Responds to NRC Re Violation Noted in IE Insp Rept 50-335/79-14.Corrective Actions:Required Valves Are Locked & Prestart Check List Will Be Revised by 790801
ML17206A971
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 07/11/1979
From: Robert E. Uhrig
FLORIDA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML17206A970 List:
References
NUDOCS 7908200013
Download: ML17206A971 (4)


Text

8 P. BOX 013100. MIAMI. FL 33101 pR

~ 3 F LORIDAPOWER 8c LIGHTCOMPANY July ll, 1979 L-79-189 Mr. James P. O'Reilly, Director, Region II Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303

Dear Mr. O'Reilly:

Re:

RII:JAD 50-335/79-14 Florida Power 5 Light Company has reviewed the subject inspection report and a response is attached.

There is no proprietary information in the report.

Very truly yours, obert E. Uhrig Vice President Advanced Systems

& Technology REU/MAS/mal Attachment cc:

Harold F. Reis, Esquire O82 OOOi~

PEOPLE... SERVING PEOPLE

ATTACHMENT Re.

RII:JAB 50-335/79-14 Findinn As required by Technical Specification 6.8.l.a,written procedures are required to be established, implemented and maintained covering the applicable proce-dures recommended in Appendix "A" of Regulatory Guide 1.33,

November, 1972.

Contrary to the above:

l.

Plant Operating Procedure 0410020 "HPSI/LPSI-Normal Operation", Section 8.1 was not followed in that safeguards pumps minimum flow isolation valve NV-3660, required to be locked open, was found open but unlocked on June 7, 1979.

2.

Plant Operating Procedure 0420020 "Containment Spray-Initial Valve Alignment",

Section 8.1.9 divas not followed in that B header eductor inlet valve 07261, required to be locked open, was found open but unlocked on June 7, 19/9.

~Res ense The valves required to be locked are now locked.,The individuals responsible for valve locking have been apprised of the importance of the finding.

The pre-start check list procedure (Administrative Procedure 0030120) will be revised by August 1, 1979.

The revised procedure will require verification of the locked valve list for a particular mode of operation prior to entry into that mode.

This requirement will be mandatory after any outage involving si gnificant val ve mani pul ation.