ML17291A869

From kanterella
Jump to navigation Jump to search
Insp Rept 50-397/95-14 on 950424-0523.Violations Noted But Not Cited.Major Areas Inspected:Refueling & Inservice Insp Activities & Licensee Response to NRC Bulletin 90-001,suppl 1
ML17291A869
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 06/15/1995
From: Powers D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML17291A868 List:
References
50-397-95-14, IEB-90-001, IEB-90-1, NUDOCS 9506230088
Download: ML17291A869 (30)


See also: IR 05000397/1995014

Text

ENCLOSURE

U.S.

NUCLEAR REGULATORY COMMISSION

REGION IV

Inspection

Report:

50-397/95-14

License:

NPF-21

Licensee:

Washington

Public Power Supply System

3000 George

Washington

Way

P.O.

Box 968,

MD 1023

Richland,

Washington

Facility Name:

Washington Nuclear Project-2

Inspection At:

Richland,

Washington

Inspection

Conducted:

April 24 through

May 23,

1995

Inspectors:

Lawrence

E. Ellershaw,

Reactor Inspector,

Maintenance

Branch

Division of Reactor Safety

Charles J.

Paulk,

Reactor

Inspector,

Maintenance

Branch

Division of Reactor Safety

John

E. Whittemore,

Reactor

Inspector,

Maintenance

Branch

Division of Reactor Safety

Approved:

r.

a

e

.

owers,

>e

,

a>ntenance

Branc

Division of Reactor Safety

oc/i~j'e ~

Date

Ins ection

Summar

Areas

Ins ected:

Routine,

announced

inspection of refueling

and inservice

inspection activities,

and licensee

response

to

NRC Bulletin 90-01,

Supplement

1,

"Loss of Fill-Oil in Transmitters

Manufactured

by Rosemount,"

in

accordance

with Temporary Instruction 2515/122,

"Evaluation of Rosemount

Pressure

Transmitter

Performance

and Licensee

Enhanced

Surveillance

Programs."

Also, followup was performed

on the securing of the residual

heat

removal

system while in the shutdown cooling mode.

Results:

Plant

0 erations

~

Excellent performance

was observed

during refueling operations.

Communications

were found to be effective

and very good

(Sections

2 and 3).

950b230088

950b19

PDR

ADOCK 05000397

9

PDR

~

The licensee

violated the Technical Specifications

by allowing shutdown

cooling to remain off for 25 minutes

more than permitted

by the

Technical Specifications.

This was

a noncited violation (Section 6.2).

Maintenance

~

Magnetic particle testing

was performed well by certified examiners

(Section 4,2).

~

A failure to implement procedures

for certifying qualification of

nondestructive

test personnel

was identified as

a noncited violation

(Section 4.3).

~

Procedures

for the performance of ultrasonic testing

were well written,

in general.

One example

was identified as

a noncited violation for not

adequately

addressing criteria for determining that important activities

had

been

accomplished

(Section 4.4).

With only one exception,

transmitter data

from calibrations required

by

the preventive

maintenance

program were found to be properly recorded

(Section 5.8).

En ineerin

~

There were strong technical

elements

in the

Rosemount transmitter

enhanced

surveillance

program (Section 5.3.2).

~

The transmitter trending program conservatively

exceeded

the scope

recommended

by the vendor

(Section 5.4).

~

The failure to question

or pursue missing or incomplete data for the

enhanced

surveillance

program

was

a weakness

(Section 5.7).

~

Licensee

actions related to the identification and disposition of failed

or failing transmitters

were conservative

(Section 5.9).

Plant

Su

ort

~

Foreign material controls

were good (Section 2).

~

Initial and continuing training provided to instrument

and control

technicians

regarding loss of fill-oil in Rosemount transmitters,

was

a

strength

(Section 5.3.2).

Mana ement Overview

~

The operations

manager

provided strong oversight

by his presence

on the

refueling bridge during refueling operations

and his guidance

given to

operators

during off-normal working hours

(Sections

2 and 3),

0

Summar

of Ins ection Findin s:

~

Three

examples of noncited violations were identified (Sections

4.3,

4.4,

and 6.2).

~

Inspection

Followup Item 397/9514-01

was opened

(Section 5.8).

Attachments:

~

Attachment

1

Persons

Contacted

and Exit Meeting

~

Attachment

2 - Data Required

by Temporary Instruction 2515/122

DETAILS

1

PLANT STATUS

During this inspection period,

the plant was

shutdown for the tenth refueling

outage.

2

REFUELING ACTIVITIES (60710)

The purpose of this part of the inspection

was to ascertain

whether refueling

activities were being controlled

and conducted

by operations

in accordance

with Technical Specifications,

approved

procedures,

and safe practices.

The inspectors

observed

core alterations

on four different shifts of operators

during this inspection.

The inspectors

found that the required Technical

Specifications

and administrative

procedures

were followed.

Prior to the

commencement

of core alterations,

contractor-supplied

personnel

performed hydrolasing

on the feedwater

nozzles to reduce radiation levels.

The inspectors

observed this activity and noted that the procedure

was being

followed by the workers.

In order to ascertain

whether the procedures

were being properly implemented,

the inspectors

reviewed the fuel handling

and service

procedures,

and the

refueling operations

procedures.

The inspectors

also reviewed the procedure

for foreign material control.

The procedures

were:

Procedure

1.3.18

2.14.1

6.3.2

6.3.5

6.3.28

Title

Foreign Material Control Around the

Spent

Fuel

Pool, the Reactor Cavity

and the Dryer-Separator

Pit

Refueling Hridge Operation

Fuel Shuffling and/or Offloading and

Reloading

Full Core Verification

Nuclear

Component Transfer List

Preparation

Revision

Date of Issue

12

April 12,

1995

April 27,

1995

April 26,

1995

7

May 10,

1994

2

February

27,

1995

7.4.9.6

Refuel Platform Crane

and Hoist

Interlock Surveillance

13

April 27,

1995

The inspectors

observed

excellent

performance

by the operators

on the bridge

during core alterations.

The communications

were very good;

repeat

backs

were

used effectively.

Whenever

an operator

had

a question related to the core

alteration, activities stopped until the question

was resolved.

The

inspectors

observed

the operations

manager

inform the operators

that they

should ensure that they understood

exactly what was being done; if not, then

they were to stop

and resolve the issue.

The operations

manager told the

senior reactor operator not to worry about the schedule,

but ensure

the

activities were performed properly.

The inspectors

also observed

core alterations

from the control

room.

The

operator

assigned

to the core alterations

had

no concurrent responsibilities

and

was keeping the control

room supervisor

informed.

At one point, the

control

room supervisor

stopped

core alterations

because

the containment

pressure

had dropped

below the Technical Specification allowable for

approximately

30 seconds

while the ventilation was shifted from the standby

gas treatment

system to normal containment ventilation.

The control

room

supervisor did not allow core alterations

to restart until the ventilation

system

was returned to normal with acceptable

containment

pressure.

The

inspectors

considered

these

actions

proper

and conservative.

The inspectors

found the control of foreign material

to have

been very good in

spite of a procedure that was difficult to implement.

On April 27,

1995,

an

operator

on the refueling floor initiated

a problem evaluation

request that

identified components

that were not secured

on the bridge in accordance

with

Procedure

1.3. 18.

The inspectors

observed

the operator take the immediate

corrective actions

before bridge activities were allowed to continue.

The inspectors

discussed

the responsibilities

of the foreign material control

watch person with several

of the watch standers.

Host of the watch standers

were familiar with the intent of the procedure,

but stated that they had

questioned

how they were to implement portions of the procedure.

The areas of

most concern

were documenting

what material

was in the foreign material

control

zone

and

who was responsible

for it.

The inspectors

discussed

this

with the reactor engineering

manager

who was responsible for the refueling

activities.

The inspectors

found that the reactor engineering

manager

was

aware of the difficulties and that improvements

were being discussed

and

evaluated

as part of the response

to the problem evaluation request.

The

inspectors

considered this to have

been the proper approach to resolving the

difficulties experienced

by the watch standers.

3

SPENT

FUEL POOL ACTIVITIES (86700)

The purpose of this part of the inspection

was to ascertain

that the spent

fuel handling activities were performed in accordance

with Technical

Specifications,

regulatory requirements,

and safe practices.

The inspectors

observed

the manipulation of spent

and

new fuel in the spent

fuel pool.

In order to determine if the operation

was in accordance

with

procedures,

the inspectors

reviewed the following procedures

related to

handling fuel assemblies

in the spent fuel pool.

Procedure

No.

1.3.40

Title

WNP-2 Outage

Mode Change or

Refueling Activity Readiness

Evaluation

Revision

Date of Issue

6

April 24,

1995

2.8.5

6.3.10

6,3.16

6.3.23

Handling Irradiated

Fuel in the

Spent

Fuel

Pool

3

April 26,

1995

Fuel

Pool Cooling and Cleanup

System

19

January

10,

1995

Post Irradiated

Fuel Surveillance

4

May 10,

1994

Irradiated

Fuel

Channel

Inspection

2

June

15,

1993

The inspectors verified that the procedures

contained:

a limitation on the

number of fuel assemblies

that could

be out of safe

geometry locations

simultaneously

(Procedure

6.3.23); provisions for verifying that the spent

fuel storage

area

crane interlocks or physical

stops

prevented

the crane

from

passing

over fuel storage

positions

(Procedure 6.3.2); provisions for

verifying that the spent fuel pit hoist

and related

handling tools were

checked for proper operation

(Procedure 6.3.2); verification that procedures

did not rely on limit switches to function as normal stopping devices

(Procedure

2. 14

F 1); and, provisions to verify that the spent fuel area

ventilation system

was operating

as required, that the efficiency of the

absolute

and charcoal filter systems

had

been determined,

that secondary

containment

would isolate

on

a high radiation signal, that the minimum water

level requirements

were monitored,

and that radiation

and airborne

radioactivity monitors were operable

(Procedure

1.3.40).

The inspectors

noted

that the spent fuel pool cooling

and cleanup

system

was not

a system required

specifically by the Technical Specifications.

These

systems

were operated

in

accordance

with Procedure

2.8.5,

"Fuel

Pool Cooling and Cleanup

System,"

Revisibn

19,

issued

January

10,

1995.

The inspectors verified by direct observation that:

the spent fuel pool water

level

was higher than the minimum level established

in the Technical

Specifications;

the secondary

containment ventilation system maintained

the

building at the specified negative

pressure,

except

as discussed

above;

the

spent fuel pool cooling and cleanup

system

was maintaining pool temperature;

personnel

handling fuel were properly qualified and supervised;

fuel handling

activities received

reviews required

by the Technical Specifications;

an

accurate

record of the fuel location

was being maintained;

and,

spent fuel

pool activities were conducted

in accordance

with approved

procedures.

The inspectors

observed

the

same excellence,

noted

above,

in the handling of

fuel assemblies

in the spent fuel pool.

Communications

were very good

among

the operators.

On April 7,

1995,

the Washington Public Power Supply System sent

a letter of

notification of a change

in commitment to the

NRC.

The change

was to perform

visual inspection

only on discharged

fuel where there

was indication of either

actual

or suspected

gross cladding defects

or anomalies.

This differed from

the previous

commitment to perform

a visual inspection

on

5 to

10 percent of

the highest

burnup assemblies

of the discharged

fuel,

The inspectors

reviewed the last three reports for the inspections

and found

that

no problems

were identified.

A reactor engineer

informed the inspectors

that there

had not been

any fuel failures since the original (Cycle 1) fuel

had

been replaced.

The inspectors

also reviewed

Procedure

6.3. 10,

"Post Irradiated

Fuel

Surveillance,"

Revision 4,

issued

May 10,

1994,

and Procedure

6,3. 16,

" Irradiated

Fuel

Channel

Inspection,"

Revision 2,

issued

June

15,

1993.

The inspectors

found the procedures

provided adequate

instructions for the

inspection of the irradiated fuel assemblies

and channels.

The inspectors

inquired about the licensee

plans to change fuel vendors

and

how that could affect the change

in commitment.

The inspectors

were informed

that fuel from the

new vendor

had

been installed for several

operating cycles

and

had

been

inspected

during the refueling outages.

No indications of

excessive

crud or oxide layer buildup were found during any of the

inspections.

The reactor engineer

considered

those inspections

to have

been

adequate

to demonstrate

that there

should not be any problems

when

a full core

load of the

new fuel occurs,

therefore,

the change

in commitment should not

have

a negative effect

on safety.

The inspectors

found this deduction to be

reasonable.

4

INSERVICE INSPECTION (73753)

The objective of this part of the inspection

was to determine

whether

inservice inspection

examinations

were performed in accordance

with Technical

Specifications

and the American Society of Mechanical

Engineers

(ASME) Boiler

and Pressure

Vessel

Code.

The inspection

was primarily conducted with major emphasis

placed

on

observation of examination

performance,

nondestructive

examination

personnel

qualifications,

and evaluation of nondestructive

examination

procedures.

Minor emphasis

was placed

on the inservice inspection

program status.

4.1

Inservice

Ins ection

Pro

ram

The second

10-year interval inservice inspection

program plan, "ISI Program

Plan,

Interval

2," Revision 0, dated

December

1994,

in effect at the time of

this inspection,

was developed

to meet the

1989 Edition of Section

XI of the

ASME Code.

The inspectors

found that guidance for implementation of the

inservice inspection

program was provided in Nuclear Operating

Standards

NOS-33,

" Inservice Inspection,"

Revision 7;

and Engineering

Directorate

Procedure

EDP-4.4,

"Preparation of Inservice

Inspection

Program

Plans,"

Revision

5.

The inspectors

also noted that Section

2.0 of the

qualification and certification program, "gualification/Certification of

Examination

Personnel

in Accordance with SNT-TC-lA for Nondestructive

Examination," Revision 9, contained

the guidance

and responsibilities for

personnel

certifications,

and is discussed

in more detail

below (Section 4.3).

4.2

Observation of Nondestructive

Examinations

The inspectors

observed

the following weld examinations:

magnetic particle

examination of main steam line pipe to Elbow Weld 26HS(1)A-6 on April 28,

1995; magnetic particle examination of main steam line penetration

pipe to

Valve Weld 26MS(1)A-17,

on May 1,

1995;

two ultrasonic examinations

of reactor

feedwater line pipe to Elbow Weld 12RFW(1)AC-6 and elbow to Pipe

Weld,12RFW(1)AC-7,

on Hay 1,

1995; three ultrasonic examinations

of main steam

line penetration

pipe to Valve Weld 26MS(1)A-17, valve to Pipe

Weld 26HS(1)A-18,

and pipe to Pipe

Weld 26HS(1)A-19,

on Hay 2,

1995;

and,

three ultrasonic examinations

of reactor feedwater line pipe to Valve

Weld 24RFW(1)A-lA, valve to Pipe

Weld 24RFW(1)A-1,

and pipe to Weldolet

Weld 24RFW(1)A-1/5RFW(11)-4,

on Hay 2,

1995.

The observed

magnetic particle examinations

were performed well by certified

examiners

using qualified Nondestructive

Examination

& Inspection

Instruction gCI 4-3,

"Magnetic Particle

Examination

WNP-2," Revision

6 (see

Section 4.4 below).

The examiners verified the yoke-lifting capacity

and

established

the yoke-leg spacing at

6 inches.

Upon completion of the

examinations,

the examiners

properly documented

the results of the

examinations

in Examination Reports

2MSH-010 and

2HSM-011.

The eight observed ultrasonic examinations

were performed

by certified

examiners

using qualified Nondestructive

Examination

& Inspection

Instruction gCI 6-13, "Ultrasonic Examination of Ferritic Steel

Piping Welds,"

Revision

7

(See Section 4.4 below).

The inspectors verified that the

examiners

checked

surface

temperature

and assured

proper cleanliness

of the

area to be examined.

To the extent that geometry allowed, the examinations of

the circumferential

welds were conducted

in two directions for each of the

perpendicular

and parallel

scans

to the weld axis,

using

a 45~,

2.25

MHz shear

wave transducer.

The examiners

also performed

a calibration check at the

beginning

and

end of each examination.

Upon completion of the examination,

the examiners

properly documented

the results

in Examination

Reports

2-011

through 2-018.

Before the ultrasonic examinations

were conducted

on Hay 1,

1995,

the

inspectors

observed

the system calibration which included both axial

and

circumferential

scans.

The transducer

selection,

sensitivity calibration,

and

construction of the distance

amplitude correction curve were performed

appropriately in accordance

with the procedure.

The inspectors

also verified,

by review of the certified material test report, that the correct calibration

block was

used (i.e., similar to the component to be examined

in terms of

material,

diameter,

and wall thickness).

During observation of ultrasonic examinations,

two instances

arose

which

appeared

to indicate confusion

on the part of certain

examiners

regarding

what

constituted

a recordable

indication.

On two separate

occasions,

the

inspectors

questioned

the examiners

when it appeared

that indications of

approximately

50 percent of the distance

amplitude correction curve were

observed

on the scope without any apparent

actions

taken

by the examiners

to

determine

whether the indications

were of geometric or metallurgical origin.

Both examiners

stated that they considered

the indications to be geometric in

nature.

Upon questioning

by the inspectors

about the observations,

the

examiners

took appropriate

measurements/recordings

in order for the required

determinations

to be made.

The inspectors

reviewed the subsequent

evaluations

of the examiners'ata,

which included reexamination

using

a 60'ransducer.

The Level III examiner for the plant determined that the indications were of

geometric origin,

and validated the examiners'nderstandings.

Further review

of the procedure

by the inspectors

indicated

weaknesses

which are described

below (see Section 4.4,

below).

4.3

Personnel

ualifications

and Certifications

The inspectors

were informed that the licensee

had contracted with a vendor to

provide nondestructive

examination

personnel,

equipment,

and services,

in

order to perform the scheduled

inservice inspections.

The inspectors

reviewed

the qualification files of the five nondestructive

examination

personnel

who

performed the examinations

observed

by the inspectors.

The files contained

proper certifications for the examiners

in the examination

methods that the

inspectors

observed.

The inspectors

also noted that the examiners

had

been

certified in accordance

with American Society of Nondestructive

Testing

Recommended

Practice

SNT-TC-IA, 1984.

The inspectors verified that each of the examiners

had received

the

ASHE

Code-required

annual

near-distance

vision acuity and color vision

examinations.

The examinations,

all of which were current,

had

been

conducted

by the vendor.

Each of the examiners'ertification

packages

had

been

reviewed

and certified by the corporate certification examiner in accordance

with paragraph

3', "Responsibility," of the qualification and certification

program manual.

Paragraph

IWA-2321, in Section

XI of the

1989 Edition of the

ASHE Code,

stated

that personnel

shall

demonstrate

natural

or corrected

near-distance

acuity,

with at least

one eye,

by reading the Jaeger

No.

1 print on

a Jaeger test

chart at not less

than

12 inches.

Equivalent measures

of near-distance

acuity

may be used (e.g.,

Ortho-Rater test).

During review of the vision records,

the inspectors

noted that three records

were not consistent

with ASHE Code

requirements (i.e.,

they

showed results that did not demonstrate

Jaeger

No.

1

natural

or corrected

near-distance

acuity).

The inspectors,

in order to

-10-

determine

the review and acceptance

standards

associated

with contractor

personnel

certifications,

reviewed

paragraph

4.4, "Vision Examination," in the

qualification and certification program manual,

and found the vision

examination

requirements

to be different from the

1989 Edition of the

ASME

Code.

The inspectors

noted that the three vision records

mentioned

above

were

consistent with the requirements

of Paragraph

4.4 in the program manual,

which, during discussion

with the corporate certification examiner,

was found

to be the basis for his review and certification process.

The nondestructive

examination

supervisor

informed the inspectors

that

paragraph

4.4, "Vision Examination,"

was written to incorporate

ASME Code

Case

N-490-1, dated

Hay 13,

1991.

Review of the

Code

Case

showed that it provided

alternative vision test requirements

for nondestructive

examiners

in lieu of

Section

XI near-distance

acuity requirements.

The nondestructive

examination

supervisor stated that the code

case

was

supposed

to have

been

included in the

second

10-year interval inservice inspection

program at the time of submittal

to the

NRC; however,

the code

case

was inadvertently left out.

Since the

submitted inservice inspection

program

was developed

to meet the

1989 Edition

of the

ASHE Code,

any use of a code

case

not committed to in that submittal

has the potential to at least create

an administrative conflict.

Since the licensee

had established

and

implemented

a procedure that

incorporated

the

use of a code

case

not authorized

by their program,

indeterminate

vision examination results

were obtained

and accepted,

thus,

allowing examiners

who may not have

met the requirements

of the

1989 Edition

of the

ASHE Code to perform nondestructive

examinations.

The nondestructive

examination supervisor

on Hay 4,

1995, initiated the following two problem

evaluation requests.

Problem Evaluation

Request

295-0466

addressed

the issue of using

a code

case

that

had not been

committed to in the inservice inspection

program submitted

to the

NRC.

The corrective action

was to revise paragraph

4.4 Section

2.0 of

the qualification and certification program manual,

to remove the provisions

of Code

Case

N-490-1.

Problem Evaluation

Request

295-0467

addressed

the issue of the vendor's

use of

alternative vision examination

requirements

while testing the inservice

inspection

personnel,

and the failure to detect

the documented

use of the

alternative

requirements.

The nondestructive

examination

supervisor took

immediate corrective action

by stopping all nondestructive

examinations

and

administering

new vision examinations

to the affected personnel,

all of whom

passed.

The inspectors verified that the vision examinations

met the

requirements

of the

1989 Edition of the

ASHE Code.

The inspectors

informed the nondestructive

examination

supervisor that the use

of a procedure

not appropriate

to the circumstances

was

a violation of

Criterion

V to Appendix

B to

10 CFR Part 50.

The violation, however, will not

be cited because

the criteria specified in Section VII.B.(l) of Appendix

C to

10 CFR Part 2 have

been met.

-11-

4.4

Inservice

Ins ection Procedures

The inspectors

reviewed the following nondestructive'examination

procedures,

including the two used during the performance of the observed

examinations,

to

verify that they were consistent

with the requirements

of the

1989 Edition of

the

ASME Code.

These

were:

Nondestructive

Examination

8 Inspection

Instructions

QCI 3-3, "Liquid Penetrant

Examination - WNP-2," Revision 5;

QCI 4-3,

"Magnetic Particle Examination - WNP-2," Revision 6;

and,

QCI 6-13,

"Ultrasonic Examination of Ferritic Steel

Piping Welds," Revision 7.

The

inspectors verified that the procedures

had

been

reviewed

and approved

by the

appropriate

licensee

personnel

and

by the authorized

nuclear inservice

inspector.

In general,

the procedures

were found to be well written and contained

sufficient detail

and instructions to perform the intended

examinations.

One

exception

was identified; it pertained

to ultrasonic examination

Procedure

QCI 6-13.

Mandatory Appendix III to Section

XI specified

minimum

information requirements

that must

be included in written ultrasonic

examination

procedures.

One of those

requirements

(Article III-2300 (g))

dealt with the data to be recorded,

the method of recording,

and,

by reference

( III-4510) the methodology to be used

in determining whether indications

were

of geometric or metallurgical origin.

The inspectors'eview

of

Procedure

QCI 6-13 revealed that Step 6.2. 1 required the recording of

geometric or metallurgical indications if they were

50 percent of distance

amplitude correction curve, or greater.

Step

6. 1.3 required the recording of

any other indications which were determined

not to be of geometrical

or

metallurgical origin, if they were

20 percent of distance

amplitude correction

curve, or greater.

However,

the procedure

was silent regarding

the

Code-required

methodology to make the determination

regarding geometric

or

metallurgical indications.

Upon informing the nondestructive

examination

supervisor of the apparent

procedural

deficiency,

the supervisor

immediately held

a documented training

session

with all of the inservice inspection

personnel

performing ultrasonic

examinations.

This session,

held

on May 2,

1995,

was devoted'o

the steps

in

Section 6.0 of Procedure

QCI 6-13, regarding clarification of recording

requirements

for consistent

application.

In addition,

a procedural

change

was

initiated to clarify the recording requirements

and to address

the

ASME

Code-required

indication interpretation

methodology.

The initiated procedure

change

was entered

and

was to be tracked in the plant tracking log under the

assigned

Number A-114645.

The inspectors,

after reviewing the inservice inspection status of completed

ultrasonic examinations

and discussing

the above

issues

with the examiners,

determined that the examiners

had complied with the procedure,

and

based

on

their experience,

had also applied the indication determination

methodology.

The inspectors

informed the nondestructive

examination

supervisor that the

use

of a procedure

which did not adequately

address criteria for determining that

important activities

have

been

accomplished

was

a second violation of

-12-

Criterion

V to Appendix

B to

10 CFR Part 50.

The violation, however, will not

be cited because

the criteria specified in Section VII.B.(1) of Appendix

C to

10 CFR Part 2 have

been met.

5

EVALUATION OF

ROSEMOUNT

PRESSURE

TRANSMITTER PERFORMANCE

AND LICENSEE

ENHANCED SURVEILLANCE PROGRAM

(TEMPORARY INSTRUCTION 2515/122)

This portion of the inspection

was conducted

at the Washington Nuclear

Project-2 site

on May 15-19,

1995.

5.1

~Back round

On March 9,

1990,

the

NRC issued Bulletin 90-01,

"Loss of Fill-Oil in

Transmitters

Manufactured

by Rosemount."

The bulletin discussed

certain

Rosemount

pressure

and differential pressure

transmitter

models identified by

the manufacturer

as being susceptible

to fill-oil leakage,

which could result

in premature failure.

With the gradual

leakage of fill-oil, a transmitter

may not have the long-term

accuracy,

time response,

and reliability needed for its intended safety

function.

Further, this condition could go undetected

over

a long period.

The bulletin requested

licensees

to identify whether these transmitters

were,

or may later be, installed in safety-related

systems.

Actions were detailed

for licensee

implementation if the identified transmitters

were presently

installed in safety-related

systems.

This requested

action included

a

historical review of installed transmitter calibration data to identify any

potential failure of installed transmitters.

The bulletin endorsed

diagnostic

methodology

recommended

in four technical bulletins previously issued

by the

vendor.

On December

22,

1992,

the

NRC issued

NRC Bulletin 90-01,

Supplement

1, to

inform licensees

of continued

NRC staff and industry actions in evaluating

loss of fill-oil in Rosemount transmitters

and to request

actions to be taken

by licensees

to assure

the reliability of transmitters

in use.

Licensees

were

requested

to replace,

or place in an enhanced

surveillance

program

Model

1153B,

1153D,

and

1154 transmitters

manufactured

before July 11,

1989,

that were installed in safety-related

applications.

The purpose of the enhanced

surveillance

program

was to ensure that installed

Rosemount transmitters

met design criteria as highly reliable components

for

which failures could

be readily detected.

Pressure

transmitters

other than

Models

1153B,

1153D,

and

1154 were excluded

from the actions

requested

in the

supplement,

due primarily to few confirmed fill-oilloss failures

and

di-fferences in the oil sensor

design.

Similarly, due to transmitter design,

manufacturing

process

improvements,

and few confirmed failures,

Model

1153B,

1153D,

and

1154 transmitters,

which were manufactured after July 11,

1989,

were also excluded

from the bulletin supplement

actions.

Additional data

collected

on those transmitters

that are outside of the scope of the

supplement will be used to verify failure reports,

determine to what extent

-13-

licensees

notify Rosemount of transmitter failures,

and to confirm that the

actions

requested

by the bulletin supplement

are sufficient.

Model

1151,

1152,

and

1153A transmitters

were excluded

from the actions

requested

by Supplement

1 due primarily to the few confirmed fill-oilloss

failures

and differences

in the oil sensor

design

as

compared to Model

1153B,

1153D,

and

1154 transmitters.

These

design differences

were thought to make

Model

1151,

1152,

and

1153A transmitters

less likely to experience

loss of

fill-oilfailure.

However,

as

a result of a possible similar failure mode,

additional insight into their performance

was necessary

to confirm that their

inclusion in an enhanced

surveillance

program

was not needed.

Similarly, due

to transmitter design

and process

improvements

and few confirmed failures,

Model

1153B,

1153D,

and

1154 transmitters

manufactured

after July ll, 1989,

were excluded

from the list of bulletin supplement

actions.

For these

'ransmitters,

the information requested

in the inspection

guidance will be

used to verify failure reports,

determine

the extent to which licensees

notify

'osemount

of transmitter failures,

and confirm that actions

taken in the

bulletin supplement

were sufficient.

The Washington Nuclear .Project-2 licensee

response

to the bulletin supplement

was provided to the

NRC in Letter G02-93-055,

dated

March 8,

1993.

Response

to

a followup NRC request for additional

information was provided in

Letter G0-94-124,

dated

Hay 23,

1994.

In the initial response,

the licensee

committed to comply with requested

actions of the bulletin supplement.

5.2

Licensee

Dis osition of Stored Transmitters

The inspector

interviewed personnel

and reviewed procurement

records to

determine

how the licensee

had dispositioned

the transmitters,

stored

in the

warehouse,

with high potential for failure,

Personnel

stated that,

in

response

to the bulletin supplement,

a data

search

and inspections

were

conducted

to identify those transmitters

at high risk of failure.

According

to procurement

records that were provided,

a total of 13 transmitters

had

been

returned to the vendor since

NRC Bulletin 90-01

was issued.

The majority of

these transmitters

were refurbished to eliminate the risk of failure and

returned to the licensee.

The licensee

was

asked for a list of all Rosemount transmitters

currently in

the warehouse.

A key word search

on the procurement

system database

provided

a list of all transmitters

plus spare parts provided

by Rosemount.

The

inspector

reviewed the list and determined that

a total of 80 Rosemount

Model

1153B

and

1153D transmitters

were currently in the warehouse.

According

to the information provided, there

were

no Rosemount

Model

1154 transmitters

in the warehouse.

Transmitters

manufactured after July 11,

1989,

were identified by serial

numbers greater

than 500,000

and transmitters

with serial

numbers

ending in

"A", were not at high risk of failure.

The licensee's

database

would not

provide spare transmitter serial

numbers

or date of manufacture.

The

inspector held

a discussion

with a licensee

representative

to determine

the

least intrusive method of checking

spare transmitter serial

numbers.

The

licensee

representative

agreed

to check receipt inspection

records

and provide

the inspector with the serial

numbers.

The inspector

stopped

the process

after the inspection

tags for 42 spare transmitters

had

been

checked

and all

serial

numbers verified to be greater

than 500,000 or ending in "A."

Based

on

this sample of 53 percent of the transmitters

in the warehouse,

with no

adverse

indication,

the inspector

concluded that all transmitters

at high risk

of failure had likely been

removed

from the licensee's

warehouse facilities.

5.3

Enhanced

Surveillance

Pro

ram

5.3. I

Background

In

a series of four technical bulletins issued

by Rosemount,

the required

elements of an enhanced

surveillance

program were developed.

These bulletins

became

appendices

to the

NRC inspection

guidance for addressing

the loss of

fill-oil issue.

The vendor segregated

inservice transmitters

into low,

medium, or high pressure

categories

and further subdivided inservice

transmitters

into two groups:

~

Transmitters that provided safety-related

indications;

and,

~

Safety-related

transmitters that monitored conditions

and initiated

reactor protection trip, engineered-safety

features

actuation,

and

anticipated trip without scram systems.

Therefore,

the enhanced

surveillance

requirements

for a given transmitter

were

determined

from the transmitter service

pressure

and its particular safety

function.

The affected

groups of transmitters

had

been identified by model

number

and

date of manufacture.

The vendor also determined that the risk of fill-oil

loss decreased

as the transmitters

aged in service at normal operating

pressure.

The vendor provided criteria expressed

in psi-months to identify

mature transmitters

that did not require

enhanced

surveillance.

The psi,

as

used

by the vendor,

was defined

as

normal operating pressure.

The threshold

criteria for ceasing

enhanced

surveillance

was the attainment of 60,000 or

130,000 psi-months,

depending

on transmitter

range

code.

Transmitters

not

attaining the required service life at operating

pressure

were classified

as

nonmature.

The following programmatic

elements

were generally

recommended

to effectively

monitor suspect

transmitters

in safety-related

service for impending failure:

The identification of the affected transmitters

to be monitored;

The trend of calibration data

on the percent shift of zero

and

span

(limits for percent shift up or down were established

to require

transmitter evaluation);

-15-

~

Comparative trending of operating

data

on the difference in the output

of redundant transmitters

(transmitter output differences

were to be

evaluated);

and,

~

The ability to detect failures after transmitters

were mature

and

no

longer included in an enhanced

surveillance

program.

Simultaneous

trending of operational

and calibrational

data for a given

transmitter

was not needed for failure identification.

The vendor technical

bulletins also discussed

monitoring methods

based

on the evaluation of

transmitter

sluggishness

or noise,

The required frequency of enhanced

surveillance varied according to the various inservice categories

and

operating

pressure.

5.3.2

Licensee

Program

The licensee's

enhanced

surveillance

program

was

implemented

by

Procedure

8.4.67,

"Rosemount Transmitter

Enhanced Monitoring," Revision 2.

The procedure

provided details in the following areas:

Trending Data Acquisition,

Calculation of Transmitter Drift,

Calculation of Transmitter Drift Limits,

Transmitter Trending,

Determination of Suspected

Oil-Loss Transmitters,

and

Actions for Suspected

Oil-Loss Transmitters.

The inspector

reviewed the procedure

and found it to be comprehensive

with

sufficient detail to administer

an effective program.

A review of the two

previous revisions revealed that the original program

had

been

improved.

The

first revision implemented

an .automatic trending

system

and enhanced

trending

evaluation technique.

The latest revision

had

added

program information,

added cautions for specific range

code instruments,

improved database

instructions,

and streamlined

instructions for determination of drift limits

and analysis of transmitter condition.

The enhanced

surveillance

program

was administered

by one engineer

who had

been responsible for all program

and database

development

and implementation

since inception.

Due to

a previous

commitment, this individual was not

available during the week of the inspection.

However,

the immediate

supervisor

was able to provide all of the information and documentation

necessary

to perform the inspection.

The inspector requested,

and

was given,

a demonstration

of the automated

trending database

that was

used to trend

individual transmitter calibration data.

The data required for a single

transmitter calibration entry was the date

and the transmitter output for the

minimum and

maximum points as-found

and as-left values.

With this information

in the data

base for at least

two calibrations,

the program would

automatically calculate

the interval

between

data entries,

percent

zero shift,

and percent

span shift since the last entry.

The cumulative shift since the

-16-

start of data collection was also trended

and tracked.

For analytical

purposes,

the system would provide hard copy tabular

and graphic information.

Graphic

and tabular depiction also included the

span

and zero shift limits for

the specific transmitter

range

code

as developed

in the vendor technical

bulletins.

According to

a licensee

representative,

the automated

trending

program

had

been

endorsed

by the vendor

as fully capable of providing the

required analytical

informat'on.

The inspector

reviewed documentation

and held discussions

with maintenance

training personnel

to assess

the effectiveness

of training that

had

been

provided to instrument

and control technicians relative to loss of fill-oil

from Rosemount transmitters.

According to records

provided, significant

training was developed

and administered

to technicians prior to issuance

of

NRC Bulletin 90-01., All technicians

(47) attended

an industry events training

presentation

provided in Lesson

Plan 82-14-3789-LP.

Since the bulletin was

issued,

the Rosemount transmitter loss of fill-oil issue

had

been

included in

the New-Hire Training Course

82-ICT-1201-LP.

This course

was recently

administered

to

a majority of current technicians

as continuing training.

The maintenance

training organization

had developed,

and put,into operation,

a

hands-on

laboratory facility containing test loops with actual

components

and

instrumentation.

This training facility was

used

by all disciplines to

actually troubleshoot,

repair,

overhaul,

and calibrate

equipment similar or

identical to that installed in the plant.

Formal training packages

had

been

developed

to train and evaluate

personnel

in the laboratory.

Course 82-ICT-4100-LP,

"Maintenance

Work Practices,"

contained

a scenario that

required

a trainee to perform

a calibration

on

an instrument loop that

contained

a Rosemount transmitter..

A laboratory guide contained evaluation

elements that evaluated

trainee ability to identify a transmitter failure due

to loss of fill-oil.

The inspector

was also

shown documentation

related to training operations

personnel

about the loss of fill-oil issue.

The continuing training program

for licensed

and non-licensed

operators

had resulted

in the administration of

training through the periodic industry events presentations.

The training that the licensee

had provided to technicians

was more

comprehensive

than similar training observed

by the inspector at other

facilities.

In addition, the technical

elements of the enhanced

surveillance

program were strong.

5.4

Sco

e of Trendin

Pro ram

The Washington Nuclear Project-2

program

was currently trending

62

transmitters that

had

been identified by the bulletin supplement

to be at high

risk of failure.

The inspector verified that these transmitters

had

been

placed into the correct surveillance

category

in accordance

with the

recommendations

of the bulletin supplement.

The licensee

had decided

not to

replace,

or return to the vendor for refurbishment,

the originally installed

transmitters.

Therefore, all of the transmitters

identified to be at

increased risk of failure were being trended.

However, all but one of these

-17-

transmitters

could have

been

removed

from the enhanced

surveillance

program

because

they were in a low-pressure

application or had matured

past

60,000 or

130,000 psi-months.

To remove these transmitters

from enhanced

surveillance,

required the licensee

to have the ability to identify a transmitter failure

within the normal activities associated

with transmitter maintenance

or

surveillance,

which was within the licensee's

capabilities.

The inspector

determined that the licensee's

program

was also trending

and

analyzing:

~

26 Model

1153B

and

1153D transmitters

manufactured after July 11,

1989,

in safety-related

applications

and not at risk of failure;

~

35 Model

1151 transmitters;

and

~

3 Model

1152 transmitters.

The licensee's

effort exceeded

the scope

recommended

by the bulletin

supplement.

5.5

Test Interval

All transmitters

subject to calibration data trending in accordance

with the

bulletin supplement fell into categories

where the

recommended

interval

between data collection was

24 months.

However,

a significant fraction of

transmitters

were being trended

annually simply because

annual

data

was

available.

Therefore, all test intervals

were meeting the recommendations

of

the bulletin supplement.

5.6

Monitorin

Techni

ues

Rosemount Inc., developed

methods with guidelines to independently

or in

combination, identify transmitters

suspected

of oil loss.

This section

discusses

the licensee's

implementation of those

methods.

5'. 1

Process

Noise Analysis

Because of interpretation difficulties and

a lack of universal applicability

due to differences

in transmitter application,

the vendor discontinued

the

development

in the use of noise

as

a diagnostic tool.

The licensee

did not

include this monitoring technique

in the enhanced

monitoring program to detect

loss of fill-oil.

5.6.2

Output Drift Analysis

There were two options for output drift analysis.

Normal calibration data

(as-found

versus as-left data)

could be evaluated

to determine

any cumulative

positive or negative drift trends.

Also, trending

and comparison of actual

operating

data

on processes

with redundant transmitters,

could identify

-18-

suspect

transmitters.

Both techniques

were field tested

and

showed the

ability to detect leaking sensors.

The licensee

did not employ any operating

data trending,

but relied

on calibration data trending to predict or identify

transmitter failure.

5.6.3

Sluggish

Response

Sluggish

response

of transmitters

was detectable

with two optional

methods.

One

was

a qualitative test where experienced

technicians

could detect

slow

response

during normal calibration

by monitoring transmitter output while

simulating

a process

input.

Additionally,

a bench test could

be performed

on

suspect

units to confirm and quantify the slow response,

The vendor technical

bulletins stated that monitoring for sluggish

response

was

an acceptable

method of detecting

a failed transmitter after it was

removed

from an enhanced

surveillance

program.

5.6.4

Licensee

Methodology

Procedure

10.24.32,

"PH CAL/TEST - Rosemount

DP Transmitters,"

Revision 9,

required the calibrating technician to identify and report

any sluggish

behavior of transmitter output during calibration.

The procedure for

Rosemount transmitter calibration also required that transmitter output'e

measured directly at the transmitter.

This required the removal of

transmitter

end covers to expose transmitter test terminal's which opened

an

environmentally qualified barrier

on transmitters potentially subject to

a

harsh environment.

The procedure

addressed

this issue

by providing

instructions

on evaluating

and properly restoring the barrier following

successful

calibration.

The inspector

concluded that the licensee

was

employing the proper monitoring techniques

needed to detect failed or failing

transmitters.

5.7

Review and Trendin

of Calibration Data

The inspector

reviewed the trended calibration data

and analysis for the

original

62 transmitters

that were identified as susceptible

to failure,

according to the supplement.

The amount of data collected for most

transmitters

was sufficient to provide for statistically valid trends.

The

implementing procedure

contained

acceptance

for transmitter drift that

mimicked the criteria specified

by the vendor technical bulletin.

A question

arose

concerning

the accuracy of the data trended.

Technical

information from the vendor

recommended

that transmitter output data

be

recorded

and trended

using milliampere fractions to three decimal

places.

The

licensee's

program

used milliampere fractions normally expressed

to two

decimal

places.

The licensee

had queried the vendor

as to the

adequacy

of

this process for identifying failed or failing transmitters.

The vendor

responded

that transmitter output data

measured

at the transmitter in two

decimal

place fractions

and inserted into the automatic trending database

was

sufficiently accurate

to identify failures.

The inspector

concluded that the

-19-

trending of calibration data

was being performed in accordance

with Rosemount

Technical Bulletin No. 4.

During the extensive

review of the hardcopy trending information, the

inspector raised

several

questions

about specific transmitter trending

and

analysis

to the licensee

representatives.

The majority of these

questions

were related to excessive

elapsed

time between

data entries

and past

due or

missing calibration data.

The inspector questioned if the required

surveillance

or preventive maintenance

performed

by the calibration

performance

had

been missed.

Based

on the reaction of licensee

personnel, it

appeared

to the inspector that these

questions

had not been

asked before.

Personnel

were eventually able to locate the missing data or explain

irregularities in the information.

However, this indicated the lack of a

questioning attitude about missing or incomplete data that was required to be

processed

by the licensee's

program.

This was considered

a weakness.

5.8

Rosemount

Transmitters Calibration Procedure

Review

The opportunity did not arise for the inspector to observe

the performance of

a transmitter calibration.

Therefore,

a sample of recently completed

calibration procedures

and master

data

sheets

was reviewed.

The inspector

also reviewed

Procedure

10.24. 1,

"ILC [Instrumentation

and Control] Data

Record Compilation

and Filing," Revision 9.

This procedure

provided guidance

on using, recording,

and handling documentation

related to plant instrument

calibration

and setpoint adjustment.

For those

completed calibrations

reviewed,

the inspector

noted that the transmitter data

was never entered

onto

the master data sheet.

Only loop component

data

was recorded

on the master

data sheet.

Transmitter da'ta

was recorded

on the i'nstrument work sheet.

An irregularity was noted in the recent

loop calibration for

Transmitter

SLC-PT-4,

which was the instrument

loop for the discharge

pressure

of the standby liquid control

pump.

Licensee

personnel

identified the

irregularity as they were delivering and explaining the documentation

to the

inspector.

Loop calibration

was

a refueling frequency preventive

maintenance

task.

According to the data provided,

the instrument

had

been calibrated

on

March 2,

1995, to meet

a due date of March 5,

1995.

The stated late date

was

July 9,

1995,

The exact problem noted

was that the transmitter output data

had not been

recorded

as required

by Step 6. 1.8 of Procedure

10.24.32.

Data

had

been recorded for the other loop components

identified as

a pressure

indicator and

a p'lant computer point input, but the required data for the

transmitter

was missing.

The inspector

asked

the licensee

personnel

who had provided the documentation

how they intended to correct this deficiency.

They responded

that they would

initiate

a problem evaluation request

and allow the corrective action

system

to identify the specific problem(s)

and provide detailed specific

and generic

corrective action.

In

a later conversation

with management,

the inspector

was

informed that the transmitter output as-found

and as-left data existed

in

other documentation

but had not been transcribed

to the final documentation

package.

The inspector believed that the method of recording calibration data

-20-

was probably

a factor in this oversight.

The

NRC followup on the licensee's

actions to resolve this item will be tracked

as Inspection

Followup Item

397/9514-01.

5.9

Transmitter Failure Anal sis

and

Re ortin

The licensee's

program

had identified potentially failing transmitters

in the

past.

According to documentation

provided,

the licensee

had returned six of

the transmitters,

which had

a high potential for failure, to the vendor for

verification of loss of fill-oil. Three of these

were confirmed

as failed or

failing due to loss of fill-oil. During the current outage,

a suspected

transmitter

was being replaced

and returned to the vendor for evaluation.

The

vendor

had not been consulted prior to the decision to replace

the transmitter

due to the important function of the transmitter.

Recently,

the licensee

had

requested

the vendor to evaluate

the trended

data of a transmitter

suspected

of failing.

The vendor determined that the transmitter

was not failing and

further provided information that the present

rate of drift would not affect

transmitter

performance

in the near future.

Based

on the above,

the licensee

had

a policy of returning transmitters

suspected

of failure to the vendor for analysis.

Also, the programmatic

criteria that

had

been

developed

to identify failed transmitters

was

conservative,

and actions

taken

by the licensee staff related to the

identification of failed or failing transmitters

tended to be conservative.

6

PROMPT ONSITE RESPONSE

TO EVENTS AT OPERATING

POWER

REACTORS (93702)

This portion of the inspection

was conducted

during the period

Hay 19-23,

1995

at the Washington

Nuclear Project-2 site

and in the Region

IV office.

6.1

~Back round

On Hay 12,

1995,

the licensee's

operating

crew failed to maintain residual

heat

removal

system

shutdown cooling as required

by Technical Specification 3.9. 11. 1.

The specification required that shutdown cooling flow

be maintained

and restored

in

1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> if lost.

The requirement for maintaining

flow was modified to allow flow to be stopped for up to

2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> in any 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />

period for any reason

determined to be necessary.

An inspector followed up on

the event to assess

the licensee's initial assessment

and preliminary

corrective action.

Following is

a sequence

of significant events describing

what occurred during the morning of Hay 12,

1995:

TIHf

ACTIVITY

0343

Shut off Loop A of the residual

heat

removal

system in the shutdown

cooling mode to support reactor pressure

vessel

inspection

activities.

-21-

0518

Started

Loop

B of the residual

heat

removal

system in the shutdown

cooling mode.

&815

A message

was put out in the daily outage

meeting that shutdown

cooling should

be secured

at 0930 to support

more vessel

inspection

activity.

0845

Shift Manager returned to control

room and told operators

that

shutdown cooling was to be secured

at 0930.

M855

Shift Manager left the control

room to perform other assigned

duties.

0951

Shutdown cooling secured.

1121

Restarted

Loop

B of the residual

heat

removal

system

in the shutdown

cooling mode.

Within minutes of restoring

shutdown cooling following the second

shutdown,

the control

room operating

crew reviewed the log and determined that shutdown

cooling was secured for a total of 185 minutes during the rolling 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />

period between

0343

and

1143.

This time exceeded

the 2-hour limit plus the

1

hour allowance for recovery in Technical Specification 3.9. 11. 1.

Problem

Evaluation

Request

295-0546

was initiated at

1125 prior to the

end of the

rolling 8-hour period.

Additionally, licensee

management

immediately

initiated

a review in accordance

with Procedure

1. 1.8,

" Incident Review

Board," Revision 3.

6. 2

~Fol 1 owo

The inspector

reviewed documentation

and interviewed personnel

to evaluate

the

licensee's initial assessment

of the event.

Inservice inspection

personnel

were interviewed to ascertain

the nature of the vessel

inspection activity and

verify that it was necessary

to stop

shutdown cooling flow.

The inspector

determined that contractor personnel

were performing activities in accordance

with General Electric Nuclear

Energy Procedure

ADM-WNP-2-1022VO,

"WNP-2 Shroud

OD Inspectability Study," Revision 0.

This procedure

had

been

approved

by the

licensee for the contractor to use in order to determine

the accessibility for

a detailed ultrasonic examination of vessel

shroud peripheral

welds currently

scheduled for the next refueling outage.

The study methodology consisted of

using long handled

go/no-go

gages to measure

access

to areas of concern.

A

very high resolution color video camera

was used to observe

the available

clearance

as the gages

were inserted into the spaces

being measured,

The

camera

was very light, tethered

only by

a single line and, therefore,

easily

affected

by any flow in the annulus

between

the vessel

and shroud.

The

inspector

viewed video from the camera

in a situation with shutdown cooling

flow present,

and agreed that flow stoppage

was necessary

to obtain the needed

information.

Within a short time the licensee

incident review board determined

the

following facts regarding the event:

-22-

~

The iteration of stopping

shutdown cooling for vessel

inspection

had

been going on for several

days;

~

No individual or position was specifically assigned

to track shutdown

cooling off time;

~

There

was only an informal method of determining

when shutdown cooling

could

be shut

down;

~

The crew, supervisor,

and manager

were fully aware of the Technical

Specification;

~

The crew was supporting

several activities associated

with the outage;

and,

~

Management

oversight did not question

shutdown cooling previously being

secured..

The incident review board

made the following recommendations:

~

Clearly identify responsibility for tracking shutdown cooling off time

and verifying shutdown/restart

times prior to stopping;

Establish

a formal method for tracking shutdown cooling off time;

Identify any other issues

being similarly informally tracked

and

establish

clear responsibilities

(this may extend

beyond operations);

and>

~

Planning

and scheduling

should schedule

windows for shutdown cooling

outages

and other evolutions

such

as entering

the drywell exclusion

area.

Soon after the event,

the licensee

operations

department

made temporary

changes

to the procedure for logs

and operating

data requiring the shutdown

cooling off time to be tracked in the control

room logs.

On May 19,

1995,

Procedure

3. 1. 10, "Operating

Data

and Logs," Revision 4, underwent

a major

revision.

The inspector

reviewed Revision

5 of the procedure

and noted that

the control

room log had

been

changed

to include

a sheet for logging and

tracking of the residual

heat

removal

system in the shutdown cooling mode for

operating

Nodes

4 and 5.

The inspector

concluded that the licensee's

immediate action

was adequate

to

address

immediate

concerns

and prevent recurrence.

A detailed analysis

was

planned to be performed in conjunction with the problem evaluation report that

had

been initiated in response

to the event.

The licensee's

self-

identification of the issue, initiation of prompt corrective action to prevent

recurrence,

and the addressing

of generic implications met the requirements

of

Section VII.B.(1) of Appendix

C to

10 CFR Part 2 for discretion.

Therefore,

-23-

the violation of Washington Nuclear Project-2 Technical Specification 3.9. 11. 1

will not be cited.

ATTACHMENT 1

PERSONS

CONTACTED AND EXIT MEETING

1

PERSONS

CONTACTED

Washin ton Public Power

Su

l

S stem

1D

2D

'R.

2p

lp

'A.

2C

'C.

lT

2J

'T.

'M.

'A.

lg

2V

2p

'M.

1D

'C.

1,2g

1D

1D

'H.

lL

1.2

Atkinson, Manager,

Reactor/Fuel

Engineering

Becker,

Supervisor,

Engineering

Barbee,

Manager,

System Engineering

Bemis,

Manager,

Regulatory

Programs

Bentrup, Station Nuclear Engineer

.

Chiang, Principal

Engineer

Foley, Licensing Engineer

King, Acting Manager,

Materials

and Inspection

Love, Manager,

Chemistry

HcDonald,

Manager,

Technical

Services

Heade,

Manager,

Technical

Programs

Honopoli, Manager,

Maintenance

Hoore, Acting Hanager,

Analytical Support

Muth, Manager,

Plant Assessments

Parrish,

Vice President,

Nuclear Operations

Powell, Licensing Engineer

Pratt,

Operations

Ramey,

In-Service Inspection

Engineer

Reddemann,

Manager,

Technical

Services

Division

Schwarz,

Hanager,

Operations

Swailes,

Plant Manager

Swank,

Manager,

Licensing

Welch, Supervisor,

Non-Destructive Examination/I

Widmeyer, Supervisor,

Performance

Monitoring

Woosley, guality Assurance

Engineer

Nuclear

Re ulator

Commission

n-Service

Inspection

'R.

2J

2D

2p

Barr, Senior Resident

Inspector

Dyer, Deputy Director, Division of Reactor Projects

Proulx, Resident

Inspector

gualls,

Reactor

Inspector

In addition to the personnel

listed above,

the inspectors

contacted

other

personnel

during this inspection period.

'Denotes

attendance

at the exit meeting

on May 3,

1995.

'Denotes

attendance

at the exit meeting

on May 18,

1995.

2

EXIT MEETING

An exit meeting

was conducted

on May 3,

1995, to discuss

the findings related

to in-service inspection

and fuel handling.

During this meeting,

the

inspectors

reviewed the scope

and findings of the report.

The licensee

did

not express

a position

on the inspection findings related to in-service

inspection

and fuel handling documented

in this report.

Another exit meeting

was conducted

on

May 18,

1995, to discuss

the findings

related to Temporary Instruction 2515/122,

"Evaluation of Rosemount

Pressure

Transmitter

Performance

and Licensee

Enhanced

Surveillance

Program."

The

licensee

did not express

a position

on the inspection findings related to the

Rosemount

pressure

transmitter inspection

documented

in this report.

A telephonic exit was conducted

on May 23,

1995,

among Messrs.

J.

Whittemore

and

D. Chamberlain,

of Region IV, and Mr. D. Swank, of Washington

Nuclear

Project-2,

to discuss

the followup on the stopping of the residual

heat

removal

system while in the shutdown

mode.

The licensee

did not express

a

position

on the findings related to the inspection of the loss of shutdown

cooling event.

The licensee

did not identify as proprietary

any information provided to, or

reviewed by, the inspectors.

)l

ATTACHMENT 2

DATA RE UIRED BY TEMPORARY INSTRUCTION 2515

122

PERFORMANCE

SURVEY

FOR

ROSEMOUNT MODEL 1151,

1152,

AND 1153A TRANSMITTERS IN

ACCORDANCE WITH TI 2515/122,

ENCLOSURE 1.

Based

on

a review of licensee

records,

the following general

information on

Model

1151,

1152,

and

1153A, transmitters

in safety-related

(non-pressure

boundary application) is provided:

1.

Total

number of transmitters

currently installed.

2.

Total

number of transmitters

installed

as of January 1991............

11

For those

Model

1151,

1152,

and

1153A transmitters

that

show symptoms of.oil

loss

based

on the trending results,

provide the following information:

3.

Total

number of transmitters

that exhibit loss of fill-oil symptoms.,

0

4.

Total

number of transmitters

(identified by licensee

or inspector)

that

exhibit loss of fill-oil symptoms

which were not previously identified

by the licensee.......

0

5.

Total

number of transmitters

identified above in Item 3 which were also

confirmed

by Rosemount

as loss of fill-oil.

. ...................,0

PERFORMANCE

SURVEY

FOR

ROSEMOUNT MODEL 1153B/D

AND 1154

POST-JULY 11,

1989

MANUFACTURED TRANSMITTERS IN ACCORDANCE WITH TI 2515/122,

ENCLOSURE 2.

,V

Based

on

a review of licensee

records,

the following general

information on

Model

1153B,

1153D, 'and

1154, post-July

11,

1989, manufactured

transmitters

in

safety-related

(non-pressure

boundary applications)

is provided:

1.

Total

number of,1153B/D transmitters

currently installed.............

10

Total

number of 1154 transmitters currently installed ..........,,...

0

2.

Total

number of transmitters

installed

as of January

1991.

~ ..........

2

For those

Model

1153

and

1154 transmitters

manufactured after July 11,

1989,

that

show symptoms of oil loss

based

on the trending results,

provide the

following information:

3.

4.

5.

Total

number of transmitters

that exhibit loss of fill-oil symptoms..

0

Total

number of transmitters

that exhibit loss of fill-oil symptoms

which were not previously identified by the licensee.

0

Total

number of transmitters

identified above in Item 3 which were also

confirmed

by Rosemount

as loss of fill-oil. ......... ...............

0