

e >c)enc

On November 21, 1988,

Niagara

Mohawk Power Corporation reported

a 10

CFR Part 21 defect regarding its Cooper Energy Services

EDGs.

The

defect consisted of a post-lube pilot valve for the

EDGs that was

classified

as non-critical by Cooper. Energy Services.

Niagara

Mohawk determined that failure of the post-lube pilot valve could

prevent the

EDGs from achieving full rated power,

and consequently

should

be classified

as safety-related.

During the current

NRC inspection, it was determined that Arizona

Nuclear

Power Project

had not received the subject

10

CFR Part 21

report.

The report was provided to the licensee, by the inspector

and

reviewed

and discussed

with the licensee.

The licensee

and the

inspector

reviewed drawing number 13-M-DGP-001, revision 23,

Lube

Oil, Diesel Generator

System

and the

EDG technical

manual

MM018-389.

Both the system

diagram

and the technical

manual

indicated that the

subject valve was not a part of the

EDGs for the diesel

generators

supplied to*Palo Verde.

The licensee

subsequently

contacted

Cooper

Bessemer

and determined that the diesel

generators

at Palo Verde do

not utilize post-lube pilot valve assemblies.

The ET-24

turbochargers

supplied with the Palo Verde engines

do not use the

subject pilot valve assemblies.

Cooper Bessemer

stated that it

would document the conversation

by means of a letter to the licensee

confirming the above

noted design differences.

The licensee

subsequently

concluded that the 10

CFR Part 21 report did not apply

to Palo Verde.

The licensee

evaluation

appeared

to be adequate.

The

item was closed.

S

A

EE

26

20.

Review of Periodic

and

S ecial

Re orts - Units 1

2 and

3 (90713

Periodic

and special

reports

submitted

by the licensee

pursuant to

Technical Specifications

(T/S) 6. 9. 1 and 6. 9. 2 were reviewed by the

inspector.

This review included the following considerations:

the report contained

the information re9uired to be reported

by NRC requirements;

test results

and/or supportinq information were consistent with design predictions

and

performance specifications;

and the validity of the reported information.

Within the scope of the above,

the following reports

were reviewed by the

inspector:

Unit 1

o

Nonthly Operating Report for November 1989.

Unit 2

o

monthly Operating Report for November

1989.

Unit 3

o

Monthly Operating

Report for November 1989.

No violations of NRC requirements

or deviations

were identified.

21.

~tit 2 tt

The inspector

met with licensee

management

representatives

periodically

during the inspection

and held an exit meeting

on December '27,

1989.

A