|
---|
Category:Inspection Report
MONTHYEARIR 05000255/20244022024-09-0606 September 2024 Public: Palisades Nuclear Plant - Decommissioning Security Inspection Report 05000255/2024402 IR 05000255/20240022024-08-0909 August 2024 NRC Inspection Report No. 05000255/2024002 IR 05000255/20240112024-07-15015 July 2024 Nuclear Plant - Restart Inspection Report 05000255/2024011 IR 05000255/20240012024-05-10010 May 2024 NRC Inspection Report No. 05000255/2024001 IR 05000255/20244012024-04-0909 April 2024 – Decommissioning Security Inspection Report 05000255/2024401 IR 05000255/20240102024-03-20020 March 2024 Plant Reference Simulator Inspection Report 05000255/2024010 IR 05000255/20230042024-02-20020 February 2024 NRC Inspection Report 05000255/2023004(DRSS) Holtec Decommissioning International, LLC, Palisades Nuclear Plant IR 05000255/20230032023-10-0404 October 2023 NRC Inspection Report No. 05000255/2023003(DRSS)-Holtec Decommissioning International, LLC, Palisades Nuclear Plant IR 05000255/20230022023-07-19019 July 2023 NRC Inspection Report 05000255/2023002 DRSS-Holtec Decommissioning International, LLC, Palisades Nuclear Plant IR 05000255/20220032022-12-28028 December 2022 NRC Inspection Report No. 05000255/2022003(DRSS); 07200007/2022001 (Drss) – Holtec Decommissioning International, LLC, Palisades Nuclear Plant IR 05000255/20224012022-11-0909 November 2022 Decommissioning Palisades Nuclear Plant - Decommissioning Security Inspection Report 05000255/2022401 IR 05000255/20220022022-08-0303 August 2022 Integrated Inspection Report 05000255/2022002 IR 05000255/20220012022-05-13013 May 2022 Integrated Inspection Report 05000255/2022001 IR 05000255/20220102022-04-0101 April 2022 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000255/2022010 IR 05000255/20210062022-03-0202 March 2022 Annual Assessment Letter for Palisades Nuclear Plant, Unit 1, (Report 05000255/2021006) IR 05000255/20210102022-02-24024 February 2022 Triennial Fire Protection Inspection Report 05000255/2021010 IR 05000255/20210042022-02-0808 February 2022 Integrated Inspection Report 05000255/2021004 and Exercise of Enforcement Discretion IR 05000255/20214042021-11-15015 November 2021 NRC Independent Spent Fuel Storage Installation Security Inspection Report 05000255/2021404 and 07200007/2021401 IR 05000255/20210032021-11-0303 November 2021 Integrated Inspection Report 05000255/2021003 IR 05000255/20214032021-10-21021 October 2021 Material Control and Accounting Program Inspection Report 05000255/2021403 IR 05000255/20214022021-10-0606 October 2021 Security Baseline Inspection Report 05000255/2021402 IR 05000255/20210052021-09-0101 September 2021 Updated Inspection Plan for Palisades Nuclear Plant (Report 05000255/2021005) IR 05000255/20210022021-08-10010 August 2021 Integrated Inspection Report 05000255/2021002 ML21197A0322021-07-21021 July 2021 Review of the Fall 2020 Steam Generator Tube Inspection Report IR 05000255/20210012021-05-12012 May 2021 Integrated Inspection Report 05000255/2021001 IR 05000255/20214012021-04-14014 April 2021 Security Baseline Inspection Report 05000255/2021401 IR 05000255/20200062021-03-0404 March 2021 Annual Assessment Letter for Palisades Nuclear Plant (Report 05000255/2020006) IR 05000255/20200042021-02-11011 February 2021 Integrated Inspection Report 05000255/2020004 IR 05000255/20204012021-01-0606 January 2021 Security Baseline Inspection Report 05000255/2020401 ML20342A1812020-12-10010 December 2020 Security Inspection Report Cover Letter 05000255/2020420 IR 05000255/20204202020-12-10010 December 2020 Security Inspection Report 05000255/2020420 IR 05000255/20204022020-11-30030 November 2020 Cyber Security Inspection Report 05000255/2020402 IR 05000255/20205012020-11-20020 November 2020 Emergency Preparedness Inspection Report 05000255/2020501 IR 05000255/20200032020-11-13013 November 2020 Integrated Inspection Report 05000255/2020003 IR 05000255/20200052020-09-0101 September 2020 Updated Inspection Plan for Palisades Nuclear Plant (Report 05000255/2020005) IR 05000255/20200102020-08-24024 August 2020 Biennial Problem Identification and Resolution Inspection Report 05000255/2020010 IR 05000255/20203012020-08-13013 August 2020 NRC Initial License Examination Report 05000255/2020301 IR 05000255/20200022020-08-11011 August 2020 Integrated Inspection Report 05000255/2020002 and Exercise of Enforcement Discretion IR 05000255/20010082020-05-12012 May 2020 Final ASP Analysis - Palisades (IR 050002552001008) IR 05000255/20200012020-05-12012 May 2020 Integrated Inspection Report 05000255/2020001 IR 05000255/20200112020-04-21021 April 2020 Design Basis Assurance Inspection (Teams) Inspection Report 05000255/2020011 IR 05000254/20204012020-03-23023 March 2020 Security Baseline Inspection Report 05000254/2020401 and 05000265/2020401 IR 05000255/20190062020-03-0303 March 2020 Annual Assessment Letter Palisades Nuclear Plant (Report 05000255/2019006) IR 05000255/20190042020-01-28028 January 2020 Integrated Inspection Report 05000255/2019004 and 07200007/2019001 ML19357A2752019-12-23023 December 2019 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000255/2020011 IR 05000255/20190112019-11-27027 November 2019 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000255/2019011 IR 05000255/20194112019-11-25025 November 2019 Security Baseline Inspection Report 05000255/2019411 and Independent Spent Fuel Storage Security Inspection Report 07200007/2019401 (Cover Letter Only) (DRS-M.Ziolkowski) IR 05000255/20190032019-11-14014 November 2019 Integrated Inspection Report 05000255/2019003 IR 05000255/20190102019-10-29029 October 2019 Reissue - Palisades Nuclear Plant - Design Basis Assurance Inspection (Programs) Inspection Report 05000255/2019010 ML19294A2872019-10-21021 October 2019 Design Basis Assurance Inspection (Programs) Inspection Report 05000255/2019010 2024-09-06
[Table view] Category:Letter
MONTHYEARML24312A2262024-11-0606 November 2024 Letter from C. Nelson, Michigan SHPO Regarding Palisades Nuclear Plant Architectural Survey ML24292A1572024-11-0505 November 2024 Ape Notification to Burt Lake Band Palisades ML24310A0142024-11-0505 November 2024 Ape Notification to Mackinac Bands of Chippewa Palisades ML24310A0132024-11-0505 November 2024 Ape Notification to Grand River Bands of Ottawa Indians Palisades ML24309A2032024-11-0404 November 2024 Ape Notification to Ottawa Tribe of Oklahoma Palisades ML24309A1972024-11-0404 November 2024 Ape Notification to Little Traverse Bay Bands of Odawa Indians Palisades ML24309A1982024-11-0404 November 2024 Ape Notification to Match E Be Nash She Wish Band of Pottawatomi Indians Palisades ML24309A1872024-11-0404 November 2024 Ape Notification to Grand Portage Band of Lake Superior Chippewa Palisades ML24309A2072024-11-0404 November 2024 Ape Notification to Quechan Tribe of the Fort Yuma Indian Reservation Palisades ML24309A1832024-11-0404 November 2024 Ape Notification to Bois Forte Band of the Minnesota Chippewa Tribe Palisades ML24309A2122024-11-0404 November 2024 Ape Notification to Sault Ste. Marie Tribe of Chippewa Indians Palisades ML24309A2042024-11-0404 November 2024 Ape Notification to Pokagon Band of Potawatomi Indians Palisades ML24292A0492024-11-0404 November 2024 Ape Notification to Bad River Band of the Lake Superior Tribe of Chippewa Indians Palisades ML24309A1932024-11-0404 November 2024 Ape Notification to Leech Lake Band of Ojibwe Palisades ML24309A2012024-11-0404 November 2024 Ape Notification to Mille Lacs Band of Ojibwe Palisades ML24309A1922024-11-0404 November 2024 Ape Notification to Lac Vieux Desert Band of Lk Superior Chippewa Indians Palisades ML24309A1892024-11-0404 November 2024 Ape Notification to Hannahville Indian Community Palisades ML24309A2002024-11-0404 November 2024 Ape Notification to Miami Tribe of Oklahoma Palisades ML24309A1952024-11-0404 November 2024 Ape Notification to Little River Band of Ottawa Indians Palisades ML24309A2112024-11-0404 November 2024 Ape Notification to Saint Croix Chippewa Indians of Wisconsin Palisades ML24309A1902024-11-0404 November 2024 Ape Notification to Lac Courte Oreilles Band of Lake Superior Chippewa Palisades ML24309A2022024-11-0404 November 2024 Ape Notification to Nottawaseppi Huron Band of the Potawatomi Palisades ML24309A1852024-11-0404 November 2024 Ape Notification to Citizen Potawatomi Nation Palisades ML24309A2142024-11-0404 November 2024 Ape Notification to White Earth Band of Minnesota Chippewa Tribe Palisades ML24309A2092024-11-0404 November 2024 Ape Notification to Red Lake Band of Chippewa Indians Palisades ML24309A1862024-11-0404 November 2024 Ape Notification to Forest County Potawatomi Community Palisades ML24309A1822024-11-0404 November 2024 Ape Notification to Bay Mills Indian Community Palisades ML24309A2052024-11-0404 November 2024 Ape Notification to Prairie Band Potawatomi Nation Palisades ML24309A2102024-11-0404 November 2024 Ape Notification to Saginaw Chippewa Indian Tribe of Michigan Palisades ML24309A2082024-11-0404 November 2024 Ape Notification to Red Cliff Band of Lake Superior Chippewa Indians Palisades ML24309A1992024-11-0404 November 2024 Ape Notification to Menominee Indian Tribe of Wisconsin Palisades ML24292A0072024-11-0404 November 2024 Ape Notification to Achp Palisades ML24309A1882024-11-0404 November 2024 Ape Notification to Grand Traverse Band of Ottawa and Chippewa Indians Palisades ML24309A1842024-11-0404 November 2024 Ape Notification to Chippewa Cree Indians of the Rocky Boys Reservation of Montana Palisades ML24309A1912024-11-0404 November 2024 Ape Notification to Lac Du Flambeau Band of Lake Superior Chippewa Indians Palisades ML24309A2132024-11-0404 November 2024 Ape Notification to Turtle Mountain Band of Chippewa Indians Palisades ML24309A2062024-11-0404 November 2024 Ape Notification to Prairie Island Indian Community Palisades PNP 2024-014, Request for USNRC to Rescind Approved Exemption Requests for 140.11(a)(4) and 50.54(w)(1), Reduction of Insurances2024-10-0909 October 2024 Request for USNRC to Rescind Approved Exemption Requests for 140.11(a)(4) and 50.54(w)(1), Reduction of Insurances PNP 2024-037, Response to Requests for Additional Information Regarding the Proposed Reauthorization of Power Operations Under Renewed Facility Operating License Number DPR-0202024-10-0404 October 2024 Response to Requests for Additional Information Regarding the Proposed Reauthorization of Power Operations Under Renewed Facility Operating License Number DPR-020 ML24267A2962024-10-0101 October 2024 Summary of Conference Call Regarding Steam Generator Tube Inspections ML24263A1712024-09-20020 September 2024 Environmental Request for Additional Information ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24219A4202024-09-12012 September 2024 Change in Estimated Hours and Review Schedule for Licensing Actions Submitted to Support Resumption of Power Operations (Epids L-2023-LLE-0025, L-2023-LLM-0005, L-2023-LLA-0174, L-2024-LLA-0013, L-2024-LLA-0060, L-2024-LLA-0071) IR 05000255/20244022024-09-0606 September 2024 Public: Palisades Nuclear Plant - Decommissioning Security Inspection Report 05000255/2024402 PNP 2024-029, Notice of Payroll Transition at Palisades Nuclear Plant2024-08-15015 August 2024 Notice of Payroll Transition at Palisades Nuclear Plant IR 05000255/20240022024-08-0909 August 2024 NRC Inspection Report No. 05000255/2024002 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 PNP 2024-032, Supplement to License Amendment Request to Revise Selected Permanently Defueled Technical Specifications Administrative Controls to Support Resumption of Power Operations2024-07-31031 July 2024 Supplement to License Amendment Request to Revise Selected Permanently Defueled Technical Specifications Administrative Controls to Support Resumption of Power Operations ML24206A0572024-07-25025 July 2024 PRM-50-125 - Letter to Alan Blind; Docketing of Petition for Rulemaking and Sufficiency Review Status (10 CFR Part 50) PNP 2024-033, Response to Request for Additional Information - License Amendment Request to Revise the Palisades Nuclear Plant Site Emergency Plan to Support Resumption of Power Operations2024-07-24024 July 2024 Response to Request for Additional Information - License Amendment Request to Revise the Palisades Nuclear Plant Site Emergency Plan to Support Resumption of Power Operations 2024-09-06
[Table view] |
See also: IR 05000255/2017007
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION III
2443 WARRENVILLE RD. SUITE 210
LISLE, IL 60532-4352
September 13, 2017
Mr. Charles Arnone
Vice President, Operations
Entergy Nuclear Operations, Inc.
Palisades Nuclear Plant
27780 Blue Star Memorial Highway
Covert, MI 49043-9530
SUBJECT: PALISADES NUCLEAR PLANT, REQUEST FOR INFORMATION FOR AN NRC
TRIENNIAL BASELINE DESIGN BASES ASSURANCE INSPECTION (TEAM):
INSPECTION REPORT 05000255/2017007.
Dear Mr. Arnone:
On October 30, 2017, the U. S. Nuclear Regulatory Commission (NRC) will begin a Triennial
Baseline Design Basis Assurance Inspection at the Palisades Nuclear Plant. This inspection
will be performed in accordance with NRC Baseline Inspection Procedure 71111.21M and
adjusted for the stations current plan to transition to decommissioning as allowed by Inspection
Manual Chapter 2515. The inspection samples to be reviewed during this inspection are
skewed toward decommissioning activities.
The Design Bases Assurance Inspection focuses on the design, maintenance, and operation of
risk significant components with low margin, or associated with an accident scenario, or a
specific system. The inspection also monitors the implementation of modifications to structures,
systems, and components as modifications to one system may also affect the design bases and
functioning of interfacing systems as well as introduce the potential for common cause failures.
The specific components and modifications to be reviewed during this baseline inspection will
be identified as part of the preparation for the inspection and finalized during the in-office
preparation week that occurs prior to the first onsite inspection week. In addition, operating
experience issues, associated with the component samples, will also be selected for review.
The inspection team may request scenarios to be performed on the simulator. This request
would require support from your simulator staff to validate scenarios, simulator time, and a crew
to perform the actions which would most likely occur during the second onsite week. The team
will work closely with your staff early on during the inspection process to ensure this activity can
be accomplished with minimal impact.
The inspection will include two weeks onsite. The inspection team will consist of four NRC
inspectors and two contractors. The current inspection schedule is as follows:
Offsite preparation: October 23-27, 2017.
Onsite weeks: October 30-November 3, 2017; and
November 13-17, 2017.
C. Arnone -2-
Experience with previous baseline design/modification inspections of similar depth and length
has shown that this type of inspection is extremely resource intensive, both for the NRC
inspectors and the licensee staff. In order to minimize the inspection impact on the site and to
ensure a productive inspection for both parties, we have enclosed a request for information
needed for the inspection.
It is important that all of these documents are up-to-date and complete in order to minimize the
number of additional documents requested during the preparation and/or the onsite portions of
the inspection. Insofar as possible, this information should be provided electronically to the lead
inspector.
The lead inspector for this inspection is Jamie Benjamin. If there are any questions about the
inspection or the material requested in the enclosure, please contact the lead inspector at
630-829-9747 or via e-mail at Jamie.Benjamin@nrc.gov.
This letter does not contain new or amended information collection requirements subject
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, Control
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget Control
Number.
This letter and its enclosure will be made available for public inspection and copying at
http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in
accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Jamie Benjamin, Senior Reactor Engineer
Engineering Branch 2
Division of Reactor Safety
Docket No. 50-255
License No. DPR-20
Enclosure:
Design Bases Assurance Inspection
Document Request
cc: Distribution via LISTSERV
C. Arnone -3-
Letter to Charles Arnone from Jamie Benjamin dated September 13, 2017
SUBJECT: PALISADES NUCLEAR PLANT, REQUEST FOR INFORMATION FOR AN NRC
TRIENNIAL BASELINE DESIGN BASES ASSURANCE INSPECTION (TEAM):
INSPECTION REPORT 05000255/2017007.
DISTRIBUTION:
Jeremy Bowen
RidsNrrPMPalisades Resource
RidsNrrDorlLpl3
RidsNrrDirsIrib Resource
Cynthia Pederson
James Trapp
Richard Skokowski
Allan Barker
Carole Ariano
Linda Linn
DRPIII
DRSIII
ADAMS Accession Number ML17258A081
OFFICE RIII RIII RIII RIII
NAME JBenjamin:cl
DATE 09/13/17
OFFICIAL RECORD COPY
DESIGN BASES ASSURANCE INSPECTION DOCUMENT REQUEST
Inspection Report: 05000255/2017007
Inspection Dates: October 30-November 3; and
November 13-17.
Inspection Procedure: IP 71111.21M, Design Bases Assurance Inspection (Team)
Lead Inspector: Jamie Benjamin, Senior Reactor Engineer, DRS
630-829-9747
Jamie.Benjamin@nrc.gov
Selected components:
Spent fuel pool
Spent fuel pool leakage detection
Spent fuel pool neutron absorber
Spent fuel pool cooling water pumps
Spent fuel pool cooling water heat exchanger
Spent fuel pool cooling water component electrical supply
Control room ventilation dampers
Control room ventilation fans
Control room ventilation electrical supply
Main steam isolation valves (LERF sample)
I. Information Requested (for the above selected components) to be available to the
team lead by October 16, 2017:
This information should be separated for each selected component or modification,
especially if provided electronically (e.g., folder with component or modification name
that includes calculations, condition reports, maintenance history, etc.).
1. List of condition reports (corrective action documents) associated with each of
the selected components for the last 6 years.
2. The maintenance history (corrective, preventive, and elective) associated with
each of the selected components for the last 10 years. Identify frequency of
preventive maintenance activities.
Enclosure
DESIGN BASES ASSURANCE INSPECTION DOCUMENT REQUEST
3. Copies of calculations associated with each of the selected components (if not
previously provided), excluding data files. Please review the calculations and
also provide copies of important referenced material (such as drawings,
engineering requests, and vendor letters).
4. System Health Reports, System Descriptions, Design Basis Documents, and/or
Training Lesson Plans associated with each of the selected components.
5. A list of modifications, including equivalency evaluations and setpoint changes,
associated with each of the selected components. This list should include a
descriptive paragraph on the purpose of the modification. Please ensure this list
only includes design completed (not canceled) modifications.
6. Copies of operability evaluations (open/closed for last 3 years) associated with
each of the selected components and plans for restoring operability, if applicable.
7. Copies of selected operator work-around evaluations associated with each of the
selected components and plans for resolution, if applicable.
8. Copies of any open temporary modifications associated with each of the selected
components, if applicable.
9. Trend data on the selected electrical/mechanical components performance for
last 3 years (For example, pumps performance including in-service testing, other
vibration monitoring, oil sample results, etc., for valves: stroke time and leak rate
results, diagnostic trend data, etc.).
10. Provide copies of the normal and abnormal operating procedures associated with
the selected components and selected scenarios.
11. List of time critical or risk significant operator actions associated with
components. Identify those actions that do not have job performance measures.
12. Copy of latest completed tests and surveillances for each component, for
example:
a. Pumps: comprehensive test, quarterly test, flow balance, etc.
b. Valves: stroke time testing, diagnostic testing, leak testing, interlocks, etc.
c. Heat Exchangers/Room Coolers: thermal performance, clean/inspect, fan
flows, etc.
d. Components: Technical Specification surveillances.
e. Acceptance criteria basis calculations should also be included.
13. A copy of any internal/external self-assessments and associated corrective
action documents generated in preparation for the inspection.
14. A copy of engineering/operations related audits completed in the last 2 years.
2
DESIGN BASES ASSURANCE INSPECTION DOCUMENT REQUEST
15. List of permanent plant modifications to structures, systems, and components
that are field work complete in the last 3 years. (For the purpose of this
inspection, permanent plant modifications include permanent: plant changes,
design changes, set point changes, equivalency evaluations, suitability analyses,
and commercial grade dedications.) The list should contain the number of each
document, the title, the revision (or date), and the affected system.
16. A list of calculation changes that have been issued for use in the last 3 years.
17. Copies of procedures addressing the following: modifications, design changes,
set point changes, equivalency evaluations or suitability analyses, commercial
grade dedications, and post-modification testing.
18. A list of corrective action documents (open and closed) in the last 3 years that
address permanent plant modifications issues, concerns, or processes. These
documents should also include the corrective action documents associated with
the modification implementation.
19. Electronic copies of Updated Final Safety Analysis Report, Technical
Specifications, Technical Specifications Bases, and Technical Requirements
Manual.
20. Electronic copies of Updated Final Safety Analysis Report, Technical
Specifications, Technical Specifications Bases, and Technical Requirements
Manual.
21. Major one line electrical drawings (ac and dc) and key diagrams (paper copies).
22. Electronic copy of Piping and Instrumentation Drawings (if available).
23. Site top ten issues list.
24. Electronic copy of the site Individual Plant Examination of External Events, if
available.
25. Current management and engineering organizational chart.
II. Additional Information to be Provided on October 30, 2017, Onsite (for final
selected components and modifications):
1. During the in-office preparation activities, the team will be making final selections
and may identify additional information needed to support the inspection. The
lead inspector will provide a list of the additional information needed during the
week of October 23, 2017.
2. Schedule of any testing/maintenance activities to be conducted on the selected
components during the two onsite inspection weeks.
III. Information Requested to be Provided Throughout the Inspection
1. Copies of any corrective action documents generated as a result of the teams
questions or queries during this inspection.
3
DESIGN BASES ASSURANCE INSPECTION DOCUMENT REQUEST
2. Copies of the list of questions submitted by the team members and the
status/resolution of the information requested (provide daily by 2:00 p.m.
during the inspection to each team member).
3. One complete set of Piping and Instrumentation Drawings (paper copies).
4. Reference materials. (make available if needed during all onsite weeks):
a. Individual Plant Examination/Probabilistic Risk Assessment report;
b. Procurement documents for components and modifications selected
(verify retrievable);
c. Plant procedures (normal, abnormal, emergency, surveillance, etc.); and
d. Vendor manuals.
If you have questions regarding the information requested, please contact the lead inspector.
4