ML17179A509

From kanterella
Jump to navigation Jump to search
Insp Repts 50-237/92-21 & 50-249/92-21 on 920720-1002. Violations Noted.Major Areas inspected:safety-related Contact Review Program,Calibration/Setpoint Program & Design Changes to Eliminate Noise & post-mod Testing
ML17179A509
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 10/08/1992
From: Darrin Butler, Gardner R, Winter R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17179A505 List:
References
50-237-92-21, 50-249-92-21, NUDOCS 9210190084
Download: ML17179A509 (14)


See also: IR 05000237/1992021

Text

  • ****

.

.

U. S. NUCLEAR REGULATORY COMMISSION

REGION III

R~ports Nb. 50-237/92021(DRS); No. 50-249/92021(DRS)

Docket Nos. 50-237; 50-249

Licenses No. DPR-19; No .. DPR-25

Li.censee:

Commonwea 1th Edison Company*

Opus West III

  • 1400 Opus Place

Downers Grove, IL

60515

Facility Name:

Dresden Nuclear Power Station - Units 2 and 3

insp~ction At:

Dresden Site, Morri~, IL

60450

Inspection Conducted: July 20 thro~gh October 2, 1992

Inspectors: f);Jd~ /( u~

R. Wint.fr

it!' /g &~

Date.

0 tJU16

/tJ/8 hz.

D. * Butler

Date

Approved By: ~w~~

R:N:Gardner;chie

~o I 8 ( q l.

Date

Plant Systems Section

Inspection summary

Inspection on July 20 through October 2, 1992 (Reports No.

50-237/92021CDRS) ~No. 50-249/92021(DRS))

Areas Inspected: .* Announced fo+lowup inspection .of previously

identified EDSFI items (Temporary InstruGtion 25111);

safety

r.elated contac;:t review program, calibration/setpoint program and

design changes to eliminate noise on the neutron monitoring

system (92701); post modification testing (37828); and design

~hanges and modifications (37700).

Results: One apparent violation was identified. -

a failrire to

promptly ~f fect corre6tiv~ actions regarding the identification

bf potential low voltage conditions that could have affected the

operability of safety related equipment*{Section 2.B).

One

violation was identified -

a failure to include saf~ty related

current sensing relays in the calibration program (Section 4).

One open item was identified {Section 3.2).

9210190084 921009

PDR

ADOCK 05000237

Q .

PDR

Inspection Summary

2

  • buring the course of th~ inspection, .the following were noted:

o

Li_censee. progress to closeout remaining EDSFI i terns was

satisfactory ..

o

Post modification testing improved.

o .

Safety related contact review program and

calibration/setpointreview program were well planned.

o

Proposed design changes to .eliminate noise on the neutron

monitoring system app~a~ed appropriate;

1. 0

DETAILS

Principal Persons Contacted

Commonwealth Edison Company CCECol

  1. C. Schroeder, Station Manager.
  • L. deiner, Technical Superintendent
  • E.

Zebus~ Project Ma-nager, Engineering Nuclear

Constructio~

.-

    • J. Gates, Assistant Technical Staff Supervisor
    • D. Smythei Technical staff
    • G. Eckert, Nuclear Engirieering Department (NED)
    • B. Viehl, NED Site Supervisor

_#*R.

Radtk~, Supervisor, Regulatory Assurance

    • E. 'Carroll, Regulatory Assurance

- *D. Lowenstein, Regulatory Assurance

  • B.- Adams, Regulatory Assurance
  1. M. Reed, Superintendent, E/I&C, NED
  1. M. Strait, Technical Staff Supervisor
  1. S. Berg, Assistant Superintendent, Production
  1. P. Piet, Licensing Administrator_

U. s. Nuclear Regulatory Commission CNRC) -

  • A. Hsia, NRR Project Manager
    • M. Peck, -Resident Inspector

_#R. Gardner, Chief, Plant Systems Section

'*Denotes those piesent at the interim exit interview on

August 7, 1992.

- #Denotes those present at the exit interview conducted by

telecon on October 2, 1992.

The inspectors aiso contacted and interviewed other licensee

_personnel.

-

2.0

Action on Previously Identified Inspection Findings

A.

(Closed) Unresolved Item 237/91038-02CDRS); 249/91042-

02CDRS):

- Inadequate calculation to determine degr:aded voltage relay-

trip setpoint.

1)

Background

The_ electrical distribution system functional inspection

(EDS~!) team determined that the degraded voltage setpoint

was set too low to adequately protect safety related motors

duiirtg a LOCA concurrent with a degraded Voltage condition

that hoveted above the degraded voltage relay setpoint (3708

to 3784 volt~).

The licensee performed a voltage dro~

calculation for the assumed worst-case 480 volt motor load

(Unit 2, Division 2, diesel generator .cooling water pump

(DGCWP)).

The DGCWP critical starting and running voltage

requirements at the 4160 bus Meie 3960 and 3950 volts,

respectively.

Compensatory measures were initiated whi9h

directed the operators to start a diesel's DGCWP when it's

associated 4160 bus degraded to 4000 volts and to isolate

th~ affected bus from of~-site power if the voltage degraded

to 3850 volts for more than 1 minute. The compensatory

measures remained in affect until new degraded voltage

setpoints were established.

2)

De~raded Voltage Ti~e Line

O

Calculation began in early 19BO's.

o

August 18, 1980, response, CECo to*NRC (Eisenhut),

acknowledged that running voltages under certain *

scenarios could be slightly less than 90% of rated

voltage (NEMA Standard - running motor value) .

CE,Co

informed the NRC that less than 90% running voltage was

adequate~ based on assumed conservatisms in the voltage

drop calculation.

For example, a 3% voltage drop was

assumed for motors fed.from motor control centers

(MCC) .

O

March 1982,* EG&G (contractor reviewer) acc~pted the

.Dresden design and 3708 to 3784 volt setpoint.

o

May 19,

1982~ NRC approved the Dresden design and

setpo~nt. *

O

Degraded voltage system declared operable March 29,

1983, for Unit 2, and February 27, 1984, for Unit 3.

o

November 13, 1990, S&L

(a~chitect engineer) completed

the Dresden *unit 3 ELMS-AC.calculation, "Balance of

Plant AC Electrical Load Monitoring System."

(~1500

page document)

o

. November 19, 1990, S&L transmitted the calculation

which identified potential low voltage conditions to

CECo.

o

December 5, 1990,.S&L meeting with CECo Nuclear

Engineering Department, station persohnel, and system

Planning .. * S&L identified the potential for MCC

volta~es to be less than

90% of rated voltage and

identified exce~sive fault currents at the 480 volt

level.

CECo indicated_that excessive fault currents

were not a problem in past cal~ulations and believed

2

0

0

0

0

the ELMS calculation contained many errors.

Degraded

voltage was not considered an issue due to the

perception that the original degraded voltage

calculation was conservative.

February 6, 1991, verification of the ELMS calculation

.

design 'inputs was assig.ned* to various -CECo departments;*

however, the verification was given a low priority.

_July 1991, NRC EDSFI team identified the degraded

voltage issue.

July 31, 1991, CECo performed a preliminary voltage

drop calculation and concluded certain equipment.may

not operate at a degraded voltage that hovered above

th~ existing degraded voltc:tge setpo.j.nt.

Following an

operability determination, a 10CFR50.72 (4 hour)

notification was made and co~pensatory measures were

put in.place.

Decembei 31,

19~1, final calculations were completed

and new degraded voltage setpoints were established.

o

New setpoints installed:

Critical Voltage

Relay settings

2

3784

3820+/-7

Jan/1992

3

3832'

3870+/-7

Feb/1992

.3)

Equipment Operability -

Old Setpoint

a)

DGCWP

O

Licensee determined (U3 BUS 34-1) the pump would

probably start and would run at the minimum relay

setting.'

6

The starting v~ltage available to the DGCWP was 319.6

volt (69.5% of rated).

O

.Motor testing determined the DGCWP.would start at 70%

  • of rated (322 .volts) with a motor starting torque of

36.9%.

o

The recommended minimum pump break away torque was 25%.

o

The licen~ee concluded the motor would start at 69.~%

of rated voltage.

3

l

\\

o

The running voltage was 83% of rated (382.5 volts);

however, the motor would hot be damaged from elevated

temperatures because the current drawn at 382.5 volts

was 121A (<129A name-plate)~

b)

_ Containment_ Cooling S.ervice Water (CCSW), Pump Vault Fans

o

Two pumps per. division (total of- four pumps)_*.-

o

One p~mp per division was located in a vault requiring

fans for cooling.

o

Safety Analysis requires one pump for safe shutdown

from a design basis accident (OBA) .

o

Vault fans will not operate at the degraded voltag~

setpoint. -

o

Assuming a single failure, one pump (non-vaulted) would

be available.

o

Pumps are normally not running and are_ manually started

when required during a OBA.

c)

Motor Starters for Low Pressure Coolant Injection (LPCI)

__ Valves and Recirculation Pump .Discharge Valves.*

o

.Due to low st~rter voltage, the valves wbuld not

operate.*

o

All LPCI pumps would start in response to a LOCA

signal; however, inje6tion would not take ~lace.

4)

Equipment Operability -

New Setpoint

o

ccsw pump fans will still b~ operated below the NEMA

90% running valu~.

The licensee does not plan to test

these-motors; however, they believe the fans will

operate satisfactory.

Safety Analysis required only

one pump .. Procedures were in place that directed the

operators to manually start a non-vaulted CCSW pump ..

o

New motor starters were installed for the LPCI

injection and recirculation pump discharge valves in

both Units.

The new starters pick *up at a lower -

voltage and will op,rate satisfactorily at the new

setpoint. -

4

5)

Analysis of Root Cause

  • The root cause may be attributed to the use of .less rigorous

calculation methods (1980 time frame) and the licensee's

fail~re tb identify, during design verification activities,

that the degrad~d voltage setpoint would result, undei

certain conditions, in safety related equipment being

inoperable.

Regarding enf6rcement on this matter, the EDSFI

tea~ ide~tified a significant, apparent corrective ~cticin

viola~lon (discussed in Se~tion 2.B)' ihvolving a failure to

promptly and effectively deal with information presented in

a contractor calculation which pointed to potential degtaded

voltage p*roblems.

The licensee took corrective action promptly after the EDSFI

team questioned the condition and the severity of the

d~graded ~oltage condition.

This indluded the initiation of

-degraded voltage* reviews ~t other CECo stations.

~he ne~

setp6int calctilations were developed usin~ current ~etpoint

methodology techniques.

.This item is consid~red closed.

In addition, this item also closes LER No.91-021,"Improper

Setpoint of Second Level Undervoltage Relays Due to

Management Deficiency."

B.

(Closed}

Unresolved Item 237/9103$-03 (DRS}; 249/91042-03

(DRS}:

Failure to take prompt corrective action.

1)

Background

On Nov~mber 13, 1990, S&L (architect engineer) completed the

Units 2 and 3 ELMS-AC calculation, "Balance of Plant

Electrical Lb~d ~onitoring System*

In a meeting held on

December 5, 1990, S&L identified to CECo.the potential for

MCC voltages to be less than 90% of rated voltage (414

v6lts).

On February 6, 1991, various CECo d~partments were

assigned to validate the ELMS-AC calculation data.

At this

time, CECo engineering did not believe voltages less than

90% 6f rated posed a threat.to safety related equipment~

Engineering believed there were adequate conservatisms in

the voltage drop calculation that would ensure continued

op_eration . of safety related loads.

As a consequence, a low

priority was given to the validation of the ELMS'-AC

  • calculation.

However, these initial assessments of th~ low

voltage condition identified by S&L appeared to be

superficial.

They did not appear to address in a spe_cific

way consequences of low voltage conditions; instead, the

assessments appeared to rest solely on th~ general

impressions and recollections of the engineers involved.

In

addition, a deviation report was not issued to address this

issue.

In July 1991, the EDSFI team performed an

approximate dalculation and identified that degraded

5

voltages (368 to 393 volts) could be experienced at the MCC

level.

The team postulated that certain safety related

equipment, such as LPCI injection and recirculation

discharge valve motor starters, would not operate.

This

would_ occur at a 4.16 _kV bus voltage that hovered above the

existing Technical Specification (TS) setpoint (3708 to 3784

. volts)..

The licensee performed a preliminary voltage drop

calc~lation and concluded that certain equipment may not

operate at the existing degraded voltage setpoint.

  • compensatory measures* were initiated at Dresden* and new

calculations were begun to determine equipment critical

operating voltages.

The licensee also initiated similar.*

actions at their other stations.-

Final calculations

performed by the licensee confirmed the inoperability of the*

LPCI injection and recirculation discharge.valve motor.

starters at a degraded voltage that.hovered above the'

existing setpoints.

2)

Safety Sign if icanc*e

Between the dates that the degraded voltage system was

declared operable and July 31, 1991, Dresden Units 2 and 3

were *operated in an unanalyzed condition.- Assuming a single

failure. (loss of one core spray (CS)

loop)~ LOCA,

an~ a

  • . *

degraded voltage.condition-that hovered.above-the .setpoint,.

the LPCI system would start; however, the LPCI injection

  • valves .and recirculation pump discharge valves would not
  • automatically reposition in response.to.the LOCA.

The motor*

starters would have. insufficient voltage to operate.

Only

one low pressure ECCS system (the redundant cs loop) would

be available to mitigate the accident.

The.minimum low

pressure systems required in the current licensing basis

were one CS loop and two LPCI pumps plus valve realignment.

3)

statement of Violation

The licensee*failed to promptly effect corrective actions

regarding the -identification of potential low voltage

conditions that could have affected the operability of

safety related equipment.

From December 5, 1990, through

July 31, 1991 (when identified by the NRC), the licens;ee

failed to take adequate corrective actions, such as issuing

a deviation report, to promptly pursue the effects of lower

operating voltages on safety related equipment, and to

recognize the effect of the lower voltages as. they related

to the TS degraded voltage set point.

This i tern is .

. considered an apparent vio.lation (237 /92021-01 (DRS);

...

. 249/92021-0l(DRS)) of 10-CFR 50, Appendix B, Criterion XVI,

"Corrective 1\\ction".

6

C.

(Closed) Violation (237/91038-07CDRS): 249/91042-07CD~S)):

The ~DSFI team determined that post modification testing

activities did not always ensure that testing overlapped

into unmodified portions of the electrical,circuit.

In

addition, there were instances where construction testing

did not contain documented evidence that specific circuit

checkout criteria had beeri met.

The inspectors reviewed the construct.ion and post

modification testing performed in six recent modifications.

The testing performed was well docume.nted and completely

tested all portions of the modification.

The inspectors

observed def ini t.e improvement in the testing program,. such

as increased engineering involvement throughout the

modification process, concise* and clear test acceptance

criteria and increased interface betwe~n engineering,

construction and station personnel.

This item is considered

closed.

,

D..

(Closed)

Deviation . ( 237 /91038-01 (DRS)) ; C 249 / 91042-

01 (DRS.)) : . The EDSFI team ha.d determined that the 350 MVA

and 250 MVA circuit breakers, including 250 MVA safety

related.non-diesel breakers on bus Nos. 23, *24, 33, and 34

in the.4kV system could experience fault currents up to 114

percent (overduty) of tpeir, maximum interrupting rating.

The licensee committed to correct the overduty concern for

the non-safety 350 MVA buses and to upgrade the 250 MVA

.

equipment to 350 MVA switchgear.

. The.switchgear upgrade.is capable of interrupting 3 phase

asymmetric fault currents to 80,000A.

The maximum expected

~ault current. is 68,138A.

The ~roposed switchgear

replacements will take place on a bus per refueling outage

schedule starting with D3R13 (September 1993) for bu~ No.

33.

This item is considered closed.

E.

(Closed)

Unresolved Item (237/91038-04CDRS)) t (249/91042-

04CDRS)):

The EDSFI team could not determine if adequate

breaker coordination existed at the 480Vac level. The

  • licensee had previously identified this co.ndition and was in

the process of resolving coordination deficiencies.

The

licensee was replacing original equipment (electro-

.

mechanical trip devices) with solid state trip .devices (RMS-

9 replacements).

The licensee prioritized the replacement

in*.the following order:

1)

2)

3)

ESS/safety related motor control center~ (MCCs) with

rionsafety related load~.

ESS/safety related main feeds.

ESS/safety related bus-tie feeds.

7

4)

Remainder of ESS/safety related trip devices.

5)

Non-ESS/safety related MCCs.

6)

Non-ESS/safety related main feeds.~

7)

Non-ESS/safety related bus-tie feeds.

8)

Remairider of non-ESS/safety related trip_ devices.

The inspectors reviewed.the proposed coorctinatidn curves and

c6ncluded adequate 6ooidination ~ould be established.

The *

licensee expects to complete the installation of the RMS-9

trip devices by the end of the Unit 2 Refueling Outage D2R14

(late 19~3) and the Unit i D3R14 (mid 1994).

This item is

considered closed.

F.

(Closed)

Open.Item C237/91031-02CDRP))

Spurious closure

of AC solenoid operated primary containment isolation valves

during fast bus transfers.

The isolatiori valves blose when

power is removed from their solenoids.

During fast bus

transfers (approximately 83.35 msec), the occurrence of

Group II isolation valves spuriously closing was increasing.

  • The licensee identified that several 12HMA111B9 relays.were

dropping out during the transfer.

Testing identified the

H~ relay drop out time was approximately 100 msec.

The licensee replaced the Unit 3 HMA relays with a General

Electric 12HGA17S63 relay.

The measured drop out times of

the HGA relays were greater than 300 msec.

The Unit 2

relays will be replaced during the next refueling outage.

The station has not experienced* a fast bus trarisfer since

installing.the HGA relays.

However, there appears to be

adequate margin_in the HGA drop out time to prevent.

reoccurrence of this condition.

This item is considered

closed.

G.

(Open)

Ooen Ite~ (237/91025-0lCDRP)):

The licensee

initiated Safety Related Co_ntact Testing Program (SRCTP) was

reviewed to determine the progress and direction taken by

CECo to identify untested contacts.

Thirteen systems were

include~ in the original program scope.

This has increased

to .a tot~l of 17 systems.

The contacts were categorized' as

Technical Specification (TS), Updated Final Safety Analysis

Report (UFSAR), important to safety_, or non-safety related.

T~st requirements were reviewed agains~ ~pplicable

.surveillance and test procedures.

Multicolored logic

tracings (overlap drawings) were used to identify the

contacts that were tested.

This process identified by

category all untested contacts.

Untested TS related

contacts were immediately tested and no contact failures

8

were identified.

The remaining untested contacts with

.testing recommendations will be given to the procedure

writers and incorporated into appropriate test procedures.

In addition,* a large number. of drawing enhancements were

identified which will be incorporated orito th~ drawings.

The piogram is developing a controlled user friendly data

  • base.

Transition of the information to CECols main frame*

computer will occur later this year.

The relay and contact

information is a living design document.

Changes to the

  • data base will be controlled by engineering through the

design control process.

In addition, the program has been

funded to verify.any changes to the data base as a result of

the Dresden USFAR rebaseline effort.

The inspectors concluded.that CECo was progressing in the

correct dir~ction to identify untested contact$.

The

program was well managed arid should provide a useful data

base for engineering and station personnel.

This item will

remain open pending NRC review of the procedure and drawing .

~nhancements.

H.

(Coen)

Violation (237/91016-02(DRP)):

The licensee

initiated a Calibration/Setpoint Program to pioperly

classify all instruments and to provide setpoint *

justification. *The program initiated.instrument walkdowns,

created a data base, re*!:rnlved instrument labeling

. discrepancies and obtained ~11 available setpoint

calculations.

Missing setpoint calculations will be

generated first prior to reviewing available calculations.

The instrument review priority will o<:;:cur in the following*

order:

reactoi protection system, engineered safety

features, Emergency Operating Procedures and Regulatory

Guide 1.97 instruments.

Balance of Plant instrumentf? with

safety importance will be reviewed at a later\\ date.

CECo is developing*a setpoint methodology based on

  • Instrument Society of America (ISA) standards and General

Electric is researching the original basis for TS numbers

and will determine whether 'the number is a safety limit or

analytical limit.

Calculation preparation, review and

approval will begin later this year.

The instrument nameplate data, safety classification,

calibration constants and setpoint information will be

transferred into a user friendly data base.

The data base

is a living document and will be controlled by engineering

through.the design cont~ol process. *A sepa~ate Instrument

.Mechanic (IM) calibration data. sheet is being developed.

The IMs will. no longer have to transfer calibration

  • .information from the previous calibration record.

The

  • inspectors concluded that the calibration/setpoint review

9

was an effective program.

The program was well managed and

should provide a useful data base for engineering and

station personnel.

This item will remain open pending NRC *

review of the. completed calculations.

3.0

Special Electrical Reviews

3.1

Design tontrol

The inspectors evaluated the licensee's performance and.*

programs relating to design changes and modifications.

The

inspectors reviewed six modifications.and performed a walk

down.of installed- equipment for three modifications.

Among

.. the areas checked were verification that proper ~eview and

  • approval were received, associated te~t procedures and

~merg~ncy operating procedures ~~re change~, training was ..

revised to refiect the design change, that controlled

drawings either were marked up or revised, modifications

received alO CFR 50.59 review, installed hardware for the

modification conformed to the modification drawing, and that

satisfactory ~ost modification testing was-performed. The

followirtg modifications were reviewed:

1)

M12-3-91-024, Load Center 38 and 39 Load Shed Logic

Revision.

.

.

2)

M12-0~92-002, Power Feed Transfer Interlock for Diesei

Generator 2/3 Auxiliaries.

3)*

M12-2/3-87-002AB, Radwaste Turbine Building Floor Drain

sump Pump A Control, Run Times and. Indication.

4)

M12-3-91-042; *LPCI Injection Valve Control Logic for

Torus Cooling System.

5)*

M12-2-92-021, Addition of 4 Cells to Unit 2 250Vdc

Battery.

6)*

M12-3-92-022, Add Interposing.Rela~ to HPCI Valve M03-

2301-10 Clo$e Logic.

  • modifications reviewed by walkdown

The inspectors concluded the licensee was adequately*

implementing the design control process.

3.2

Design Changes - Neutron Monitoring Syst~m

The insp~ctors reviewed past and proposed design changes to

eliminate noise on the neutron monitoring system~

One past

Unit 2 ~edification installed hew stainless steel jacketed

Whittaker signal cables.

This cable was installed outside

10

the existing rigid conduit .. However, the s~sceptibility to

noise appeared* to increase.

Since t~is modification,

Dresden has documented four Licensee Event Reports (LER) on

source range monitor/intermediate range monitor spiking.

Operational testing identified several motor operated valves

(MOVs) as the major contributors to electro~magnetic

interference (EMI) and.varistors were installed across the

motor shunt field of five MOVs to reduce interference.

In

addition, EMI comparisons were made_ between cab~es run

6utside of conduit, cables run in flexible conduit, and .

cables run in rigid conduit.

Rigid conduit provided the

best EM! isolation.

Evaluations were also made between the

presently *installed stainless steel jacketed Whittaker cable

and triple shielded coaxial cable.

The triple shielded

coaxial was determined to be less susceptible to noise.

The licensee plans to replace the Whittaker cable with

triple ~hielded cable routed in rigid.conduit on Unit 2

during refueling outage D2Rl3 (Januaryi 1993).

No actions

are.planned for Unit 3 since EMI noise has been acceptably

low with the present cable. configuration~

An additional

improvement will be to u~e quick disconnect, watertight Lerno

connectors which will be easier to install and maintain than

the previous*HN type connectors.

S~veral engineering issues

al!?O have to be resolved including pull.tension, the exact

grounding point and.method of grounding triple axial signal*

cable.

This item is considered open (237/92021-02(DRS); 249/92021-

02(DRS)) pending NRC review of the final modification

package and actual cable in~tallation.

4.0

SBGT System Review

The Dresden Standby Gas Treatment (SBGT) starting logic was

reviewed to determine if a loss of power to the B tr~in

(when in standby), with A train in primary, could cause the

loss of both SBGT trains durin~ an Engineered Safety Feature

(ESF) actuation (Quad Cities LER 92-013).

The inspectors

  • concluded that Dresden's SBGT logic was not susceptible to

the.Quad Cities design deficiency and would operate as

designed.

However, the inspectors identified that four SBGT

heater current sensing relays (two pe+ train) were not .

included in a calibration program.

Successful testing of

the SBGT system has demonstrated functional operability of

these relays.

The following relay failure modes could

occur:

o

Relay setpoint drift high could prevent the primary

train from starting; however, the standby train should

start.

11

l .

. .,

0

Relay setpoint contact fails to close; however, the

standby train should start.

O

Relay setpoint drift low could permit operation of the

primary train with impaired heat.er operation.

o

Relay.setpoint contact failed closed would permit

operation of the primary train with impaired heate~

operation.

The licensee determined the relays were in calibration and

verified proper contact operation on August 7, 1992.

Failure to include ~afety related cuirent sensing relays in*

a calibration program is a violation (237/92021-03(DRS);

249/920~1-03(DRS)) of 10 .CFR 50, Appendix B, Criteria XI,

"Test Control".

  • 5.0 *open Items

.Open items are matters which have been discussed with the

lic~nsee~ which will be reviewed further by th~ inspector, *

  • and which involve some action on .the part of the NRC or

licensee or both.

One open item was disclosed during ~he

inspection in Section 3.2.

6.Q Exit Interview

~he irispectors conducted an interim exit interview on

August 7, 1992, at the Dresden site ahd by telecon on

October 2, 1992, to discuss the areas reviewed during the

inspection and the inspection findings.

NRC personnel and

lic~nsee representatives who attended this meeting are

doc~mented in Section 1.0 of thi~ report.

The licensee did

no~ ~dentify any docu~ents or processes as propri~tary.

12