ML17304A585

From kanterella
Jump to navigation Jump to search
Insp Repts 50-528/88-27,50-529/88-26 & 50-530/88-25 on 880801-11.Violations Noted.Major Areas Inspected:Licensee Action on Previous Insp Findings,Radiation Protection & Chemistry & Radwaste Organization & Mgt
ML17304A585
Person / Time
Site: Palo Verde  
Issue date: 09/06/1988
From: Cillis M, Tenbrook W, Yuhas G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML17304A581 List:
References
50-528-88-27, 50-529-88-26, 50-530-88-25, NUDOCS 8809300147
Download: ML17304A585 (28)


See also: IR 05000528/1988027

Text

U. S.

NUCLEAR REGULATORY COMMISSION

REGION V

Report Nos. 50-528/88-27,

50-529/88-26

and 50-530/88-25

Docket Nos. 50-528,

50-529

and 50-530

License

Nos.

NPF-41,

NPF-51

and NPF-74

Licensee:

Arizona Nuclear

Power Project

P. 0.

Box 52304

Phoenix, Arizona

85072-2034

Facility Name:

Palo Verde Nuclear Generating Station,

Units 1,

2 and

3

Inspection at:

Palo Verde Site - Wintersburg, Arizona

Inspection

by:

Inspection

Conducted:

August 1-11,

1988

6 iLap

)s,

r.

a iat)on

pec~a

est

7C Ef

a

e

)gne

Approved by:

GP

~Summer:

en roo

,

a

s

son

pecsa

>st

u

s,

ie

,

mergency

repare

ness

an

adiological Protection

Branch

te

cygne

a

e

cygne

Ins ection durin

the

eriod of Au ust 1-11

1988

Re ort Nos. 50-528/88-27,

and

-5 /

A~Id:

R

i

di

p

i

i

1 dig:

on prev>ous inspection findings; radiation protection, chemistry and radwaste

organization

and management; facilities and equipment;

review of LERs and

licensee

reports related to radiation protection matters;

and

a tour 'of the

licensee's facilities.

Inspection

procedures

30703,

83722,

83727,

92701

and

92702 were addressed.

88093VOlff/ VVVVV/

PDR

AQOCK 05000528

Q

PDC

-2-

Results:

The licensee's

ALARA (As Low As Reasonably

Achievable)

Committee

has

not carried out its responsibilities

as required

by procedure

(Section 2).

Members of the licensee's staff perceive that the reorganization of radiation

protection,

chemistry

and radwaste

personnel

has

reduced

the effectiveness

of

their respective

programs

(Section 3).

A new facility for respiratory

equipment

decontamination

and processing

had

been established

without a

required

10 CFR 50.59 safety evaluation

(Section 6.a).

Missing or improperly

maintained

high radiation area

posting

and barricades

were identified in the

Unit 2 auxiliary building Technical Specification 6.12 (Section 6.f).

The findings of this inspection

and other recent

inspections

indicate

a

declining trend in the radiological controls area, failure to take timely

corrective action in response

to licensee identified findings and

a

significant need for additional

high level licensee

management

involvement

and

oversight.

DETAILS

1.

Persons

Contacted

a.

Licensee Staff

  • J
  • W.
  • J
  • R
  • J
  • L
  • J
  • J
  • T
  • L
  • E
  • K.
  • W.
  • R.

R.

  • D

J.

L.

T.

D.

T.

L.

J.

D. Driscoll, Assistant

Vice President,

Nuclear Production

Quinn, Director, Nuclear Safety

and Licensing

J. Scott, Acting Unit II Plant Manager

M. Butler, Director, Standards

and Technical

Support

M. Allen, Unit 1, Plant Manager

G. Papworth, Director, Quality Assurance/Quality

Control

R. Mann, Central

Radiation Protection

Manager

M. Sills, Manager Radiation Protection

and Chemistry

D. Shriver,

Compliance

Manager

A. Souza,

Manager, Quality Audits and Monitoring

D. Griswold, Acting Radiation Protection

Manager,

Unit 2

Oberdorf, Radiation Protection

Manager,

Unit

1

E. Sneed,

Radiation Protection

Manager, Unit 3

L. Selman,

ALARA Supervisor

V. Logan, Dosimetry Supervisor

Stover, Acting Nuclear Safety Department

Manager

C. Schlag,

Supervisor,

Radwaste

Standards

J. Grusecki,

Lead Radiation Protection Technician

Phillips,

OCS Engineer

Wickline, Operations

Engineer

Haggard,

Lead Radiation Protection Technician

Hughes,

Central

Radiation Protection Technician

B. Steward,

Standards

Radiation Protection

Engineer

Support

b.

Contractor Staff

A

lied Radiolo ical Controls

M. Hedgecock,

Senior Radiation Protection Technician

c.

Nuclear

Re ulator

Commission

T. J. Polich, Senior Resident

Inspector

Denotes

attendance

at the August ll, 1988, exit interview.

In addition, the inspectors

met and held discussions

with other licensee

and contractor personnel.

2.

Followu

of 0 en Items

and Items of Noncom liance

92701,

92702

0 en

Followu

(50-528/86-08-03 '0-529/87-19-01

50-530/87-19-01

.These

items concerned

the operability of the combustible

gas monitors in

the gaseous

radwaste

system

(GRS).

The licensee

continued to operate

in

a technical specification action statement

with regard to these monitors,

4

4

pending

NRC approval of a proposed

amendment

to the technical

specifications.

NRC is expected

to act

on the proposal

on or about

September

30,

1988.

Upon approval of the amendment,

the

GRS oxygen

monitors would be modified during the

1989 refueling outages.

Closed)

IN 87-07,

IN 88-08,

IN 88-22:

The inspectors verified that the

scensee

a

receive

an

was

eva uating/had

evaluated

the following

Information Notices:

IN No.

Tit1e

87-07

guality Control of Onsite Dewatering/Solidification Operations

by Outside Contractors

88-08

Chemical

Reactions with Radioactive

Maste Solidification Agents

88-22

Disposal of Sludge

from Onsite

Sewage

Treatment Facilities at

Nuclear Power Stations

These matters

are closed at Units I,

2 and 3.

0 en

Followu

(50-528/88-24-03

..An examination

was performed for the

purpose

o

eterm~n~ng

w at e

ect the reorganization of December

1987

had in the area of radiation protection,

chemistry and radwaste.

The

examination disclosed that the licensee's

performance

in the area of

radiation protection

and

ALARA had deteriorated

as is indicated

by the

findings in the subsequent

paragraphs

of this report and as identified in

Inspection

Reports

50-528/88-13

and 50-528/88-22.

This item will be

examined during

a subsequent

inspection.

Closed

Followu

50-529

GC-88-01

The inspector verified by a review

o

snspectson

reports t at t ese

>tems

had

been previously reviewed

and

closed.

0 en) Enforcement

50-529/88-22-01,

50-529/88-22-02

These

items concerned

the apparent

overexposure

of a Unit 2 contract

worker during the second

calendar quarter of 1988.

The licensee

reported

the event in Licensee

Event Report

(LER) 88-011-LO, dated

June

22,

1988.

The licensee's

staff performed

an evaluation of the event.

The results

of the evaluation

were documented

in the licensee's

Special

Plant Event

Evaluation Report

(SPEER)

Ho. 88-02-004,

dated July 7, 1988.

Additional

information related to this matter

was provided in Region

V Inspection

Reports

50-529/88-14

and 50-529/88-22.

The licensee

acknowledged

the

violations contained

in Inspection

Report 50-529/88-22 during an

enforcement

conference

held in the Region

V office, August 17,

1988.

A.

~8ack round

The Region

V onsite examination of this event continued during this

inspection period.

The examination disclosed

the following

information:'

A recent licensee guality Assurance

audit found deficiencies

in the

licensee

s ALARA program.

The guality Assurance deficiencies

were

not reflected in the

SPEER report.

The guality Assurance

audit had

concluded that the

ALARA objectives

and work practices

were not

being adequately

met.

Specifically, the audit report dated

May 26,

1988, stated that the ALARA program

was not completely in compliance

with Regulatory

Guides 8.8, 8. 10,

and

10 CFR Part 20.

The report

identified that monthly ALARA committee meetings

had not been held

in over

a year.

The

SPEER identified that the planning for the job was

incomplete

and insufficient to prevent the overexposure

of the contractor.

Based

on the above information, the inspector held additional

discussions

with personnel

involved in the overexposure,

reviewed

the licensee's

ALARA implementing procedures

and other licensee

documents

related to the overexposure

event for the purpose of

verifying the previous

information and to determine

what involvement

the guality Assurance

Group had

had in the

ALARA program prior to

the overexposure.

Controllin

Documents

10 CFR Part 20.1(c) requires that licensee's

engaged

in activities

under licenses

issued

by the Nuclear Regulatory

Commission

make

every reasonable effort to maintain radiation exposures

as

low as is

reasonably

achievable.

Technical Specifications 6.8.1 requires

in part that, "Written

procedures

shall be...implemented...covering

procedures

referenced

below:

a.

The applicable

procedures

recommended

in Appendix A of

Regulatory Guide 1.33, Revision 2, February

1978, ...."

Regulatory

Guide 1.33, Appendix A, Section 7.e(9), requires

procedures

addressing

implementation of an ALARA Program.

Procedure

75PR-9ZZ03 Section

5. 1,

"Management

Commitment" states

in

part:

"ALARA Public Service upper leve'I management

is firmly

committed to an aggressive

ALARA program..."

Procedures

and other documents

reviewed are

as follows:

(1)

Procedure

75RP-9Z203,

"ALARA Program"

(2)

Procedure

75AC-9Z205,

"ALARA Committee"

(3)

Procedure

75RP-9ZZ94,

"ALARA Pre Job Review"

(4)

Procedure

.75RP-9ZZ97,

"ALARA Post Job Review"

(5)

ALARA Prejob Review records for 1987

and

1988

(6)

ANPP Letter, dated

June

15,

1988, from a Unit 2 Lead Technician

to the Unit 2 Radiation Protection

Manager

(7)

ANPP Letter No. 215-00555-JRM/JMS/RDM,

dated July 29,

1988

(8)

LER 88-011-00,

dated

June

22,

1988

(9)

ALARA 1987 Annual Report

(10)

ANPP Letter No. 222-00152-RBO/JH,

dated

March 21,

1988

(11) Regulatory Guide 8.8, "Information Relevant to Ensuring that

Occupational

Exposures

at Nuclear

Power Stations will be

ALARA."

(12)

ANPP Letter No. 215-00526-JRM,

dated

June

15,

1988

(13)

ANPP Letter from a Unit 2 Lead Radiation Protection Technician

dated August 6, 1988, with ANPP Letter No. 215-00514-JRM/RLS,

dated

May 20,

1988,

as

an attachment.

(14)

ANPP Letter No. 222-00287-JMS/JLH,

dated July 20,

1988

(15)

ANPP Letter No. 030-00906-LAS/DAH/CTS, dated

May 26,

1988

C.

Procedural

Re uirements/Commitments

(1)

Procedure

75AC-9ZZ05, Revision 2, dated

November 26,

1986

establishes

an

ALARA Committee

composed of the following

members:

1

The Manager of Radiation Protection

and Chemistry-

Chairman

2

The ALARA Supervisor - Alternate Chairman

3

The Compliance

Manager

4

The Manager of Operations

5

The Manager of the Maintenance

Department

6

The Manager of the

PVNGS Operations

Engineering

Department

7

The Manager of Outage

Management

8

The Radiological Services

Manager

9

The Radioactive Material Control Manager

10

The Chemistry Services

Manager

11

A Corporate

ALARA Representative

12

The Nuclear Construction

Manager

13

The Plant Services

Manager

The procedure

also requires that alternate

members

be

designated

in writing by the department

members.

Section 4.0

of the procedure identifies

a list of eleven

items for which

the ALARA Committee

have responsibility.

Section 5.2. 1 states

in part:

"The ALARA Committee should meet at least monthly at

the discretion of the ALARA Committee Chairman."

~Findin s:

The

ALARA committee

had

gone through

two refueling

outages

without conducting

a meeting.

The ALARA

supervisor stated that the last ALARA Committee

meeting

was held in March 1987.

Many ALARA Committee

members

had

been assigned

new

responsibilities

between

November

1987 and Apri1

1988.

No action

was

taken to redesignate

the

Committee's

membership until May 1988.

The ALARA

Committee

Chairman

had submitted his resignation

in

January

1988.

The Chairman's

termination

became

effective in April 1988.

At the time of this inspection

the ALARA Supervisor

informed the inspector that there were only three of

thirteen alternate

ALARA Committee

members that were

designated

in writing.

The ALARA supervisor

stated that the

ALARA Committee

stopped functioning as

a group since March

1987 and

could not have functioned

as

a group because

of the

reorganization of December

1988.

The ALARA

supervisor

added that

he

had verbally informed the

ALARA Committee

Chairman

on numerous

occasions

between

March 1987 and April 1988 that the

ALARA

comnittee responsibilities

were not being

implemented.

The supervisor

added that other

Committee

members

were aware of the situation

and

no

one

had informed management

of the situation until

May 1988 (see

paragraph

D, below).

a

2.

Procedure

75RP-9ZZ94 states

in part:

"... 6.1.3.4

6.1.3.5

If the final man-rem estimate is less

than

10,

the

ALARA Supervisor

shou Id review and approve

all formal

ALARA reviews, final man-rem

estimates,

and pre-job briefing checklists

as

soon

as practical.

If the final man-rem estimate is greater

than

10, the ALARA Supervisor will complete

the ALARA

Evaluation

Form (Appendix D) and will forward

both the Prejob-Review

Form and the

ALARA

Evaluation

Form to the Chairman of the ALARA

Committee for final review and approval....

6.1.4.5

Findings

The ALARA Representative

shall also perform

a

final man-rem estimate.

If the estimate

is

10

man-rem or greater,

the pre-job review shall

be

forwarded to the

ALARA Committee,

by the

ALARA

Supervisor, for their review and approval."

During 1987, of 126 jobs requiring pre-job review and

approval of the

ALARA supervisor,

approximately

61 were

not reviewed

and approved.

For 1988 of 73 jobs,

50 were

not reviewed

and approved.

In 1987, there were eleven pre-job estimates

of greater

than

10 man-rem.

Two of the eleven

had not received

the

final review and approval of the ALARA Committee

Chairman.

In 1988, there were eight pre-job estimates

of greater

than

10 man-rem

and two of the eight had not been reviewed

and approved

by the

ALARA Committee Chairman.

In 1987, there were eleven pre-job estimates

of greater

'han

10 man-rem.

None of the eleven were reviewed

and

approved

in advance

by the

ALARA Committee.

In 1988, to

the date of the inspection,

there were eight pre-job

estimates

of greater

than

10 man-rem.

None of the eight

were approved in advance

by the ALARA Committee.

The

eight included the pre-job estimate that involved the work

performed

by the individual that was overexposed.

3.

Procedure

75RP-9ZZ97 states

in part:

The ALARA supervisor shall determine whether

a post-job review

is required for jobs with exposures

of 1.0 man-rem to 10.0

man-rem.

Jobs with exposures

of 10.0 man-rem or more shall

be

reviewed

and

a presentation

of the review shall

be

made to the

ALARA Committee.

~Findin:

In 1987, there were nine (9) jobs with exposures

in

excess of 10 man-rem

and

as of August 11,

1988

a

presentation

of the post job reviews

had not been

made to the ALARA Coranittee.

4.

Procedure

75PR-9ZZ03 states

in part:

"...5.9

Program Evaluation

An annual

evaluation of the

ALARA Program's

effectiveness

shall

be performed to ensure

a

continuing commitment to maintaining personnel

radiation exposure

ALARA.

The ALARA Supervisor shall

be responsible for assimilating

the information

provided

by the Radiological Services

Manager,

0

~Findin:

Licensee Audit

preparing

the evaluation

and making recommendations

for program

improvement

based

on this information.

The

PVNGS Plant Manager

and the Vice President of

Nuclear Production shall review and approve,

as

appropriate,

the evaluation

and any recommended

improvements...."

An evaluation

was not performed for 1987.

The ALARA

supervisor stated that he had

recommended

that the

evaluation

be performed

by an independent

group.

He

added that he had prepared

to have the evaluation

conducted

by an independent

group; however,

the

contract

was subsequently

cancelled.

A review of references

B(10) and B(15) above disclosed that the

licensee's

Radiation Protection

and Chemistry Standards

group and

guality Assurance

group

had performed

a review of the ALARA program

in February

and April 1988.

Both audits

had identified similar

conditions discussed

in paragraph

C, above.

Reference

B(10) had

been submitted to the

ALARA Committee Chairman,

Standards

and

Technical

Support Director and Central

Radiation Protection

Manager.

The text of the report states

that

a potential

item of noncompliance

was identified.

The item referred to was the lack of the monthly

meetings.

The concluding statement

in the report appears

contradictory in that it states

that the

ALARA program is fully

established

and in compliance with NRC Regulatory Guide 8.8

guidelines.

The Director of Standards

and Technical

Support

concluded that the

ALARA program

was being implemented.

The

Director of Standards felt that there were

no major problems with

the ALARA program based

on the concluding statement

in the report;

therefore,

no immediate corrective actions

were taken to resolve the

findings identified in reference

B(10).

The guality Assurance audit reference

B(15), which was dated

May 26,

1988 was debriefed with the licensee's

staff on April 27,

1988.

Both the ALARA Chairman

and alternate

ALARA Chairman

were in

attendance

at the debriefing.

Distribution of the audit report to

upper management

was not made until May 26,

1988.

The quality

Assurance audit report had identified the

same

problems identified

by the audit performed

by the Radiation Protection

and Chemistry

Standards

audit.

The guality Assurance

audit findings were

documented

in CAR No. CA88-0036.

The

CAR reported

the findings

discussed

in paragraph

(A)-above.

The licensee

response

to the

CAR

was

made

on June

10,

1988.

The response

revealed that

an attempt

was

made to conduct

an

ALARA Committee meeting

on May 9,

1988,

however,

no quorum was achieved,

and

a second

meeting

was scheduled

for May 11,

1988; again

no quorum was achieved.

Subsequently,

the

ALARA committee procedure

was revised to clearly define the ALARA

Committee membership

and

ALARA Committee meetings

were held on June

24,

1988, July 20,

1988 and August 5,

1988.

The three meetings

have

been

devoted to reestablishing

the

ALARA committee responsibilities

that had

been

ignored for the previous

15 months.

E'.

Miscellaneous

Information

The pre-job review for the work involving the contractor that

had received

the overexposure

disclosed that the man-rem

estimate

was calculated

to be 12.0 man-rem.

The ALARA

Committee did not review and approve

the pre-job review package

prior to performing the work as required

by reference

B(3),

above.

(2)

This observation

was discussed

with the licensee's

staff.

The

licensee

stated that the ALARA Committee's

review and approval

in itself would not have prevented

the overexposure

since it

was decided at

a meeting held

on May 20,

1988, that the job

could

be done safely.

Personnel

in attendance

at the meeting

included:

ALARA Supervisor,

Unit 2 Work Control Manager, Unit

2 Radiation Protection

Manager, Unit 2 Plant Manager

and

ALARA

Committee Chairman.

The inspector

informed the staff that the

attachment

to reference

B(13), also dated

May 20,

1988,

and

prepared

by the ALARA Supervisor

and approved

by the ALARA

Committee

Chairman stated

in part:

"Due to the high dose

rates,

I feel the proposed

plan will not work and will cause

further delays

in the outage."

The ALARA supervisor

recommends

that the water level

be raised in the upender pit to place the

underwater

vacuum under water,

and the pit be vacuumed prior to

drain down."

The statement,

"the proposed

plan will not work"

referred to the licensee's

plan to apply and

remove strippable

paint in the upender pit.

The inspector stated that it

appeared

that there

were

some doubts

as to whether or not the

job could

be done safety which had

been

expressed

by several

other members of the licensee's

Radiation Protection

and

ALARA

work group staff.-

The inspector

was informed that the letter

attached

to reference

B(13) had not been officially issued.

The ALARA supervisor

and

ALARA Committee

Chairman stated that

the letter was typed and signed

on May 19,

1988.

It was their

intention to make the recommendations

discussed

in the letter;

however, after attending

the meeting of May 20,

1988, they had

changed their minds

and thought that they had retracted

the

letter.

The ALARA Supervisor

suspected

that

a copy of the

letter was

made

by an individual he had discussed it with and

shown it to.

Both the ALARA supervisor

and

ALARA Corrmittee

chairman stated that their decision of May 20 to proceed with

the work was

based

on

a review of survey data which

subsequently

turned out to be inadequate

and on information

presented

by other individuals that attended

the May 20

meeting.

The inspection disclosed that

some

key individuals involved in

the job planning,

review and approval of work had not visited

the work area

where the worker received

the overexposure.

Some

had only made

one entry into the containment building the

(3)

(~)

(5)

entire month of May.

The maximum number of entries

into the

containment

by some of the key individuals involved was four.

At least

two members of the ALARA group informed the inspector

that they had verbally expressed

an opinion that painting the

refueling pit was not necessary.

Several

members of the

radiation protection

group had voiced

a similar opinion;

however,

none of the individuals, including the

Lead Radiation

Protection Technician

and the contract Radiation Protection

Technician covering the work on the day that the overexposure

occurred,

made

an effort to officially stop the work in

accordance

with station procedures.

This was identified in

NRC

Inspection

Report 50-529/88-22

and the licensee's

evaluation.

The

SPEER did not address

the status of the licensee's

ALARA

program discussed

herein.

The

SPEER states

that the

ALARA

reviewer was remiss

because it was felt that

he could have

been

more involved in the pre job planning.

The

SPEER did not

address

the lack of involvement by the

ALARA Committee.

The

SPEER identified that the assigned

ARC Radiation Protection

Technician performed the functions of Radiation Protection

Technician

and decontamination

foreman for the job,

Reference

B(7) was

issued

on July 29,

1988,

as

a result of this finding.

The letter essentially

requested

that workers should not be

assigned

to perform dual responsibilities.

On August 9, 1988,

the inspector

spoke to two workers working in the Unit 2

Auxiliary Building.

The

ARC Radiation Protection Technician

that had provided the coverage

during the work involving the

overexposure

was providing radiation protection

coverage

for

the August

9 job.

The workers informed the inspector that the

ARC Radiation Protection Technician

was also the

Foreman for

the job.

Based

on

a further discussion with the contract Radiation

Protection Technician,

the observation

regarding

a second rapid

rise

on the teledosimetry

device

was determined

to be incorrect

due to

a misunderstanding

on the part of the

NRC inspector.

The exposed

individual was told to exit the area

based

on the

expiration of his staytime.

The teledosimetry

device

had only

registered

a rapidly increasing

dose

on one occasion,

not two

as is indicated

on page

5 of Inspection

Report 50-529/88-22.

F.

Conclusions

The inspector discussed

the above observations

with the licensee's

staff.

The staff acknowledged

the inspector's

observations.

The

following areas

were discussed:

Failure of the ALARA program to function in accordance

with

ALARA implementing procedures.

Failure of key staff members

to notify management

of the

deterior'ation of the

ALARA program in a timely manner.

10

Failure to take timely corrective actions.

Failure of the licensee's

investigation (e.g.

SPEER)

to surface

the findings identified by licensee

internal audits

and the

inspector.

The failure of the

ALARA Committee

and other portions of the

ALARA program

may be germane

to the overexposure

event.

The licensee's

staff acknowledged

the inspectors

observations.

The

staff felt that the failure of the

ALARA Committee did not have

a

direct affect on the overexposure

of May 23,

1988.

The inspector

informed the licensee

that failure to implement the

ALARA program procedura'1

requirements

as described

in paragraph

(c)

above

was

an apparent violation (50-528/88-27-01,

50-529/88-26-01

and 50-530/88-25-01).

3.

Radiation Protection,

Plant Chemistr

, and Radwaste:

Or anization

and

ana

ement Contro

s

An examination

was conducted

to determinine if the licensee's

radiation

protection,

chemistry

and radwaste

groups

are organized,

staffed

and

motivated to effectively control radiation, radioactive material

and

plant chemistry.

Discussion related to this subject

were held with the

Manager,

Central

Radiation Protection

and the inspector

reviewed

applicable portions of Region

V Inspection

Reports

50-528/87-24

and

50-528/88-13.

The examination disclosed that the organizational

structure

had not

changed

from what is discussed

in Inspection

Reports

50-528/87-24

and

50-529/88-13.

The Manager,

Central Radiation Protection is designated

as

the acting Regulatory Guide 1.8 qualified Radiation Protection

Manager

pursuant to the operating license for Units I, 2 and 3.

This position

was previously held by the Manager,

Radiation Protection

and Chemistry

(RP8C),

who resigned

in April 1988.

The central

RPM does

not have any

direct supervisory authority over each of the

RPMs assigned

in Units I, 2

and

3 even

though Section 4.6.1. 1 of procedure

75PR-OZZ01,

"Radiation

Protection

Program" states

that the site

RPM is responsible

for ensuring

the radiation protection

program

and station operations

meet the

radiation protection requirements

of 10 CFR Part 19,

10

CFR Part

20 and

10 CFR Part 50, Appendix I".

The acting central

RPb) stated

that he held

weekly meetings with each of the Unit RPMs to ensure

the station

radiation protection requirements

were being met.

Procedure

75PR-OZZOI assigns

each of the Unit Managers

the responsibility

and authority for implementing the Unit Radiation Protection

Program.

The examination also disclosed:

t

Not all of the Unit RPMs meet Regulatory

Guide 1.8 qualification

requirements.

11

The Radiation Protection

Standards

supervisor

was assigned

as acting

Manager,

Radiation Protection

and Chemistry.

The acting Manager,

RP&C has

been assigned

as

a back

up central

RPM;

Weekly counter-part

meetings

in the area of Chemistry are not

normally held with each of the Unit 1,

2 and

3 Chemistry Managers.

The Director, Standards

and Technical

Support stated that

a program,

similar to that adopted

by the Site

RPM, is being considered

in the

Chemistry area to ensure

consistency

and to ensure that the

Chemistry program requirements

are being met.

Staffing in the area of Chemistry,

Radiation Protection

and Radwaste

was consistent with licensee's

procedures.

The inspector

concluded that the licensee's

organization

was consistent

with Technical Specifications 6.2 as

amended

in December of 1987.

The

amendment

involved a complete reorganization of the Radiation Protection,

Chemistry and Radwaste

organizations,

as described

in the Inspection

Reports

referenced

herein.

Many members

(e.g. fifteen to twenty) of the licensee's staff expressed

their opinion to the inspector that the reorganization

has

had

a negative

effect on the radiation protection,

chemistry and radwaste

groups.

The

opinions were not solicited by the inspector.

The staff members (i.e.

from management

level to working level) freely expressed

their personal

opinions that they felt the reorganization

was not working well and the

effectiveness

of the programs

had been

reduced.

This observation

was brought to the licensee's

attention at the exit

interview.

4.

Units

1

2 and

3 Facilities

(83727

The radiation protection,

radwaste,

'laundry and chemistry laboratory

areas

of the three units were toured during the inspection.

Discussion

with the plant staff'evealed

that

a

new respiratory processing facility

was placed in service

on or about July 28,

1988 (see

paragraph

7,

herein).

The respiratory processing facility represents

a change

from

what was previously reported in Region

V Inspection

Reports

50-528/87-18,

50-529/87-19

and 50-530/87-20.

The licensee 'ry Act.ve Waste Processing

and Storage

(DAWPS) facility

was a'Iso placed in service since this subject

was last examined.

A

description of the

DAWPS is provided in Section 11.4.2.5 of the Updated

Final Safety Analysis Report.

Discussions

with the licensee's staff revealed that

no further additions

or major changes

in radiation protection facilities are being planned for

or considered.

The staff stated that current facilities appear

to

adequately

support the radiation protection

program.

5.

Onsite Followu

of Re orts of Nonroutine Events

92700

Closed

Licensee

Event

Re ort 50-529/88-07-LO

4

I

i

12

This report concerned

an actuation of the fuel building essential

ventilation system

(FBEVS) and control

room essential

ventilation system

(CREVS) by a fuel building ventilation exhaust radiation monitor (RU-145)

mal function.

Engineered

safety features

functioned

as designed.

The

inspector verified that the fuel building was evacuated,

locked and

posted

upon

FBEVS actuation

and control

room recognition of a saturation

indication on RU-145.

No fuel movements

occurred while RU-145 and

RU-146

were inoperable.

Gas

grab samples

were obtained shiftly while the

monitors were inoperable,

as required..

The faulty system microprocessor

board

was replaced,

and

no further problems

had been observed.

An

Engineering Evaluation Request

(EER)

had

been

issued for a previous

system

board malfunction observed

during

a functional test of the

monitor.

The System E'ngineer stated that root cause of failure of the

system

board for the

FBEVS actuation

event would be determined

under the

prior EER.

This item is closed.

The inspectors

conducted

several

tours of Units

1 and

2 radiologically

controlled areas,

outside radioactive material

storage

areas

adjacent

to

Units 1,

2 and 3,

and of the respiratory processing facility located in

trailers 3-2 and 41.

Independent

radiation measurements

were conducted

using

a Model

RO-2 ion chamber survey instrument,

Serial

82691,

due for

calibration

on October

14,

1988.

The inspectors

made the following observations:

a.

The stripchart for the Eberline

AMS-3 monitoring Trailer 3-2 exhaust

had apparently

run out during the weekend of July 30 - August 1,

1988.

The licensee's

staff immediately replaced

the strip chart

after it was brought to their attention

by the inspector.

Discussions

held with the licensee's

staff disclosed that Trailer

3-2 was recently modified for the purpose of decontaminating

and

processing of respiratory equipment that are required for reuse.

The inspector

was informed that Trailer 3-2 was put into service

on

or about July 28,

1988.

The trailer is equipped with all of the

necessary

equipment

needed for cleaning

and processing

respiratory

equipment that are

used site wide.

Previously, this function was

performed in a mobile laboratory.

The trailer is equipped with its

own

HVAC system which is continuously monitored with an Eberline

AVES-3 continuous air monitoring system.

Respirators

requiring

processing

are stored in the facility until such time that they are

returned to the units for reuse.

10 CFR 50.59(b)(1) states

4a part, that:

"The licensee

shall

maintain records of changes

in the facility...made pursuant

to this

section,

to the extent that these

changes

constitute

changes

in the

facility as described

in the safety analysis report....

These

records

must include

a written evaluation...."

Sections

11.4

and 12.5 of the licensee's

Final Safety Analysis

Report

(FSAR) identify systems

and facilities that are within the

13

site boundary that have

been

approved for handling

and processing

of

radioactively contaminated material.

Contrary to the above, Trailer 3-2 was recently converted into a

respiratory processing facility.

At the time of this inspection,

the trailer was being used to temporarily store

and process

radioactively contaminated

respirators.

As of August ll, 1988, the

licensee

had not performed

a written safety evaluation

addressing

the processing of radioactive

equipment

in Trailer 3-2.

This observation

was brought to the licensee's

attention

who agreed

that

a safety evaluation

should

have

been performed.

The inspector

was

informed that the licensee's

staff has

been

requested

to perform

a written safety evaluation.

The inspector

informed the licensee

that failure to perform the written evaluation

was

an apparent

violation (50-528/88-27-02,

50-529/88-26-02,

50-530/88-25-02).

. b.

10 CFR Part 19. 11, "Posting of Notices to Workers", states

in part:

"(a)

Each licensee

shall post current copies of the following

documents..."-

"...(4)

Any notice of violation involving radiological working

II

conditions, ...

"...(d)

Documents,

notices,

or forms posted pursuant to this

section shall appear in

a sufficient number of places

to permit

individuals engaged

in licensed activities to observe

them

on the

way to or from any particular licensed activity location to which

the document applies,

shall

be conspicuous,

and shall

be replaced if

defaced or altered.

"(e)

Commission

documents

posted pursuant

to paragraph

(a)(4) of

this section shall

be posted within 2 working days after receipt of

the documents

from the Commission;

the licensee's,response,

if any,

shall

be posted within 2 working days after dispatch

by the

licensee.

Such

documents

shall

remain posted for a minimum of 5

working days or until action correcting the violation has

been

completed,

whichever is later."

On August 4, 1988,

the inspectors

noted that copies of a Notice of

Violation accompanying

Inspection

Report 50-529/88-14

dated July ~,

1988,

and the licensee's

response

to the

NOY, dated August 1, 1988,

were not posted

on the way to licensed activity locations within

Units 1,

2 and 3.

Discussions

held with the licensee's

staff and

a

review of the inspection report revealed

the following:

The violations identified in the

NOV involved:

(1)

a shipment

of radioactive

waste which arrived at the burial site with

loose chain restraints,

and the shipment

was observed

to have

shifted during shipment

as evidenced

by loosened

or broken

bracing,

and (2) the failure to perform an evaluation prior to

a release

of 15.3 curies of noble gases

that had

been vented

from portions of the gaseous

radwaste

system.

4

14

C.

The licensee's

Compliance Supervisor stated that

he had

reviewed the

NOV and determined that the violation, as

described

in Appendix A, did not involve

a violation of

radiological working conditions.

He concluded that no

Technical Specifications limits were exceeded

and the release

did not have

any effect on workers within or outside

the site

boundary.

The inspector. noted that the text of the inspection

report revealed that the release

involved the venting the

gaseous

radwaste

system

by the depressurization

through drain

valves to the Radwaste

Building Sump.

It is believed that the

released

noble gases

flowed from the

sump through the drain

system to the

140 foot elevation

and into the

HVAC system to

the plant vent.

The inspector

concluded that radiological

working conditions of the plant workers could have

been

affected; but, agrees

that the release

was not that significant

and that

no plant workers

became

contaminated.

The inspector discussed

the above observation with the

Compliance supervisor

and at the exit interview.

The

Compliance supervisor

iranediately posted

the

NOV and

implemented

a policy that all

NOV involving radiation

protection activities would be posted

in the future.

The

inspector

concluded that the licensee's

actions

were both

appropriate

and timely under the circumstances.

The inspector

noted

some inconsistencies

in the policies established

in radiation protection

programs

being implemented at Units

1 and 2.

The inspector noted that Unit 2 unit allows personnel

to don

protective clothing (PC) at various satellite stations

located at

various locations within the controlled area,

such

as

the Radwaste

Building.

The Unit

1 Radiation Protection

Manager

does

not allow

workers to use satellite stations for donning protective clothing.

Personnel

required to don

PCs in unit

1 must

don their clothing at

the radiation protection control entry point.

Similarly, one Unit

displays instructions for the removal of PC's while another Unit has

done

away with the posted instructions.

These observations

were brought to the attention of the licensee's

staff during the inspection

and at the exit interview.

d.

No unmonitored personnel

were observed

in the areas

that were

toured.

e.

All portable radiation detection

instruments

observed

were in

current calibration.

On August 9, 1988, the inspector

noted

some inconsistencies

in the

barricading

and posting of high radiation

and contaminated

areas

located in Unit 2 "A" and "B" Shutdown Cooling Pipe Gallery and Heat

Exchanger

rooms.

The following observations

were made.

(1)

The outlet end of the Unit 2 "A" Shutdown

Heat exchanger

had

whole body radiation levels of 140 mrem/hr at eighteen

inches.

The area

was not barricaded

in that the installed barricade

had

0

15

come loose

from the heat

exchanger

casing

and part of it was

on

the floor.

(2)

Radiation levels of 120 mrem/hr at eighteen

inches

from Unit 2

"B" Shutdown cooling valve S1B-V910 were not conspicuously

posted

and one side

was, not barricaded.

(3)

Radiation levels of 150 mrem/hr at eighteen

inches

from Unit 2

"A" Shutdown Cooling valve SlA-V172 and piping EW-UV65 were not

conspicuously

posted

and two sides of the area

were not

barricaded.

One side, consisting of a four to five foot pipe

penetration

opening adjacent

to this area,

had not been

posted

at all.

The opening provided access

to both the high radiation

area

and

a contaminated

area

located in the pipe gallery side

of the Heat Exchanger.

The inspector

noted that personnel

could have entered

areas

(2) and

(3) without observing

the one sign that was installed in both areas.

The inspector notified the acting Radiation Protection

Manager

who

took immediate action to have the area

resurveyed

and reposted.

Independent

radiation mea'surements

were obtained

by the

RPM with an

identical survey instrument

used

by the inspector.

The licensee's

radiation measurements

were in agreement with the inspector's.

The

RPM stated that the areas

had not been properly posted,

as

prescribed

in station radiation protection procedures.

The

RPM

subsequently

reported that one barricade

in "A" Heat Exchanger

pipe

gallery (e.g.

item (3), above),

had

become

loose,and

part of it was

on the floor.

Technical Specifications,

6. 12. 1 states,

in part:

"In lieu of the "control devices" or "alarm signal" required

by

paragraph

20.203(c)(2) of 10 CFR Part 20,

each high radiation area

in which the dose rate is greater

than

100 mrem/hr but less

than

1000 mrem/hr shall

be barricaded

and conspicuously

posted.

Additionally,'icensee

procedure

75RP-OZZOl, "Radiological Posting",

Section 6. 1, requires that radiologically controlled areas

shall

be

identified by prominently displayed

signs at all accessible

sides,

specifying the types of hazards

(e.g. radiation, airborne,

contaminated,

etc.).

Section 6.2 of the procedure

requires

that

radiation

p) otection shall

segregate

radio'logically controlled area

by enclosing

the area

boundaries

with magenta

and yellow ribbon,

rope or tape.

The above observations

were brought to the licensee 's attention at

the exit interview.

The licensee's

staff acknowledged

the

inspectors

observations.

The inspector

informed the licensee that

failure to conspicuously

post

and barricade

the high radiation areas

was

an apparent violation (50-529/88-26-03).

7.

Exit Interview

e

16

The inspectors

met with the individuals denoted

in paragraph

1 at the

completion of the inspection

on August 11,

1988.

The scope

and findings

of the inspection

were summarized.

The licensee

was informed of the

apparent violations discussed

in paragraphs

2, 6(a)

and 6(f).

The inspector

informed the licensee

that the apparent violations

discussed

in paragraphs

2 and 6(f) would be discussed

during the August

17,

1988,

Enforcement

Conference

and the apparent violation discussed

in

paragraph

6(a) would be addressed

in this inspection report.

The licensee

acknowledged

the apparent violations.