ML17179B080

From kanterella
Jump to navigation Jump to search
Insp Repts 50-237/92-33 & 50-249/92-33 on 921130-1204. Violations Noted.Major Areas Inspected:Control Rod Mispositioning Which Occurred on 920918 & Failure to Promptly Rept Event
ML17179B080
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 09/07/1993
From: Beverly Clayton, Hiland P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17179B079 List:
References
50-237-92-33, 50-249-92-33, NUDOCS 9309200076
Download: ML17179B080 (20)


See also: IR 05000237/1992033

Text

SPECIAL INSPECTION TEAM REPORT

        • .*:*****:****:-****:***:*.***:-: ... * .*.*::;;.:-:-*

DRESDEN CONTROL ROD MISPOSITIONING EVENT

SEPTEMBER 18, 1992

INSPECTION REPORT NO'S. 50-237/92033(DRP); 50-249/92033(DRP)

9309200076 930909 I

PDR

ADOCK 05000237

G

PDR

TABLE OF CONTENTS

Table of Contents ..........*........*...........*..**..*...... i

Executive Summary ......**.......*..*......................... ii

Inspection Report Sumrnary .*.....**.*...*..*......*.......*.. iii

1. 0

Introduction .................................................. 1

I . I

Event Su11UTiary . .*..**...***....*..*..**........................ I

1.2

Team Formation **.*...**....*.................................... 2

. 1.3

Team Char.ter .................................................. 2

2 .. 0

Sequence of Events ............................................ 2

3.0

Special Inspection Team Review .*.............................. 4

3.1

Cause of the Rod Mispositioning Event .......*.....*..........* 4

3.2

Initial Licensee Response .......*.....*....................... 4

3.3

Event Safety Significance ...........*................*........ 5

3.4

Adequacy of Control Rod Movement Procedures ................... 5

3.5

Management Involvement in the Event .......................... L5

3.6

Review of Procedural Compliance ............................... 6

3.7

Previous Events ...*.......*..*.*.............................. 8

3.8

Reportability in accordance with 10 CFR 50.72/73 .**........... 9

3.9

Station Personnel Attitude and External Pressures ......*...... 9

3.10

Licensee Investigation of Control Rod Mispositioning Event ... 11

3.11

Crew Briefings and Corrective Action ..*...................... 11

3.12

Personnel Qualifications and Shift Staffing Levels ........... 12

3.13

Licensee's Long Term Corrective Action ....................... 13

4.0

Conclusions ..*.**.**......*...*..... ~ ........................ 13

5. 0

Exit . ........................................................ 14

Team Charter ....*.*........*.............*........ Attachment 1

November 25, 1992, CECo Letter to NRC ............. Attachment 2

December 3, 1992, CECo Letter to NRC ........*...... Attachment 3

Personnel Contacted *.*... ~ ***..................... Attachment 4

i

EXECUTIVE SUMMARY .

A special inspection team was assigned to support the NRC Office of

Investigations (01) in response to the Dresden Unit 2 control rod

mispositioning event which occurred on September 18, 1992.

The team conducted

a technical review of the circumstances surrounding the event. The inspection

concentrated on the adequacy of the licensee's procedures,. operator actions,

management involvement, corrective actions, and the safety significance of the

event.

No nuclear safety limits were approached or exceeded and no deviations

were identified in the areas inspected.

Two apparent violations with multiple

examples were identified.

The two apparent violations included:

Inadequate corrective action for a previous event

Failure to follow procedures (five examples} *

The initial cause for the September 18, 1992, control rod misposition event

was a personnel error during a routine maneuver.

While no safety limits were

approached, the event is a concern because the subsequent failure to follow

programmatic controls was apparently due to deliberate misconduct by the

individuals involved.

None of the five individuals (a licensed reactor

operator, a licensed senior reactor operator, and three non-licensed

i ndi vi dua 1 s) reported the error as prescribed_ by station procedure$. . The

event was discovered when a licensee first line supervisor overheard reference

to a control rod mispositioning during a conversation on November 23, 1992.

ii

U. S. NUCLEAR REGULATORY COMMISSION

REGION III

Report No. 50-237/92033(DRP); 50-249/92033(DRP)

Docket No. 50-237; 50-249

License No~ DPR-19; DPR-25

Licensee:

Commonwealth Edison Company

1400 Opus Place

Downers Grove, IL 60515

Facility Name:

Dresden Nuclear Generating Station, Unit 2 and 3

Inspection At:

Dresden Site, Morri~, IL

Inspection Conducted:

November 30 - December 4, 1992

Inspectors: F.

H.

B.

L. Brush, Rill, Clinton Resident Inspector

Peterson, RIII, Operator Licensing Examiner

Siegel, NRR, Project Manag r, Division of Reactor Projects

Approved By:

Approved By:

~ )_ t.U

Patrick L. Hiland

Team Leader

TnspP.ction Summary

Branch 1

. qh/13

~

Inspection on November 30 - December 4, 1992 {Report No. 50-237/92033(DRP);

50-249/92033(0RP))

Areas Inspected: Special team inspection conducted in response to a Dresden

Unit 2 control rod mispositioning which occurred on September 18, 1992, and

the failure to promptly report that event. The inspectors reviewed the

sequence of events, the safety significance of the event, the licensee's

investigation, the qualifications of the personnel involved, the licensee's

corrective actions, the licensee's corrective action program with respect to

identifying other .incidents of not reporting operational problems, and the

technical adequacy of applicable procedures.

Results:

Two apparent violations with multiple examples were identified.

No

nuclear safety limits were approached or exceeded and no deviations were

identified in the areas inspected. The special inspection team concluded the

following:

iii

1.

The licensee's corrective actions- to-a control rod mispositioning event

that took place on April 10, 1992, were inadequate.

The qualified

nuclear engineer (QNE) involved in the September 18 event was also

involved in procedural violations during the April 10 event when a

control rod was mispositioned due to mechanical_ problems.

The licensee

took corrective actions to deal with the mechanical problem; however,

the licensee failed to take corrective actions toward~ personnel failure

to take required procedural mitigating actions in accordance with

station procedures. This was an apparent violation of 10 CFR Part 50,

Appendix B, Criterion XVI, "Corrective Action."

2.

The station control room engineer (SCRE), nuclear station operator

(NSO), and QNE failed to follow numerous Dresden Station procedure

requirements.

The most significant of these we~e: failure to take

mitigating actions in accordance with Dre~den Operating Abriormal

-Procedure (DOA) 300-12,* "Misp~sitioned Control Rod," including the

failure to immediately stop all rod movements, and the failure to take

corrective action"to insert the mispositioned rod to its full-in

position; failure to establish the required second verification for

control rod movements with the rod worth minimizer (RWM) rod blocks out

of service; failure to obtain prior approvals from a senior reactor

operator (SRO) for rod manipulatfori and .load change; and the intentional

failure to record and notify the appropriate personnel of the event.

This was an apparent violation of Dresden Technical Specification (TS)

6.2.A.1 which requires implementation of plant operating procedures.

1.0

Introduction

On November 24, 1992, Dresden senior.site management informed the NRC

Region III office of a potential failure to report a control rod

misposition event that had occurred on September 18, 1992.

Initial

information from the licensee indicated that five employees, both*

licensed and non-licensed, had knowledge of a control rod misposition

event at the time of occurrence, but failed to report the event in

accordance with site procedures.

In response to the initial

information, Region III management directed the Region III Operator

Licensing Branch Chief to conduct a preliminary _on-site assessment of

the known facts the evening of November 24. That. initial assessment*

concluded that the information provided by the licensee was reasonably

accurate and that an unreported control rod misposition event had

occurred on September 18. Several apparent violations of site

procedures, 10 CFR Part*so, ahd/or plant technical specifications were

identified.

On November 25, 1992, Commonwealth Edison's Chief Nuclear Operating

Officer, Mr. M. J. Wallace, in a letter to Mr.

A~ B. Davis, Regional

Administrator, Region III, described the licensee's immediate actions

upon receipt of information that a control rod misposition event was

intentionally not reported. That letter also described the licensee's

planned follow up actions, which included senior management oversight

and a special investigative task force.

1.1

Event Summary

On September 18, 1992, control rod movements were being performed to

reduce the flow control line {FCL).

At the time of the event, reactor

power was about 85 percent and the FCL was at 103.7 percent. That

~ombination resulted in high average power range monitor {APRM) alarms.

In order to clear the high APRM alarms, the FCL was to be lowered by

inserting control rods. Control rod insertion was being performed in

accordance with"Special Instructions" {SI) prepared by a qualified QNE

and approved by a licensed SRO.

During the control rod movement

sequence, a wrong control .rod was: inserted from its "full out" notch

position 48 to notch position 36, a distance of about three feet of the

twelve foot control rod length.

Contrary to procedural requirements, control rods continued to be

inserted before taking corrective action for the mispositioned rod.

The

mispositioned rod was event~ally restored to its "full out" position

under the direction of the QNE.

Five individuals were aware of the

sequence of e~ents concerning the mispositioned control rod; the station

control room engineer {licensed SRO), the qualified nuclear engineer,

the Unit .2 nuclear station operator {licensed reactor operator {RO)),.

and two nuclear engineers in-training. None of the five knowledgeable

persons reported the control rod movement error as required by~station

procedures.

1

On November 23, 1992, a licensee first line supervisor overheard

reference.to a control rod misposition event during a conversation.

Additional questioning and review of available records indicated to

licensee first line supervision that a potential intentional failure.to

.follow station reporting requirements had occurred. That information

was reported to licensee senior management on the morning of November

24.

'

1.2

Special Inspection Team Formation

Subsequent to the notification of this event, the NRC Office of

.*

Investigation (01) concluded that an immediate investigative effort was

appropriate. The 01 investigative report i~ an internal NRC document

separate from this inspection report. Region III management determined

that a special inspection team was warranted to support that

investigation. The p~rpose of the team was to provide technical

assistance to the investigative effort due to the seriousness of the

apparent withholding of information concerning the September 18 control

rod mispositioning event.

On Friday, November 27, 1992, the special

inspection team was formed consisting of the following personnel:

Team Members:

P. Hiland, R-111, Chief, DRP Section 18

B. Siegel, NRR, Project Manager

H. Peterson, R-111, Operator License Examiner

F. Brush, R-111, Clinton Resident Inspector

Th~ team arrived on site November 30, 1992.

1.3

Special Inspection Team Charter

A*charter was formulated for the special inspection team and transmitted

from E. G. Greenman, to P. L. Hiland on November 30, 1992, with .copies

to appropriate EDO, 01, NRR, AEOD, and Riii personnel (Attachment 1).

The special .inspection team was terminated on December 31, 1992.

2.0

Sequent~ of Events (Charter Item 1)

A chronology of actions related to the ~od mispositioning event on

September 18, 1992~ was assembled by the licensee. That chronology was

  • used along with information from interviews, computer alarm typer

printouts, and the control rod SI sheets*to develop the following*

chronology of events:

NOTE:

All *times are in Central Standard Time (a.m.).

Asterisked times are approximate.

Initial Pl.ant Conditions

Unit 2

Unit 3

699 MWe

762 MWe

2

TIME

07:I5*

07:25

07:3I-07:56

OS: I5-0S: 17

OS: I7

OS: I 7-09: 45 .

09:49

09:52*

09:53*

09:57-I0:05

l0:05-IO:I3*

IO:I3-IO:I6

IO:I9-I0:22

I0:23

I0:26

I0:30*

EVENT

The lead nuclear engineer (LNE) directed the QNE to reduce

the flow control line by inserting peripheral control rods.

The QNE, with two nuclear engineers in training (NEITs),

proceeded to the control room.

The QNE and NEITs entered the control room.

Control rod arrays SCI (4 rods) and SC2 (4 rods) inserted

from full-out notch position 4S to full in notch

position 00.

Four control rods_ from array 3 inserted to position I2.

Control rod H-I selected to clear rod block monitor alarms.

Reactor po~er increased about IOO MWe using reactor

recirculation flow.

QNE filled out another control rod SI

sheet to insert array SDI.

The Unit 2 NSO inserted control rod H-I from position 4S to

position 36 by mistake.

The QNE instructed and the NSO

inserted array SDI (4 rods).

The QNE informed the SCRE that the NSO had inserted a wrong

  • rod.

The QNE filled out an SI to insert control rod H-I, along_

with four other rods in array 5, to position 00.

The NSO inserted five rods from array 5 to position 00.

The SCRE, NSO, QNE, and NEITs held a discussion in the

Unit 2 back panel area.

The NSO, at the direction of .the QNE, withdrew array 3

(4 rods) from position I2 to 4S.

The NSO, at the direction of the QNE, inserted array SD2

{4 rods) to position 00.

The NSO, at the direction of the QNE, withdrew two rods from

array 5 to position 4S.

The LNE entered the control room to provide guidance to the

QNE concerning the number (too many) of peripheral cohtrol

rods that had been inserted.

QNE filled out SI sheets to insert arrays IOAI and IOA2 from

position 4S to position 20.

3

10:34-10:36

10:38-10:42

The NSO inserted arrays lOAl and 10A2 to position 20.

The NSO withdrew the remaining rods in array 5 to position

48.

11 :25

The LNE left the control room.

NOTE: The inspectors concluded that at least one of the SI sheets was signed

by the SCRE subsequent to the rod adjustments. It was also concluded

that the QNE made changes to at least one SI sheet without the SCRE's

knowledge.

3.0

Special Inspection Team Review

3.1

Cause of the Rod Mispositioning Event .

  • The September 18, 1992, rod mispositioning event was caused by personnel

error on the part of the NSO and QNE.

The initial mistakes were made by

not following approved plant procedures; however, the subsequent actions

to not report the event exhibited a lack of integrity from individuals

knowledgeable of the event occurrence (SCRE, NSO, and QNE).

The lack of

management oversight by the Shift Engineer (SE), SCRE, and the LNE was

also a contributing factor.

3.2 * Initial Licensee Response

Upon becoming aware of the potential for an intentional failure to

report the September 18 corttrol rod mispositioning*event, licensee

management initiated steps to perform an investigation.

In addition,

the NRC Region III office was verbally informed of the event on

November 24, 1992.

On November 25, 1992, the licensee.provided a letter

(Attachment 2) from Commonwealth Edison's Chief Nuclear Operating

Officer to the Region III Regi~nal Administrator detailing both the

immediate and' planned actions in response to the event.

As detailed in

that correspondence, the licensee suspended the individuals involved

while a licensee investigation was conducted.

Licensee senior

management initiated coverage on all shifts to communicate the event to

all operations personnel, communicate and enforce management

expectations, 'and provide oversight of the qualified nuclear engineers'

activities. The li.censee's speci.al task force was provided a charter by

the General Manager of BWR-Nuclear Operations, and directed to perform

an investigation into the September 18 control rod mispositioning event.

On December 3, 1992, the licensee provided a letter (Attachment 3) from

Commonwealth Edison's Chief Nuclear Operating Officer to the Region III

Regional Administrator summarizing the investigation into the control

rod. misposition event. The licensee concluded that inappropriate

actions had been taken by five individuals in response to the

September 18, 1992, control rod mispositioning event.

As a result of

that conclusion, one individual was suspended, and four other

individuals were released from employment with Commonwealth Edison.

4

3.3

Event Safety Significance {Charter Item 2)

The inspectors conducted a detailed review of the data produced by the

Powerplex computer system on September 18, 1992.

The Powerplex computer

system calculated the core thermal parameters a~ part of its function to

monitor the fuel. A revi~w of the reactor coolant and off gas

radiological activity data for the month ~f September was also

conducted. There were no fuel thermal limit violations, and no

increases in radioactivity. The inspectors concluded that the September

18 control rod mispositioning event and subsequent rod manipulations did

not cause nuclear safety limits to be approached.

3.4

Adequacy of Control Rod Movement Procedures {Charter Item 2)

The inspectors conducted a detailed review of the following control rod

movement procedures: . Dresden* General Procedure (DGP) 03-04,

Revision 17, "Contrdl Rod Movements"; Dresden Administrative Procedure

(OAP) 14-14, Revision 0, "Control Rod Sequences"; Dresden Operating

Abnormal Procedure (DOA) 300-12, Revision 02, "Mispositioned Control Rod

(W-2, W-3)"; and Dresden Technical Surveillance Procedure (DTS) 8231;

Revision 02, "Returning Mispositioned Control Rod(s) To Their In-

Sequence Position." The inspectors concluded that these procedures were

technically adequate.

The inspectors also reviewed the flow control line instruction (FCLI)

and SI sheets (OAP 14-14, forms 14.;.148,14-14C, and 14-14D) that were

used to document the rod movements before and after the rod

mispositioning event.

The sheets delineating the control rod moves

prior to the event were technically adequate; however, the SI sheets

following the event did not reflect the movements that took place. The

QNE filled in some of the SI sheets after the control rods had been

moved, rather than obtaining prior approval by a licensed SRO as

required by procedure. A review of the process computer alarm typer

printouts confirmed that the rod* movements on various SI sheets were not

accomplished sequentially .. Moreover, the control rod in question (rod

H-1) was not delineated as a mispositioned rod on any of the FCLI or SI -

sheets.

3.5

Management Involvement in the September 18. 1992. Event (Charter Item 5)

Five individuals were directly involved with the rod mispositioning

event, and the subsequent failure to report the incident. The

individuals included the SCRE, the Unit 2 NSO, the QNE, and two NEITs.

The SCRE (a licensed SRO) was the senior licensee manager directly

involved with the event.

Other licensee management, either directly or indirectly involved were

the shift engineer (SE) and the lead nuclear engineer (LNE).

Both of

these individuals had responsibility to monitor and direct performances

of their subordinates. The LNE was directly involved with identifying

the incorrect operations by the QNE for a similar incident on April 10,

1992.

The QNE was reprimanded for improper rod manipulations following

5

the April 10 event. During the September 18 event the LNE identified

that too many peripheral rods were inserted, and entered the control

room to counsel the QNE.

The LNE failed to bring this situation to

upper management attention. The SE, who had the overall responsibility

of the day shift on September 18, was unaware of the acti*ons taken

regarding control rod movements .. The SE was present in the control room

during the time of the September 18 event; however, the SE was unaware .

of activities being performed. This indicated a lack of management

oversight to ensure proper performance and adherence to station

procedures, and to assure safe plant operations.

3.6

Review of Procedural Compliance (Charter Item 3)

On September 18, 1992, the control room midnight shift was experiencing

high average power range monitor (APRM) alarms due to the existing flow

control line (FCL).

The midnight shift SCRE obtained verbal control rod

adjustment instructions from the lead nuclear engineer (LNE) to insert

several peripheral ~ontrol rods in an attempt t~ reduce the FCL.

Those

rod adjustments were made; however, the APRM alarms did not clear.

At about 7:15 a.m. on September 18, the LNE instructed the qualified

nuclear engineer (QNE) to perform additional FCL rod adjustments.

The

QNE then proceeded to the control room with two NEITs and prepared a set

of "Special Instructions," forms14-14C and 14-140 from Dresden

Administrative Procedure {OAP) 14-14, "Flow Control Line Instructions."

The initial set of special instructions (SI) were approved by the day-

shift SCRE.

At about 7:30 a.m., with the approval of the SCRE, the

Unit 2 day shift NSO initiated FCL rod adjustments in accordance with

QNE instructions. During the initial rod manipulation, the utility

reactor operator was utilized as a "second verifier." At the time of

control rod manipulations, the rod worth minimizer (RWM) rod blocks were

bypassed. Therefore, a second verifier for rod movement was required in

accordance with Dresden Gene~al Procedur~ (DGP) 03-04, "Control Rod.

Movements," and Dresden Operating Procedure (DOP) 0400-02, "Rod Worth

Minimizer.".

At 8:17 a.m. the Unit 2 NSO stopped rod insertion after

partially completing one page in a series of Sis, and the second

verifier left the Unit 2 control panel area.

The Unit 2 NSO selected *

edge control rod H-1 to bypass the rod.block monitor (RBM) inputs; this

was a station routine practice.

At 9:49 a.m. the NSO recommenced rod insertions and mistakenly inserted

control rod H-1 from full-out notch position 48 to.notch position 36.

Control rod H-1 was not included in.the original approved Sis. The NSO

inserted the incorrect rod (H-1) without an approved or written rod

insertion instruction, and without.a second verifier for rod

manipulations as required by Dresden General Procedure {DGP) 03-04,

"Control Rod Movements," and Dresden Operating Procedure, DOP 0400-02,

"Rod Worth Minimizer." *Dresden Technical Specifications 6.2~A~l states

the applicable procedures recommended in Appendix A of Regulatory Guide

1.33, Revision 2 dated February 1978, shall be established, implemented,

and maintained. Regulatory Guide 1.33 Appendix A.Le. included

6

administrative procedures, general plant operating procedures*, and

procedures for startup, operation, and shutdown of safety related

systems.

Failure of the NSO and the QNE to adequately perform the

required second verification was an example of an apparent violation of

approved procedures (92033-0la/50-237, 249 (DRP)).

At the time of initial event occurrence, the QNE recognized the error

and informed the NSO.

It was apparent from the action taken to stop rod

insertion that the NSO also recognized the error.

Upon recognition of

the control rod mispositioning, the NSO was required to take mitigating

actions in accordance with Dresden Operating Abnormal Procedure (DOA)

300-12, "Mispositioned Control Rod."

DOA 300-12 section C.2, immediate

operator actions, required that the NSO discontinue all control rod

movement and recirculation flow increase.s. Subsequent corrective action

was delineated in DOA 300-12, section D.2.a.(1); "lE a single control

rod is inserted greater.than one even notch from its in-sequence

position, THEN continuously insert the mispositioned control rod to

position 00. " The NSO failed to ta~e the required corrective * a*ct ion and

took unapproved directions from the QNE to insert two additional arrays

of control rods in an attempt to recover the correct rod sequence. _

Failure of the NSO to discontinue control rod movements and insert the

mispositioned control rod to its fully inserted position was an example

of an apparent violation of approved procedures (92033-0lb/50-237, 249

(DRP)).

The NSO failed to adequately perform any portion of the abnormal

procedure for a mispositioned control rod, DOA 300-12. Additional

required operator actions.that were not performed by the NSO included,

notifying supervisors, logging the event in the NSO operating logs,*and

monitoring Off-Gas release for possible fuel damage.* The NSO and QNE

. continued.to correct the rod configuration, and by 12:00 noon the NSO

indicated in the operating log that FCL adj~stments were completed.

There was no.mention of any problems associated with the rod

manipulations, a significant load increase, or the existence of a

mispositioned control rod in the NSO log.

Failure to take additional .

required corrective action per*ooA 300-12 and the failure of the NSO to

properly document required Unit log entries was an example of an

apparent violation of approved procedures (92033-0lc/50-237,249* (DRP))*.

After the initial rod mispo.sitioning, the NSO took immediate action

(within less than fifty seconds) and inserted control rod array 801. from

position 48 to 06, contrary to the required immediate action to stop all

rod motion.

This array of rods was apparently part of the approved Sis;

however, it was performed out of sequence from the original FCL plan.

It was not part of the same SI which was partially completed at

8:17 a.m .* The NSO and QNE proceeded to further manipulate the control

rod configuration to c*orrect the Unit 2 rod sequence without prior SCRE

approval.

The SCRE and the NSO failed to adequately perform their

duties and responsibilities in accordance with OAP 07-29,. "Reactivity

Management Controls." This was an example of an apparent violation of

approved procedures (92033-0ld/50-237, 249 (DRP)) *

. 1

The QNE directed the NSO to insert a second array (array 5) of five

control rods from position 48 to 00, this included the initially

mispositioned rod H-1 being inserted from position 36 to 00. This

action was directed by the QNE to the Unit 2 NSO without written or

approved instructions from a licensed SRO.

The QNE did not develop or

have the SCRE review and approve this rod sequehce change SI until after

the rod manipulation had been completed.

The rod manipulation, a

liCensed activity, was not directed by the SE or the SCRE as required by

OAP 07-01, "Operations Department Organization." Directing licensed

activity by a non-licensed individual, i.e. the QNE, without prior SRO

approval was an example of an apparent violation of approved procedures

(1) (92033-0lel/50-237, 24.9 (DRP)).

The inspectors noted that an increase in reactor recirculation flow ~as

performed between 8:30 and 10:40 a.m .. The flow increase resulted in a

load increase of about 100 Mwe, 12% reactor power.

As stated during

.

interviews, the on-duty SCRE and SE were unaware of this load increase.

The inspectors concluded that this load change was performed without

prior knowledge or approval by an SRO licensed individual. This was an

example of an apparent violation of approved procedures

(92033-0le2/50-237, 249 (DRP)).

Following the completion of the rod sequence manipulation, the SCRE

reprimanded the individuals involved, this included the NSO, QNE, and

two NEITs.

During discussions with these individuals, the SCRE

empha~ized the need to slow down, reduce levity in the control room,

prevent personnel from getting into trouble, and stated this event was

not going to leave the control room.

3.7

Previous Events {Charter Item 13) *

The inspectors ~eviewed* information on*past events of a similar nature

to that of the September 18 event .. Two previous events, April 10 and

May 12~ 1992, were noted as potential concerns.

Both events were

identified and reported in accordance with the licensee's deviation

report program (DVR).

The May 12 event occurred*on Unit 3 during a.planned reactor shutdown.

Control rods were being.inserted in accordance with unit shutdown

procedures and the control rod sequence package.

The Unit 3 NSO

incorrectly inserted control rod C-5 from position 12 to position 8.

This rod was inserted out of sequence, and the appropriate control rod

was G-5. * A mispositioned control rod was identified and procedure DOA

300-12 was implemented.

The NSO immediately stopped all rod movements,

entered DOA 300-12, and performed the required subsequent action by

inserting the mispositi-0ned control rod to position 00. After a review

of thi.s event, the inspectors*concluded that appropriate corrective

actions were taken.

8

The April 10, 1992, event occurred on Unit 2 during a control rod

sequence adjustment to increase the FCL.

Control Rod M-4 was being

inserted from position 16 to position 14, when the rod "triple-notched"

and inserted to positi-0n 10.

Under the QNE's direction, the NSO

continued to insert control rods (rod M-12) and_ then withdrew Control

Rod M-4 from position 10 to position 14. Subsequently, the rod sequence

configuration was corrected.

The licensee identified that Control Rod M-4 was mispositioned; however,

corrective actions described in Deviation Report (DVR) 12-2-92-64

concentrated on the mechanical problem associated with the root cause of

the control rod triple-notch. Although the control rod drive hydraulic

(CRDH) drive water pressure w~s normal (280 psi over reactor pressure),

there was a mechanical problem in the insert speed control valve (valve

123) causing drive speed to be too fast.

The inspectors concluded the

licensee took corrective actions for the mechanical problem; however,

the immediate actions and operator response to the mispositioned control

rod were not in accordance with approved plant procedures.

The operators did not take the mitigating actions in accordance with DOA

300-12, "Mispositioned Control Rod." Control Rod M-4 was mispositioned

greater than one even notch, and the procedure required subsequent

action to insert the affected rod to position 00.

The NSO failed to

perform the required action and withdrew the rod to position 14. This*

was an example of an apparent violation of approved procedure (92033-

02a/50-237, 249 (DRP)).

In addition, the QNE directed the NSO to withdraw the mispositioned rod

without SRO approval.

The SE and/or SCRE were designated to direct

licensed activities as required by OAP 07-01, "Operations Department

Organization." Directing control rod movement without a senior

operating license was an example of an apparent violation of approval

procedures (92033-02b/50-237, 249 (DRP)).

For the April 10 event, *the licensee identified the abnormal plant

condition (mispositioned control rod), but.did not identify the failure

to implement required procedural corrective actions.* The licensee

concentrated.on the mechanical problem with the CRD system, and failed

to implement-corrective actions to assure response to future

mispositioned control rods was in accordance with plant procedures.

This was an apparent violation of 10 CFR 50 Appendix B, Criteria XVI,

"Corrective Action," (92033-02/50-237, 249 (DRP)).

3.8

Reportability Requirements of 10 CFR 50.72 and 50.73 (Charter Item 4l

After reviewing the requirements of 10 CFR 50.72 and 50.73, the

inspectors determined *that the September 18, 1992, control rod

mispositioning event was not reportable to the NRC.

9

3.9

Station Personnel Attitude and External Pressure

(Charter Items 7. 11. & 13)

The inspection team interviewed over thirty station personnel.

The -

spectrum of personnel interviewed included nuclear engineers, mechanics,

quality control inspectors, senior reactor- operators, reactor operators,-

nuclear engineers in-training, first line supervisors, training

supervisors, unit operating engineers, technical staff engineers,

equipment operators, and radiation protection technicians.

The following observations were made by the inspection team:

Although there was not a specific training module to emphasize

reporting of errors or deficiencies, it appeared that it was -

emphasized during tailgate (informal work group discussions)

sessions on past events- and during the normal course of performing

duties by first line management.

The impression obtained from the interviews was that management

was not stressing operations over safety, and that personnel

believed management expected errors and deficiencies to be

promptly reported.

.There was a _concern among workers that additional layoffs could

occur, or the Dresden Station could be shut down in response to

company financial concerns.

The performance of marginal workers was believed to have improved

because* of the fear of layoffs, and that performance, not

seniority, would be the basis for retention.

Although Dresden.Station had a disciplinary policy, there was a

concern among workers that it was not applied in a consistent

manner~

Communication between workers in different disciplines was

believed to be improved over the past year. -

Although general training wa~ held on the use of the new problem

identification form {PIF), which was part-of a new integrated

reporting program, some workers thought more specific follow up

  • training was needed for everyone to be comfortable with its use.

Some workers interviewed had not received PIF training.

Most personnel thought the PIF was a significant improvement over

the old system, Deviation Report {DVR), and it was simpler and

worked reasonably well, considering it had only been in effect 3

months.

Those that had used the PIF were encouraged by the fact that

prompt responses were received, and corrective actions were

initiated if the issue was approved.

10

Most of those interviewed believed Dresden's performance over the

past twelve months had imp roved, but that it still had a long way

to go.

Some individuals believed there were still a small number of

employees that had an "attitude problem."

From interviews and general observation, it was apparent that a feeling

of apprehension had influenced Dresden personnel in the performance of

their duties. Plant management had distributed memorandums and

conducted presentations to inform plant personnel that making a mistake *

did not result in employment termination; however, some negative

impressions remained following management corrective action to the

September 18 event.

-

There was external pressure on Dresden station employees, both staff and

management.

Although the external pressures had increased {Commonwealth

Edison Corporate and the.NRC) due to Dresden's performance, it was not

perceived as necessarily excessive. The added attention by the NRC was

believed appropriate for declining performance.

3.10 Licensee Investigation of September 18. 1992. Event (Charter Item 8)

Based on the inspection team's review of the licensee's investigation,

the licensee's report required more detail. That report did not include

specifics associated with the violations of plant procedures, technical

specifications, or 10 CFR regulations. The licensee did identify

incorrect actions which were taken by the individuals involved. in the

event; however, the actions were only identified as "inappropriate

actions." Undoubtedly, these inappropriate ~ctions were the failure to

follow existtng plant procedures.

The report failed to elevate the

significance of this event, rather it.appeared to minimize the

deliberate lack of following station procedures {abnormal, general, and

operating), and the deliberate misconduct of operators to*conceal their

error.

The* personnel actions to conceal the event exhibited a lack of

integrity.

  • . The 1 i censee' s root cause determination of the inappropriate actions *

were stipulated as "personnel errors." It was true that personnel error

initiated the event; however, the lack of management oversight by the

SE, SCRE, and LNE was also a contributing factor.

3.11 Crew Briefings and* Corrective Action (Charter Items 9 & 10)

During the interviews discussed in Paragraph 3.9, licensee personnel

were questioned regarding the extent they were briefed or informed of

.the September 18, 1992, rod mispositioning event.

In general, personnel

interviewed were aware of the event. All of the employees present at

Dresden the week of November 23 were informed through tailgate sessions

and/or the station manager's November 24 "Urgent Noti~e." Because of

11

the Thanksgiving holiday; many employees were not at the site the latter

part of the week and did not find out about the event until Monday,

November 30, 1992.

Those employees found out through a combination of

tailgate sessions, the station manager's "Urgent Notice," and/or word of

mouth upon return to work.

Following completion of licensee's special task group investigation on

December 2, 1992, a follow up letter from the Station Manager to Dresden

workers, dated December 2, 1992, was distributed to all employees

entering or leaving that day after 2:00 p.m.

This letter contained a

summary of the licensee's task group findings and the actions taken

against the five individuals involved.

In addition, the Station Manager

personally conducted a series of meetings with station employees.

One

member of the inspection team observed a meeting on December 2 which was

attended primarily by the operations staff. The Station Manager's

presentation was an expansion of the December 2 letter. It emphasized

the reason for dismissal was not for the control rod mispositioning

error, but was due to the lack of ethics and integrity.

Employees were

asked for their comments following the formal presentation, and several

candid questions were asked related to the personnel actions taken and

disciplinary actions related to mispositioning control rod errors in

general. The Assistant Superintendent for Operations also gave a short

presentation emphasizing the need to continue with the work at hand.

The inspection team concluded that not only operating crews, but all

station employees, had been and were being adequately informed about

this event through a combination of meetings, tailgate sessions, and

station management lectures.

3.12 Personnel Qualifications and Shift Staffing Levels (Charter Items 6 &

ill

.

The inspectors reviewed the training records for the lead nuclear

engineer and the qualified nuclear engineer on duty September 18, 1992.

The records were found to be complete; however, the nuclear engineer

training program was not*definitive in all of its requirements.which

permitted some interpretation by the person performing the training.

The inspectors interviewed several Dresden station qualified nuclear

engineers on December 4,

1992~ The purpose of the interviews was to

evaluate the technical knowledge of the qualified nuclear engineers.

Based on the response to a prepared set of technical questions, the

inspectors concluded that the individuals were knowledgeable of the

field of nuclear engineering as it.would pertain to the duties of a

station nuclear engineer.

The involvement of engineering in the

training of qualified nuclear engineers appeared adequate.

The

inspectors noted_that the nuclear engineer's qualification program

implementing procedures were under revision at the time of the

inspection.

12

On September 18, 1992, the Dresden operating shift staffing was

adequately maintained and no overtime guidelines were exceeded.

The

inspection team noted that numerous operators routinely worked overtime

hours, but did not exceed any of the overtime limits, i.e. 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> in a

24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period, 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in a 48 hour5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> period, or 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> in a seven day

period. At Dresden, the operating crews consisted of.four SRO licensed*

operators (SE, SCRE, Unit 2 Shift Supervisor, and Unit 3 Shift

Supervisor) and four RO licensed operators (Unit 2 NSO, Unit 3 NSO,

Center Desk RO, and Utility RO).

The NRC Operator Licensing Section

evaluated qualifications of the Dresden licensed operators on a periodic

basis. The evaluations were made ~tilizing both the initial license and

the requalification examination processes. Through these examinations

the competency of licensed operators and adequacy of the licensee's

training program was determined.

Based on two previous requalification

examinations, the Dresden training program and its licensed operators

were evaluated to be adequate~ However, there were several identified

weaknesses, including plant communications, Emergency Operating

Procedure utilization, and operator knowledge of administrative topics.

The latter concern was addressed during the July 1992 license operator

exam, when the licensee initially indicated to the NRC that

administrative topics were not crucial, and that referencing procedures

was expected.

The licensee initially challenged the NRC on several exam questions

related to administrative topics. After some conversation and

correspondence with the licensee, the Dresden Station management

acknowledged that *"In order for operators to perform their job in a safe

and error free manner, knowledge of Dresden Administrative Procedures

(OAPs) is a necessary requirement,""(ref. licensee letter from T. J.

Kovach to USNRC dated September 30, 1992).

The licensee indicated that

training was to be provided to enhance overall awareness of

administrative procedures to the members of the operating department.

3.13 Licensee's Long Term Corrective Action {Charter Item 9)

On December 10, 1992, the licensee discussed with Region III management

the intended long term action pl an for the *September 18 control rod

mispositioning event. That action plan included the following

attributes: Communicate the details of the event to all nuclear stati.on

employees; develop a clear interface between the qualified nuclear

engineers and li~ensed operators; evaluite the nuclear engineer training

program; develop a corporate policy on expectations for integrity;

initiate action to reduce further control rod mispositioning events;

evaluate the general employee training program with regard to the

subject event; and define responsibility for independent verification of

control rod movement.

13 '

4.0

Conclusions

After completing the charter, the team was able to make the following

conclusions:

The control rod positioning error did not cause any nuclear safety

limit to be approached.

The control rod mispositioning itself was not reportable to the

NRC; however, it was required to be reported to licensee's upper

management in accordance with station procedures.

There was apparent deliberate.misconduct by the individuals

involved.

Several apparent violations of station approved procedures and NRC

requirements were identified.

Licensee short term corre~tive action for this event appears

adequate; however, long term corrective actions will require

further assessment as it is implemented.

5.0

Exit Interview

The team met with licensee representatives (denoted in Attachment 4} in

an exit meeting on August 26, 1993, and summarized the purpose, Special

Inspection Team charter items, and findings of the inspection. The team

discussed the likely informational content of the inspection report with

regard to documents*or processes reviewed by the team during the

inspection.

The licensee did not identify any such documents or

processes as proprietary.

14

ATTACHMENT 4

Personnel Contacted

Commonwealth Edison Company CCECol

  • M. Lyster, Site Vice President
  • G. Spedl, Dresden Station Manager
  • * C. W. Schroeder, Former Dresden Station Manager

G. Smith, Assistant Superintendent Operation

D. Elias, Safety Review and Analysis Manager

  • T. Rieck, Nuclear Fuel Servi~es Manager

R. Flessner, Safety Programs Director - SR&A

M. Healy, counsel to CECo, Newman & Holtzinger

J. Gutierrez, counsel to CECo, NeWll1an & Holtzinger

  • D. Ambler, Executive Assistant to the Site Vice President
  • L. Ciuffini, Reactor Operator
  • A. D'Antonio, Site Quality Verification Supervisor
  • M. Falcone, Nuclear Operations Staff
  • R. Flahive, Technical Services Superintendent
  • B. Gurley, NRC Coordinator
  • N. Kauffman, Human Resource Supervisor
  • J. Kotowski, Operations Manager
  • S. Lawson, Operating Engineer
  • R. Mitzel, Shift Engineer
  • J. Paczolt, Dresden Reactor Operator
  • K. Peterman, Work Planning
  • G. Piccard, Dresden System Engineer
  • P. Piet, Licensing Administrator
  • s. Reece-Koenig, Performance Assistant Administrator
  • J. Shields, Regulatory Assurance Supervisor
  • R. Weidner, Dresden Training Supervisor

Nuclear Regulatory Commission CNRC)

  • J. Martin, Regional Administrator, Riii *
  • T. Martin, Deputy Director, Division of Reactor Projects, Rill
  • P. Hiland, Chief, Reactor Projects Section lB, Rill
  • F. Brush, Resident Inspector, Clinton
  • H. Peterson, Senior Resident Inspector, Byron
  • M~ Leach, Senior Resident Inspector, Dresden

R. Anderson, Investigator, Office of Investigation NRC Region III

. J. Ulie, Investigat~r, Offic~ of.Investigation NRC Region Ill

B. Clayton, Branch Chief, Division of Reactor Projects Branch 1

W. Rogers, Senior Resident Inspector, Dresden Station

M. Peck, Resident Inspector, Dresden Station

  • A. Stone, Resident Inspector, Dresden Station

Illinois Department of Nuclear Safety

  • R. Zuffa, Resident Engineer, IONS
  • Indicated persons at the exit interview on August 26, 1993.