ML17264B020
| ML17264B020 | |
| Person / Time | |
|---|---|
| Site: | Ginna |
| Issue date: | 09/09/1997 |
| From: | NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | |
| Shared Package | |
| ML17264B019 | List: |
| References | |
| 50-244-97-06, 50-244-97-6, NUDOCS 9709160078 | |
| Download: ML17264B020 (90) | |
See also: IR 05000244/1997006
Text
U.S. NUCLEAR REGULATORY COMMISSION
REGION I
License No.
Report No.
50-244/97-06
Docket No.
50-244
Licensee:
Facility Name:
Location:
Inspection Period:
Inspectors:
Rochester
Gas and Electric Corporation (RGSE)
R, E, Ginna Nuclear Power Plant
1503 Lake Road
Ontario, New York 14519
June 30, 1997 through August 3, 1997
P. D. Drysdale, Senior Resident Inspector
C. C. Osterholtz, Resident Inspector
J. C. Jang, Senior Radiation Specialist
Approved by:
L. T. Doerflein, Chief
Projects Branch
1
Division of Reactor Projects
9709ih0078
970909
ADQCK 08000244
8
EXECUTIVE SUMMARY
R. E. Ginna Nuclear Power Plant
NRC Inspection Report 50-244/97-06
This integrated inspection included aspects of licensee operations,
engineering,
maintenance,
and plant support.
The report covered
a 5-week period of resident
inspection.
In addition, it includes the results of an announced
inspection by a regional
specialist in the radiological environmental effluent monitoring area.
~Oerations
The licensee was taking appropriate actions toward resolving repeated
problems associated
with the operability of the auxiliary feedwater (AFW) recirculation line air-operated valves.
The AFW system configuration accurately reflected the normal configuration designated
in
plant drawings.
The procedure governing operator workarounds
and operator challenges
included the
appropriate definitions and criteria, and the procedure's flowchart provided good guidance.
The procedure was also an efficient tool to aid the quick and accurate identification of
workarounds
and challenges.
However, the inspectors were concerned that the licensee
had not evaluated
all plant and equipment deficiencies for identification as an operator
workaround or challenge.
The licensee took appropriate actions and correctly implemented the improved technical
specifications for high steam flow bistable inoperability.
The application of LCO 3,0.3 was
brief and the licensee's decision to manually trip the high steam flow bistables effectively
satisfied the improved technical specification requirements.
The licensee's intentions to
evaluate
a new setpoint value and to pursue the necessity of the high steam flow function
with Westinghouse
were appropriate.
Annunciator response
(AR) procedures
gave good guidance for response to abnormal
events.
AR references
and transitions to emergency,
abnormal, and equipment restoration
procedures
were appropriate
and accurate.
Maintenance
Observed maintenance
activities were performed in accordance with procedure
requirements.
Equipment received adequate
post-maintenance
testing prior to its return to
service.
Good personnel
and plant safety practices were observed during the maintenance
work that was completed.
However, the maintenance
activity to replace the bus 14 UV
coil was considered deficient in that the maintenance
had to postponed
due to a
discrepancy with the part number on the replacement
coil.
Surveillance procedures
were current and properly followed, and all surveillance work was
properly authorized.
The as-found and as-left test data met the expected performance
values and the specified acceptance
criteria stated in the Updated Final Safety Analysis
Report.
Executive Summary (cont'd)
The licensee successfully replaced the spent fuel pool weir gate bladder and its leakage
was significantly reduced.
Planned maintenance to seal the bottom of the fuel transfer
canal was appropriately scheduled for completion prior to the next refueling outage.
The licensee's attempts to reduce vibrations in the 8-control rod drive system motor-
generator
(B-MG) set, though unsuccessful,
were considered
positive since no action had
been required.
A system procedure was deficient in that it did not contain guidance on the
use of equipment routinely used to aid in motor-generator
set synchronization,
and a
procedure change was initiated.
The licensee's intention to provide a permanently installed
hardware aid for MG set synchronization was appropriate.
The licensee's vendor manual program was previously deficient in meeting established
program requirements,
and did not satisfy the requirements of 10 CFR 50, Appendix B,
Criterion V, "Instructions, Procedures,
and Drawings."
However,'the overall consequences
of this problem were minor, and the licensee's ongoing corrective actions to resolve the
problem were significant.
This item was considered
a Non-Cited Violation and was closed
(NCV 50-244/97-06-01).
~En ineerin
following fouling of all four service water (SW) pump strainers
adequately
addressed
pertinent system parameters.
The data obtained from previous
periodic tests substantiated
the licensee's conclusion that pump operability had been
maintained throughout the operability assessment
period.
The licensee's root cause analysis effectively identified the lack of lubrication as a direct
contributor to premature circuit breaker secondary contact failures.
The procedure
changes
made were appropriate to ensure that proper lubrication was maintained.
The
training conducted to enhance
maintenance
worker awareness
of secondary contact
degradation was effective, as evidenced by discoveries of secondary contact degradation
during routine maintenance.
The licensee aggressively pursued discrepancies
in the C- and D-SW pump escalated
discharge pressures.
The licensee's conclusion that the discrepancy was caused by
mispositioned flow transducers
appeared
likely, given the noted variance in actual SW flow
to the component cooling water heat exchangers
from previous tests.
The licensee's
intention to increase the surveillance frequency on the C- and D-SW pumps to further
evaluate flow transducer performance was appropriate.
~
The NRC granted the licensee an exemption from the accidental criticality monitoring
requirements of 10 CFR 70,24.
The NRC concluded that the existing engineered
features
in the new fuel preparation
area (NFPA) that were designed to preclude an accidental
criticality, together with the low probability of such an event and the existing radiation
monitors, constituted good cause for the exemption.
Item URI 50-244/96-12-01 was
closed.
Executive Summary (cont'd)
The licensee met the radiological effluent monitoring program (REMP) requirements
specified in the Offsite Dose Calculation Manual (ODCM), including management
controls,
quality assurance
audits, measurement
laboratory quality assurance/quality
controls for
REMP samples by a contractor laboratory, and the meteorological monitoring program.
The
ODCM was significantly upgraded from previous versions and was properly implemented.
Two weaknesses
were identified and categorized
as inspector follow-up items in the areas
of the environmental thermoluminescent
dosimeter program and meteorological monitoring
system.
(IFI 50-244/97-06-02 and IFI 50-244/97-06-03)
TABLE OF CONTENTS
EXECUTIVE SUMMARY
TABLE OF CONTENTS .....
v
I. Operations
01
02
03
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
Conduct of Operations .,
~
~
~
~
~
~
~
~
~
~
~
~
01.1
General Comments
01.2
Summary of Plant Status ......
Operational Status of Facilities and Equipment ...
02.1
(AFW) System Walkdown and
Recirculation Line Air-Operated Valve Performance......
~
02.2
Operator Workarounds and Challenges
02.3
Improved Technical Specification (ITS) Limiting Condition for
Operation (LCO) 3.0.3 Entry for High Steam Flow Bistables
.
Operations Procedures
and Documentation
03.1
Annunciator Response
Procedure
Review
~
~
~
~
~
~
~
~
~
~
~
~
1
1
1
1
2
2
3
4
5
5
II. Maintenance ...................
~ .
M1
M2
M8
Conduct of Maintenance
M1.1
Observations of Maintenance Activities............
M1.2
Observations of Surveillance Activities
Maintenance
and Material Condition of Facilities and Equipment
M2.1
Spent Fuel Pool Weir Gate Bladder Replacement ~...
~ .
M2.2
B-Motor-Generator (B-MG) Set Realignment ....
Miscellaneous Maintenance
Issues
M8.1
(Closed) URI 50-244/97-02-02: Vendor Manual Program
Requirements
~
~
~
~
~
~
~
~
~
~
~
~
~
~
6
6
6
7
8
8
8
10
10
III. Engineering
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
E2
E8
Engineering Support of Facilities and Equipment .. ~.............
E2.1
Service Water Pump Operability Assessment
Following Strainer
Foullllg
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
E2.2
Circuit Breaker Secondary Contact Failure Root Cause Analysis
E2.3
Service Water Pump High Discharge Pressures ............
Miscellaneous
Engineering Issues
E8.1
(Closed) URI 50-244/96-12-01: Criticality Monitor for the New
Fuel Preparation Area ..
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
10
10
10
11
13
14
14
IV. Plant Support
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
R1
Radiological Protection and Chemistry (RP&C) Controls...........
R1.1
Implementation of the Radiological Environmental Monitoring
Program (REMP)
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
R1.2
Environmental Thermoluminescent
Dosimeter (TLD) Program
and Comparisons of Collocated TLD Results
R2
Status of RP&C Facilities and Equipment
.
14
14
14
15
18
v
Table of Contents (cont'd)
R3
R6
R7
R2.1
Calibration of Meteorological Monitoring System and Air
Samplers
~
~
~
~
~
~
~
~
~
~
~
~
RPRC Procedures
and Documentation ........
R3.1
Review of REMP and ODCM Procedures,
and Audit Reports
RPSC Organization and Administration
R6.1
Review of The REMP Organization and Administration
Quality Assurance
(QA) in RP5C Activities...........,.....
R7,1
Review of Quality Assurance Audit Reports and QA/QC
Laboratory Actiwties
18
20
20
21
21
21
21
V, Management Meetings..........,............
~
~
~
~
~
~
~
~
~
~
X1
Exit Meeting Summary
. ~.....
~
~
~
~
X2
Pre-Decisional Enforcement Conference
Summary
L2
Review of UFSAR Commitments.............
22
22
22
22
ATTACHMENTS
Attachment
I - Partial List of Persons
Contacted
- Inspection Procedures
Used
- Items Opened, Closed, and Discussed
- List of Acronyms Used
Attachment
II - Predecisional
Enforcement Conference
List of Attendees
and
Presentation
Slides
Re ort Details
I. 0 erations
01
Conduct of
Operations'1.1
General Comments
Ins ection Procedure
The inspectors observed plant operations to verify that the facility was operated
safely and in accordance
with licensee procedures
and regulatory requirements.
This review included:
1) tours of the accessible
areas of the facility; 2) verification
that the plant was operated
in conformance with the improved technical
specifications (ITS), and appropriate action statements
for out-of-service equipment
were implemented; 3) verification of engineered
safety feature (ESF) system
operability; 4) verification of proper control room and operator shift staffing; and
5) verification that logs and records accurately identified equipment status or
deficiencies.
01.2
Summar
of Plant Status
The Ginna plant remained at full power throughout the inspection period.
All
operator performance observed throughout the inspection period was good.
Operators demonstrated
effective communications
and performed actions in
accordance
with procedural requirements.
On June 30, 1997, air operated valve
AOV-4238 (condensate
recirculation control valve to the B-condenser)
failed open.
The automatic digital feedwater control system (ADFCS) automatically started the
A-standby condensate
pump and no secondary plant transient was observed.
Offsite power was reduced to one source between 12:43 a.m. and 12:32 p.m. on
July 20, 1997, when circuit 751 was lost after an animal climbed a power
distribution pole and caused
a short circuit. This resulted in a loss of power to
safeguards
buses
16 and 17 and generated
an automatic start of the B-emergency
diesel generator
(B-EDG). Operators immediately aligned circuit 767 to provide
power to buses
16 and 17 and then secured the B-EDG. The loss of circuit 751
caused
no primary or secondary plant transients,
and the circuit was realigned to
power buses
16 and 17 after it was restored.
ITS limiting condition for operation (LCO) 3.0.3 was entered for 49 minutes on
July 30, 1997, when the licensee discovered that all four bistables for high steam
flow were inoperable
(see section 02.3).
LCO 3.0.3 was exited after operators
manually placed the bistables in the trip position.
No power reduction was required.
'Topical headings such as 01, M8, etc., are used in accordance with the NRC standardized
reactor inspection report outline.
Individual reports are not expected to address
all outline
topics.
02
Operational Status of Facilities and Equipment
02.1
Auxiliar Feedwater
AFW S stem Walkdown and Recirculation Line Air-0 crated
Valve Performance
aO
Ins ection Sco
e (71707)
The inspector performed
a walkdown of the AFW system and evaluated
performance problems associated
with the motor-driven AFW pump recirculation
line AOVs.
b.
Observations
and Findin s
The motor-driven AFW pump recirculation air-operated valves AOV-4304 (A-train)
and AOV-4310 (B-train) for the motor-driven AFW pumps have repeatedly failed
their periodic test criteria of 1) starting to open with AFW discharge flow between
75 and 100 gallons per minute (gpm), and 2) being full open at 40 gpm (see
Inspection Report (IR) 50-244/97-01).
On July 14, 1997, AOV-4310 also failed to
open during the performance of periodic test PT-16Q-B, "AFW Pump B - Quarterly,"
and the licensee generated
ACTION Report 97-1117 to initiate corrective action.
The operability of the AFW pump recirculation line AOVs do not affect the ability of
the AFW pumps to perform their engineered
safety feature (ESF) function.
However, the pumps could be damaged if the recirculation lines are not available
below a pump flow of 40 gpm.
The unreliability of the recirculation flow path made
a "workaround" necessary for control room operators to ensure that AFW flow
remains greater than 40 gpm (see section 02.2).
On July 23, 1997, the inspector
attended
a meeting between instrumentation
and control (IRC) personnel,
results
and tests (R5T) personnel,
and the AFW system engineer who explored possible
resolutions to the recirculation line AOV problems.
The licensee identified that a
fundamental reason for the AOV failures was that the controllers used to throttle
the valves were pressure
sensing controllers which were calibrated and tested using
AFW pump discharge flow. The licensee concluded that either the AOV controller
test and calibration methods should be changed to be consistent with a pressure
controlled AOV, or that an instrument design change was needed to replace the
pressure
controllers with flow controllers.
However, the licensee felt more specific
information was necessary
prior to making a final recommendation.
The licensee s
planned actions included:
Comparison of AFW discharge pressure
vs. flow to determine ifthe
controller is being used in too small a pressure
range
Diagnostic testing of the valve actuators
Analysis of controller history, maintenance,
and repairs
Reviewing the methods of other utilities for accomplishing AFW recirculation
line testing and flow control
The inspector also performed
a walkdown of the AFW system using the licensee s
piping and instrumentation drawings (PRIDs) to verify all valves in the system were
in their proper position, to check for system leaks, and to ensure that no equipment
conditions existed that might degrade system performance.
No discrepancies
were
noted during the walkdown.
C.
Conclusions
The inspector concluded that the licensee was taking appropriate actions toward
resolving repeated
problems associated with the operability of the AFW recirculation
line AOVs. The actual AFW system configuration accurately reflected the normal
configuration designated
in plant drawings.
02.2
0 erator Workarounds
and Challen
es
a 0
Ins ection Sco
e (71707)
The inspectors reviewed the licensee's
procedures
and implementation controls for
operator workarounds
and challenges.
b.
Observations
and Findin s
The inspectors reviewed administrative procedure A-52.16, "Operator
'orkaround/Challenge
Control." The procedure defined an operator workaround as
"...a long term equipment deficiency that affects a decision making process or
requires additional operator action to compensate
for the condition.
The condition
could have an adverse impact on normal or emergency plant operation ifthe
compensatory
action is not performed."
An operator challenge was defined as an
item that "...willnot in and of itself impact plant operations without compensatory
actions.
These items are normally considered
as a burden to operations..."
Procedure A-52.16 also contained
a flow chart for operations personnel to use for
identifying plant equipment deficiencies as workarounds or challenges.
The licensee
currently had six identified operator workarounds
and nineteen identified operat~-
challenges.
The inspector compared the workarounds
and challenges against the
flowchart procedure criteria and found them to be consistent with procedure
requirements.
The inspector identified two plant deficiencies that appeared to meet the criteria for
an operator workaround.
One deficiency involved the unreliability of the B-AFW
recirculation line AOV (see section 02.1).
The licensee agreed that the AOV's
unreliability represented
a workaround, and subsequently
added the B-AFW
recirculation line deficiency to the workaround list. Another deficiency involved the
reactor vessel level indication system (RVLIS) that required operators to refer to
revised emergency preparedness
implementation procedures
(EPIPs) when
consulting the Ginna Emergency Action Levels (EAL) chart to evaluate an event for
a Site Area Emergency.- The EPIPs were recently revised to add a 9% bias to the
indicated RVLIS level (see IR 50-244/97-05).
The inspector noted that the EAL
deficiency was only tagged on the control room chart, and not on the chart located
in the technical support center.
Based on the inspector's questions,
the licensee
revised the EAL charts in the control room, the technical support center, and the
emergency operating facility to indicate that a RVLIS level of 77% (formerly 68%)
with no RCPs running constituted
a Site Area Emergency for reactor coolant system
(RCS) leakage.
After all the EAL charts were revised, and the control room chart
tag removed, the workaround no longer applied.
C.
Conclusions
The inspectors concluded that the procedure governing operator workarounds and
operator challenges included appropriate definitions and criteria, and that the
procedure's flowchart provided good guidance.
The procedure
also appeared to be
an efficient tool to aid in the quick and accurate identification of workarounds
and
challenges.
However, based upon two examples of deficiencies that were not
formally designated
as operator workarounds, the inspectors were concerned that
the licensee had not evaluated
all plant and equipment deficiencies for identification
as an operator workaround or challenge.
02.3
Im roved Technical S ecification
ITS Limitin Condition for 0 aration
Ent
for Hi h Steam Flow Bistables
Ins ection Sco
e (71707)
-'The inspector reviewed the licensee's
actions following their discovery that all four
high steam flow inputs to the main steam isolation circuitry were inoperable.
b.
Observations
and Findin s
On July 30, 1997, the licensee entered
LCO 3.0.3 for approximately 49 minutes
when it was determined that all four high steam flow inputs into the main steam
isolation (MSI) circuitry were inoperable.
This was due to the fact that the existing
channel bistable setpoint would not ensure that the ITS "trip allowable
value" (C0,55E6 Ibn ~hr) would be met after incorporation of the setpoint's
uncertainty and drift, even though the setpoints were within the limits of the "trip
setpoint value" specified in the ITS (60.4E6 pounds mass per hour (Ibm/hr)). Since
the ITS did not address the simultaneous
inoperability of all four high steam flow
inputs to the MSI circuitry, the licensee entered
High steam flow is just one of three inputs to the MSI circuitry. To obtain an
automatic MSI, high steam flow must be present together with a low average
(RCS) temperature
(Tave; K545 degrees fahrenheit
(
F))
and a safety injection (Sl) signal.
This MSI function acts as a back up to the "Hi Hi
Containment Pressure"
MSI function (18 psig), and the "Hi Hi Steam Flow" MSI
- function (S3.6E6 Ibm/hr). The ITS required that the steam flow input to the MSI
circuit have two channels operable
in each steam line. The licensee determined that
'. if all four high steam flow bistables were manually placed in the trip position, then
the high steam flow input to the MSI circuitry would again be operable, since it
would then be performing its safety function for that circuitry. The licensee
subsequently
manually tripped the high steam flow bistables and exited LCO 3.0.3.
In this condition, the plant would receive an automatic MSI with only a low Tave
coincident with an Sl signaI present.
The high steam flow bistables are automatically tripped at 10% power.
Therefore,
at 100% power, they were already in the tripped position when the licensee
manually placed them in trip. The licensee indicated that they would evaluate an
appropriate setpoint value that would ensure that allowable limits would be met.
They also indicated that they planned to pursue with Westinghouse
the actual need
for this circuitry, since it primarily provided a back up function and was not
specifically credited in any accident analysis.
C.
Conclusions
The inspector concluded that the licensee took appropriate actions and correctly
implemented
ITS requirements
regarding high steam flow bistable inoperability,
The
application of LCO 3.0.3 was brief and the licensee's decision to manually trip the
high steam flow bistables effectively satisfied the ITS requirements.
The licensee's
intentions to evaluate
a new setpoint value and to pursue the necessity of the high
steam flow function with Westinghouse
were appropriate.
03
Operations Procedures
and Documentation
~
~
~
'
"'03.1 -Annunciator Res onse-Procedure
Review
a.
Ins ection Sco
e (71707)
The inspector reviewed the annunciator response
(AR) procedures
for appropriate
guidance
and for proper referral to pertinent procedures.
-b.
Observations
and Findin s
The inspectors reviewed ten AR procedures
in the control room associated
with
abnormal plant events, including low condenser
vacuum, high steam flow, reactor
coolant pump high vibrations, and low flow to the spent fuel pool.
In all cases
reviewed, the AR procedures
gave guidance consistent with other plant procedures,
and the references
and transitions to emergency,
abnormal, and equipment
restoration procedures,
when warranted by their respective entrance criteria,-were
also included as part of the AR. The inspector also checked local AR procedures
in
the diesel generator rooms and near the AFW pumps to verify that the proper
revisions were provided.
C.
Conclusions
The inspectors concluded that the AR procedures
gave good guidance for response
to abnormal events.
AR references
and transitions to emergency,
abnormal, and
equipment restoration procedures
were appropriate
and accurate.
II. Maintenance
M1
Conduct of Maintenance
M1.1
Observations of Maintenance Activities
a.
Ins ection Sco
e 62707
The inspectors observed
portions of plant maintenance
activities to verify
conformance with the maintenance
rule, that the correct parts and tools were
utilized, that the applicable industry codes and ITS requirements were satisfied, that
adequate
measures
were in place to ensure personnel safety and prevent damage to
plant structures,
systems,
and components,
and that the licensee properly verified
equipment operability upon completion of post maintenance
testing.
b.
Observations
and Findin s
The inspectors observed
all or portions of the following maintenance
work activities:
Bus 14 undervoltage
(UV) coil replacement while performing PT-9.1.14,
"Undervoltage Protection - 480 Volt Safeguard
Bus 14." This work was
initiated on July 10, 1997, but was interrupted and postponed
until the
refueling outage due to a discrepancy with the part number on the
replacement coil. During the pre-job briefing, the inspector inquired as to
how the licensee verified that the part number on the replacement
UV coil
was correct.
The licensee subsequently
discovered that the part number on
the replacement coil had one letter and one number different from the part
number specified in the work order.
The licensee believed that the
replacement coil part was the correct part, but that an administrative
paperwork error had occurred.
The inspectors expressed
concern that a
replacement part with the wrong identification number was staged for the
job and no verification was performed prior to the pre-job briefing. The
licensee generated
an ACTION Report (97-1108) to investigate and correct
the deficiency.
The installed UV coil was still within its calibration
requirements.
Realignment of the B-control rod drive system motor-generator
(MG) set per
procedure M-11.35, "Rod Drive Motor Generator Set - Generator
Maintenance" observed
on July 14, 1997 (see section M2.2),
B-Safety Injection (B-Sl) pump breaker routine maintenance
per procedure
M-32.1.50, "DB-50 Circuit Breaker Maintenance" observed
on July 21,
1997.
The inspector noted that maintenance
workers identified and replaced
several secondary contacts that showed early signs of degradation
(see
.
section E2.1).
c.
Conclusions
The inspectors concluded that the observed maintenance
activities were performed
in accordance
with procedure requirements.
Equipment received adequate
post-
maintenance
testing prior to its return to service.
Good personnel
and plant safety
practices were observed
during the maintenance
work that was completed.
However, the maintenance
activity to replace the bus 14 UV coil was considered
deficient in that the maintenance
had to postponed
due to a discrepancy with the
part number on the replacement coil.
M1.2
Observations of Surveillance Activities
a.
Ins ection Sco
e 61726
The inspectors observed selected surveillance tests to verify that approved
procedures
were in use and procedure details were adequate,
that test
instrumentation was properly calibrated and used, that ITS surveillance requirements
were satisfied, that testing was performed by qualified and knowledgeable
personnel,
and that test results satisfied acceptance
criteria or were properly
dispositioned.
b.
Observations
and Findin s
The inspectors observed portions of the following surveillance activities:
PT-9.1.17, "Undervoltage Protection - 480 Volt Safeguard
Bus 17," and
PT-9.1.18, "Undervoltage Protection - 480 Volt Safeguard
Bus 18,"
observed
on June 30, 1997.
PT-12.2, "Emergency Diesel Generator B," observed
on July 8, 1997.
In
addition to the regular PT, special diagnostic test equipment was installed to
record data for cylinder pressure,
engine vibrations, and diesel cooler service
water flow.
~
PT-2.7.1, "Service Water Pumps," observed
on July 17 and July 24, 1997
(see section E2.3).
c.
Conclusions
The inspectors confirmed that the procedures
used were current and properly
followed, and that the shift supervisor authorized
all surveillance work to proceed.
The licensee properly certified the qualifications of all surveillance test personnel
involved in the tests.
The as-found and as-left test data met the expected
., performance values and the specified acceptance
criteria stated in the Updated Final
Safety Analysis Report.
M2
Maintenance and Material Condition of Facilities and Equipment
M2.1
S ent Fuel Pool Weir Gate Bladder Re lacement
aO
Ins ection Sco
e (62707)
The inspector reviewed the licensee's efforts to decrease
spent fuel pool (SFP)
leakage through the weir gate into the fuel transfer canal.
b.
Observations
and Findin s
On July 7, 1997, the licensee replaced the bladder seal in the SFP weir gate in an
attempt to reduce the ongoing leakage into the refueling transfer canal.
This
maintenance
was performed as part of an effort to eliminate a known leak path of
SFP water into the residual heat removal (RHR) pump room through the fuel transfer
canal (see IR 50-244/95-17 and IR 50-244/97-05).
The replacement
bladder had
not been previously used, but was approximately 15 years old. After the
installation, no appreciable
change
in the weir gate leakage was observed.
On
July 8, 1997, the licensee again replaced the weir gate bladder using one that was
recently manufactured,
and the leak rate dropped significantly. The licensee
indicated that they intended to dry out the refueling transfer canal and to apply a
sealant to its metal liner prior to the next refueling outage.
The licensee expected
that the sealant would prevent any water in the transfer canal from leaking into the
RHR pump room.
C.
Conclusions
The inspectors concluded that the licensee successfully replaced the SFP weir gate
bladder in that its leak rate was significantly reduced.
The maintenance
to seal the
bottom of the fuel transfer canal was appropriately scheduled for completion prior to
the next refueling outage.
M2.2
B-Motor-Generator
B-MG Set Reali nment
a 0
Ins ection Sco
e (62707)
The inspector observed
and reviewed the licensee's efforts to reduce vibrations in
the B-control rod drive system motor-generator
(MG) set.
b.
Observations
and Findin s
On July 14, 1997, the inspector observed the licensee perform a realignment of the
B-MG set.
Following review of previous vibration and temperature
checks, the
- licensee noted that B-MG set vibrations had more than doubled since the last
bearing replacement
in February 1997.
Bearing temperature
also increased from
approximately 88
F to 114
F over the same time period.
Vibration and
temperature
readings for the B-MG set were still well within the acceptable
range,
but no such increase had been recorded for the A-MG set.
Engineering personnel
indicated that the vibration peaks noted were indicative of motor-generator
alignment problems and were not related to excessive
bearing wear.
However, if
the MG set continued to operate with the increased vibration, bearing life could be
reduced.
The licensee therefore performed
a realignment to determine if any
variance in the motor-generator
base mounts had developed.
During the
realignment, the licensee noted
a very small amount of variance on the northeast
base mount and made minor adjustments to eliminate it. Once the realignment was
completed,
and the B-MG set returned to service, the licensee took additional
vibration and temperature
readings; however, no decrease
in either vibration or
temperature
was noted.
The licensee indicated that all the data pertaining to the
B-MG set would have to be reevaluated to identify other possible corrective
measures.
Following the realignment, the inspector observed operations
personnel return the
8-MG set to service per procedure
S-1A, "Startup of Rod Drive Motor-Generator
Sets."
The inspector noted that after the B-MG set was running and ready to be
paralleled with the A-MG set, operations
personnel deviated from procedure S-1A
and referred to a written addendum
to the work package.
Using the addendum,
operators opened the B-MG set breaker cabinet and installed a Simpson multimeter
to compare phases between the A- and B-MG sets so that they could be
synchronized
more easily.
Procedure
S-1A contained
a NOTE that indicated MG set
synchronization would occur automatically when the two sources were in phase
once the motor-generator
breaker switch was manipulated.
The inspector inquired
why the Simpson multimeter was necessary for this activity. The licensee indicated
that the "automatic feature" associated
with MG set synchronization
had never
really worked, and that an operator would sometimes have to manipulate the motor-
generator breaker switch as many as a dozen times before "catching" both sources
in phase.
The licensee therefore deemed it more appropriate to install the Simpson
multimeter and to manipulate the MG breaker switch only once.
-The inspector observed that a Simpson multimeter was consistently being used to
perform MG set synchronization,
but that use of the multimeter had not been
incorporated
in'.o procedure S-1A. The licensee indicated that although the Simpson
installation enhanced
the synchronization,
it had not previously been required to
perform the task, and therefore was not incorporated into the procedure.
However,
the licensee also indicated that operating the MG breaker switch multiple times in
order to catch both MGs in phase by chance was not appropriate.
The licensee
initiated a revision to incorporate the Simpson installation into procedure S-1A, and
indicated that a permanent synchronization
aid would be installed during the next
refueling outage.
Conclusions
. The inspector concluded that the licensee's attempts to reduce vibrations in the
B-MG set, though unsuccessful,
were considered
positive since no action had been
required.
Procedure S-1A was deficient in that it did not contain guidance on the
use of equipment routinely being used to aid in MG set synchronization.
The
licensee appropriately initiated a procedure change to include the pertinent steps.
10
The licensee's intention to provide a permanently installed alternative to the
Simpson multimeter for MG set synchronization was also appropriate.
M8
IVIIscellaneous Maintenance Issues
M8.1
Closed
URI 60-244 97-02-02: Vendor Manual Pro ram Re uirements
URI 60-244/97-02-02 was opened
on May 5, 1997, after the inspectors discovered
multiple deficiencies in the licensee's vendor manual program.
Since that time, the
licensee has made significant progress to upgrade this program.
The backlog of
vendor contacts was reduced from over 100 to 50, and the licensee obtained
contracted services to eliminate the backlog and maintain the required vendor
manuals current.
Approximately 150 vendors are currently required to be contacted
every three years, 82 of which are planned to be contacted
in the first year.
Additionally, the licensee developed
a new interface procedure,
IP-RDM-2, "Vendor
Technical Document Change Requests," to establish vendor manual program
responsibilities and requirements.
The procedure was in the final stages of
management
review at the end of the current inspection.
The new program
provided for system engineer ownership of the vendor manuals that apply to their
respective systems.
Accordingly, system engineer training sessions
on vendor
manual program requirements were scheduled
for September
1997.
The inspectors considered that the licensee's vendor manual program was
previously deficient in meeting established
program requirements,
and did not
satisfy the requirements of 10 CFR 50, Appendix B, Criterion V, "Instructions,
Procedures,
and Drawings."
However, the overall consequences
of this problem
appeared
to be minor, and the licensee's
ongoing corrective actions to resolve the
problem have been significant.
Therefore, the inspectors considered this item to be
a Non-Cited Violation in accordance with Section lV of the NRC Enforcement Policy
and is closed. (NCV 50-244/97-06-01)
III~ En ineerin
E2
Engineering Support of Facilities and Equipment
E2.1
Service Water Pum
0 erabilit
Assessment
Followin
Strainer Foulin
a0
Ins ection Sco
e (37551)
The inspectors reviewed the licensee's operability assessment
performed in
response to fouled service water (SW) pump suction strainers.
b.
Observations
and Findin s
The licensee identified that all four SW pump suction strainers were fouled on
April 15, 1997, after divers were dispatched
in the SW pump bay to investigate
a
decrease
in SW header discharge pressure
observed
by control room operators
(see
11
IR 50-244/97-03).
The strainers were cleaned on the same day that the fouling
was identified.
The licensee performed an operability assessment
to determine if the fouled
condition had been severe enough to affect SW pump operability.
The assessment
indicated that the last time all four strainers were inspected
and cleaned was on
May 12, 1996.
On July 15, 1996, the A-SW pump strainer had been inspected
and
cleaned prior to a pump overhaul, and the strainer was found to be approximately
10% fouled.
The A- and B-SW pumps had satisfactorily passed
a performance test on January
23, 1997.
The C-SW pump had been satisfactorily tested on January
10, 1997.
The D-SW pump was also tested on January
10, but its differential pressure was
low in the alert range, and required an increased
surveillance frequency,
Subsequent
tests were performed on the D-SW pump on February 25 and April 3,
1997.
The test results were consistent with the January
10 test.
The licensee
reviewed plant process computer system
(PPCS) data from the time each SW pump
was last satisfactorily tested until April 15, 1997.
The review revealed that no
abnormal changes
in SW pump discharge
pressures
occurred over that period.
The
licensee also reviewed containment recirculation fan cooler (CRFC) SW flow data
over the same interval, and discovered that SW flow had remained steady with no
anomalies.
The licensee concluded that all the SW pumps were capable of fulfillingtheir
required safety-related functions and were operable throughout the assessment
period.
This conclusion was based upon the fact that the D-SW pump was capable
of satisfying its required performance testing as recently as April 3, 1997 (twelve
days before divers entered the SW bay).
The conclusion was also based upon the
review of pump discharge pressure data and CRFC service water flows, which both
indicated continued normal operating values.
Conclusions
The inspectors concluded the that the operability assessment
of all four SW pumps
adequately
addressed
pertinent system parameters.
The data obtained from
previous periodic tests appeared to substantiate
the licensee's conclusion that pump
operability had been maintained throughout the operability assessment. period.
Circuit Breaker Seconda
Contact Failure Root Cause Anal sis
Ins ection Sco
e (37551)
The inspector reviewed the licensee's root cause analysis performed in response to
several noted instances of circuit breaker secondary contact degradation
and
breaker failure.
12
Observations
and Findin s
On November 6, 1996, the licensee identified several damaged
secondary contacts
on a failed Westinghouse
DB-75 output breaker for the B-EDG (see IR
50-244/96-11)
~
On December 12, 1996, the licensee discovered damaged
secondary contacts on a failed Westinghouse
DB-25 supply breaker for the B-SW
pump (see IR 50-244/96-12).
On January 9, 1997, the licensee discovered
a bent
secondary contact on the A-reactor trip bypass breaker.
In all three cases the
breaker contacts were replaced and the breakers were successfully tested.
The
licensee generated
ACTION Report 97-0001 on January 9, 1997, to initiate a root
cause analysis and a corrective action plan for the secondary contact failures.
The licensee contacted Westinghouse
for guidance.
had
investigated bent secondary contacts in the past and concluded that the
most probable cause was misalignment between the breaker and its cell (see
Technical Bulletin NSD-TB-91-03-RO). Westinghouse
also
stated that abrasive materials should not be used to clean the contacts to
prevent removing the lubricating silver plating on the contact surface.
This
was contrary to the licensee's maintenance
procedures which had previously
provided guidance to use "Scotch Brite" pads (an abrasive material) to clean
breaker contact surfaces.
The licensee submitted three bent secondary contacts to RGRE's Materials Science
Laboratory for analysis.
The analysis concluded that the contacts had experienced
galling (metal transfer) between the contact mating surfaces,
and that the silver
plating had worn off leaving the underlying copper exposed.
The licensee therefore
concluded that use of Scotch Brite pads had accelerated
metal fatigue on the
contacts and was a direct contributor to their premature failure. The licensee
changed the necessary
preventive and corrective maintenance
procedures to
remove the use of Scotch Brite pads for cleaning silver-plated secondary contacts.
The licensee also conducted training for maintenance
workers to heighten their
awareness
of the problems associated with secondary contact degradation.
During
subsequent
oreventive maintenance
activities, several secondary contacts were
identified by maintenance
personnel to be in the early stages of degradation
and
were replaced.
Conclusions
The inspector concluded that the licensee's root cause analysis effectively identified
a lack of lubrication as a direct contributor to premature secondary contact failures.
The procedure changes
made were appropriate to ensure that proper lubrication was
maintained.
The training conducted to enhance
maintenance
worker awareness
concerning secondary contact degradation was effective, as evidenced by the
subsequent
discoveries of secondary contact degradation
during routine
maintenance.
13
Service Water Pum
Hi h Dischar
e Pressures
Ins ection Sco
e (37551)
The inspector reviewed the licensee's
response to observed
escalated
SW pump
discharge
pressures
during the performance of a routine quarterly surveillance.
Observations
and Findin s
On July 17, 1997, the licensee performed quarterly surveillance test PT-2.7.1,
"Service Water Pumps," on the C- and D-SW pumps (supplying the B-service water
header) to verify pump operability, and to record and track pump vibration and
temperature
data.
The test results indicated higher pump discharge pressures
than
those indicated in previous tests.
The licensee generated
an ACTION Report
(97-1123) to address these anomalies,
The licensee first considered that a probable cause for the pressure
increases
might
be the recent repair of a partially blocked bubbler tube used to measure
level in the
SW inlet bay (see IR 50-244/97-05).
However, this did not appear to significantly
effect the calculation for pump discharge pressure.
The licensee subsequently
discovered that the Controlotron transducers
used to measure flow for the test had
not been reinstalled in the same position after they were last cleaned.
The licensee
subsequently
removed, cleaned, lubricated, and reinstalled the Controlotron
transducers
and reperformed PT-2.7.1 on July 17. That test showed no appreciable
change from the results obtained earlier that day.
The licensee then analyzed the data from both the PTs performed on July 17, and
discovered that total SW flow to the component cooling water (CCW) heat
exchanger
had decreased
approximately 600 gallons per minute (gpm) from
previously performed tests, and that this flow decrease
accounted for the escalated
discharge pressures.
The licensee again performed PT-2.7.1 on July 24, 1997,
paying particular attention to SW flow to the CCW heat exchangers
and the SW
header test flow indication from the Controlotron transducers.
This test resulted in
data that was consistent with tests run prior to July 17. It appeared
the
recalibration of the flow transducers
did have an effect once a period of time had
elapsed following the calibration.
The licensee concluded that the Controlotron transducers
had not operated properly
on July 17 due to their being mispositioned.
However, the licensee was unable to
determine why the recalibration of the transducers
on July 17 did not immediately
result in a change
in the test data.
The licensee stated that the frequency of
surveillance testing for the C- and D-SW pumps would be. doubled, and that the
installed transducers
would remain installed during the increased
surveillance period
to eliminate any relocation error.
c.
Conclusions
14
The inspectors concluded that the licensee aggressively pursued discrepancies
in
the C- and D-SW pump test results that indicated escalated
pump discharge
pressures.
The licensee's conclusion that the discrepancy was caused by
mispositioned flow transducers
appeared
likely, given the noted variance in actual
SW flow to the CCW heat exchangers
from previously run tests.
The licensee's
intention to increase the surveillance frequency on the C- and D-SW pumps to
further evaluate flow transducer performance was appropriate.
Miscellaneous Engineering Issues
E8.1
Closed
URI 50-244 96-12-01: Criticalit Monitor for the New Fuel Pre aration
Area
URI 50-244/96-12-01
was opened
on February 7, 1997, in response to the
licensee's
evaluation of the necessity to have a criticality monitor in the new fuel
preparation
area (NFPA) as required by 10 CFR 70.24, "CriticalityAccident
Requirements"
(see IR 50-244/96-07).
This rule requires that facilities licensed to
possess
greater than 700 grams of Uranium-235 have the ability to detect specific
radiation levels at defined distances from a critical source.
In a letter dated July 16, 1997, the NRC granted RG&E an exemption from the
requirements of 10 CFR 70.24.
The NRC concluded that the existing engineered
features in the NFPA that were designed to preclude an accidental criticality,
together with the low probability of such an event and the existing radiation
monitors installed in accordance with General Design Criterion 63, constituted good
cause for the exemption.
Therefore, this item is closed. (URI 50-244/96-12-01)
IV. Plant Su
ort
R1
Radiological Protection and Chemistry (RP&C) Controls
R1.1
lm Iementation of the Radiolo ical Environmental Monitorin
Pro ram
a.
Ins ection Sco
e 84750-02
The inspection consisted of:
1) a tour of the environmental sampling stations; 2) a
tour of the REMP analytical measurement
laboratory; 3) a tour of the meteorological
monitoring system and the control room; and 4) a review of the licensee's
compliance with 10 CFR 20, 40 CFR 190, and Appendix
I to 10 CFR 50.
b.
Observations
and Findin s
The inspector toured a milk farm, air sampling stations, and other selected
monitoring stations (i.e., fish, vegetation, water, and thermoluminescent
dosimeters
(TLDs)). Milksamples at the farm were available and all air sampling equipment
15
was operable at the time of the tour.
The inspector also toured the indication and
the control water sampling stations.
The reviewed sampling stations were located
as defined by the offsite dose calculation manual (ODCM).
The inspector noted that the licensee had a contractor laboratory (James A.
FitzPatrick Environmental Laboratory (JAFEL)) and sent all REMP sample media there
with the exception of tritium samples and TLDs. The inspector toured the JAFEL,
and reviewed JAFEL analytical procedures
and measurement
instruments.
The
reviewed JAFEL procedures
were detailed, and easy to follow; and ODCM
requirements
(such as lower limitof detection (LLDs) and action levels) were
incorporated into the appropriate procedures.
The JAFEL had six gamma spectrometers,
two proportional counters,
one liquid
scintillation counter, chemical balances,
refrigerators, freezers,
a sample receiving
area, and sample storage space.
All laboratory equipment was operable at the time
of the tour.
The inspector observed
sample processes
for the licensee's water and
charcoal cartridge samples.
The JAFEL staff followed its procedures for sample
receiving, surveying, logging, and sample preparation.
The inspector also reviewed
analytical methodology, data evaluation, and the staff's adherence
to reporting
requirements.
The inspector noted that the JAFEL staff was very knowledgeable
in
these areas.
The inspector also verified the operability of the meteorological readout devices
located in the Ginna control room and the meteorological tower base station.
The
readout devices and meteorological instrumentations
were operable at the time of
this inspection.
The inspector also reviewed the licensee's compliance with Appendix
I to
10 CFR 50, 10 CFR 20.1301
and 40 CFR 190 (dose limits to the public) using
direct radiation measurement
data (environmental TLD readings).
The measured
doses to the public were well below regulatory requirements.
C.
Conclusion
Based on the above observations
and findings, the inspector determined that the
licensee effectively implemented the REMP as required by the ODCM.
R1.2
Environmental Thermoluminescent
Dosimeter
TLD Pro ram and Com arisons of
Collocated TLD Results
a.
Ins ection Sco
e 84750-02
The inspection consisted of technical evaluations of the licensee's environmental
TLD program based on the following guidance:
1)
Regulatory Guide 4.13, "Performance, Testing, and Procedural Specifications
for Thermoluminescence
Dosimetry:
Environmental Applications."
16
2)
ANSI N545-1975, "Performance, Testing, and Procedural Specifications for
Thermoluminescence
Dosimetry (Environmental Applications)."
The U.S. Nuclear Regulatory Commission (NRC) Direct Radiation Monitoring
Network is operated by NRC Region
I to provide continuous measurements
of the
ambient radiation levels around nuclear power plants throughout the United States
during normal operations.
The monitoring results are published in NUREG-0837
quarterly.
One purpose of this program is to serve as a basis of comparison with
similar programs conducted
by individual utilities which operate nuclear power
plants.
Therefore, at least four NRC TLDs are collocated with the licensee's TLD
stations at each nuclear power plant.
During this inspection, the collocated TLDs
measurement
results were used to evaluate the licensee's
measurement
capability.
Observations
and Findin
s
The inspector reviewed the implementation of the licensee's environmental
thermoluminescent.dosimetry
program.
The Radiation Protection/Chemistry
Department had responsibilities to process the environmental TLDs on site.
The
licensee used Panasonic
UD-814AS1 TLDs and the UD-710A TLD Reader.
The inspector reviewed the following procedures to determine their technical
validity:
RP-TLD-ENV-READOUT,
RP-TLD-710A-OPS,
RP-TLD-710A-CAL,
RP-TLD-710A-QC,
"Readout and Report of Environmental TLD."
"Operation of Panasonic
UD-710A TLD Reader."
"Calibration of the Panasonic
UD-710A Automatic TLD
Reader."
"UD-710A TLD Reader QC Check."
"Collecting Environmental and Post Accident TLDs."
During review of the above procedures,
the inspector noted that procedures
RP-TLD.-710A-OPS, RP-TLD-710A-CAL, and RP-TLD-710A-QC described only the
personnel TLD program, and not the environmental TLD program.
For example,
radiation exposures
provided to the "QC" TLDs (300 and 3,000 mR) described
in
procedure
RP-TLD-710A-QC were too high to apply to the environmental TLD
program.
The inspector noted that the licensee did not perform any tests
(e.g., uniformity, reproducibility, moisture dependence,
etc.) described by the
previously mentioned references.
The inspector noted that the licensee determined
the element correction factor (ECF) only once every two years even though ECFs of
the TLDs could change due to harsh environmental conditions, such as heat'and
moisture.
The inspector also noted that the licensee did not use control TLDs to
measure the transit dose, even though the transit time was about 6-7 days, based
on the 1996 and 1997 logs.
The monitoring results of five collocated TLDs were compared
and are listed in
.Table
1 below. Although there were some differences between
NRC and licensee s
programs (such as differing monitoring periods, starting dates of the quarters,
17
monitoring heights, and transit doses); the comparison results were generally in
good agreement, with the exception of the data for the 4th Quarter of 1996.
Table
1
COMPARISONS OF COLLOCATED TLD RESULTS
Unit= mR/90 days for NRC
Unit= mRem/91 days for GINNA
STATION ID
1st Qtr, 1996
2nd Qtr, 1996 (a)
3rd Qtr, 1996 (a)
4th Qtr, 1996
NRC
11
GINNA
31
NRC
15
GINNA 36
NRC
18
GINNA
39
NRC
19
GINNA 40
NRC
28
GINNA
9
12.7%0.6; 4.0 (b)
13.9s3.5
(c)
10.5%0.6; 3.8
13.6 2 3.4
10.8 %0.6; 3.8
14.0 2 3.5
11.2a0.6; 3.9
13.3 a 3.3
13,1 20.7; 4.1
13.3 a 3.4
13.2 20.4
11.7 k 3.0
TLD Missing
11.322.8
12;2a0,3
12.6 a 3.2
11.6 %0.3
11.7 2 2.9
11.8 20.3
1 1.2 2 2.8
13A 20.4
12.6 2 3.2
13.9 a0.4
11.5 R 2.9
12.3 a0.4
12.8 2 3.2
10.8 20.3
11.8 2 3.0
12.9 %0.4
1 1.3 2 2.9
15.0a0.6; 4.0
9.7 2 2.6
14.5 %0.6; 3,9
10.4 a 2.6
13.920.6: 3.9
11.7 %3.0
13.0%0.6: 3.8
10.6 2 2.7
13.720.6; 3.9
10.8 R 2.7
a
ross
xposure
lusted Data
ue to oss o t e
ransit TLD, mR ~ stan
ar
error
-(b)
mR s standard error; total error
(c)
mR a 2 sigma error
The licensee stated that their lower measurement
results for the 4th Quarter of
1996 were due to the transit dose.
Procedure
RP-TLD-ENV-READOUT indicated
that there was no transit dose when TLDs were processed
on-site.
The inspector
indicated that the transit dose (measured
by the control TLDs) should be
incorporated into the environmental TLD program because
the environmental TLDs
were exposed to natural radiation background
or other sources originating from the
plant.
Although the licensee had a capability to measure direct radiation using
environmental TLDs, as shown in Table 1, the inspector determined that the
licensee's environmental TLD measurement
results had the potential to be
unreliable.
The inspector identified the following weaknesses:
~
Environmental TLDs were not tested to demonstrate
their reliability;
~
No transit dose was applied to calculate net exposure;
18
TLD procedures
were written only for the personnel TLD program;
No environmental TLD quality control (QC) program was implemented.
These items will be reviewed in a subsequent
inspection (IFl 50-244/97-06-02).
c.
Conclusions
Based on the above procedure reviews, technical discussions,
and data evaluation,
the inspector determined that the licensee's environmental TLD program lacked
elements that could effect its reliability.
R2
Status of RPLC Facilities and Equipment
R2.1
Calibration of Meteorolo ical Monitorin
S stem and Air Sam
lers
a.
Ins ection Sco
e 84750-02
The inspection consisted of;
1) a review of the most recent meteorological
instrumentation calibration results for wind speed, wind direction, and delta
temperature;
and 2) a review of air sampler calibration data.
b.
Observations
and Findin s
The inspector reviewed the most recent meteorological monitoring system
calibration results for wind speed, wind direction, and delta temperature.
The
reviewed calibration results were within the licensee's acceptance
criteria. The
inspector also verified the operability of meteorological readout devices located in
the control room and the meteorological tower base.
The meteorological
instrumentation was operable at the time of this inspection.
Although calibration results were within the acceptance
criteria and the instruments
were operable, the actual readings
in the control room and at the meteorological
tower base were compared to evaluate system integrity. The inspector compared
the wind speed, wind direction, and temperature outputs of the towers to the
control room panel (strip chart).
The control room panel was designed for
temperature
readings at three levels (33 ft., 150 ft., and 250ft.) while wind speed
and direction were only read for the 33 ft. level. The comparison results were in
good agreement only for the temperature,
as shown in Table 2 below.
Table 2
Comparisons
between Tower Base and the Control Room Readouts
33 feet
Temperature
Control Room
73.3 'F
Wind
Speed
Wind
Direction
Tower Base
(Channels A/B)
Control Room
Tower Base
(Channels A/B)
Control Room
Tower Base
(Channels A/B)
73 4'F/73 3 'F
12 mph
9.1 mph/9.5 mph
300'90'/289's
shown in Table 2, the comparisons of wind speed
and wind direction were not
consistent.
The inspector questioned the IS.C staff regarding
a potential line loss of
the signal between the tower and the control room.
The inspector was concerned
that the 10-degree difference between two readings could impact effective
response
activities in the case of a radiological event, specifically the projected dose
calculations to the public.
The inspector also noted that the height of the sensors for Channels A and B were
about 3 feet apart at the 33 ft. and 150 ft. levels.
This could have resulted in a
discrepancy
in the delta temperature
measurement.
The inspector stated that the
potential line loss of the signal and the licensee's
procedure for determining which
channel to use during normal and emergency operations were categorized
as an
inspector follow-up item (IFI 50-244/97-06-03).
The inspector also'eviewed the licensee's
air sampler calibration procedures
and
records.
Calibration of gas meters was performed according to the specified
frequencies stated in the appropriate procedure.
Results of these calibrations were
within the licensee's specified acceptance
criteria.
Conclusion
Based on the above reviews, the inspector concluded that a potential weakness
existed relative to line losses or other errors leading to discrepancies
between the
meteorological tower and the control room indication.
The air sampler calibration
program was effectively implemented.
20
R3
RPRC Procedures
and Documentation
R3.1
Review of REMP and ODCM Procedures
and Audit Re orts
a 0
lns ection Sco
e 84570-02
The inspection consisted of review of:
1) selected contractor (JAFEL) procedures
for compliance with the licensee's
REMP; 2) the licensee's
1995 and 1996 Annual
REMP reports; and 3) the licensee's
ODCM.
b.
Observations
and Findin s
The inspector reviewed selected contractor's analytical procedures for compliance
with the licensee's
ODCM requirements,
including sample receiving and logging
processes.
The reviewed procedures
were concise and provided the required
direction and guidance for implementing an effective REMP.
The inspector reviewed the Annual Radiological Environmental Operating Reports for
1995 and 1996.
These annual reports provided measurement
results of the REMP
samples around the Ginna site and met the ODCM reporting requirements.
The
reviewed analytical results indicated that all samples were collected and analyzed
as
required by the ODCM. However, the inspector noted that the licensee did not
explain anomalous
changes
or trends in the annual reports.
For example, direct
--radiation measurement
results (TLD data) at the fence (Station ¹13) indicated that
the measurement
result of the 4th quarter of 1996 decreased
by a factor of
approximately three from the 3rd quarter of 1996.
Inspector follow-up revealed
that the licensee moved a trailer (which contained contaminated
materials) from the
vicinity of TLD Station ¹13 to another location.
Also, the licensee measured
a
positive Iodine-131 (I-131) activity (1813 pCi/kg) in a cladophora
(algae) sample at
the radioactive liquid discharge
area in 1995.
Although the measured
I-131 activity
was low (near the LLD value) and did not negatively impact the environment, the
licensee did not explain or provide evaluation of this matter in the annual report.
The inspector noted that the licensee also did not measure
1-131 in the algae sample
in 1996.
The inspector discussed
these matters with the licensee and noted that
the responsible
individual had reviewed the data and concluded that there was no
impact to the environment or to the public. The licensee acknowledged the
importance of evaluating and documenting
anomalous
measurements.
The licensee
stated that the evaluation results for trending or sudden changes would be
described
in the future annual reports.
The inspector reviewed the REMP portion of the licensee's
ODCM, Revision 9,
effective October 1996.
The inspector noted that this ODCM was an improvement
over previous versions,
as noted during the previous inspection (See IR
50-244/97-05).
The inspector noted that the licensee planned to update the ODCM
to include revising sampling location maps.
C.
Conclusion
Based on the above reviews, the inspector determined that:
1) analytical
procedures for the REMP were sufficiently detailed to facilitate performance of all
21
necessary
steps; 2) the licensee implemented the ODCM requirements for sampling,
analyzing, and reporting for the REMP; 3) better evaluation of anomalous
measurements
and data should be incorporated
in the annual report; and 4) the
licensee's
ODCM had improved over previous versions.
R6
RP&C Organization and Administration
R6.1
Review of The REMP Or anization and Administration
a.
Ins ection Sco
e (84750-02)
The inspector reviewed the organization and administration of the REMP and
discussed with the licensee changes
made since the last inspection conducted
in
October 1995.
b.
Observations
and Findin s
The licensee made some changes
in the REMP management
(responsibility of the
REMP sample analyses)
since the previous inspection.
REMP samples were
collected and prepared for shipping by the Health Physics Technician, Health
Physics/Chemistry
Department.
REMP samples were analyzed by a contractor
laboratory (James A. FitzPatrick Environmental Laboratory (JAFEL) since the 4th
quarter of 1996), with the exception of tritium in water and TLDs measurements.
Tritium in water and TLDs were analyzed at the site, All analytical results form the
contractor laboratory were reviewed by the Radiochemist.
c.
Conclusion
The inspector concluded that the changes
did not reduce the REMP philosophy
and/or practices.
R7
Quality Assurance
(QA) in RP&C Activities
R7.1
Review of Qualit
Assurance Audit Re orts and QA QC Laborator
Activities
a.
Ins ection Sco
e 84750-02
The inspection consisted of:
1) a review of the 1996 audit; and 2) a review of
analytical measurements
laboratory QA/QC activities.
b.
Observation
and Findin s
The inspector reviewed the 1996 Quality Assurance Audit Report (Report Number
AINT-1996-0005-NAB). This audit was conducted by quality department personnel
and covered the REMP and other areas, such as radioactive liquid and gaseous
effluent controls.
The inspector noted that the audit team also included other
technical personnel from another utility. The 1996 audit team identified no findings
22
but made two observations to enhance the REMP. The inspector noted that the
scope and technical depth of the audits were sufficient for assessing
the REMP.
The QA/QC program for analyses of REMP samples
is conducted
by JAFEL. The
JAFEL has interlaboratory and intralaboratory QC programs.
The QC program
consisted of measurements
of blind duplicate, spike, and split samples.
The JAFEL
published
a QC report annually.
The inspector reviewed the 1995 annual QC
reports.
Intra/interlaboratory comparisons
of QC data listed in the annual QC
reports were within the JAFEL's acceptance
criteria.
C.
Conclusion
Based on the above reviews, the inspector determined that the licensee met the QA
audit requirement,
and the JAFEL's QA/QC program for the REMP provided
effective validation of analytical results.
V. Mana ement IVleetin s
Exit IVleeting Summary
The inspectors presented
the inspection results from the Radiological Environmental
Monitoring Program (REMP) to members of licensee management
at the conclusion
of that inspection on August 1, 1997. At the end of the inspection period, the
inspectors presented the overall results to members of licensee management
on
August 12, 1997.
The licensee acknowledged the findings presented.
The inspectors asked the licensee whether any materials examined during the
inspection should be considered
proprietary.
No proprietary information was
identified.
X2
Pre-Decisional Enforcement Conference Summary
On August 5, 1997, a pre-decisional enforcement conference was held with the
licensee in the NRC Region
I office in King of Prussia,
PA, to discuss the vehicle
barrier system issues identified in Inspection Report 50-244/97-08.
The licensee
presentation
included a discussion of the significance, root causes
and corrective
actions for the apparent violations.
A list of attendees
at the conference
and the
presentation
slides used by the licensee are included in this report as Attachment 2.
The enforcement action for the vehicle barrier violations was issued in a letter to the
licensee dated August 15, 1997.
L2
Review of UFSAR Commitments
While performing the inspections discussed
in this report, the inspector reviewed
the applicable portions of the UFSAR that related to the areas inspected.
The
inspectors verified that the UFSAR wording was consistent with the observed plant
practices, procedures
and/or parameters,
with the exception of the follow-up item
IFI 50-244/97-06-03 (Section R2.1).
ATTACHMENT I
PARTIALLIST OF PERSONS CONTACTED
Licensee
D. Fillion
B. Flynn
C. Forkell
G, Graus
A. Harhay
J. Hotchkiss
R. Jaquin
G. Jones
G. Joss
N. Leoni
R. Marchionda
F. Mis
R. Ploof
J. Smith
J. Widay
T. White
G. Wrobel
Radiochemist
Primary Systems Engineering Manager
Electrical Systems Engineering
Manager
I&C/Electrical Maintenance
Manager
Chemistry & Radiological Protection Manager
Mechanical Maintenance
Manager
Nuclear Safety and Licensing
Chemist,
Results and Test Supervisor
Radiation Protection and Chemistry
Production Superintendent
Principle Health Physicist
Secondary Systems Engineering Manager
Maintenance Superintendent
Plant Manager
Operations Manager
Nuclear Safety & Licensing Manager
INSPECTION PROCEDURES USED
'IP 37551:
IP 61726:
IP 62707:
IP 71707:
IP 71750:
IP 92902:
IP 84750:
Onsite Engineering
Surveillance Observation
Maintenance Observation
Plant Operations
Plant Support
Follow-up - Maintenance
Radioactive Waste Treatment, and Effluent and Environmental Monitoring
ITEMS OPENED, CLOSED, AND DISCUSSED
~Oened
NCV 50-244/97-06-01
Vendor Manual Program Requirements
IFI 50-244/97-06-02;
IFI 50-244/97-06-03;
Closed
NCV '50-244/97-06-01
URI 50-244/97-02-02
URI 50-244/96-1 2-01
Environmental TLD Program Enhancement
Potential Signal Loss of the Meteorological Monitoring System
Vendor Manual Program Requirements
Vendor Manual Program Requirements
Criticality Monitor for the New Fuel Preparation Area
Attachment
I
LIST OF ACRONYMS USED
CRFC
GPM
IFI
IN
IP
IR
LCO
mR/hr
MSI
'ORC
ppm
RP&C
Sl
SR
Tave
Advanced Digital Feedwater Control System
Air Operated Valve
Component Cooling Water
Containment Recirculation Fan Cooler
Emergency Operating Procedure
Engineered Safety Feature
Gallons per Minute
High Efficiency Particulate Analysis (filter)
Instrumentation
and Controls
Inspector Follow-up Item
Information Notice
Inspection Procedure
Inspection Report
Inservice Test
Improved Technical Specification
Limiting Condition for Operation
milli-Rem per hour
Main Steam Isolation
Noncited Violation
Offsite Dose Calculation Manual
Piping and Instrumentation Drawing
Plant Operations Review Committee
Plant Process Computer System
parts per million
Probabilistic Safety Assessment
Periodic Test
Quality Assurance
Quality Control
Radiologically Controlled Area
Reactor Coolant Pump
Radiological Environmental Monitoring Program
Radiation Monitoring System
Radiation Protection
Radiological Protection and Chemistry
Reactor Vessel Level Instrumentation System
Radiation Work Permit
Spent Fuel Pool
Safety Injection
Surveillance Requirement
Reactor Coolant System Average Temperature
Thermoluminescent
Dosimeter
Attachment
I
Updated Final Safety Analysis Report
Unresolved Item
ATTACHMENTII
PRE-DECISIONAL ENFORCEMENT CONFERENCE ATTENDEES
AUGUST 5, 1997
Licensee;
R. Mecredy
T. Marlow
G. Wrobel
L. Sucheski
R. Teed
R. Ploof
R. Novgrad
Vice President - Nuclear Operations
Manager, Nuclear Engineering Services Department
Manager, Nuclear Safety & Licensing
System Engineer, Civil 5 Structural
Supervisor, Nuclear Security
Manager, Balance of Plant System Engineering
Consultant for RGSE
NRC;
L. Nicholson
M. Modes
G. Smith
L. Doerflein
G. Vissing
T. Moslak
R. Rosano
Deputy Director, Division of Reactor Safety
Chief, EP, Safeguards,
5. Incident Response
Branch
Security Specialist
Chief, Projects Branch 1, DRP
Project Manager,
Project Engineer,
Senior Project Manager,
AT
ENT II
VBS ENFORCEMENT CONFERENCE
Agenda
~ Opening Remarks - R. Mecredy
~
Apparent Violation - G. Wrobel
~
VBS Program History 8 Timeline - R. Ploof
~
Vehicle Barrier System - L. Sucheski
~
Cable-Bollard System - L. Sucheski
~
Standoff Distances
- L. Sucheski
~
Long Term Corrective Actions - T. Marlow
~
Concluding Remarks - R. Mecredy
RGAE
8/5/97
I
VBS ENI'ORCEMENT CONJ'ERENCE
Qpewng Remarks
~ Acknowledgment
~ Evolution in Understanding
~ Vehicle SpeedlDirection
~ Comprehensive Corrective
Actions
8/5/97
2
VBS ENFORCEMENT CONFERENCE
Apparent Violation
o
Vehicle Barrier NW, NE, Guardhouse Openings
v
Adequate for high speed.
Slow speed not considered
~
Cable-Bollard System
v'dequate for high speed. Tampering not considered
o
Standoff Distances
v
Characterization as minimUm not appropriate
v
As inspected condition acceptable
RG&E
8/5/97
3
RG&E
1/84
- Installed initial vehicle barrier system
1/94
- EWR 10224 initiated to evaluate vehicle bomb threat
8/94
- Final Rule issued 10CFR 73.55
12/94 - NUREG 6190 Rev 1 volumes I &IIissued
2/95
- RG&E submits summary description of VBS to NRC
6/95
- NRC notifies NEI regarding passive barrier tampering
2/96
- RG&E completes installation of vehicle barrier system
2/96
- RG&E submits revised summary description to NRC
5/96
- RG&E quarterly inspection
8/96
- RG&E quarterly inspection identifies guardhouse opening
1/97. - RG&E quarterly inspection
S/5/97
4
VBS ENFORCEMENT CONFERENCE
Program HI/st~ 8 Timeline
3/97
- NRC issues NUREG errata - 20'enetration ofjersey barriers
4/97
- RG&E initiates EWR to evaluate additional
20'/97
- RG&E quarterly inspection
5/97
- RG&E installs additional jersey barrier guardhouse opening *
5/97
- RG&E initiates corrective action NE & guardhouse openings*
5/97
- NRC Inspection identifies deficiencies
5/97
- Immediate compensatory measures implemented
7/97
- Short term (engineering) corrective actions completed
- Prior to NRC Inspection
RG&E
8/5/97
5
I
~
'0,
S
0 j
~ ~
L
I
VBS ENFORCEMENT CONFERENCE
Vehicle Barrller Northwest Qpening
Understanding the Facts
~
Distance Between End of Bollard 8 Cliff14'
Installed per Drawings
Immediate Corrective Actions
~
Installed Additional Jersey Barriers
8/5/97
7
VBS EXFORCEMEXT CONFERENCE
Northwest Arrangement Sketch
(APPROX.)
STAKED JERSEY
BARRIER
1/3
KE MAX.
2 JERSEY BARRIERS
UNSTAKED, KEYED
TOGETHER TO ACT
AS OBSTACLES.
FENCE
FENCE
RG&E
8/5/91
8
VBS ENFORCEMENT CONFERENCE
Vehicle Barrier Northwest Opening
Significance of the Issue(s)
~ No Actual Consequences
~ Minimum Potential Consequences
v'low Moving Vehicle
v
Double Chain Link Fence with Intrusion Alarm
v
Monitoring with Security Cameras
Distance to Vital Equipment
v'rained Security Force
~ Regulatory Significance
v'ailure to Control Access, but not Easily or Likelyto
be Exploited
8/5/97
VBS EXFORCEMEXT CONFERENCE
Vehicle Barrier Northeast Opening
Understanding the Facts
~
Distance Between End ofBollard 8 Cliff8'
Self Identified
Immediate Corrective Actions
~
Installed Additional Jersey Barrier
8/5/97
10
g
0
~ I
~+~'W~
g g+
a~~~
I
I
I
~
~
VBS ENFORCEMENT CONFERENCE
Vehicle Barrier Northeast Opening
Significance of the Issue(s)
~ No Actual Consequences
~ Minimum Potential Consequences
Slow Moving Vehicle
Double Chain Link Fence with Intrusion Alarm
v'onitoring with Security Cameras
v
Distance to Vital Equipment
v
Trained Security Force
~ Regulatory Significance
v
Failure to Control Access, but not Easily or Likelyto
be Exploited
8/5/97
12
VBS EXFORCEMEXT COXFEREXCE
Vehicie Barrier'arardhouse
Opening
Understanding the Facts
~
Jersey Barrier Opening - 8'
Self identified
Immediate Corrective Actions
~
installed Additional Jersey Barrier
RG&E
8/5/97
13
f
g
P
r
3
i
l
~
k
I
zP
jP
~ I'W
~
~ '
~
VBS ENFORCEMENT CONFERENCE
Vehicle Barrier Guardhouse Opening
Significance of the issue(s)
o No Actual Consequences
~ Minimum Potential Consequences
u'low Moving Vehicle
Double Chain Link Fence with Intrusion Alarm
v
Monitoring with Security Cameras
v'rained Security Force
~ Regulatory Significance
v'ailure to Control Access, but not Easily or Likelyto
be Exploited
8/5/97
15
VBS EXFORCEMEXT CONFERENCE
Root Cause
VEHICLE8
IER OPENINGS
~
Design Assumptions
v
Vehicle Speed 8 Direction
8/5/97
16
VBS ENFORCEMENT CONFERENCE
Cable-Bollard System
Understanding the Facts
~
Cable Supported with Open Hooks
immediate Corrective Actions
~
Installed Metal Clamps
~
Installed Welded Steel Plates Every Other Post
8/5/97
17
Qw
VBS ENFORCEMENT CONFERENCE
Significance of the Issue(s)
CABLE-BOLL
~ No Actual Consequences
SYSTEM
~ Minimum Potential Consequences
Distance to Vital Equipment
v
Time Involved in Tampering
Double Chain Link Fence with Intrusion Alarm
v
Monitoring with Security Cameras
v
Trained Security Force
~ Regulatory Significance
e
Failure to Control Access, but not Easily or Likelyto
be Exploited
8/5/97
18
VBS ENFORCEMENT CONFERENCE
Root Cause
CABLE-BQLLARDSYSTEM
~
Design Assumptions
v
Vehicle Speed
v Use ofHand Tools
~
Evolving Industry Guidance Not Considered
8/5/97
19
VBS E~NFORCEMENT CONFERENCE
Understanding of the Facts
STANDOFF DISTANCES
~
Clarification of Inspection Apparent Violation
v'ubmittal Identified Distances 230'
155'r
Inspection Report Identified 225'
138ctual
Surveyed Distances 224'" 8 152'"
~
Distance Scaled from Construction Drawings
~
Engineering Judgment regarding Degree of Sensitivity
8/5/97
20
VBS ENFORCEMENT CONFERENCE
Immediate Corrective Action
STANDOFF DISTANCES
~
Implement Compensatory Measures
v Place 3 Tractor Trailers 8 4 Jersey Barriers
~
Measured Actual Distances
~
Reviewed Computer Models 8 Assimilated Design
Documentation
~
Analysis Rerun at 200'
100'Acceptable
~
Calculation Reviewed by Independent Expert
8/5/97
21
VBS EXFORCEMEXT CORI'EREXCE
Significance of the Issue(s)
STANDOFF DISTANCES
~ No Actual Consequences
~ No Potential Consequences
v Analysis Confirmed Acceptability of As Inspected
Configuration
~ Minimal Regulatory Significance
155'ersus 152'" - within Tl Guidance
v 230'ersus 224'"
8/5/97
22
VBS ENFORCEMENT CONFERENCE
Root. Cause
STANBOFF INSTANCES
o
Plant Change Process Implementation
v Insufficient Documentation of Engineering
Judgment
8/5/97
23
Cl
Jf
g
J
a
J
I I
I
~
0 ~
a
A ~
a v
I
VBS ENFORCEMENT CONFERENCE
Root Cause Analysis
o Purpose
v'elfCritical Approach
e Comprehensive
~ Method
v Change/Barrier Analysis
- Historical Sequence
Documents
8, Work
- Regulatory 8 Industry Documents
8/5/97
25
S'
VBS EXFORCEMEXT COXFEREXCE
Root Cause Analysis
~
Vehicle Barrier Openings
v'hy didn't designer, technical reviewer or
security identify?
~
Cable Bollard System
v Why weren't hardened fasteners used?
~
Standoff Distances
v'hy wasn't engineering judgment
documented
SI5/97
26
w.
VBS ENFORCEMENT CONFERENCE
Root Cause Analysis
Root Cause Results
~ Imperfect Interpretation ofNRC
Recluiremenfs
~ Failure to Incorporate NRC Guidance into
Design
~ Misapplication ofPlant Change Process
Implementation
$/5/97
27
VBS I;NFORCEMENT CONFERENCE
Lessons Learned
~ Security System
v Increase Knowledge
v Improve Interface
v Clarify Security System Ownership
~ Provide Specific 8 Documented Design
Inputs 8 Assumptions
~ Formally Evaluate Evolving Design
Requirements
8/5/97
28
h
<<
w
VBS ENFORCEMENT CONFERENCE
Long Term Correct//ve Action Focus Areas
~
Security System Ownership
~
Plant Change Process Expectations
~
Training
8/5/97
29
.
VBS ENFORCEMENT CONFERENCE
SECURITY SYSTEM OWNERSHIP
o
Security Plan Revised 8 Submitted - 7/25/97
~
Design Basis Review Completed - 7/31/97
Design Inputs
v'0CFR 73.55
v'inna Sfation Security Plan
e Regulatory Guide 5.44, Perimeter Intrusion Systems
Results
v Compliance Verified -1 ACTIONReport
~
LVeekly VBS Inspecfion by Security Force Established - 8/6/97
~
Quarterly VBS Inspecfion Checklist Developed - 8/15/97
~
Summary Description Revised 8 Submitted - 8/31/97
RG&E
8/5/97
30
c
VBS EXFORCEMEXT CONFERENCE
PLANT CHANGE PROCKSS EXPECTATIONS
~
Revise Plant Change Process - 8/37/97
NRC Non Safety Related Design Changes Require:
v Specific Design Inputs 8 Assumptions
v Testing
v Inspection 6 Measurement
Formal Distrl'bution 8 Tracking ofEvolving
Requirements
~
Implement Results of Plant Change Process Self
Assessment
- /0//7/97.
~
Perform External Assessment Design Criteria - 12/31/97
v Sample ofRegulatory Driven Non Saf-efy Related
Modifications
8/5/97
31
4
c
f
A A
~
~
~ ~
S ~
~
~
o
N ~
~
) a
a
~
~
~
~ ~
VBS ENFORCEMENT CONFERENCE
~ Significance
~ Compensatory Measures
~ Immediate Corrective Action
~ Long Term Corrective Actions
8!5/97
33
'
A. ~
~%g