ATTACHMENT TO LICENSE A'HENDHENT NO. 43 PROVISIONAL OPERATINA LICENSE NO.

DPR-18 DOCKET NO. 50-244 Change the Technical Specifications contained in Appendix.A of License No.

DPR-18 as indicated below.

The revised pages contain the captioned amendment number and marginal lines to reflect the area of change.

REMOVE INSERT 3.1-1 3.1-'2 3.1-3 3.1-4

3. 8-2a
4. 3-3 4.11-2 3.1-1 3.1-2 3.1-3 3.1-4 3.1-4a*

3;1-4b 3.1-4c 3.1-4d*

3.1-4e*

3.8-2a 4.3-3 4.3-4 4.11-2

  • Included for pagination purposes only.

TECEINICAL SPECIFICATIONS DEFINITIONS The following terms are defined for uniform interpreta-tion of the specification.

Thermal Power The rate that the thermal energy generated by the fuel f

is accumulated by the coolant as it passes through the reactor vessel.

Reactor 0 eratin Modes Mode Refueling Cold Shutdown Reactivity

~k k'10 Coolant Temperature f

T

< 140 200 Hot Shutdown 540 Operating

~fl 0

580 Any operation within the containment involving movement of fuel and/or control rods when the vessel head is.un-bolted.

~Oerable Capable of performing all intended functions in the intended manner.

Amendment No. 43 1-1

1 1

~

0 3.0 I

IIMITING CONDITIONS FOR OPERATION 3.1 Reactor Coolant S stem Applicability:

Applies to the operating status of the Reactor Coolant System when fuel is in the reactor.

To specify those conditions of the Reactor Coolant System which must be met to assure safe reactor operation.

Specification:

3.1.1 0 erational Com onents 3.1.1.1 Reactor Coolant K,oo s a ~

b.

When the reactor power is above 130 MWT (8.5%),

both reactor coolant loops and their associated steam generators and reactor coolant pumps shall be in operation.

I If the conditions of 3.1.1.l.a are not met, then immediate power reduction shall be initiated under administrative control. If the shutdown margin meets the one loop requirements of Figure 3.10-2, then the power shall be reduced to less than 130 MWT. If the one loop shutdown. margin of Figure 3.10-2 is not met, the plant shall be taken to the hot shutdown condition and the one loop shutdown margin shall be met.

3.1-1 Amendment. No. 1S, 43

0

c.

Except for special tests, when the average coolant temperature is above 350'F, or when the reactor is at hot shutdown or is critical with the reactor power less than or equal to 130 MWT (8.5%), at least one reactor coolant loop and its associated steam generator and reactor coolant pump shall be in opera-tion.

The other loop and its associated steam'enerator must be operable so that heat. could be removed via natural circulation.

However, both reactor coolant pumps may be de-energized for up to 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> provided (1) no operations are permitted that would cause dilution of the reactor coolant system boron concentration, and (2) core outlet temperature is maintained at least 10'F below saturation temperature.

d.

e.

If the conditions of 3.1.'l.l.c'are not met, suspend all operations involving a reduction in boron concentration of the Reactor Coolant System and immediately initiate corrective action to return the required coolant loop to operation.

When the reactor is at cold shutdown or wRen the average coolant temperature is between 200'F and 350'F, at least two of the following coolant loops.

shall be operable:

(i) reactor coolant steam generator (ii) reactor'coolant steam generator 3.1-2 loop A and its associated and reactor coolant pump.

loop B and"its-'associated and reactor coolant pump.--

Change Np. ~

Amendment Np. ~, pf, ~ 43

(iii) residual heat removal loop.A.*

(iv) residual heat removal loop B.*

f.

Except during steam generator crevice cleaning operations, while at cold shutdown or when the average coolant temperature is between 200'F and 350'F, at least one of the coolant loops listed in paragraph 3.1.1.1.e shall be in operation.

However, both reactor coolant pumps and residual heat removal pumps may be de-energized for up to 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> pro-vided 1) no operations are permitted that would cause dilution of the reactor coolant system boron concentration, and 2) core outlet temperature is maintained at least 10'F below saturation tempera-ture.

g.

h.

If the conditions of 3.1.1.1.e are not met, immediately initiate corrective action to return the required loops to operable status, and if not in cold shutdown already, be in cold'hutdown within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

If the conditions of 3.1.1,1.f are not met, then suspend all operations involving a reduction in boron concentration of the Reactor Coolant System and immediately initiate corrective action to return the required coolant loop to operation.

  • The normal or emergency power source may be inoperable while in cold shutdown'.

3.1-3 Amendment No.

43

i.

At least one reactor coolant pump'or "the residual heat removal system shall be in operation when a

reduction is made in the boron concentration of the reactor coolant.

j.

At least one reactor coolant pump shall be in operation for a planned transition from one Reactor Operating Mode to another involving an increase in the boron concentration of the reactor coolant, except for emergency boration.

k.

A reactor coolant pump shall not be started with one or more of the RCS cold leg temperatures

< 330'F unless

1) the pressurizer water volume is less than 324 cubic feet (38% level) or 2) the secondary water temperature of each steam generator is less than 50'F above each of the RCS cold leg temperatures.

3.1.1.2 Steam Generator a.

The temperature difference across the tube sheet shall not exceed 100'F.

3.1.1.3 Safetv Valves a.

During cold shutdown or refuel.ing when the reactor head is bolted on the vessel, at least one pressurizer e

code safety valve shall be operable with a'lift setting of 2485 psig+ 15.

b':.

If the conditions of.. 3.1.1.3.a are not met, immediately suspend all operations involving positive reactivity changes and place an operable RHR loop into operation in the shutdown cooling mode.

3.1-4 Change No.M Amendment Mo.~~~,43

C.

Whenever the reactor is. at hot shutdown or critical, both pressurizer code safety valves shall be operable with a lift setting of 2485 psig

+ lX.

d.

If one pressurizer code safety valve is not operable while the reactor is at hot shutdown or critical, then either restore the inoperable valve to operable status within 15 minutes or be in at least hot shutdown within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and below a Tavg of 350'F within an additional 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.

3.1.1.4 Relief Va1vea a.

Both pressurizer power operated relief valves (PORVs) and their associated block valves shall be operable whenever the reactor is at hot shutdown or critical.

b.

With 'one or more PORV(s) inoperable, within 1

hour'ither restore the PORV(s) to operable status or close the associated block valve(s); otherwise, be in at least hot shutdown within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in cold shutdown within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

c.

With one or more block valves(s) inoperable, within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> either restore the block valves(s) to operable status or close the block valve(s) and remove power from the block valve(s); otherwise, be in at least hot shutdown within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in cold shutdown within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />...

3.1-.4a Change No. ~

Amendment No. P3,+6. ~,

43

3.1.1.S Pressurizer Whenever the reactor is at hot shutdown or critical the pressurizer shall have at least 100 kw of heaters operable and a water level maintained between 12K and 875 of level span.

If the pressurizer is inoperable due to heaters or )vater level, restore the pressurizer to operable status within 6 hrs

. or have the RHR system in operation within an additional 6 hrs.

Bases:

The plant is designed to operate with all reactor coolant loops in operation and maintain the DNBR above 1.30 during all normal

~ q 3.1-4b Change No. V Amendment No. R, PS ~,

43

operations and anticipated transients.

Heat transfer analyses show that reactor heat equivalent to 130 MWT (8.5%) can be removed by natural circulation alone.

Therefore operation with one operating reactor coolant loop while below 130 MWT provides adequate margin.

The specification permits an orderly reduction in power if a reactor coolant pump is lost during operation between 130 MWT and 50% of rated power.

Above 50% power, an automatic reactor trip will occur if either pump is lost.

The power-to-flow ratio will be maintained equal to or less than one which ensures that the minimum DNB ratio increases at lower flow since the maximum enthalpy rise does not increase.

When the reactor coolant system average temperature is above 350'F, a single reactor coolant loop provides sufficient heat removal capability for removing decay heat;

however, single failure considerations require one loop be in operation and the other loop be capable of removing heat via natural circulation.

When the re'actor coolant system average temperature is between 200'F and 3SO'F or while in cold shutdown, a single reactor coolant loop or RHR loop provides sufficient heat removal capability for removing decay heat; but single failure.considerations require that at least two loops be operable.

Thus, if the reactor coolant loops are not operable, this specification requires two RHR loops to be operable.

When the boron concentration of the reactor coolant system is to r'e reduced the process must be uniform.to prevent sudden reactivity 3.1 4c Amendment No.

changes in the reactor.

Mixing of the reactor coolant will be sufficient to prevent a sudden increase in reactivity if at least one reactor coolant pump or one residual heat, removal pump is running while the change is taking place.

The residual heat removal pump will circulate the primary system volume in approximately one half hour.

The pressurizer is of no concern because of the low pressurizer volume and because the pressurizer boron concentration will be higher than that of the rest of the reactor coolant.

Nhen the boron concentration of the reactor coolant system is to be increased, the process must be uniform to prevent sudden reactivity increases in the reactor during subsequent startup of the reactor coolant pumps.

Mixing of the reactor coolant will be sufficient to maintain a uniform boron concentration if at least one reactor coolant pump is running while the change is taking place.

Emergency boration without a reactor coolant pump in operation is not prohibited by this specification.

Prohibiting reactor coolant pump starts without a large void in the pressurizer or without a limited RCS temperature differential will prevent RCS overpressurization due to'xpansion of cooler RCS water as it enters a warmer steam generator.

A 38% level in the pressurizer will accommodate the swell resulting from a reactor coolant pump start with a RCS temperature of 140'F and steam generator secondary side temperature of 340'F, or the maximum temperature which usually exists prior to cooling the reactor with the"RHR system.

3.1-4d Amendment No.

<3

Temperature requirements for the steam generator correspond with C

measured NDT for the shell and allowable thermal stresses in the tube sheet.

.Each of the pressurizer code safety valves is designed to relieve 288,000 lbs. per hr. of saturated steam at the valve set point.

Below 3SO'P and 350 psig in the reactor coolant system, the residual heat removal system can remove decay heat and thereby control system temperature and pressure.

If no residual heat were removed by any of the means available the amount of steam which could be generated at. safety valve relief pressure would be less than half the valves'apacity.

One valve therefore provides adequate defense against overpressurization.

The power operated relief valves (PORVs) operate to relieve RCS pressure below the setting of the pressurizer code safety valves.

These relief valves have remotely operated block valves to pro-vide a positive shutoff capability should a relief valve become inoperable.

The electrical power for both the relief valves and the block valves is capab'Ie of being supplied from an emergency power source to ensure the ability to seal this possible RCS leakage path.

The requirement that 100 kw of pressurizer heaters and their associated controls be capable of being supplied electrical power from an emer gency bus provides assurance that these heaters can be energized during a loss of offsite power condition to maintain natural circulation at hot shutdown and during cooldown.(

)

References (I) FSAR Section 14.1.6 (2)

FSAR Section 7.2.3 (3) Letter from L.

D. White, Jr. to D. L. Ziemann, USNRC, dated October 17, 1979 3.1.4 e -.

Amendment No. ~ 43

flange.

I'f this condition is not met, all operations involving movement of fuel or control rods in the reactor vessel shall be suspended.

3.8.2 If any of the specified limiting conditions for refueling is not met, refueling of the reactor shall cease; work shall be initiated to correct the violated conditions 3.8.3 so that the specified limits are met; no operations which may increase the reactivity of the core shall be made.

If the conditions of 3.8.l.d are not met, then in addition to the requirements of 3.8.2, close all containment penetrations providing direct access from the containment atmosphere to the outside atmosphere within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.

Basis:

Tile equipment and general procedures to be utilized during refueling are discussed in the FSAR; Detailed instructions, the above specified precautions, and the design of the fuel handling equipment incorporating built-in interlocks and safety features, provide assurance that no incident could occur during the refueling operations that would result in a hazard

3. 8-2a Amendment No.

'.3.

4 4.3.4.1 4.3.4.2 4.3.5 4.3.5.1 4.3.5.2 4.3.6.3 Re 1 i ef Val ves Each PORY shall be demonstrated operable at least once.

per 18 months by performance of a'NANNEL CALIBRATION.

Except during cold aHd refueling shutdown each block valve shall be demonstrated operable at least once per 92 days by operating the valve through one complete cycle of full travel unless the valve is already closed.

Reactor Coolant Loops When reactor power is above 130 MWt (8.5%), the reactor coolant pumps shall be verified to be in operation and circulating reactor coolant at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

When the average coolant temperature is above 350'F but the reactor is not critical, when the reactor is at hot

shutdown, or when the reactor is critical but reactor power is less than or equal to 130 MWt (8.5%):

a) the operating reactor coolant pump(s) shall be verified to be in operation and circulating reactor coolant at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, and b) if a. reactor coolant pump is not operating, but must be, operable, it shall be demonstrated operable once

~ per 7 days by verifying correct breaker alignments and indicated power availability.

When the reactor is at cold shutdown or when the average coolant temperature is between 200'F and 350'F, and fuel is in the reactor, the following shall be performed to demonstrate a loop is operable.

Tests need not be per-formed if a loop is not relied upon to satisfy the re-quirements of Specification 3.l.l.l.e.

4.3-3 Amendment No. Q, 43

I

4.3.5.4 4.3. 5.5 a) to %castrate a reactor coolanioop

operable, the reactor coolant pump(s), if not in operation, shall be demonstrated operable at least once per 7 days by verifying correct breaker, alignments.

.~d,indicated power availability.

b) to demonstrate a residual heat removal pump is

operable, the surveillance specified in the Inservice Pump and Valve Test. Program prepared pursuant to 10 CFR 50.55a shall be performed.

Nhen the reactor is at cold shutdown or when the average coolant temperature is between 200'F and 350'F and fuel is in the reactor at least one coolant loop shall be verified to be in operation and circulating reactor coolant at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

In addition to the above requirements, in order to demonstrate that a reactor coolant. loop is operable the steam generator water level shall be greater than or equal to 16% of the narrow range instrument span.

Basis:

This material'surveillance program monitors changes in the fracture toughness properties of ferritic materials in the reactor vessel beltline region of the reactor resulting from exposure to neutron irradiation and the thermal environment.

The test data obtained from this program will be used to determine the conditions under 4

which the reactor vessel can be operated with adequate margins of safety against fracture throughout its service life.

The surveillance requirements on pressurizer equipment will assure proper performance of the pressurizer function and give early indication of malfunctions.

4.3-4 Amendment No.

4P, "B

~ ~

4.11.1.2 d.

Flow shall be main'tained through the system using either the filter or, bypass flow path for at least 15 minutes each month.

After each replacement of a charcoal filter drawer or after any structural maintenance on the charcoal housing for the spent fuel pit charcoal adsorber

system, the condition of Specification 4.11.1.1.b shall be demonstrated for the affected portion of the system.

4.11.2 Residual Heat Removal and Coolant Circulation 4.11.2.1 When the reactor is in the refueling mode and fuel is in the reactor, at least one residual heat removal loop shall be verified to be in operation and circulating 4.11.2.2 4.11.3 4.11.3.1 reactor coolant at least once per 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.

When the water level above the top of reactor vessel flange is less than 23 feet, both RHR pumps shall be verified to be operable by performing the surveillance specified in the Inservice Pump and Valve Test Program prepared pursuant to 10 CFR 50.55a.

Water Level - Reactor Vessel The water level in the reactor cavity shall be determined to be at least its minimum required depth within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> prior to the start of and at least once per 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> thereafter during movement of fuel assemblies or control rods in containment.

Basis The measurement of the air flow assures that air is being withdrawn from the spent fuel pit area and passed through the adsorbers.

The flow is measured prior to employing the 4.11-2 adsorbers to establish that Amendment No. $4, P5, 43

7590-01 UNITED STATES NUCLEAR REGULATORY COMMISSION DOCKET NO. 50-244 ROCHESTER GAS AND E LECTRI C CORPORAT ION NOTICE OF ISSUANCE OF ANENDHENT TO PROVISIONAL OPERATING LICENSE The U. S. Nuclear Regulatory Commission (the Commission) has issued Amendment No. 43 to Provisional Operating License No. DPR-18, to Rochester Gas and Electric Corporation (the licensee),

which revised the Technical Specifications for operation of the R.

E. Ginna Nuclear Power Plant (the facility) located in llayne County, New York.

The amendment is effective as of its date of issuance.

The amendment modifies the provisions of the Technical Specifications to provide for redundancy in decay heat removal capability in all modes of operation.

The application for the amendment complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act),

and the Commission's rules and regulations.

The Commission has made appropriate findings as required by the Act and the Commission's rules and regulations in 10 CFR Chapter I, which are set forth in the license r

amendment.

Prior public notice of this amendment was not required since the amendment does not involve a significant hazards considerati'on The Commission has determined that the issuance of this amendment will not result in any significant environmental impact and that pursuant to 10 CFR 551.5(d)(4) an environmental impact statement'r negative declaration and environmental impact appraisal need not be prepared in connection with issuance of this amendment.

V For further details with re'spect to this 'action, see (1) the application for amendment notarized November 12, 1980 (transmitted by letter dated November 17, 1980),

and (2) Amendment No.

43 to License No.

DPR-18, including the Commission's letter of transmittal.

These items are available for public inspection at the Commission's Public Document

Room, 1717 H Street, N. W., ltashington, D. C.

and at the Rochester Public Library, 115 South Avenue, Rochester, New York 14627.

A copy of item (2) may be obtained upon request addressed to the U.

S.

Nuclear Regulatory Commission,

'llashington, D.

C. 20555, Attention:

Director, Division of Licensing.

Dated at Bethesda, Maryland, this 3rd day of June, 1981.

FOR THE NUCLEAR REGULATORY COMMISSION enn s K. Crutch e

h f Operating Reactors Branch 0'5 Division of Licensing 1