ML17262A655

From kanterella
Jump to navigation Jump to search
Insp Rept 50-244/91-18 on 910812-16.No Violations Noted. Major Areas Inspected:Licensee Actions in Response to Generic Ltr 88-17, Loss of Decay Heat Removal During non-power Operation Including mid-loop Operating Procedures
ML17262A655
Person / Time
Site: Ginna 
Issue date: 11/04/1991
From: Eapen P, Moy D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17262A654 List:
References
50-244-91-18, GL-88-17, NUDOCS 9111180072
Download: ML17262A655 (14)


See also: IR 05000244/1991018

Text

U.S.

NUCLEAR REGULATORY COMMISSION

REGION I

Report

No.

50-244/91-18

Docket No.

50-244

License

No.

DPR-18

Licensee:

Rochester

Gas

and Electric Cor oration

49 East Avenue

Rochester

New York

14649

Facility Name:

Ginna Nuclear Power Plant

Inspection At:

Ontario

New York

Inspection

Conducted:

Au ust

-16

1991

Inspector:

D. T. Moy,

eacto

En ineer

Systems

Section

E

DRS

ov,4 ice

date

Approved by:

Dr.

P.

K. Eapen,

Chief.

Systems

Section,

EB,

DRS

date

Ins ection Summar:

Routine

announced

safet

ins ection

on Au ust

12-16

1991.

Ins ection

Re ort No. 50-244/91-18

.

L "

7. "L

of Decay Heat

Removal" during non-power operation.

The inspector

reviewed

mid-loop operating

procedures,

instrumentation,

plant hardware modification

and thermal hydraulic analysis

as related to reduced reactor coolant

system

inventory operation.

Ins ection Results:

The Generic Letter 88-17 recommendations

as described

in

the licensee

s response

were adequately

implemented.

No violations or additional

unresolved

items were identified.

'Vf11i80072 9iif04

PDR

ADOCK 05000244

6

PDR

'

1.0

Lon

Term Pro

rammed

Enhancement

for Generic Letter 88-17

"Loss of Deca

Heat Removal'on-Power

0 eration

Loss of Decay Heat

Removal

(DHR) during non-power operation

and the

consequences

of such

a loss are of significant safety concern.

Many

events of loss of DHR have occurred at nuclear

power plants while the

RCS

has

been drained

down for such

a mid-loop activities

as

steam generator

inspection

and repair of a reactor coolant

pump.

These activities are

often in progress

when both the reactor coolant

system

and

the'ontainment

are less

than adequately

secured.

GL 87-12,

"Loss of Residual

Heat

Removal

(RHR) while the Reactor Coolant

System

(RCS) is Partially Filled," was i ssued to all licensees

of

operating

PWRs

and holders of construction

permits

on July 9,

1987.

Responses

to the

NRC indicated that

some licensees

did not understand

the

identified problems,

and the problems

have continued,

as evidenced

by

occurrence

of events

since the generic letter was issued.

The seriousness

and continuation of these

problems resulted

in issuance

of GL 88-. 17.

It requires

the recipients to respond with two plans of

actions:

a.

A short-term

program entitled "expeditious actions" that was

essentially limited to reduced

inventory conditions.

b.

A longer-term

program entitled

programmed

enhancements.

The Generic Letter stated that the

programmed

enhancements

consisting of

hardware installation and/or modification,

and

programmed

enhancements

that depend

upon hardware installation

and modification, should

be

implemented:

a.

by the

end of the first refueling outage that is initiated

18 months

or later following receipt of the GL, or

'.

by the

end of the

second refueling outage following the receipt of

the GL, which ever occurs first. If a shutdown for refueling has

been initiated as of the date of receipt of this letter, that is to

be counted

as the first refueling outage.

Programmed

enhancements

that do not depend

upon hardware

changes

were to

be implemented within 18 months of receipt of the GL.

The licensee

provided the responses

for "expeditious actions"

and

"programmed

enhancements"

respectively

in letters dated January

4,

1989

and February

1,

1989.

NRC reviewed the

above expeditious

actions

response

and documented

the conclusion in

NRC letter dated

February

22,

1989.

The

licensee's

short term or expeditious actions

program

was previously

reviewed

as detailed in Inspection

Report 50-244/89-05.

The purpose of this inspection

was to assess

the adequacy

of the licensee's

long term progr'am for Generic Letter 88-17 as detailed

below:

1. 1

-Instrumentation for Mid Loo

0 eration

Generic Letter 88-17 provided the following recommendations

for

instrumentation for Mid Loop operation:

Provide reliable indications of parameters

that describe

the state of

the

RCS and the performance

of systems

normally used to cool the

RCS

for both normal

and accident conditions.

At -a minimum, provide the

following i'n the Control

Room:

b.

two independent

RCS level indications

at least

two independent

temperatures

measurements

representative

of the core exit whenever

the Reactor

Vessel

(RV) head is located

on top of the

RV

the capability of continuously monitoring

DHR system

performance

whenever

a

DHR system is being

used for cooling the

RCS.

d.

visible and audible indications of abnormal

conditions in

temperature,

level,

and

DHR system performance.

Ins ection Findin

(a)

Reactor

Coolant

S stem Water Level Indications

As stated

in the response

to Generic Letter 88-17,

the Licensee

upgraded

and installed

two reactor

water level indications in

the control

room.

Engineering

Work Request

(EWR) 4671,

(Rev.

0,

December

19,

1989) Reactor

Loop Level Upgrade

replaced

the

pr'esent

reactor coolant

system

(RCS) "B" loop level indication

hardware

including pressure

transmitter,

local level indicator

and the control board indicator with modern

equipment.

A

functionally independent

and reliable level indication instrument

system

was also installed

on the

RCS "A" loop.

The inspector

reviewed "Calibration and Uncertainly Analysis" -of

Loop Level

Upgrade Modification Package

(EWR 4671),

Rev 1,

April 18,

1990.

This Calculation

was based

on Westinghouse's

report "Report

on Calculation of Instrument Uncertainties for

the

R.

E. Ginna dated

November

1983.

The calculated

instrument

uncertainties

for the upgraded

level indication system

were 2.31

inches

and 1.73 inches for loops

A and

B respectively.

Both are

within their respective

maximums of 3.0 inches

and 2.5 inches

specified in the Design Criteria Section of "Loop Level Upgrade"

package

EWR-4671.

These uncertainties

are

based

on the assumption

'4

'hat the transmitters

were calibrated to

a 0.5% accuracy

and

Main Control board was'calibrated

to

a .1.50% accuracy.

The

inspector

reviewed this calculation

and found it to be

technically adequate.

(b)

The inspector

concluded that the'evel

instrument uncertainties

are appropriate for use during mid-loop operation.

The inspector

reviewed the "Level Correction for LIT-432A due to

RHR Flow,"

EWR 4671-ME-001,

Rev.

0, February

8,- 1990.

The licensee

incorporated corrections to account for the location of the

'ensing

line tap

and the pressure

loss

due to the Flow in the

RHR suction line.

The inspector verified that the flow correction

=

factors were incorporated

in the plant process

computer

system.

The inspector

had

no further concerns

in this regard.

Core Exit Thermocou les

Tem erature

Indications

The licensee

assures

the availability of two core exit

thermocouples

during reduced

inventory operations

(Operating

procedures

No. 0-2.3. 1,

Rev.

43,

Step

3. 14. 1 to 3. 14.3.2).

The

thermocouples

are digitally displayed

in the control

room.

The

range of this indication is from 0 to 2300'F.

The temperature

indications are fed to the Plant Process

Computer

System

(PPSC)

to monitor and alarm

as necessary.

The temperatures

are required

to be manually logged

once per hour when the

PPCS is'perating;

otherwise,

these

temperatures

are required to be logged at

15

minute intervals.

(c)

Monitorin

Deca

Heat

Removal

S stem Performance

The licensee

monitors

pump motor current to detect

RHR pump

vortexing.

The

PPCS continually monitors the following

parameters

in the control

room:

Point ID

Descri tion of Parameter

F0626

L0432A/B

L0432ACF

L0432ACL

I0685A/B

P0682A/B

F0683A/B

T0684A/B

NPSHRHRA/B

RHR l oop flow

Reactor Coolant loop A/B level

Level correction for

RHR flow

Corrected

level

RHR pump A/B motor current

RHR pump A/B suction pressure

RHR discharge

flow loop A/B flow

RHR pump A/B suction temperature

RHR pump A/B margin to

NPSH loss

The inspector

reviewed

each of the above

parameters

5 alarm

setpoint against

the "Analog Input Point Data

Base Values"

and

verified that the alarm setpoints

were adequately

established

for mid-loop operation.

The inspector also noted that, the

RHR system is routinely

monitored in the main control

room utilizing RHR system flow

( FT 626),

system pressure

(PT 420 5 PT 420A),

system temperature

(FT-630)

and loop level

(PT 432A & B).

Based

on the above,

the inspector

concluded that the .licensee

implemented visible and audible indications of temperature,

level

and

RHR system

performance

per Generic Letter 88-17.

1.2

Review of Mid Loo

0 eratin

Procedures

Generic Letter 88-17

recommended

the development

and implementation of

the following to cover reduced

inventory operation.

(a)

procedures

that cover

normal operation of the

NSSS,

containment,

and supporting

systems

under conditions for which cooling would

normally be provided by

DHR systems.

(b)

procedures

that cover emergency,

abnormal,

off-normal, or the

equivalent operation of the

NSSS,

the containment,

and supporting

systems if an off-normal condition occurs while operating

under

, conditions for which cooling would normally be provided by

DHR

systems,

k

(c)

administrati've controls that support

and supplement

the procedures

in items above,

and all other actions identified in this

communication,

as appropriate.

The .inspector

selected

the following mid-loop operating

procedures

for review to determine

whether

the Licensee

has

completed

the Generic Letter 88-17 recommendations:

Operating

procedure

No. 0-2.3. 1.

Rev.

43, June

18,

1991, "Draining

and Operation at Reduced

Inventory of the reactor coolant system".

Operating

procedure

No. 0-2.3. 1A, Rev.

9,

May 3,

1991,

"Containment

closure capabilities

in two hours during

RCS Reduced

Inventory

Operation".

Operating

procedure

No.

RHR.2,

Rev.

3, April 20,

1990,

"Loss of

RHR while operating at

RCS reduced

inventory conditions.

These

procedures

provide instructions for operation and'urveillance

whenever there is fuel in the reactor vessel

and the reactor coolant

system is in

a reduced

inventory condition (3 feet below the top of

the reactor flange or

RCS less

than

64 inches

on the level

B indicator

in the control room)..

0'

A majority of the licensee's

mid loop operating

procedures

were

developed

using the plant and utility experi.ence.

For each 'of the

above procedures,

the inspector verified that the precautions,

limitation and entry conditions to mid-loop operation

were techni'cally

adequate.

The inspector

found that the licensee's

actions

were

consistent

with the

GL recommendation

in this regard.

1.3

Review of RCS Inventor

Addition

In this area,

the Generic Letter 88-17

recommended

to:

(a)

Provide adequate

operating,

operable,

and/or available

equipment

of high reliability for cooling the

RCS and for avoiding

a loss

of

RCS cooling.

(b)

Maintain sufficient existing equipment

in an operable

or available

status

so as to mit'igate loss of DHR or loss of

RCS inventory

should they occur.

This should include at least

one high pressure

injection

pump and

one other system.

The water addition rate

provided by each

equipment

should

be at least sufficient to keep

the core covered.

(c)

Provide adequate

equipment for personnel

communications that

involve activities related to the

RCS of systems

necessary

to

maintain the

RCS in a stable

and controlled condition.

The inspector verified that the Licensee

has procedures

and

administrative control (Operating procedure

No. 0-2.3. 1,

Rev.

43,

steps

3. 17 to 3. 19) to provide at least

two adequate

means of adding

inventory to the

RCS, in addition to the

pumps of the normal

DHR

systems.

One source of inventory makeup is the gravity flow from

refueling water storage

tank

(RWST)

(DWG. 33013-1261,

Rev.

19 and

-1247,

Rev.

16).

(The injection flow into

RCS via the gravity feed

system is approximately

2500

GPM.)

The second

source of the makeup

is the High Pressure

charging

system path from the

RWST through the

charging

pump and heat exchangers.

(The injection flow into

RCS via

this high pressure

system is approximately

60

GPM)

(DWG 33013-1265

sheets

1

& 2,

Rev. 4).

The third source of the makeup is from RWST

through the safety injection pumps.

(The safety injection rate is

approximately

500

GPM)

(DWG. 33013-1262

sheet

1&2 Rev.

7 & 3

respectively).

The inspector verified that these

flow paths are

available

as stated

in the licensee's

response

letter to GL.

Inspector further verified that injection flow is higher than the

core boil off rate

(51

GPM) and sufficient to keep the core covered

during mid-loop operation.

The inspector

concluded that the licensee's

actions

were acceptable

as they were consistent with the licensee's

commitments in this regard.

0'

1.4

Review of Thermal

H draulic Anal sis

The Generic letter

recommended

that licensees

conduct analyses

to

supplement existing information and develop

a bases for procedures,

instrumentation installation

and response,

and equipment

NSSS

interactions

and 'response.

The inspector

reviewed Westinghouse's

Mid Loop'Calculation

Report

NS-OPLS-OPL-I-89-111,

dated

February

20,

1989.

This report provides

best estimate calculations of the time to reach saturation,

the boil

off rate,

the minimum vent size required to prevent pressurization

and the estimated

time to core uncovery

as

a function of time after

shutdown.

The inspector

reviewed the following sections of the report:

Time for RCS in the core to reach saturation

temperature

Time to core uncovery with a large vent area

Makeup flow rate for boil off

Vent area

required to reduce

RCS pressurization

The inspector verified that the results of the

above calculations

were incorporated

in the mid loop operating

procedures.

For example,

the time to core uncovery (hrs) vs.

time after shutdown curve is used

in Operating

procedure 0.2.3. 1: 18 step

5. 14.2. 1 to 5. 14.3.4.

For

another

example,

core boiling vs. time after shutdown

data

were

used

in drain

down operating

procedure 0.2.3. 1:5, steps

3. 17 to 3. 19.

The

inspector

found that the licensee's

actions

were acceptable

as they

were, consistent with the licensee's

commitments

in this regard.

1.5

Technical

S ecification

The Generic letter

recommended

that Technical specifications that

restrict or limit the safety benefit of the actions identified in the

GL should

be identified and appropriate

changes

should

be submitted to

the

NRC.

The inspector verified that the facility has

no technical

specification

that would limit the safety benefits of the action in the GL, as stated

in'he licensee

response.

1.6

Reactor

Coolant

S

stem

erturbation

Generic Letter 88-17

has

recommended. that the licensee

should consider

training, procedures,

and controls that reasonably

avoid perturbing

activities

when

RCS inventory is low and decay heat is high.

The inspector verified that the Licensee

has

implemented

procedures

and administrative controls to preclude operations that would lead to

perturbations

in the

RCS.

Operating

procedure

No. 0-2.3. 1,

for'raining

down in the notice after

step 5.0, establishes

administrative

control for requesting,

reviewing, working or authorizing activities

that

may affect or perturb the

RCS water level while the

RCS is

operating at reduced

inventory mid-loop conditions.

This procedure

also provides

a detail list of- components

which may perturb the

RCS

level during the

low loop level operation.

The inspector

concluded that the procedures

and administrative controls

established

to minimize reactor perturbation during mid-loop operation

were consistent with the programmed

enhancements

described

in GL 88-17.

2.0

A/

C Involvement in Mid Loo

0

eration'he

inspector

reviewed the licensee's

Quality Assurance

Surveillance

Report

91-024.

The purpose of the licensee's

audit was to provide

an assessment

of control

room activities for entering,

maintaining

and leaving the reduced

inventory condition.

The highlights of this assessment

were:

Operator

performance

during low level operation

was appropriate

and timely.

The responses

to unanticipated

annunciators

were good.

Conditions

such

as

Board modification

The inspector

concluded

addressed

the technical

3.0

Conclusion

the adverse

weather alert

and the ongoing Control

were addressed

in a safe

manner.

that the licensee's

QA surveillance effectively

adequacy

of the mid-loop operation.

Management

support

was evident for the activities related to mid loop

operation..

The evaluations

were detailed

and technically sound.

The line

supervisor

and cognizant engineer

were knowledgeable

in the safety concerns

and the regulatory positions discussed

in GL 88-17.

The engineer

recommendations

were adequately

implemented.

QA surveillance for mid-loop

operation

was technical

and thorough.

'

4.0

Plant Tours

The inspector

made tours of the Ginna plant including the control

room,

charging

and

RHR pump

rooms to observe

any work in progress,

housekeeping

and cleanliness.

No unacceptable

conditions were found.

5.0

Exit Interview

On August 16,

1991,

an exit interview was conducted with the licensee's

senior site representative

(denoted

in attachment)

to summarize

the

observations

and conclusions

of this inspection.

ATTACHMENT

Mid Loo

0 eration

Ins ection

Person

contacted

Rochester

Gas

and Electric

Com

an

W. Backus

J. Bitter

R. Eliaz

T.

Kaza

F. Maciuska

R. Marchionda

T. Marlow

D. Markowski

J. St. Martin

C. Rioch

T. Schuler

Operation

Engineer

Electrical

Engineer

Nuclear Safety 5 Licensing Engineer

'omputer System, Engineer

Supervisor-Licensee

Training

Superintendant

Support Svc.

Superintendant

Ginna production

Mechanical

Engineer

Corrective Action-Engipeer

Liaison Engineer

Operation

Engineer

W. Stiewe

J.

Widay

Electrical

gC Engineer

Plant Manager

U.S. Nuclear

Re viator

Commission

T. Moslak

Senior

Resident

Inspector