ML17265A129

From kanterella
Jump to navigation Jump to search
Insp Rept 50-244/97-13 on 971027-31 & 1105-07.Violations Noted.Major Areas Inspected:Reviewed Status of MOV Program for Purpose of Determining If Rg&E Had Met Commitments Under GL 89-10
ML17265A129
Person / Time
Site: Ginna 
Issue date: 12/24/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17264B152 List:
References
50-244-97-13, GL-89-10, NUDOCS 9801050169
Download: ML17265A129 (20)


See also: IR 05000244/1997013

Text

U.S. NUCLEAR REGULATORYCOMMISSION

REGION I

License No.

DPR-18

Report No.

50-244/97-1 3

Docket No.

50-244

Licensee:

Rochester Gas and Electric Corporation (RGRE)

Facility Name:

R. E. Ginna Nuclear Power Plant

Location:

1503 Lake Road

Ontario, New York 14519

Inspection Period:

October 27-31 and November 5-7, 1997

Inspectors:

Kenneth Kolaczyk, Systems Engineering Branch, DRS

Doug Dempsey, Systems Engineering Branch, DRS

Lois James, Systems Engineering Branch, DRS

Mark Holbrook, Contractor, INEL

Approved by:

Eugene M. Kelly, Chief

Systems Engineering Branch

Dive~i n of Reactor Safety

980i050i69 97i224

PDR

ADOCK 05000244

8

PDR

EXECUTIVE SUMMARY

R. E. Ginna Nuclear Power Plant

NRC Inspection Report 50-244/97-13

This special inspection reviewed the status of the Ginna Motor Operated Valve (MOV)

program for the purpose of determining if Rochester Gas and Electric (RGSE) had met their

commitments under Generic Letter (GL) 89-10

~

Substantial improvements were evident.

Self assessments

and independent reviews were

utilized to develop significant enhancements

in MOV design and testing.

Program

documents and procedures were rewritten, test data reexamined, revised assumptions

developed and new diagnostic test equipment procured.

The quality of design calculations

was generally good, and degraded voltage and weak link analyses were redone.

However,

the NRC was unable to reach closure regarding the GL 89-10 baseline program because of

the following:

~

Calculations (performed by a vendor) had not been finalized and accepted under the

Ginna Station Quality Assurance

(QA) program and had not received formal RGRE

review and approval. The failure to approve the vendor's calculations is a poor

engineering practice with respect to configuration control and was a violation of 10 CFR 50 Appendix B Criterion Vll, "Control of Purchased

Material Equipment and

Services" (VIO 97-13-02).

~

Input assumptions were used in several instances without adequate validation,

resulting in incorrect design calculations, which under-estimated

the thrust

requirements for three MOVs. The failure to adequately validate MOV design inputs

was a violation of 10 CFR 50, Appendix B, Criterion III, "Design Control"

(VIO 97-13-03).

The acceptability of administrative controls which govern the use of a programmable

database,

SMARTBOOK, for safety related calculational input was left unresolved

(UNR 97-13-01).

TABLEOF CONTENTS

EXECUTIVE SUMMARY

PAGE

~

~

~

~

~

~

~

II

III. Engineering

E1

Motor-Operated Valve Program Review (Tl 2515/109)

E1.1

MOV Sizing and Switch Settings .........

~

E1.2

Grouping Criteria

E1.3

Valve Factor Selection ............

E1 4

PORV Block Valves

E1.5

Reactor Coolant Pump Seal Water Return Valve

E1.6

Tracking and Trending

E8

Miscellaneous Engineering Issues....... ~....

E8.1

(Closed) Follow-up Item 50-244/96-08-03.

E8.2

(Closed) Follow-up Item 50-244/95-06-02.

E8.3

(Closed) VIO 50-244/96-08-01:...

~ ~,

.

E8.4

(Closed) VIO 50-244/96-08-02 ~....

~ .,

E8.5

(Closed) Follow-up Item 50-244/95-06-06

~

E8.7

(Closed) Follow-up Item 50-244/95-06-07

E8.8

(Closed) Unresolved Item 50-244/95-06-09

E9

Review of Updated Final Safety Analysis Report (UFSAR)

V. Management Meetings

X1

Exit Meeting Summary ...

.

1

~

~

~

~

~

~

~

1

.

1.5

~

~

~ 6.7

~

~

~ 9

~

~

~

~

1 1

. 11

~

~

~

~ 12

~

~

~

~

~

1 2

~ . 13

. 13

~

~

~

~

~ 13

. 14

~

~

~

'

~

~

~

1 4

... 14

... 14

Re ort Details

III. En ineerin

E1

Motor-Operated Valve Program Review (Tl 2515/109)

Backcaround

On June 28, 1989, the NRC issued Generic Letter (GL) 89-10, "Safety-

Related Motor-Operated Valve Testing and Surveillance," which requested

licensees to establish

a program to ensure that switch settings for safety-

related motor-operated valves (MOVs) were selected,

set, and maintained

properly.

NRC inspections at Ginna have been conducted based on guidance

contained in NRC Temporary Instruction (Tl) 2515/109, "Inspection

Requirements for Generic Letter 89-10."

During an inspection performed in July 1996, the NRC determined the MOV

program could not be closed, principally because

unfounded engineering

assumptions were used in calculations for the Residual Heat Removal (RHR) core

deluge valves, and because the tracking and trending program was not being

effectively used.

The inadequate verification of design assumptions for the core

deluge valves was discussed

during a November 1996 enforcement conference.

RGKE subsequently committed to a number of corrective actions and program

enhancements.

These commitments were described in a January 13, 1997, letter

to the NRC.

The purpose of this current inspection was to examine the actions implemented by

RGSE to address the problems identified during the July 1996 inspection and to

determine if the related actions were sufficient to warrant "closure" of the NRC

staff's review of the Ginna GL 89-10 MOV program.

E1.1

MOV Sizin

and Switch Settin

s

a.

Ins ection Sco

e

The inspectors reviewed the test results and engineering evaluations for the seven

MOVs listed below. The review consisted of examining calculational inputs

associated

with: (1) valve factor, which correlates differential pressure to the stem-

thrust requirement; (2) stem friction coefficient, which affects the conversion of

actuator output torque to valve-stem thrust; and (3) rate of loading or load sensitive

behavior, which reflects the change (usually a loss) in deliverable stem thrust under

dynamic conditions as compared with the available thrust measured under static

conditions.

RCS-MOV-313

RCS-MOV-51 5/51 6

CCW-MOV-81 3

CS-MOV-860A

MS-MOV-3504A

SW-MOV-4664

Reactor Coolant Pump Seal Water Return Isolation

Pressurizer Relief Stop (Block) Valves

Component Cooling Water Supply

Train 1A Containment Spray Pump Discharge

Turbine Driven Auxiliary Feedwater Steam Admission

Turbine Building Service Water Isolation 1A2

The inspectors also reviewed MOV program documents,

Engineering Work Request

(EWR) 5111, "The Motor-Operated Valve Qualification Program Plan" and

Engineering Work Request (EWR) 5080, "Design Analysis Ginna Station GL 89-10

MOVs."

Observations

and Findin s

General

Following the July 1996 inspection and subsequent

enforcement conference,

program documents and procedures were rewritten, test data reexamined, and

revised assumptions

and calculations developed.

Based on recent industry

information contained in NRC Information Notice (IN) 96-48, "Motor-Operated Valve

Performance Issues," and NUREG/CR-6478, "Motor-Operated Valve (MOV) Actuator

Motor and Gearbox Testing," RGSE also revised their methods for calculating motor

actuator capability in the closing direction by discontinuing the Use of run

efficiencies and replacing them with more conservative pullout efficiencies.

This

action required the adjustment of several torque switch settings during the most

recent refueling outage.

New dynamic test methods to require the use of on-line

pressure transmitters (where possible) were implemented.

This improved method

provided a differential pressure

(DP) measurement

over the complete valve stroke

and increased the accuracy and confidence level of MOV performance

determinations.

However, RG&E did not adequately assess

MOV design guidance or control design

information in all cases.

Specifically, input assumptions

were used for certain

double disc gate valves in unapproved applications without adequate justification,

and errors were detected

in several design calculations.

Thrust calculations that

were performed using the Electric Power Research Institute's MOV Performance

Prediction Program (PPP) had not been formally approved and accepted by RGRE,

as required by the Ginna Quality Assurance

(QA) manual.

These issues are

discussed

in detail in Sections E1.3, 4 and 5.

Process Controls and Guidance

Program Plan EWR 5111 is the guidance document for the Ginna MOV program,

describing the assumptions

and the methods used to establish and set torque

switch settings.

Program document EWR 5080, identified the MOVs included in the

GL 89-10 program and described the maximum DP each MOV must overcome to

perform its safety function.

MOV design inputs were consolidated in a computerized (Microsoft Access)

database

program called the "SMARTBOOK." The program used design inputs and

valve specifications to calculate required thrust values using the standard industry

equations,

including adjustments for load sensitive behavior and degradation of

actuator capability. These values were reproduced onto data sheets, which RG&E

used to establish the MOV switch settings.

A series of "lower tier" procedures,

including M-64.1.2, "MOVATsTesting of Motor Operated Valves," outlined the

methodology for setting the torque switch settings.

The SMARTBOOKprogram simplified the storage and retrieval of MOV data and the

calculation of thrust values.

However the program was not procured as safety-

related and it was not apparent how RG&E verified that the outputs were correct.

Ginna staff indicated they performed hand calculations to verify the correctness of

the program outputs independently.

However, none of these verifications or

independent calculations were documented,

nor was it evident how the information

in the program was controlled.

Finally, aside from a description of the program in

EWR 5111, there was no formalized procedural guidance for how the program

should be used or how its associated

calculations should be checked and verified.

Load Sensitive Behavior

RG&E used a 15% margin in thrust calculations to accommodate the effects of load

sensitive behavior.

The margin was applied as a "bias" value and was based upon

a statistical analysis of dynamic tests performed on eleven Ginna globe and gate

valves of various sizes and pressure classes.

The statistical analysis indicated the

15% margin was appropriate for the valve population at a 97% "confidence level."

The inspectors reviewed the load sensitive behavior study and statistical analysis

and determined the 15% margin bounded the majority of the test data.

Including

the margin as a bias value resulted in an additional conservatism when compared

with alternative methods used in the industry.

Stem Friction Coefficient

RG&E assumed

a value of 0.20 for a stem friction coefficient. This value was

based upon a statistical analysis of Ginna gate and globe valve dynamic and static

test data.

The inspectors reviewed the test data and noted only one valve, MOV

738A, had a stem friction coefficient that exceeded

the assumed

value under

dynamic conditions and that difference was not significant.

Further, there was

limited variation in the data.

Therefore, the inspectors determined the stem friction

coefficient assumption was appropriate.

Control of Purchased

Services

Following the July 1996 MOV inspection, RG&E used

a contractor to assist in the

enhancements

to the Ginna MOV program.

New MOV thrust and weak link

calculations were developed using the SMARTBOOKprogram.

RG&E used the

revised calculations as the basis for establishing MOV operability.

Although the quality of the revised engineering calculations and program documents

was good, RGSE did not followthe requirements of the Ginna Quality Assurance

(QA) program and engineering procedures before using the vendor supplied

engineering calculations to establish MOV design basis capability.

Specifically,

Engineering Procedure

(EP) 3-P-154 "Review and Approval of Vendor Drawings,

Design and Manufacturing Technical Documents," states that vendor-supplied

calculations shall not be used to establish

a basis for operability of safety-related

equipment unless formal, final approval of the calculations has been obtained in

accordance with EP-3-P-154.

The approval shall be documented using a

memorandum incorporated into each vendor calculation.

However, as of the time of

this inspection, RGRE had not completed its formal final approval of the calculations

of record for all Ginna GL 89-10 MOVs.

Conclusions

Assumptions for load sensitive behavior and stem friction coefficient were

technically acceptable.

RGSE used the outputs from the SMARTBOOKprogram to change or validate the

switch settings of safety-related

MOVs. However, RG5E had not formally

controlled the data contained in the program or validated the program outputs in a

documented manner.

This issue was partially addressed

as part of a

recommendation from a QA audit of the GL 89-10 program conducted in

August 1997. This would otherwise be acceptable

provided that each MOV

calculation receives effective independent verification and approval.

The

acceptability of the current administrative requirements for use of the program was

unresolved at the end of the inspection.

(UNR 97-13-01)

The inspectors considered the use of unapproved calculations to be a poor

engineering practice and a potential problem for configuration control, particularly

since the torque switch settings for a number of MOVs were adjusted during the

recent outage based on these calculations.

10 CFR Part 50, Appendix B, Criterion

Vll, "Control of Purchased

Material, Equipment, and Services," requires, in part, that

"Measures shall be established to assure that purchased

.

~

. services conform to

the procurement documents.

Documentary evidence that material conforms to the

procurement requirements shall be available at the nuclear power plant site... prior

to the use of such material.

This documentary evidence shall be retained at the

nuclear power plant site... and shall be sufficient to identify the specific

requirements,

such as codes, standards,

or specifications, met by the purchased

material." The failure to review the vendor supplied calculations and document they

conformed to the procurement requirements before using them as a basis to

establish MOV operability was a violation (VIO 97-13-02) of 10 CFR 50 Appendix B

Criterion Vll, "Control of Purchased

Material, Equipment and Services."

Grou in

Criteria

Ins ection Sco

e

There are 60 valves in the Ginna GL 89-10 program population.

RGRE used the

standard

industry (Limitorque) equation to establish MOV switch settings.

The

switch settings of thirty-one of the valves were verified through dynamic tests.

The

remaining valves that could not be dynamically tested were placed in one of

fourteen valve groups based on valve type (e.g, flex-wedge, double disc, globe

etc.).

If a sufficient number of valves were available using the first criteria, then

valve size, type, and ANSI pressure class rating were used to subdivide the valve

groups further.

Observations

and Findin s

RGSE applied the highest valve factor obtained through dynamic tests to the

nondynamically tested valves in the respective group.

However, using the highest

valve factor (from a test), and inferring that factor would represent the performance

of the remaining valves in the grouped population, may not be conservative without

further analysis.

Specifically, for groups in which the data are scattered,

applying

the highest valve factor may not encompass the statistical performance variation of

the valves.

This issue was discussed

in NRC Information Notice (IN) 97-07,

"Problems Identified During Generic Letter 89-10 Closeout Inspections," dated

March 6, 1997, which noted that "..

~ some licensees

have selected

a valve factor

based on a sample of tests that does not accommodate

reasonable

variation in the

valve factor for other MOVs in the group."

RGRE's grouping criteria contained valves with wide ranges of sizes, pressure

classes,

and manufacturers.

The inspectors questioned the rationale for two

groups: (1) Group C contained seven Crane flex-wedge gate valves and two. Borg

Warner flex-wedge gate valves, and (2) Group K contained seven butterfly valves

from two different valve manufacturers.

To assess

the significance of the valve

factor variation, and in response to the inspectors'uestions,

RG&E reassessed

the

valve factors using a mean plus two standard deviation statistical method for each

group.

The results indicated the assumed valve factor bounded the majority of the

test data.

Conclusions

In groups B, D, and E, the assumed valve factor did not bound the upper limitof the

data scatter.

Although only a few valves were affected and the inspectors did not

identify any operability concerns, the bounding nature of this assumption needs to

be re-evaluated by RGS.E (IFI 97-13-04) during the periodic verification program

under their GL 96-05 commitments.

E1.3

Valve Factor Selection

a.

Ins ection Sco

e

The inspectors evaluated valve factors used in groups that had no available or

meaningful in-plant test results.

RGRE applied valve factors that were based on

friction coefficients obtained from the Electric Power Research Institute's (EPRI's)

"separate effects "friction testing performed in support of the MOV Performance

Prediction Program.

b.

Observations

and Findin s

Friction coefficients were used in the standard industry equation to develop a

predicted thrust value for 21 separate

valves in groups A, C, H, J, M, and N.

However, this method was technically incorrect in some instances,

since the EPRI

friction factors were obtained under controlled conditions that do not account for

changes

in the performance of installed valves, and which could reasonably

be

expected.

Specifically, unlike actual valve factors obtained from in-plant tests, the

friction coefficients do not account for possible valve guide wear or bending, disc

tipping, the force required to wedge certain valves or other valve-specific

performance characteristics.

NRC technical concerns regarding selective use of the EPRI data were outlined on

page 2 of the February 20, 1997, safety evaluation report (SER) supplement that

approved use of the EPRI program.

In the SER, the NRC indicated:

"The NRC staff has reviewed the EPRI methodology as a complete package

in that certain nonconservative

assumptions

in the models are compensated

by other conservative assumptions

in the analytical formulas.

Selective use

of test data or methods from the EPRI program may result in underpredicting

the thrust or torque required to operate gate, globe or butterfly valves."

Based on a review of Ginna program documents and selected thrust calculations,

the inspectors found th=-,: ."IGRE did not address the NRC comments in the SER

regarding selective use of coefficients from the EPRI program.

C.

Conclusions

Although data from the EPRI program were used in the above instances

in a

technically incorrect manner, this application did not appreciably impact

functionality since most valves appeared to have adequate

design margin.

The use

of EPRI coefficients in an approved methodology for the 21 MOVs associated with

the groups discussed

above willneed to be re-evaluated

by the NRC (IFI 97-13-05)

for purposes of GL 89-10 program closure.

Notable exceptions with respect to

margin included the pressurizer power operated relief (PORV) block valves, and the

reactor coolant seal water return valve, which are discussed

in the following

sections.

PORV Block Valves

Ins ection Sco

e

The inspectors reviewed Altran Calculation No. 96190-C-28, dated June 1997 for

the PORV block valves.

This calculation established the minimum required design

basis thrust and torque limits for purposes of diagnostic setup and testing of the

valves.

The calculation referenced

use of the EPRI Topical Report (TR)-103232,

dated November 1994, associated with use of a 0.42 valve factor assumption.

The

inspectors also evaluated the design application of these valves, particularly with

respect to leak tightness, as described below.

Observations

and Findin s

~Back round

The PORV block valves, (MOVs 515/516) are three-inch Anchor Darling double disc

gate valves designed to achieve

a leak tight seal when the upstream and

downstream parallel discs are "hard seated" against their respective seat.

This

design is intended to force the discs apart by the sliding action of angled upper and

lower disc wedges as the disc assembly strikes the bottom of the valve. This

condition is called "wedging" and typically requires greater force than just achieving

full seat overlap (also referred to as flow isolation or blockage) for this type of

valve. The amount of flow through the valve at the full seat overlap position will

depend on the DP loading, the disc area, and the contact stress.

Significant

additional thrust can be required to spread the disc wedges sufficiently to meet

leakage limitations and can be affected by the orientation of the valve discs.

Specifically, valves with the upper wedge located downstream of flow (non-

preferred direction) can require much more thrust to achieve a hard seat wedged

disc position.

Past calculations assumed

a 0.5 valve factor, but the technical basis for this value

was questioned during the July 1996 inspection.

Since the block valves could not

receive a dynamic test, the thrust requirements for these valves are currently based

on a 0.42 disc friction coefficient obtained from the so-called EPRI "separate

effects" testing.

The PORV block valve thrust is controlled in the close direction by

a torque switch. The switch settings were established

based upon Ginna design

document EWR 5080, which indicated the block valves had two safety-related

functions; isolate a stuck open PORV, and open to depressurize the reactor coolant

system.

Chapter 5.4.10 of the Ginna Updated Final Safety Analysis Report

(UFSAR) indicated the design leakage

limitfor the block valves was within the

capacity of one charging pump (approximately 60 gpm).

Because of the relative small design margin, and the potential that the lab-developed

EPRI friction coefficient (OA2) would not approximate actual valve performance

characteristics,

the inspectors requested

RGSE to reevaluate thrust margins using

the more appropriate NRC-approved

EPRI "hand calculation" method.

Two values

were calculated:

(a) thrust required to achieve full seat overlap and (b) thrust

required to achieve wedging.

Since the licensee was unaware of the orientation of

the block valve discs, photograph X-rays were taken of both valves on October 31,

1997.

The photographs revealed valve 516 was oriented in the non-preferred

direction.

Prior to this inspection, the block valves were set to approximately 11,000 pounds

(Ibs) force.

By the inspector's independent calculations, this was above the EPRI-

predicted required thrust for flow isolation (10, 200 Ibs) but less than what would

be predicted to achieve hard seat contact or full wedging.

While there are no

specific design basis leakage criteria for the PORV block valves, other than being

less than the charging pump's capacity, a setup to only achieve the flow blockage

condition does not take full advantage of the wedging design for these particular

valves.

The Ginna Technical Specification Bases 3.4.11 define the licensing design

basis for the PORV block valve closure as "...terminating the RCS depressurization

and coolant inventory. As stated in the NRC's SER for the EPRI PPM, the

inspectors did not consider torque switch setup for thrusts predicted at or near flow

isolation to be sufficiently justified with respect to design function. The term

isolation is more aptly described

as "blockage," but does not necessarily ensure any

measure of leak tightness.

loss" associated with a stuck-open PORV which is, in

effect, a small break LOCA.

In response to the inspectors'oncerns,

the torque switch setting for these valves

was changed to increase thrust output to 13,843 and 14,652 Ibs respectively,

which was equivalent to better than 80% wedging.

The analytical work to support

the thrust increase was outlined in calculations 19703245 and 19703246

performed on November 3, 1997. Additional increases

in thrust output were

precluded by the weak link structural limits. The inspectors independently

calculated

a predicted thrust, using the program value for rate of loading effects,

and determined the torque switch setting for the block valves was adequate.

However, the inspectors noted the revised calculations contained an error in that

RGSE failed to provide an allowance for rate of loading when determining MOV

target thrust.

Conclusions

Although the past (prior to November 1997) switch settings may not have achieved

complete wedging (and leak tightness) under all differential pressures,

the

inspectors concluded partial wedging and flow blockage would likely have occurred

under design conditions,

RGRE was unaware that the thrust required to achieve

wedging was dependent

on disc orientation.

Further, the valves may not prevent

flow under all differential pressure conditions when the torque switch settings are

set to achieve only full seat overlap.

The current PORV block valve switch settings were established

on

November 3, 1997, in part, based upon incorrectly performed calculations that did

not adequately consider a value for rate of loading.

10 CFR 50, Appendix B,

Criterion III, "Design Control," requires, in part, that "~ .. measures

shall be

established to assure that applicable regulatory requirements

and design basis for

structures, systems,

and components

are correctly translated into specifications,

drawings, and procedures."

The failure to apply a correct value for rate of loading

in the November 3, 1997, calculations and the use of incorrect equations to

calculate the required thrust for the PORV block valves was the first example of a

violation (VIO 97-13-03) of 10 CFR 50, Appendix B, Criterion III, "Design Control ~"

E1.5

Reactor Coolant Pum

Seal Water Return Valve

a.

Ins ection Sco

e

The inspectors reviewed the thrust calculations and design requirements for the

reactor coolant pump seal water return valve, (MOV 313),

a 3-inch, Aloyco split-

wedge containment isolation valve.

The disk assembly consists of two separable

disk halves connected by a ball and socket joint. The wedging action is similar to

that of the Anchor-Darling double disk gate valve in that significantly more thrust is

required to wedge the valve disks than to achieve primary flow blockage.

Similar to

the Anchor Darling valves, thrust can be affected by orientation of the valve discs in

preferred or non preferred directions.

Also valve leak tightness may not be assured

under all DP conditions unless the valve discs are wedged closed.

b.

Observations and Findin s

RGRE had previously dynamically tested MOV 313 at 62% of design basis DP, but

was unable to derive a valve factor from the test data.

Accordingly, a thrust was

calculated using a 0.65 valve factor obtained from a friction coefficient (EPRI

separate effects testing) corrected for wedge angle.

The valve factor was applied in

the standard industry equation, in Altran Calculation 96190-C-84approved

for

release

(by the vendor) on October 10, 1997. The minimum required closing thrust,

including load sensitive behavior, was recorded to be 2,048 lbs. The current switch

setting (based upon this aforementioned calculation of record) is 2,400 lbs. The

inspectors considered the predicted thrust requirement to be low and incorrect,

without proper consideration for leak tightness, and inconsistent with the EPRI

methodology appropriate for the assumed valve factor.

10

Because of the general NRC concern that using the EPRI friction coefficients in the

standard industry equation would not accurately predict the required thrust, the

inspectors questioned the thrust requirements for MOV 313.

Since the valve's

wedge orientation was unknown, the predicted thrust values were independently

calculated by the NRC assuming the valve discs were in the nonpreferred direction.

Using the appropriate

EPRI equations associated with the 0.65 valve factor, and

including load sensitive behavior, the current design setup for MOV 313 was

determined to be as follows:

Flow blockage:

2140 Ibs

Current Switch Setting

2400 Ibs

Wedging

6603 Ibs

Although these thrust numbers indicate that the valve would achieve flow blockage

with the current switch setting, the valve would apparently not achieve complete

wedging.

Therefore, absent further analysis, leak tightness (the design function of

the valve) may not be assured.

It should be noted that thrust requirements using

EPRI methods for the wedged condition exceed by a factor of three those for "flow

isolation."

Use of the standard industry equation is essentially equivalent to the

EPRI hand calculation for flow isolation, with the difference of a "torque reaction

factor" that amounts to approximately 4-5% higher thrust.

Using the standard

equation would, therefore, significantly under-estimate the thrust for a containment

isolation valve.

The need to ensure that sufficient wedging is achieved to meet

valve-specific leak tightness requirements was outlined in the February 20, 1997,

safety evaluation report (SER) supplement which evaluated the EPRI test data for

Aloyco valves.

In the SER supplement, the NRC indicated "...model users will also

need to justify that leakage limits are satisfied for the specific valves where only

flow blockage is achieved."

Based upon an independent review of the past dynamic test results for MOV 313,

and discussions with Ginna staff, the inspectors found that the "loads" under

dynamic conditions were dominated by packing.

Although no appreciable dynamic

effects were evident (the test was done at approximately 90 psid) to derive a valve

factor, the successful stroke under test coupled with low delta-P conditions and

high margin form a qualitative case for functionality. Therefore, notwithstanding

the incorrect design basis calculations, operability was not in question.

Although

the predicted thrust for a fullywedged condition would exceed'weak

link structural

limits, the existing setup has successfully passed Appendix J containment leak rate

testing.

While the inspectors did not verify past leak rate test results for MOV 313,

the above arguments were considered sufficient basis for operability; pending either

correct use of the EPRI methodology or better technical justification for use of the

0.65 valve factor. As of the end of this inspection, the licensee disagreed with the

inspectors'echnical

conclusions and proposed violation of Appendix B, Criterion III.

RGRE staff consider the Altran calculations in question to be correct and adequate.

11

C.

Conclusions

Since MOV 313 would only develop enough thrust to achieve primary flow

blockage, additional design consideration and analysis should have been performed

to ensure the valve would perform its containment isolation function under design

basis leak tightness conditions.

Incorrect equations were used in Altran Calculation

96190-C-84to predict the minimum required thrust, resulting in an underestimate of

thrust requirements and an incorrect design.

10 CFR 50, Appendix B, Criterion III, "Design Control," requires, in part, that "...

measures

shall be established to assure that applicable regulatory requirements and

design basis for structures, systems,

and components

are correctly translated into

specifications, drawings, and procedures."

The failure to perform the required

analysis to ensure MOV 313 would remain leak tight under design conditions was

the second example of a violation (VIO 97-13-03) of 10 CFR 50, Appendix B,

Criterion III,'Design Control."

E1.6

Trackin

and Trendin

aO

Ins ection Sco

e

The inspectors reviewed Attachment J, "Assessment

and Feedback Criteria," of

EWR 5111 which contained the guidance for the MOV tracking and trending

program.

Items to be monitored included MOV running load, stem friction

coefficient, motor current and voltage and torque switch settings.

Some of this

data had been placed into the SMARTBOOKcomputerized database

for analysis.

b.

Observations

and Conclusions

The scope of the trending program appeared to be adequate to detect meaningful

trends in valve performance.

At the time of the inspection. RGSE was still in the

process of developing

a procedure to implement the tracking and trending program.

As such, the program had not been fullydeveloped.

The development of a tracking

and trending procedure was scheduled to be completed by January 31, 1998. The

inspector determined that date was appropriate for program closure.

E8

IVliscellaneous Engineering Issues

E8.1

Closed

Follow-u

Item 50-244 96-08-03:pressure

isolation valve concerns.

This

item was opened to track NRC analysis of the acceptability of the RHR core deluge

piping configuration.

The RHR core deluge piping consists of two parallel six-inch

lines that branch off the RHR cold leg return piping in the containment structure and

connect into the reactor vessel head.

Each deluge line contains one normally closed

motor-operated deluge valve, MOV-852A/B, and an associated

swing check valve,

853A/B located between the reactor vessel head and the respective MOV. When a

~ safety injection actuator signal occurs, the core deluge valves are designed to open

and allow RHR system water to discharge through swing check valves and into the

reactor vessel.

The design pressure of the piping between the MOV and the reactor

12

vessel is 2485 psi; the design pressure of the upstream piping is 600 psi. The

inspectors were concerned if the swing check valve failed, the possibility of an inner

system loss of coolant accident (ISLOCA) event could exist if the deluge valves

were opened when reactor coolant system pressure was greater than the 600 psi

piping.

Independent examination of the RHR deluge piping configuration conducted by the

Office of Nuclear Reactor Regulation (NRR) concluded the current piping

configuration was adequate.

This conclusion was based,

in part, on the fact that

the upstream check valves 853A/B receive periodic leak checks to verify their

integrity. The inspectors reviewed the results of recent leakage test performed on

the check valves and verified the leakage test results for the past five years were

consistently below the Technical Specification leakage limit of 5 gpm.

Based upon

the minimal check valve leakage, and the determination reached by NRR that the

current configuration was acceptable, this item is closed.

Closed

Follow-u

Item 50-244 95-06-02: margin justification for valve factor.

This item was opened to identify the fact that RGRE would need to justify certain

valve factor assumptions.

Although the overall quality of the MOV program was

improved, it was not evident that the design verification effort for the GL 89-10

program was adequately performed in all instances.

Specifically, as discussed

in

sections E.1.3 - E.1

~ 5 of this report, valve factors for the PORV block and reactor

coolant seal water return valve MOV 313 were inadequately verified. Therefore,

this item is closed and will be tracked as part of VIO 97-13-02 and 03.

Closed

VIO 50-244 96-08-01:design control. This violation concerned

RGKE's

failure to establish adequate

design control measures

in the GL 89-10 program.

As

a result, RGSE did not adequately assure the RHR core deluge valves would operate

under design conditions.

Corrective action included: contracting with a vendor to

reanalyze existing MOV program data and verifying the remaining valves were

operable, revising the design control process, reestablishing participation in industry

forums, and instituting third party reviews of the MOV program.

As discussed

in Section E1.1, MOV program documents appeared

up-to-date and

reflect the most recent industry practices.

The revised design control process

as

outlined in Engineering Procedure

(EP) 3-S-125, "Design Verification and Technical

Review" appeared to improve the rigor of the design review process by instituting a

design review checklist and clarifying the responsibilities of the independent

reviewer.

Additional oversight of the MOV program was evident.

Several

independent reviews of the program had been completed and the Quality Assurance

department was developing a schedule to periodically audit the MOV program.

The

corrective action from this item was therefore considered to be adequate,

and the

item is closed.

Specific issues associated with design control will be followed under

VIO 97-13-02 and 03.

13

Closed

VIO 50-244 96-08-02:ineffective corrective action.

This violation

concerned RG&E's failure to ensure the RHR core deluge valves had adequate

capability to operate under design basis conditions despite evidence the valves had

limited design margin.

The marginal performance of the valves had been previously

noted in a March -April 1995 NRC MOV inspection report and during testing of the

valves during the spring 1996 refuel outage.

Immediate actions consisted of

shutting down the Ginna Station in August 1996 and installing larger actuators on

MOVs 852A/B. Additional action included revising the Commitment and Action

Tracking System (CATS) to require the explicit identification and resolution of each

action item contained in NRC inspection reports and other docketed

correspondence.

Previously, one CATS item was assigned to an inspection report.

The revised CATS process appeared to adequately track commitments,

observations,

and issues identified in NRC correspondence.

The inspectors

determined RG&E has implemented adequate corrective actions.

Therefore, this

issue is closed.

Closed

Follow-u

Item 50-244 95-06-06: periodic verification of design basis

assumptions.

This item was opened to track development of the periodic

verification program.

Although the periodic verification program had not been

completed, Ginna MOV engineers indicated the program would generally follow the

testing guidance developed by the joint owner's group.

RG&E did not include a

specific margin to account for valve degradation.

However, Attachment G, "Switch

Setting and Static Testing Criteria," of EWR 5080, did specify that it is desirable to

set the torque switch to maintain a minimum 10% margin above the target thrust to

account for the effects of stem lubrication degradation.

If this could not be

achieved, then the attachment required that the stem lubrication frequency be

increased.

This approach appeared to be reasonable.

To ensure MOVs are tested in their as-found condition when necessary

during the

periodic verification program, testing and preventive maintenance activities are

currently coordinated through informal, (i.e., word-of-mouth) communications.

Specifically, when as-found data on a valve is required, the MOV engineer notifies

the MOV maintenance

engineer not to overhaul the valve before testing is

completed.

This method appeared to be working appropriately, and revised

procedures were under consideration to require maintenance

personnel to contact

the MOV engineer before working on a valve.

The inspectors concluded the

planned periodic verification and MOV testing programs were appropriate.

Accordingly this item is closed.

Final acceptance

of the Ginna periodic verification

program will be reviewed as part of RG&E's response to GL 96-05, "Periodic

Verification of Design -Basis Capability of Safety-Related Motor-Operated Valves."

Closed

Follow-u

Item 50-244 95-06-07: post-maintenance

testing.

This item

was opened to document RG&E did not currently perform a valve thrust verification

test (either static or dynamic), following packing adjustment, if gland nut torque

remains below the original diagnostic baseline value.

The inspectors considered this

position to be technically indeterminate

as well as contrary to industry practice

since packing adjustment may effect valve performance.

Following the August

1996 MOV inspection, RG&E stopped adjusting valve packing if a subsequent thrust

verification would not be performed.

A study was then commenced to determine

what amount of packing adjustment, if any, could be allowed before a thrust

verification was necessary.

The study included an analysis of Ginna valve

performance characteristics

before and after packing gland adjustment.

Although

the study had not been completed at the time of the inspection, RG&E believes the

results will indicate a thrust verification is not required, if gland nut torque remains

below the original diagnostic test value.

The inspector concluded RG&E's approach

was adequate to address this issue.

Therefore, this item is closed.

E8.8

Closed

Unresolved Item 50-244 95-06-09:Pressure

Locking/Thermal Binding

(PLTB) of Gate Valves.

This item was opened to track the status of RG&E's

corrective actions for gate valves determined to be susceptible to pressure locking.

In a letter dated February 16, 1996, RG&E described the process used to evaluate

valves for susceptibility to PLTB, and the results of the evaluation.

Although

several valves met the initial screening criteria for susceptibility to PLTB, valve

operability was confirmed in a subsequent

RG&E reanalysis completed in

November 1996. The actions taken by RG&E to address

PLTB at Ginna are

currently under review by the Office of Nuclear Reactor Regulation (NRR) ~

Therefore, this item is closed.

E9

Review of Updated Final Safety Analysis Report (UFSAR)

The inspectors verified that the PORV design criteria described in Section 5.4 of the

Ginna UFSAR were consistent with design assumptions

and calculational results

used in the GL 89-10 program.

V. Mana ement IVleetln s

X1

Exit Meeting Summary

RG&E was informed of the scope and purpose of this inspection at an entrance meeting on

October 27, 1997.

The findings were discussed with RG&E representatives

during the

inspection, and were formally presented

during two meetings on October 31 and

November 7, 1997 at the Gir<<ia site.

A final exit was held by telephone on

November 18, 1997.

RG&E disagreed with the characterization of the design control

findings identified during this inspection.

15

PARTIALLIST OF PERSONS CONTACTED

Rochester Gas 5, Electric

R. Mecredy

B. Flynn

F. Maciuska

R. Marchionda

M. Farnan

J. Smith

J. Widay

G. Wrobel

T. Marlow

K. Muller

T. Alexander

D. Kuhn

M. Lilley

M. Zweille

Vice President, Nuclear Operations

Primary Systems Engineering Manager

Operations Training Manager

Production Superintendent

Equipment Diagnostic Coordinator

Maintenance Superintendent

Plant Manager

Nuclear Safety 5 Licensing Manager

Dept Manager NES

Mechanical Engineer

Nuclear Assurance Manager

Quality Assurance Analyst

Quality Assurance Manager

Senior Engineer

NRC

P. Drysdale, Senior Resident Inspector

C. Osterholtz, Resident Inspector

INSPECTION PROCEDURES USED

Tl 2515/109 (Part 3), Inspection Requirements for Generic Letter 89-10 "Safety-Related

Motor-Operated Valve Testing and Surveillance"

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Closed

50-244/95-06-02

50-244/95-06-06

50-244/95-06-07

50-244/95-06-09

50-244/96-08-01

50-244/96-08-02

50-244/96-08-03

UNR

Margin justification for valve factor

UNR

Periodic verification

IFI

Post-Maintenance

Testing

UNR

Pressure

Locking and Thermal Binding

VIO

Failure to verify design inputs for 852A/B

VIO

Inadequate corrective action

IFI

Pressure isolation valve concerns

16

~Qened

50-244/97-1 3-01

50-244/97-1 3-02

50-244/97-1 3-03

50-244/97-1 3-04

50-244/97-1 3-05

UNR

Design Control for SMARTBOOKProgram

VIO

Failure to approve and accept vendor calculations

VIO

Inadequate verification of design assumptions for MOV

313 and RCS 515/516

IFI

Grouping Criteria for Groups B,D,E

IFI

Valve factors for Groups A,C,H,J,M,N

LIST OF ACRONYMS USED

DP

EP

EPRI

EWR

GL

INEL

IR

LOCA

MOV

PORV

PLTB

QA

RCS

RSS

RV

RHR

RGRE

Sl

TS

Tl

differential pressure

Engineering Procedure

Electric Power Research Institute

Engineering Work Request

Generic Letter

Idaho National Engineering Laboratory

Inspection Report

Loss of Coolant Accident

Motor-Operated Valve

Power Operated Relief block Valves

pressure locking or thermal binding

Quality Assurance

reactor coolant system

Reactor Safety Study

relief valve

residual heat removal

Rochester Gas and Electric

safety injection

technical specifications

Temporary Instruction