EOP:

AP-ELEC. 1 TITLE:

LOSS OF g12A OR 12B TRANSFORMER REV:

6 PAGE 1 of 12 ROCHESTER GAS AND ELECTRIC C

PORATION GINNA STATION CONTROLLED COPY NUNBE TECHNICAL VIEW ~ Q

+

P C REVIEW D TE 4

'9~

6 P

T SUPERIN N

NT 4 EFFECTI DATE QA~ NON-CATEGORY 1.0 REVIEWED BY:

6 INNASTATION START:

DATE IMF COMPLETED:

DATE TIME'oaS0SOSZS e00227 PDR ADOCK 0500024 F

PNU

f'7 l

~

C I

J' l

~

F

~

EOP:

AP-ELEC. 1 LOSS OF N12A OR 12B TRANSFORMER REV:

6 PAGE 2 of 12 A.

PURPOSE This procedure provides actions to respond to a loss of N12 SS Transformer.

B.

ENTRY CONDITIONS/SYMPTOMS 1.

SYMPTOMS The symptoms of loss of N12 SS Transformer are:

a.

Annunciator,L-20, 12A XFMR OR 12A BUS TROUBLE ALARM lit, or c.

Annunciator L-28, 12B XFMR OR 12B BUS TROUBLE ALARM lit.

EOP:

AP-ELEC. 1 TITLE:

LOSS OF N12A OR 12B TRANSFORMER REV 6

PAGE 3 of 12 STBP ACTION/EXPECTED RESPONSE

RESPONSE

NOT OBTAINED CAUTION IF AT ANY TIME DURING THIS PROCEDURE A REACTOR TRIP OR SI IS REQUIRED, E-O, REACTOR TRIP OR SAFETY INJECTION, SHALL BE PERFORMED.

NOTE:

Steps 1 through 3 are IMMEDIATE ACTION steps.

O 1

Verify BOTH EMERGENCY D/Gs START I

IP one OR both emergency D/Gs do not start, THEN refer to ER-D/G.l, RESTORATION OF A PAILED D/G.

O 2

Verify Power To Both Trains Of Safeguards Busses:

o Bus 14 AND Bus 18 - GREATBR THAN 420 VOLTS

-AND-o Bus 16 AND Bus 17 - GREATER THAN 420 VOLTS Try to restore pover to all AC emergency busses.

IP pover can NOT be restored to at least one train, THEN go to ECA-O.O, LOSS OP ALL AC

POWER, Step 1.

O 3

Verify Service Water System Operation:

a.

SW pumps - AT LBAST ONE RUNNING IN EACH LOOP b.

SW header pressure

- GREATER THAN 40 PSIG IN EACH LOOP

a. Manually start pumps as necessary.

(260 KW each)

b. Manually align valves as necessary.

4

EOP:

AP-ELEC. 1 T1TLE:

LOSS OF N12A OR 12B TRANSFORMER REV0 6

PAGE 4 of 12 STEP ACTION/EXPECTED RESPONSE

RESPONSE

NOT OBTAINED 4 Verify CCW Pump Operation:

a. At least one CCV pump - RUNNING
b. Alarm A-22 (CCV PUMP DISCHARGE LO PRESS 60 PSI) - EXTINGUISHED
a. Start one CCV pump (120 kw).
b. Start second CCV pump (120 kw).

5 Establish Appropriate Steps Of This Procedure To Be Performed:

IR turbine generator is tripped, THEN go to Step 12.

o Turbine generator ON LINE 6

Check S/G Level CONTROLLING Place MRV regulating valves in IN AUTO MANUAL and control feed flow as required.

7 Establish Charging Flow:

a.

Check D/G loading - LESS THAN 1875 KV

b. Start -

ONE CHARGING PUMP (75 KV each)

c. Ad]ust charging flow and HCV-142 as necessary

- TO MAINTAINRCP LABYRINTH SEAL D/P GREATER THAN 15 INCHES H20 AND PRESSURIZER LEVEL GREATER THAN 13X a.

Shed sufficient non-essential loads to provide adequate D/G capacity for charging pumps (75 KV each).

l.

EOP:

AP-ELEC.1 TITLE:

LOSS OF N12A OR 12B TRANSFORMER REV:

6 PAGE 5 of 12 STEP ACTION/EXPECTED RESPONSE

RESPONSE

NOT OBTAINED 8 Verify Letdown In Service:

o Letdown flow - APPROXIMATELY 40 GPM o

Letdown pressure

- APPROXIMATELY 250 PSIG IF letdown is isolated, THEN:

a. Adjust charging pump speed and HCV-142 to establish greater than 20 GPM charging line flow to REGEN Hx.
b. Verify letdown isolation valve AOV-371 is open.
c. Place letdown orifice valves to close (AOV-200A, AOV-200B, AOV-202).
d. Place letdown controllers TCV-130 and PCV-135 in manual'at 25X.

e.

Open loop B cold leg to REGEN Hx AOV-427.

f. Open on 40 GPM letdown orifice isolation valve.
g. Place TCV;130 in AUTO at approximately 105'F.
h. Place PCV-135 in AUTO at 250 psig.
i. Adjust charging pump speed and HCV-142 as necessary.

EOP:

AP-ELEC. 1 LOSS OF N12A OR 12B TRANSFORMER REV:

6 PAGE 6 of 12 STEP ACTION/EXPECTED RESPONSE

RESPONSE

NOT OBTAINED CAUTION o

OBSERVE D/G LOADING LIMITS OF 2300 KV FOR 1/2 HOUR, 2250 KV FOR 2 HOURS, AND 1950 KV FOR CONTINUOUS SERVICE.

o ANYTIME EMERGENCY D/GS ARE THE ONLY SOURCE OF AC POVBR TO THE PLANT, PERSONNEL SHOULD BE ASSIGNED TO MAINTAIN SURVBILLANCE OF THE D/GS.

9 Establish That PRZR Proportional Heaters Are Operable:

a.

PRZR heater control group switch

- RBSBT IF proportional heaters inoperable, THEN energize PRZR backup heaters as necessary.

b. Breaker - RECLOSED 10 Check IF CNMT Recirc Fan Required:

a.

CNMT temperature

- LESS THAN 125'F AND STABLB OR DECRBASING (PPCS GROUP DISPLAY TCV)

a. Start one CNMT recirc fan as D/G loading permits (240 KV each fan).

NOTE:

Power operation may continue if conditions required by Tech Spec section 3.7 are met.

11 Establish CLOSE MONITORING OF PLANT CONDITIONS~

AND GO TO STEP 23

EOP:

AP-ELEC. 1 LOSS OF g12A OR 12B TRANSFORMER REV 6

PAGE 7 of 12 STEP ACTION/EXPECTED RESPONSE

RESPONSE

NOT OBTAINED 12 Verify AFW Pumps Running:

a.

MDAFV pumps - RUNNING VITH PROPER DISCHARGE PRESSURE AND FLOV

a. Start MDAFW pumps (230 KV each).

b.

TDAFV pump - RUNNING VITH PROPER

b. Start TDAFV pump.

DISCHARGE PRESSURE AND FLOV NOTE:

Attempts to restore offsite pover should continue, (Refer to ER-ELEC.1, RESTORATION OF. OFFSITE POVER).

13 Verify Natural Circulation Per Attachment NC

AP-ELEC. 1 LOSS OF N12A OR 12B TRANSFORMER REV 6

PAGE 8 of 12 STEP ACTION/EXPECTED RESPONSE

RESPONSE

NOT OBTAINED CAUTION o

OBSERVE D/G LOADING LIMITS OF 2300 KW FOR 1/2 HOUR, 2250 KW FOR 2 HOURS, AND 1950 KW POR CONTINUOUS SERVICE.

o ANYTIME EMERGENCY D/GS ARE THE ONLY SOURCE OF AC POWER TO THE PLANT, PERSONNEL SHOULD BE ASSIGNED TO MAINTAIN SURVEILLANCE OP THE D/GS.

14 Establish 480 Volt Non-Safeguards Busses Energization As Follows:

a. Dispatch an AO to verify - ALL LOADS ON BUSSES 13 AND 15 ARE STRIPPED
a. Operate local trip mechanisms as necessary to strip all loads.
b. Close bus 13 - bus 14 tie breaker - TIE BREAKER CLOSED
c. Close bus 15 - bus 16 tie breaker

- TIE BREAKER CLOSED

d. Close MCC lA breaker - BREAKER CLOSED
e. Close MCC 1B breaker.-

BREAKER CLOSED

f. Close MCC 1E breaker - BREAKER CLOSED
g. Close MCC 1F breaker - BREAKER CLOSED
h. Close MCC 1G1 or 1G2 breaker-BREAKER CLOSED
b. IF breaker can NOT be closed, THEN notify electricians.
c. IF breaker can NOT be closed, THEN notify electricians.
d. IF breaker can NOT be closed, THEN notify electricians.
e. IF breaker can NOT be closed, THEN notify electricians.
f. IP breaker can NOT be closed, THEN notify electricians.
g. IP breaker can NOT be closed, THEN notify electricians.
h. IP breaker can NOT be closed, THEN notify electricians.

A

EOP:

AP-ELEC.1 TITLE:

LOSS OF N12A OR 12B TRANSFORMER REV 6

PAGE 9 of 12 STEP ACTION/EXPECTED RESPONSE

RESPONSE

NOT OBTAINED 15 Establish IA:

a. Start - 2 IA compressors as D/G loading permits (100 KW per compressor)
b. Verify IA pressure

- GREATER THAN 100 PSIG IF IA can NOT be established, THEN refer to AP-IA.1, LOSS OF INSTRUMENT AIR.

16 Verify Instrument Bus 1D-ENERGIZED IF instrument bus 1D NOT energized, THEN svitch instrument bus 1D to maintenance supply.

17 Establish Charging Flow:

a.

Check D/G loading - LESS THAN 1875 KW

b. Start -

ONE CHARGING PUMP (75 KW each)

c. Adjust charging flov and HCV-142 as necessary

- TO MAINTAINRCP LABYRINTH SEAL D/P GREATER THAN 15 INCHES H20 AND PRESSURIZER LEVEL GREATER THAN 13X'.

Shed sufficient non-essential loads to provide adequate D/G capacity for charging pumps (75 KW each).

EOP:

AP-ELEC.1 LOSS OF 512A OR 12B TRANSFORMER REV 6

PAGE 10 of 12 STEP ACTION/EXPECTED RESPONSE

RESPONSE

NOT OBTAINED 18 Verify Letdown In Service:

o Letdown flow - APPROXIMATELY 40 GPM IF letdown is isolated, THEN:

a. Bstablish charging line flow to REGEN Hx greater than 20 GPM.

o Letdown pressure

- APPROXIMATELY

b. Place letdown orifice valve 250 PSIG switches to close.
c. Place low press LTDN press PCV-135 in manual at 25X open.
d. Increase PRZR level to greater than 13X.
e. Verify LTDN loop B cold leg to RHx AOV-427 and LTDN isol vlv RHx to NRHx AOV-371 open.
f. Open letdown orifice valve AOV-200A or 'AOV-200B.
g. Ad)ust PCV-135 for 250 psig and place in AUTO.

NOTE:

PRZR heaters should be restored within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> of initiation of natural circulation.

19 Restore PRZR heaters:

o PRZR heaters

- RESTORED (Refer to BR-PRZR.l, RBSTORATION OF PRZR HBATBRS DURING BLACKOUT)

IF at least 100 KV of PRZR heaters can NOT be restored within. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, THEN be on RHR within an additional 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.

(Refer to Technical Specification 3.1.1.5.)

20 Check S/G Levels:

a.

Both S/G narrow range levels-GREATER THAN 25X

a. Control total AFW flow greater than 200 gpm until both S/G levels greater than 25X.

P, IE I

I

EOP:

AP-ELEC. 1 TITLE:

LOSS OF N12A OR 12B TRANSFORMER REV 6

PAGE ll of 12 STEP ACTION/EXPECTED RESPONSE

RESPONSE

NOT OBTAINED NOTE:

Vhen turbine shaft stops spinning and turning gear oil pump is running, turbine should be placed on turning gear.

21 Complete The Following As D/G Loading Permits:

a. Turning gear oil pump -

STARTED (42 KV) b.

DC emergency oil pump -

STOPPED

c. Both control rod shroud fans-STARTED (60 KV per fan)
d. Vaste gas compressor

- STARTED AS NECESSARY e.

Main transformer cooling fans-STARTED AS NECESSARY

a. Verify DC emergency oil pump running and break vacuum to accelerate coastdown.

Continue with Step 21c.

VHEN shaft

stops, THEN stop DC emergency oil pump.
c. Notify electricians if no control rod shroud fans start.

NOTE:

Refer to 0-9.3, NRC IMMEDIATE NOTIFICATION, for reporting requirements.

22 Establish If Cooldown is Required:

a.

Cooldown - DETERMINED NECESSARY (Refer to ES-0.2, NATURAL CIRCULATION COOLDOVN)

a. IF unit is to remain at hot
shutdown, THEN refer to 0-3, HOT SHUTDOWN VITH XENON PRESENT.

23 Establish RESTORATION OF OFFSITE POWER (Refer to ER-ELEC.l, RESTORATION OF OFFSITE POWER)

AP-ELEC.1 LOSS OF g12A OR 12B TRANSFORMER REV:

6 PAGE 12 of 12 STEP ACTION/EXPECTED RESPONSE

RESPONSE

NOT OBTAINED 24 Complete NOTIFICATION TO HIGHER SUPERVISION 25 Return to Procedure And Step In Effect

-END-

P

EOP:

AP-ELEC. 1 TITLE:

LOSS OF 412A OR 12B TRANSFORMER REV 6

PAGE 1 of 1 FIGURE MIN SUBCOOLING NOTE:

Subcooling Margin = Saturation Temperature From Figure Below [-] Core Exit T/C Indication RC 2500 2400 2300 2200 2100 2000 1900 1800 1700 1600 1400 1300 1200 1100 1000 900 800 700 600 500 400 300 200 100 0

20 S

PRESSURE (PSIG)

RCS PRESSURE INCREMENTS 20 PSIG SUBCOOLED REGION INADEQUATE SUBCOOLING REGION CNMT TEMPERATURE INCREMENTS 10'F NORMAL CNMT 0

250 300 350 400 450 500 550 600 650 700 CORE EXIT SATURATION TEMPERATURE ('F)

EOP:

AP-ELEC. 1 LOSS OF N12A OR 12B TRANSFORMER REV 6

PAGE 1 of 1 ATTACHMENT NC NOTE: It may take several minutes following initial transient for natural circulation to develop.

The following conditions indicate natural circulation flow:

o RCS subcooling based on core exit T/Cs GREATER THAN REQUIREMENTS OF FIGURE MIN SUBCOOLING o

S/G pressures STABLE OR DECREASING o

RCS hot leg temperatures STABLE OR DECREASING o

Core exit T/Cs STABLE OR DECREASING o

RCS cold leg temperatures AT SATURATION TEMPERATURE FOR S/G PRESSURE The following equipment should be operating to support natural circulation and cooling:

o Control rod shroud fans o

PRZR heaters (Refer to ER-PRZR.1, RESTORATION OF PRZR HEATERS DURING BLACKOUT) o One Reactor Compartment Cooling Fan

)

E