ML17157A372

From kanterella
Jump to navigation Jump to search
Insp Repts 50-387/90-200 & 50-388/90-200 on 900813-17 & 27-31.Team Identified 14 Findings.Major Areas Inspected: Plant Walkdowns & Technical Reviews of Calculations
ML17157A372
Person / Time
Site: Susquehanna  
Issue date: 10/12/1990
From: Gramm R, Jeffrey Jacobson, Lanning W
Office of Nuclear Reactor Regulation
To:
Shared Package
ML17157A371 List:
References
50-387-90-200, 50-388-90-200, NUDOCS 9010240232
Download: ML17157A372 (79)


See also: IR 05000387/1990200

Text

U.S.

NUCLEAR REGULATORY CO/MISSION

OFFICE

OF NUCLEAR REACTOR REGULATION

Division of Reactor Inspection

and Safeguards

NRC Inspection Report:

50-387/90-200

50-388/90-200

Docket Nos.:

50-387

50-388

License No.: NPF-14

NPF-22

Licensee:

Pennsylvania

Power and Light Company

Facility Name:

Susquehanna

Steam Electric Station Units

1 and

2

Inspection

Conducted:

August 13-17

and 27-31,

1990

Inspection

Team:

NRC Consultants:

Jeffrey B. Jacobson,

Team Leader,

NRR

Jul io Lara, Region I

Roy Mathew, Region I

Shashikant

V. Athavale,

NRR

Richard Jolliffe, AEOD

Atty E. Almond,

NRR

Omar Hazzoni,

AECL

Alek Josefowicz,

AECL

Jim Beaton,

AECL

Prepared

by:

Je

r

a

son,

Team Lea er

Team

n

c

n Development Section

C

Specia

In

ection Branch

Division f Reactor Inspection

and Safeguards

Office of Nuclear

Reactor Regulation

loh~J o

Date

Reviewed by:

o

r

.

ramm,

~e

Team Inspection

Development Section

C

Special

Inspection

Branch

Division of Reactor Inspection

and Safeguards

Office of Nu lear Reactor Regulation

Approved by:

ay

e D.

La

ing,

>e

Sp

ial Inspection

Branch

Division of Reactor

Inspection

and Safeguards

Office of Nuclear Reactor Regulation

eosoahaisz

vosoisl f

PDR

ADOCK 05000387

6

veau

I

>

~ '

(

I

EXECUTIVE SUtNARY

During August

13 through

17 and

27 through 31, 1990,

a Nuclear Regulatory

Commission

(NRC) inspection

team conducted

an electrical distribution system

.functional inspection

(EDSFI) at Susquehanna

Steam Electric Station

(SSES)

Units

1 and

2 to determine if the electrical distribution system

(EDS) wou1d be

capable of performing its intended safety functions as designed,

installed,

and

configured.

The team also assessed

the licensee's

engineering

and technical

support of EDS activities.

The team conducted plant walkdowns

and technical

reviews of the calculations

and associated

documents pertinent to the

EDS and

interviewed corporate

and plant personnel.

The team identified 14 findings that were discussed

with the licensee

during

the exit meeting

on August 31, 1990.

Weaknesses

in the licensee's

discrepancy

management

program may have contributed to the findings related to the unquali-

fied Limitorque valve motor actuators,

the inadequate

setpoints for degraded

grid relays,

the inoperable level indication for the diesel fuel oil storage

tanks

and the inadequate

evaluation of relay setpoint calibration data.

Although the licensee

had identified these deficiencies before this inspection,

,it had failed to adequately

and effectively correct the problems.

Weaknesses

or errors in the original plant design

may have contributed to the

findings related to the lack of overpressure

protection for the diesel

emergency

service water

(ESW) piping, the overvoltage condition on the

dc system,

and the misapplication of an undervoltage

relay.

Certain of the findings were of particular concern

because

of their potential

safety significance.

These

included the inadequate

setpoints for the degraded

grid relays,

the unqualified Limitorque valve motor actuators,

the inadequate

testing of dc circuit breakers,

and the inoperable level indication for diesel

fuel oil storage

tanks.

Specifically, at their current setpoint,

the degraded

grid relays

cannot ensure that adequate

voltage will be available to all

safety-related

loads.

During the inspection,

interim operator

procedures

were

implemented which mitigated this concern until proper setpoints

can be

established.

In addition,

numerous safety-related

Limitorque valve motor

actuators

are not environmentally qualified because

they are operated with

250-volt control power and nontested

motors.

The testing of dc circuit

breakers with an ac current source

has resulted

in uncertainty

as to their

expected field performance.

Finally, the inoperability of level indication for

the diesel fuel oil storage

tanks could lead to uncertainties

in actual fuel

levels during accident conditions.

The team also noted strengths

in the plant and corporate organizations.

Among

these

were good coordination

between

corporate engineering,

the site,

and

nuclear licensing;

good control of instrument setpoints;

and

a high quality of

engineering

associated

with recent modifications.

The Pennsylvania

Power and

Light Company

(PPSL)

team that interacted with the inspection

team was very

well prepared,

technically competent,

and organized.

In addition, internal

gA audits were thorough

and identified some

key programmatic

concerns

although

corrective action for these

concerns

were found to be slow or lacking in

several

instances.

TABLE OF

CONTENTS

1.0

INTRODUCTION..................................................

Pa>ac

2.0

ELECTRICAL DESIGN.............................................

2.1

2.2

Offsite Grid and 13.8-kVac Systems.................

4160-Vac Class

1E System...........................

2.2.1

Switchgear Short Circuit Ratings............

2.2.2

Protective Relaying.........................

2.2.3

Transfer of 4160-Vac

ESF Buses

Between Offsi

~ ~ ~ ~ ~ ~

te Sou

~ ~ ~ ~ ~ ~

~ ~ ~ ~ ~ ~

~ ~ ~ ~ ~

rces.

1

2

3

3

3

2.3

2.4

2.5

2.6

Emergency Diesel Generators........................

480-Vac Class

1E System............................

2.4.1

4160-Vac/480-Vac

1E Transformers Sizing.....

2.4.2

480-Yac Switchgear Short Circuit Ratings....

2.4.3

Yoltage Regulation/Review of ASDOP Program..

120-Vac Class

1E System............................

250/125-Vdc Class

1E System........................

2.6.1

Yoltage Drop................................

2.6.2

Battery Sizing/Short Circuit Study..........

2.6.3

DC System Overvoltage.......................

2.6.4

Motor Control Center Circuit Breakers.......

5

5

5

6

7

7

8

9

10

2.7

2.8

2.9

2.10

Protective Coordination............................

120-Vac

1E Distribution System.....................

Penetration Sizing.................................

Degraded

Voltage and Loss of Yoltage Relays.......

10

11

12

12

3.0

MECHANICAL DESIGN........... "... -. -."...... -.... -... -.... - .. -. - ..

15

3.1

3.2

3.3

3.4

3.5

Heating, Yenti lation and Air Conditioning

Power Demands for Major Loads............

Emergency Service Water System...........

Diesel Generators

and Auxiliary Systems..

Fire Protection System...................

Systems.............

~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ t ~ ~ ~ ~ ~ ~

~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~

15

16

17

18

20

4.0

ELECTRICAL EQUIPMENT TESTING AND SURVEILLANCE......................

21

4.1

4.2

4.3

4.4

4.5

4.6

Diesel Generator Testing.......

Setpoint Calculation

and Contro

Circuit Breaker Testing........

Fuse Control...................

Inverter Testing...............

Battery Testing................

~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 0 ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~

~ ~ ~ ~ ~ ~ ~ ~

~ ~ ~

~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~

1

~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 0 ~ ~

~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~

~ ~ ~ ~ ~ ~ ~ ~ I ~ ~ ~ ~ ~ ~

~ ~ ~ ~ ~ ~ ~ ~

~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~

~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~

21

21

22

23

24

24

5.0

ENGINEERING AND TECHNICAL SUPPORT....................

~

~

5.1

Equipment Modifications.........................

5.2

Discrepancy

Management System...................

5.2.1

Deficiency Control System................

5.2.2

Summary of Discrepancy

Management

System

6.0

GENERAL CONCLUSIONS..................................

25

26

~ ~ ~ ~ ~ ~ ~

Review.

26

32

~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~

33

~Pa

e

~ o ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~

5

APPENDIX A - Deficiency Sheets............................

APPENDIX

B - Personnel Contacted..........................

A-1

B-1

1.0

INTRODUCTION

During recent inspections,

the Nuclear Regulatory

Commission

(NRC) inspection

teams

observed that the functionality of safety-related

systems

had been

compromised

as

a result of design deficiencies

introduced during design modifi-

cations of the electrical distribution system.

Inspection

teams also discov-

ered that the actual configuration of the installed equipment

does not adhere

to the original design.

Consequently,

the

NRC initiated the electrical distri-

bution system functional inspections

to determine if the electrical distribu-

tion systems

(EDSs) at operating nuclear

power plants are adequate.

The two main objectives of this inspection were {1) to ensure that

EDS power

sources

and equipment

were adequate

to support the operation of the plant's

safety-related

equipment

and (2) to assess

the licensee's

engineering

and

technical

support associated

with this system.

The team reviewed calculations

and associated

documents

to ensure that electrical

power of acceptable

voltage,

current,

and frequency would be available to safety-related

equipment

powered

from the station

EDS.

The review included portions of the onsite

and offsite

EDS including the station startup transformers,

13.8-kVac system,

the 4160-Vac

Class

1E system,

the emergency diesel generators,

the 480-Vac Class lE system,

the 120-Vac Class lE system,

the station batteries,

and the 250-Vdc and 125-Ydc

Class

lE systems.

The team also reviewed the mechanical

systems

which inter-

face with the

EDS, conducted

an onsite walkdown, and reviewed maintenance,

calibration,

and surveillance activities for the above mentioned listed sys-

tems.

In addition, the team reviewed selected modifications and the licensee's

discrepancy

management

program to assess

the capabi lity and performance of

engineering

and technical

support.

The team verified conformance with General

Design Criteria

(GDC) 17 and

18 and

appropriate criteria of Appendix 8 to 10

CFR Part 50.

The team reviewed plant

Technical Specifications,

the Final Safety Analysis Report,,

and appropriate

safety evaluation reports to verify that technical

requirements

and licensee

commitments

were being met.

The specific areas

reviewed and the team's find-

ings are described

in Sections

2 through

5 of this report.

A summary of the

conclusions,

strengths,

and weaknesses

is given in Section 6.

Each finding

addressed

in the report is provided in Appendix A and is categorized

as either

an open or an unresolved

item.

A list of personnel

contacted

is provided in

Appendix

B and persons

attending the exit meeting are indicated with asterisks

before their names.

2.0

ELECTRICAL DESIGN

To obtain

a clearer understanding

of the electrical design,

the team examined

system descriptions,

design reports, electrical

design calculations

{including

system loading, fault level, protection settings

and coordination, voltage

regulation,

and equipment sizing), design

changes,

nonconformance

reports,

and

equipment specifications.

The specific areas of the design review are dis-

cussed

below.

2.1

Offsite Grid and 13.8-kVac Systems

The power system grid provides for two independent offsite power sources.

One

source is established

by tapping the Montour-Mountain 230-kV line north of the

I

~

I

~

Susquehanna

plant to startup transformer

10.

The second offsite power source

is supplied at 230-kY from a tie between

the 500-kV and 230-kV switchyards at

the south

end of the plant and connects

to startup transformer

20.

The two

step-down transformers

supply power from the offsite grid to two separate

non-Class

lE 13.8-kVac buses.

These

buses

supply the systems that are not

designated

Class lE and also the Class

1E systems

through two engineered

safety

feature

(ESF) step-down transformers

per bus.

The team asked the licensee

about the

1975 to 1985 data contained in the

FSAR

(page 8.2-10), which indicated that for the Montour-Mountain 230-kV line, 1.96

outages

had occurred every

100 circuit miles.

The licensee

responded

that the

FSAR reliability data is no longer accurate

because

considerable

improvements

had

been

made during the last

4 years.

The licensee

said that the

FSAR will be

revised to include the latest data,

which reflects the improved reliability as

a result of licensee's

upgrading surveillance

and maintenance

of the line.

The transformers

were sized to provide for all load requirements for the most

stringent operating condition, which is a loss of coolant accident

(LOCA) in

one unit with the other unit carrying full load and with one of the two offsite

sources

out of service.

The kilovolt ampere capability, connections

to the

safety buses, field installation, protection, testing

and surveillance,

and

voltage regulation of the offsite power source

and

ESF transformers

were

adequate.

The transfer

scheme at the 13.8-kVac level allows for the supply of power to

the plant auxiliary systems that are not designated

Class

1E during plant

startup

and shutdown.

A synchronizing relay is used to allow the transfer of

the two sources

of power within predetermined

limits of phase

angle.

The

licensee

had selected

the setting of the synchronizing relay to avoid undue

protective relay tripping under the inrush current introduced

by the transfer.

However,

no consideration

had been given to the need to verify that the voltage

drop through the transformer would be acceptable.

In response

to the team's

concern,

the licensee

performed preliminary calculations that showed the

voltage drop would not exceed

25 percent.

This was acceptable

to the team.

2.2

4160-Vac Class

1E System

The onsite

power sources

consist of four load group channels.

Each load group

channel

can be supplied

by one of four emergency

diesel generators.

Any three

out of the four load group channels is capable of meeting the design-basis

requirements.

The 4160-Vac buses

supply the large motors

and

one

power center

per bus;

each is rated at 750

kVA and feed the smaller loads at 480 Vac.

The

5-kVac cables

connect the 4160-Vac buses

and transformers.

All redundant safety

loads are divided between division

1 and

2 buses.

The

4160-Vac safety

buses

and their connected

loads

had adequate

load current and

short circuit current capabilities,

protection,

and cable connections

between

loads

and buses.

Testing

and surveillance

and compliance with the single-

failure criterion appeared

adequate.

In addition, the fast bus transfer

scheme

met applicable separation

requirements for safety systems.

a

~I

2.2.1

Switchgear Short Circuit Ratings

The licensee

does not have

a calculation index,

or other system for controlling

the use of non-valid or superseded

calculations.

As a result, three calcula-

tions were found to exist for the short circuit ratings of the lE switchgear.

These calculations

were produced during 1980 and

1982 and,

even though the

calculational results

and assumptions

were not the

same,

the licensee

consid-

ered

them valid and had put them into effect simultaneously.

These calcula-

tions were found to contain several

nonconservative

features

including those

listed below.

There were errors in the application of breaker interrupting factors.

\\

Maximum possible voltage was improperly considered.

The addition of ESF transformers

installed before plant startup

was not

incorporated into two of the calculations.

One of the calculations

was considered

"non-g" and

had not received

appropriate

technical

review.

In response

to the team's

concerns,

the licensee

performed

a fourth calculation

(SC-I) and gave it to the team to review in preliminary form on August 31,

1990.

This calculation indicated that most of the team's

comments

and concerns

had been addressed.

However, the available margin between

duty and rated

values for the short circuit capability was minimal.

The licensee

committed to

perform formal short circuit calculations to allow for a proper evaluation of

this issue.

This item is identified as Item 1 of Open Item 90-200-01, of

Appendix A to this report.

2.2.2

Protective Relaying

The team identified that the ground sensors for the 4160-Vac system were set at

2 amperes with an accuracy of 2 amperes.

This would give a maximum pickup trip

of 4 amperes.

The team was concerned that the protective relaying

schemes

and

settings

would be insensitive to ground faults involving fault impedance,

as

well as those occurring inside windings of machines.

To verify protection for

these

cases,

the team performed its own calculations to reevaluate

the maximum

ground fault current.

The team found that when capacitive

components

are

included, the ground fault current would be more than

4 amperes,

which would be

adequate

to actuate

the ground sensor relays.

2.2.3

Transfer of 4160-Vac

ESF Buses

Between Offsite Sources

During

a loss of one offsite power source,

the

EDS is designed

so that the

feeder breaker to the

ESF transformer will trip and the alternate

feeder

breaker will close to supply voltage.

This is a slow bus transfer

because all

4160-Vac bus

loads will experience

an undervoltage trip before the alternate

source provides

power to the buses.

Therefore,

the transfer

scheme

would

preclude the possibility of. closing in on an out-of-phase

condition and

no

undue transient effects

on

1E motors or undue voltage drops would be caused

by

this transfer.

No other concerns

were noted with the 4160-Vac transfer.

'f

~

2.3

Emergency Diesel Generators

Although the emergency

diesel

generators

(EDGs)

had

an adequate

kilowatt

rating, appeared

able to start

and accelerate

the assigned

safety

loads in the

required time sequence,

was adequately

protected,

and had sufficient voltage

and frequency regulation under transient

and steady state conditions, the team

identified problems in the diesel

loading tabulations

and with the diesel

overcurrent relays.

Details of the teams findings in these

areas

are discussed

below.

Cable losses

had not been included in the loading tabulations

in the calcula-

tions pertaining to the loading of the

EDGs.

As a result, the licensee

per-

formed

a calculation for the largest

EDG cable connection to the bus

(EDG E)

and found that the associated

losses

were approximately

8

kW.

The team consid-

ered these

losses sufficiently important to warrant

a revision of the loading

tabulations

although the existing loading margin of approximately

7 percent

(326

kW) for overall diesel capacity would still be sufficient after all the

cable losses

were included.

The licensee

committed to perform complete calcu-

lations

and to revise the A-E diesel

loading tables accordingly.

This item is

included as part of Open Item 90-200-01,

Item 2 in Appendix A to this report.

In the modeling of the transient conditions

imposed

by the restart of the

largest

load [2000-HP residual

heat

removal

(RHR) pumpj, the bus preload

was

assumed

to be 2000

kW when the actual

bus preload could be as high as 2600'W.

When the team discussed

this discrepancy with the licensee,

the licensee

contacted

the diesel manufacturer

who performed

an additional

computer analysis

for the case with the bus preload at 2600 N.

The analysis

showed that the

diesel

generator

can successfully restart

an

RHR pump with a bus preload

of.

2600

kW.

Therefore,

the

EDGs had adequate ability to successfully start

and

accelerate

the assigned

safety loads.

The additional diesel

loading requirements for a Unit I design-basis

accident

(DBA) and

a Unit 2 forced shutdown scenario

are given in Emergency

Operating

Procedures

(EOPs).

These required accident

and shutdown

loads are based

on

Loading Calculation

E-RGF-002

and

FSAR Table 8.3-1a to preclude

any overloading

of the diesel generators.

The

EOPs

do not require

any manual tripping of

loads.

All DBA and shutdown loads,

except motor-operated

valves,

are

conservatively

assumed

to be connected

to the diesel generator

as

shown in the

FSAR.

Procedure

AR-016-001 requires control room operators

to verify and shut

down

diesel

generator

loads if an overcurrent alarm condition occurs.

This alarm is

provided by an inverse time overcurrent relay.

However, the team found that

the overcurrent relay settings

were not adequate for diesel generator

E and

that all diesel relays exhibited excessive drifting, which was not properly

accounted for in the relay setting. calculations.

The team was concerned that

because

of the improper settings

and the drifting of setpoints,

the overload

alarm might not be initiated if a diesel generator

was overloaded.

This item

is identified as Unresolved

Item 90-200-02 in Appendix A to this report.

2.4

480-Vac Class

1E System

The 480-Vac Class

1E distribution system including the load center

(LC) trans-

formers, switchgear

and motor control center

(NCC) short circuit ratings,

ground fault protection,

motor overload protection,

and voltage regulation

was

~

~

I

reviewed

and appeared

adequate.

The 120-Vac Class

1E distribution system

protection coordination

and the design features of the 120-Vac

1E inverters

also appeared

adequate

and met applicable

requirements.

Specific details of

the team's

review are described

below.

2.4.1

4160-Vac/480-Vac

1E Transformers Sizing

Bechtel Calculation E2020.02,

Revision 1, related to the loading of the Unit 1

NCCs and

LCs was reviewed

by the team.

The team observed that under worst-case

conditions for LCs 1B230 and IB240 there is a 5-percent

margin between the

rating and the loading of the transformers,

which is adequate

but would limit

future increases

in loads

on these

buses.

The 1B240

LC had

no spaces

available

for additional circuit breakers

and

1B230

LC had only one spare

space.

In

addition,

2 of the 20 Unit 1 NCCs

(OB136 and OS146) were found to be loaded to

86 percent

and 80 percent,

respectively,

which would limit the future increases

in loads for the areas

serviced

by those

NCCs.

The team noted the drawings for

the two NCCs had warning notes describing the loading limitations.

2.4.2

480-Vac Switchgear Short Circuit Ratings

The team identified that Bechtel Calculation E2005.03,

Revision 0, which

related to the ability of the

NCC circuit breakers to accommodate

postulated

fault currents,

did not include cases

where the 4160-Vac/480-Yac transformers

and

LCs were loaded to the maximum.

These

cases

were described

in Calculation

E2020.02,

Revision 1, for sizing of the transformers

and were used

as input to

the

ASDOP computer program.

The calculation only applied to Unit 1, which also

feeds the station

common loads,

and the calculation

used

a nominal system

voltage value instead of the highest voltage.

The team's

review of the existing calculation,

considering the missing require-

ments,

indicated that the rating of NCC circuit breakers

would not be exceeded

under the worst-case

conditions (i.e., highest

system voltage, highest trans-

former loading,

and negating

the cables

between

the

LC and NCC).

The licensee

indicated that the calculations will be updated

under

a program for review and

revision of all calculations.

Bechtel Calculation E2006.01,

Revision 4, documented

the basis for selection of

480-Vac power

cables

between

the

LC to NCC with regard to short circuit ratings

of those cables.

However, there

was

no calculation for the selection of the

cables

from the

NCCs to the ultimate loads although there

was

a set of require-

ments in the design-basis

calculation

document ("Electr ical Protective Devices

- DBC-1") that governed the selection of the settings for protective devices.

The protective devices

were set

so that insulation for the cables

would not be

damaged

by thermal effects of fault currents.

2.4.3

Voltage Regulation/Review of ASDOP Program

The licensee

used the

ASDOP computer program to calculate

a voltage profile for

the ac system to the 120-Vac level and calculated

short circuit fault levels

and protective relay settings

by hand.

Because

the computer program could not

model the emergency

diesel generators

(EDGs), the licensee

had not used it to

verify the behavior of the

EDGs during the starting of large loads or blocks of

~

~ * i

~

~

loads following a loss of offsite power

(LOOP).

However, the licensee

had

verified the voltage regulation following a

LOOP during an actual

run of the

EGGs.

The initial settings of the stepdown transformer s had been selected

so that the

loads would riot be exposed to voltages

10 percent higher than their nominal

rating anywhere in the system

(13.8-kVac to 480-Vac).

It was

assumed

that the

on-load tap changers

of the 230-kVac/13.8-kVac

stepdown transformers

would

maintain the system voltage in the desired

range

and that the 4-kV bus voltage

would be maintained

by the

EDG automatic voltage regulator

when the Class

1E

system

was operated

from the

EDG.

As a result of the

ASDOP analysis,

the

licensee

had changed

the load restarting

sequence

to maintain the 480-Vac bus

voltages at or above

80 percent of nominal rating.

Table E-57, Revision 5, and Bechtel voltage drop Calculations

E2006.01

(Revision 0) and E2006.04 listed the

maximum distance to the load and maximum

permissible

load (horsepower/amperes)

for each

cable size in the 480-Vac

Class

IE system.

These were design guides written to ensure

the voltage would

remain at or above

80 percent of the nominal rating for starting the

EDG and at

90 percent for other loads.

Even though this was not a verification of the

actual

design,

the team found this approach

of documenting

the voltage drop

study acceptable.

The

LC protection for the

HCC feeder circuit breakers

was

set to permit simultaneous restart of all motor loads with all non-motor loads

energized

in accordance

with design-basis

calculation "Electrical Protective

Devices - DBC-1."

2.5

120-Vac Class

1E System

The Class

1E instrument circuits required for post-LOCA monitoring are supplied

from recently installed Class lE 120-Vac Topaz inverters that are backed

by the

Class

1E batteries.

Instrumentation

and control (ISC) load groups of the

engineered

safety features

system

and other safety-related

systems

are fed from

four independent,

electrically and physically isolated Class

lE 120-Vac buses.

These

buses

are not supported

by battery-backed

inverters; if a,loss of offsite

power occurred,

the instruments

would be disabled until powered

by a Class

1E

emergency

diesel generator

(EDG).

In the case of a

LOOP, components

of each

instrument

loop could fail either at the high- or low-side of their range.

The

team noted that spurious actions of equipment

could occur because

of differ-

ences

in reset times for each

component of the loop.

Although effects of such

a scenario

were not analyzed

by the licensee,

safety

loops have

been tested

by

actually shutting off the power during each refueling outage

and

no spurious

actions

were noted during the performance of this testing.

The licensee

used the

DAPPER computer

program to analyze voltages in the

120-Vac system.

The program was used for voltage calculations of portions of

. the distribution network connecting

the 120-Vac buses to various

load groups

ard individual loads. 'he available-voltage

value used

as input for the

DAPPER

calculation

was the result of another voltage study and

a

2 percent correction

factor was used

because

of calculational uncertainties.

The inputs for load

data

and for bus data were taken from vendor supplied manuals for the applica-

ble equipment, while the input for the cable data

was derived from the station

raceway

schedule.

Actual cable lengths obtained through

raceway walkdowns were

used.

Resistances

of fuses

and breakers

were neglected.

Results of the

DAPPER study were validated

by the licensee

against

long-hand

calculations

and were found to be within a margin of 0.2 percent.

An evalua-

tion of the

DAPPER study results

indicated that

some

120-Vac loads

may not be

supplied with adequate

voltage under all design-bases

conditions.

As a result,

the licensee is planning to install 120-Vac regulating transformers

to bolster

the available voltage.

In addition, the licensee is currently evaluating-

changes

to the degraded grid relay setpoints

(see Section 2.10 of this report)

which should also serve to ensure

adequate

voltage at the 120-Vac level.

2.6

250/125-Vdc Class lE System

The 125-Ydc system

has four independent

channel

bus arrangements,

each supplied

from a Class

1E battery

connected

to a Class

1E charger.

These four redundant

and independent

buses

are grouped into two power trains.

Loads

can be trans-

ferred from one channel of the 125-Ydc system to another

channel of the

same

division during service testing of the battery and/or testing of the charger

during

a refueling outage.

During normal operation,

no two battery

systems

are

connected to each other.

The 250-Vdc system

has

two independent

redundant

bus

arrangements,

with each

bus connected

to a Class

1E 250-Vdc battery

and charger

unit.

The specific aspects

of the 250/125-Vdc Class IE system review are

discussed

below.

2.6.1

Voltage Drop

The voltage drop calculations for the 125-Vdc system consist of two parts:

The

first part determined

the voltage drop between

the battery

and the load center,

and the second part calculated

the voltage drop for the circuit network between

the load center

and the Class

1E distribution panel(s).

The resulting values

of the voltages

on the Class

1E distribution panel

were compared to the desired

minimum values required to achieve acceptable

voltages at the terminals of the

Class

lE devices.

Calculation E-AAA-391, Revision 1, "Unit 1 125 Vdc system,"

used conductor

resistance

values derived from tables of the National Electric Code (1990)

and

compensated for a maximum ambient temperature

of 50'C.

Actual measured

cable

lengths

were used

and the end of life (EOL) battery voltage of 105 volts was

used

as the lowest terminal voltage.

Results of these calculations

indicated

that the available

minimum voltage was inadequate for some loads.

To resolve

this problem, the licensee

changed

the

EOL battery voltage from 105 volts to

109.2 volts, and the plant maintenance

group was instructed to include the

new

EOL value in the acceptance

criteria portion of the station battery test

procedures.

The calculations

were recently performed only for the A battery;

however,

the licensee

has

a program to perform such calculations for the

remaining batteries

in the near future.

Voltage drop calculations for the 250-Ydc circuits also consisted of two parts.

The first part computed

the voltage drop between

the Class

1E batteries

and the

250-Vdc motor control centers

(liCCs).

Calculation E-AAA-255, Revision 0,

July 19, 1990,

showed that

a minimum voltage of 210 volts was required at the

HCCs to provide adequate

voltage at the load terminals.

The second part of the

voltage drop was originally done by the architect engineer

who assumed

a

maximum voltage drop of 20 percent

between

the

MCCs and the connected

loads

and

calculated

the maximum cable length of the connecting

cable to achieve the

~ ~

20-percent

drop.

The installed lengths of the cables

were compared to the

allowed maximum length to verify that the installed lengths

were either less

than or equal to the calculated

maximum allowable length.

Calculation E2015.03,

Revision 3, Hay 17, 1983,

"250-Vdc Motor Feeder

Cable

Sizing," and Calculation E2015.01,

Revision 2, April 8, 1983, "Available Fault

and Voltage Drop at Station 125- and 250-Vdc Systems,"

indicated that there

was

no margin between

the calculated

maximum cable length

and the installed

cable length for motor-operated

valve

(NOV) HV-E51-2F013.

In addition,

a

nonconservative

resistance

correction factor of 40'C was used instead of 50'C.

Using the correct value of maximum ambient temperature,

the minimum terminal

voltage at this valve would be lower than that required by the original design.

As a result, the licensee

performed

a

new calculation which demonstrated,

on

the basis of motor current, that the operating torque developed

by the operator

motor at this reduced voltage would be adequate.

The licensee

informed the team that it is aware of problems resulting from

various inconsistencies

in its calculations

and is in the process of recalcu-

lating voltages

using proper temperature for resistance

correction, actual

installed cable lengths,

and

a higher

EOL voltage for the 250-volt batteries.

The current

EOL voltage for the 250-volt batteries is 210 volts, which is

inadequate

to maintain 210 volts at the NCCs.

The voltage drop calculation

indicated that the

EOL voltage of these batteries

must be raised to a minimum

of 220.8 volts to.maintain

210 volts at the YiCCs.

In order to maintain the

battery voltage at 220.8 volts during accident conditions,

some

loads that are

not designated

Class

1E are required to be stripped.

Although the licensee

had

revised

Emergency

Operating

Procedure

EO-100-30 accordingly, the acceptance

criteria for the battery surveillance testing procedures

had not been revised

to change

the value of the minimum acceptable

terminal voltage to 220.8 volts.

The licensee

said that procedures for the surveillance test would be revised in

the near future to include an

EOL voltage greater

than or equal to 220.8 volts.

2.6.2

Battery Sizing/Short Circuit Study

The licensee is currently in the process

of revising old calculations

using

more conservative

bases.

At the time of the inspection,

the licensee

had

completed the revision for the Unit 1 125-Vdc battery

A (Calculation E-AAA-391,

Revision 1) and planned to revise similar calculations for all the remaining

125-Vdc and 250-Vdc battery/charger

combinations.

The calculation for the

A battery

has

a 6.72-percent

margin for its worst-case

loading.

A minimum

electrolyte temperature

equal to 60'F was used

as the basis for the sizing

calculation which was performed in accordance

with the guidelines of IEEE

Standard

485.

The duty cycle from the Technical Specification tables

was used,

which is more conservative

than the actual

duty cycle.

However, the actual

duty cycle calculation did not account for the nameplate

rating of the invert-

ers

and used

a value approximately

equal to 30 percent of the rating. If the

inverters are

loaded

beyond the assumed

30-percent

loading (by a high impedance

fault on its output side),

the condition would go unnoticed

because

there is no

indication or annunciation for such conditions.

The licensee

revised the

sizing calculation to account for the higher potential inverter loading which

reduced

the battery margin from 6.72 percent to approximately

4 percent.

The

team found the revised calculation acceptable.

The short circuit current calculation for the distt ibution network of the

125-Ydc battery

was performed using

a maximum electrolyte temperature

of 90'F,

and the actual

length of the cables.

The team found this approach

conservative

and acceptable.

However, fault calculations for the 250-Vdc distribution

network did not use the higher electrolyte temperature

or the actual

length of

the cables.

During the inspection,

the licensee

revised this calculation using

actual installed cable lengths

and

a temperature

of 25'C and demonstrated

that

the resulting values of short circuit current were still within the ratings of

the breakers

and buses.

2.6.3

DC System Overvoltage

During regular maintenance

and after periodic testing,

the station batteries

are

charged with an equalizing current while the batteries

are connected to the

dc distribution system.

On-line equalizing

imposes

a higher voltage

on equip-

ment connected

to the load side of the system.

The voltage could be as high as

142.8

Ydc for the 125-Vdc system

and 285.6

Vdc for the 250-Vdc system.

Overvoltage

could shorten

equipment life and could prevent the affected equip-

ment from performing its intended design function.

In 1985 the licensee

had

a

consultant

perform an evaluation of the effects of such overvoltages

on the

capability of Class

IE dc system equipment.

The study indicated that the

following equipment

could be affected

by overvoltages.

DC Cutler-Hammer Rela s:

Normally closed contacts of these relays

have

been

used

or

ypassing

the thermal overload trip contact of Class

1E

motor-operated

valve

(NOY) circuits.

These

normal,ly deenergized

relays

are energized

during periodic testing of NOYs to allow the valve motor to

be tripped in the event of an overload condition.

Because failure of this

relay at any time would keep the bypass active

and would not have

any

affect on the safe

shutdown capability of the systems,

the licensee

has

not taken

any corrective action for these relays.

250-Vdc

Pum

Motors:

The list of the affected motors consists

of Class

1E

motors

an

a

ew non-Class

1E motors.

These motors are nominally rated

for an operating voltage of 240 Vdc and could be degraded if operated with

an overvoltage condition for an extended duration.

As a corrective

action, the licensee

revised the

EOPs to restrict operation of these

motors during battery equalizing.

However, this measure

is not effective

for the 1P215 high-pressure

coolant injection and 1P220 reactor core

isolation cooling condenser

vacuum

pump motors which are started automati-

cally, therefore,

the licensee

intends to implement additional corrective

action for these motors.

To az Inverters:

These

Class

1E inverters supply 120-Yac power to instru-

ments require

for post-LOCA monitoring.

The inverters were specified for

an input voltage of 105 to 140 Ydc.

Higher input voltage could damage

and

disable the inverters.

In its

stu@

, the consultant

recommended

that the

maximum setting for the high voltage

be reduced

and annunciation for this

condition be provided.

The licensee

lowered the high-voltage setting but

did not provide any alarms to indicate tripping of inverters

as

a result

of overvoltage conditions.

Westin house

Rela

s MG-6

SG

and AR:

These relays are used

as auxiliary

re ays in

C ass

1E contro

circu ts.

The study indicated that exposure to

over voltages

could shorten the life of these relays from 40 years to

17 years

and

recommended

replacement within this time.

The licensee

does

not have any program to track and replace

such relays, but intends to

issue

an engineering

work request

(EWR) in the near future to expand its

equipment qualification program to track and replace

the affected relays.

Circle Seal Solenoids:

Circle Seal

solenoid valves were specifically

manu acture

or 125-Vdc operation

and were qualified for a life of

40 years.

The maximum and minimum voltage ratings for these

solenoids is

plus or minus

10 percent,

and they were subjected

to a maximum of 130-Vdc

during qualification testing

by the valve vendor.

The overvoltage

evaluation

study indicated that these valves should be replaced.

The

licensee

has replaced

two of the three valves identified.

Since the third

valve would be required only after shutdown of the plant, the licensee

has

decided to replace the third valve at

a later date.

Backdraft Isolation

Dam ers:

The

ASCO solenoids for the isolation dampers

were qua i

e

or a maximum of 140 Vdc.

Nonconformance

Report

(NCR)84-994 dated August 14, 1984, indicates that these short-duty-rated

solenoids

are continuously energized

because

of their location and could

fail with no prior indication.

The study

recommends

replacement of these

solenoids.

The licensee

does not have

any program to replace

these

solenoids,

but intends to issue

an

EWR for replacement of the solenoids

for affected isolation dampers

in the near future.

2.6.4

Motor Control Center Circuit Breakers

During a walkdown, the team noted spare

breakers

in the 250/125-Vdc control

centers

and load centers

were left in the drawn-out position as

a permanent

arrangement.

This partially drawn-out position of the breakers

is a configu-

ration that was not analyzed for seismic forces.

In response

to the team's

concern,

the licensee

racked in all spare

breakers

in the respective

breaker

cubicles until further analysis is completed regarding

seismic qualifications

of the affected

load centers.

This item is identified as

Open Item 90-200-04

in Appendix A to this report.

The team also noted that 250-Vdc load center breaker

(GE AK 2-25) nameplate

rating is only 250-Vdc.

The team, raised

a concern regarding the qualification

of the breaker during higher voltage conditions of float/equalize voltage

(264-285

Vdc)'.

Subsequent

discussions

with the licensee

and with the manufac-

turer showed that the 250-Vdc nameplate

value is nominal,and the breaker is

rated for 300-Vdc maximum.

2.7

Protective Coordination

Adequate protection

and coordination

was generally found for the 480-Vac

circuits, including feeders for a non-Class

1E load connected

to a Class lE bus

and for a Class

1E load from a Class lE bus.

Coordination

between

the down-

stream breakers

and the upstream

load center breakers

and trip settings

was

adequate

for the non-Class

lE load turbine bui lding stack vent vacuum

pump

~

~

1P160.

Coordination of the downstream breakers,

the upstream

load center

10

~

~

b'reakers,

and with the 4160-Vac switchgear breakers

and the trip settings

was

acceptable for the Class

1E load to

RHR pump sunction shutoff valve

HV-E11-1F009.

The principles governing the settings of the electrical protective devices

were

listed in design basis calculation

DBC-1 "Electrical Protective Devices."

The

protective relays were generally set

so that normal load would not exceed

80 percent of the relay setting range, to allow for drift and other tolerances.

The protection

was set to stay within the long term and emergency rating of

cables

and transformers.

Motor overload relays,

where not blocked, were set

not to trip during acceleration

and operation of motors with terminal voltage

equal to 100 percent or 80 percent of nominal.

The relays were set to account

for both the reduced voltage

and the motors'ervice factor of 1.15.

Mhen a non-Class

lE load was energized

from a Class lE MCC there

was

no coordi-

nation between

the two breakers

in series [e.g., in MCC 1B216 breakers

81 (1E)

and

52A (non-lE)], but there

was full coordination

among either of the two

breakers

and the

LC breaker feeding the

MCC, which agreed with FSAR Section

8.1.6.1.H.5

and Calculation

DBC-1.

The ground fault protection of the 480-Vac lE system

had been blocked

due to a

lack of coordination

between various protective devices.

The 480-Vac distribu-

tion system

had

a solidly grounded neutral.

However, the circuit breakers

(CBs) rated less

than

50 amperes

or motor starters

rated less

than the National

Electrical Manufacturers Association's

(NEMA) size

2 in the MCCs, did not have

a ground fault protection (device 50/G),

and the magnetic trip units on these

CBs had been set higher than the setting of the ground fault protection of the

LC CB feeding the

MCC.

Since this had effectively eliminated the possibility

of maintaining coordination

between

the two protective elements,

the ground

fault protection in the

LC had been blocked.

This created

a situation where

the fault on loads fed by those

flCC circuits must be cleared

by the overload

protection device, or the magnetic trip element in the

CB, after the fault

persisted

long enough to change

from phase-to-ground

to phase-to-phase.

However, this may not work in case of an arcing ground fault with the fault

current lower than the setting of the CB's magnetic trip.

The licensee indi-

cated that the blocking of the ground fault protection at the

LC level was the

original decision taken

as part of a policy that low voltage ground fault

protection

was

done primarily for economic reasons.

The team accepted

the

licensee's

position on this point.

2.8

120-Vac lE Distribution System

t)o deficiencies

were found in the protective coordination of the 120-Vac

Class

1E system

and the control power circuits wer e adequate.

The portion of

the 120-Vac Class lE system

used in control

and annunciation circuits is

supplied from a 480-Vac Class lE MCC through

a 480-208/120-Vac transformer

and

is an interruptible system.

The 120-Vac single-phase

system

was protected with

circuit breakers

in the main power distribution panels.

The circuit breakers

supplied

power to fuse distribution panels.

The system

was arranged hierar-

chically with up to four protective devices in-line from the main distribution

panel to the individual control and annunciation circuits.

The protective

devices

were selected

in a sequential

manner (i.e.,

a 20-ampere circuit breaker

fed

a circuit with a 10-ampere

fuse that fed a number of circuits with 6-ampere

11

fuses that fed a number of circuits with 3-ampere fuses.)

The. licensee indi-

cated that there were

no requirements for, and

no coordination between,

those

fuses for response

to fault currents.

The criteria for selecting

the fuses

had

been strictly for the protection of circuit integrity during overload condi-

tions.

Additional fuses

were installed in the grounded neutral wires for

circuits going through containment penetrations

to provide redundant

overload

protection.

Bechtel Calculations

E2010.04,

Revision 1, and E2010.05,

Revision 0, provided

design

guides for selecting

maximum allowable length of wires

(AWG 14)

and size

of control transformers

(depending

on the

NEHA starter size

and the number of

relays) in the

HCC control circuits.

The wires and control transformers

were

selected

to maintain the voltage at above the minimum pickup voltage of 102-Vac

for all devices.

Calculation E2010.04 allowed

a 20-percent

margin in the

length of the control circuit.

Host, but not all, of the lengths of the wires

in the control circuits had been verified to an as-built condition.

Even

though the design guides did not provide verification of the actual design,

this approach of documenting

the sizing of the control transformers

and voltage

drop study was acceptable.

The licensee

had

a procedure to verify the length

of wires in a control circuit whenever the circuit was modified.

The control transformers

selected

using Calculation E2010.05

had sufficient

capacity.

The criteria listed in the calculations

were valid for steady state

conditions.

During transients

such

as starting of large loads,

the

HCC bus

voltage could dip below 432-Vac and the control circuit voltage could be below

the relays

and contactors

pickup voltage; therefore, it would not be possible

to successfully start

HCC loads until the voltage recovered

to the 432-Vac

level.

The licensee

stated that sufficient indication was available in the

control

room to alert operators of such

a condition and that the

HCC loads

would either automatically attempt to restart or would be restarted

by an

operator after the bus voltage

had recovered.

This explanation

was accepted

by

the team.

2.9

Penetration

Sizing

The 4160-Vac system penetration protection for the reactor recirculation

pumps

feeder

and the 480-Vac system penetration

protection for the hydrogen

recombiner were reviewed

by the inspection

team.

The values of maximum short

circuit currents

and settings of breaker trips for these penetrations

were

acceptable

to the team for penetration protection.

2.10

Degraded

Voltage and Loss of Voltage Relays

The Susquehanna

degraded grid and loss of voltage protective

scheme

consists of

different levels of protection to preclude

equipment

damage

and to transfer

Class

1E loads to the emergency

power supply whenever the available voltage to

the Class

1E 4160-Vac buses is not sufficient to power the required safety

loads.

Each 4160-Vac bus is provided with undervoltage

relay protection to

either transfer

loads to the alternate

power source or to the emergency

diesel

generators

(EDGs).

The following relays are used to provide these

levels of

protection:

12

~

~

~

Undervoltage relay 27AI is set at 96.5 percent of the nominal

bus voltage

to monitor the availability of the incoming offsite power supply.

This

relay also is used to initiate an alarm after

a 10-second

delay.

Undervoltage relay 27A initiates

a bus transfer to the alternate

power

source

on a loss of voltage to the 4160-Vac buses.

It is set to drop out

at 20 percent of the rated

bus voltage.

If the alternate

power source is

not available,

the

EOG is automatically started after

a 0.5-second

delay.

Undervoltage relays

27B1, 27B2, 27B3, and 27B4 provide backup protection

for initiating bus transfers

and undervo'itage

alarms if degraded

voltage

conditions occur.

Devices 27Bl and 27B2 are set to drop out at 84 percent of rated

bus voltage

and initiate an alarm after

a 10-second

delay.

If the degraded

condition

exists with no

LOCA signal present,

the relays will initiate a bus transfer

after a 5-minute delay.

The delay is provided to allow sufficient time for

operator action to restore

the voltage to acceptable

levels. If the degraded

condition exists with a

LOCA signal present,

the relays will initiate a bus

transfer after

a 10-second

delay.

The 10-second

delay is provided to prevent

motor starting transients

from initiating undesired

bus transfers.

Devices

27B3 and 27B4 are set to drop out at 65 percent of rated

bus voltage

and initiate a bus transfer after

a 3-second

delay.

The setting

and delay is

provided to prevent

bus transfers

during voltage dips that can result from

fault currents that

can occur prior to overcurrent relay operations.

Degraded voltage and loss of voltage protection

schemes

are provided to prevent

spurious trips of the offsite power supplies,

to provide protection for equip-

ment operating at low voltages

so that the equipment will not be damaged,

and

to ensure that equipment

can operate at the lower voltages to perform its

design functions during design-basis

events.

The undervoltage

setpoints

determine

the level of reduced voltage at which the 4160-Vac buses

are isolated

from the offsite power system

and are connected to the

EDGs.

Therefore,

the

relay settings

should be set

so that the safety-related

equipment is able to

perform its intended functions under conditions that are above the undervoltage

setpoints.

During a previous inspection,

the

NRC noted that the licensee's

undervoltage

protective

scheme for the 4160-Yac buses

allows the system voltage to be

significantly lower than the nominal value for the buses without the

undervoltage

relays actuating (i.e., at 84 percent).

The licensee

subsequently

determined that approximately

93 percent of rated

bus voltage must be available

at the 4160-Vac buses to ensure that all safety-related

equipment

has suffi-

cient voltage to operate.

Therefore,

the current relay setpoints

do not

provide sufficient protection to ensure that all equipment will operate

during

degraded

voltage conditions during which the available voltage is less than

93

percent but greater

than 84 percent.

The licensee's

original basis for these

relay setpoints

was based

on the assumption that all postulated

system distur-

bances either at the grid or within the plant would result in actuating

the

protective

scheme relays.

Therefore,

considering

the desire to minimize the

probability of spurious trips of the offsite power supplies,

the relay

setpoints

were

chosen at the present

value.

13

~

~

In Hay of 1990, the licensee identified a condition in which a single failure

~

~

~

~

~

~

~

~

~

~

~

~

during

a

LOCA could result in degraded

system voltages without the undervoltage

protection relays actuating.

This condition could occur

when all Class

1E

buses

are supplied from one startup bus.

The licensee

evaluated

the postulated

event

and concluded that the probability of the event was minimal because

the

Susquehanna

power system is very stable.

Furthermore,

the'icensee

contended

that the postulated

single, failure had to occur during

a very narrow timeframe

at the beginning of a

LOCA to cause

a degraded

voltage condition and the

probability of this event was very low; therefore,

no immediate action was

necessary

and the condition was determined

not to be reportable to the

NRC

under the criteria of 10

CFR 50.72 or 50.73.

During this inspection,

the team

became

aware of the significant number of Class lE loads at the 480-Vac and

120-Vac buses that would not operate

dur ing the postulated

event.

The licensee

was requested

to provide

a safety

assessment

addressing

the adequacy of the

current undervoltage

protective

scheme to enable

equipment to perform its

intended functions.

The licensee

stated that

a detailed study was in progress

and that the following actions

are planned in the interim to minimize the

probability of being in a sustained

degraded

voltage condition:

The dropout setpoints for 27Bl and

27B2 undervoltage

relays will be

increased

from 84 percent to a yet undetermined

value.

The 27B3 and 27B4

dropout setpoints

also will be increased

from 65 percent to a yet undeter-

mined value.

These setpoints will be based

on the results of an ongoing

voltage study.

The time delays for these relays are expected to remain

the

same.

The licensee

committed to submit

a technical specification

change

request

to the

NRC by September

30, 1990.

Operation procedures

have been revised to incorporate additional operator

actions to be taken if the 96.5-percent

undervoltage

alarm is received.

These actions include:

If the undervoltage

alarm is received

and the alternate

power supply

is available,

the operators

wi 11 initiate a transfer to the alternate

source.

If the undervoltage

alarm is received

and the alternate

power supply

also is in a degraded

condition, the operators will initiate manual

start of the

EDG.

After the

EDG has reached

rated

speed

and voltage,

the operators will initiate a loss of voltage to the affected

4160-Vac buses

by tripping the normal feed circuit .breakers,

which

will result in the

EDG automatically closing its output circuit

breaker onto the 4160-Vac bus thereby restoring

power to the bus.

The above operator actions

were incorporated into operator

procedures

during

this inspection.

Though these corrective actions collectively provide greater

assurance

that

equipment will be able to perform their intended functions with a stable

power

supply from either offsite or emergency

sources, it does require operator

actions,

which is an undesirable

method to ensure

equipment functionality upon

14

receipt of the

LOCA signal.

This item is identified as Unresolved

~

~

Item 90-200-05

in, Appendix A to this report.

3.0

MECHANICAL DESIGN

The team review included

a walkdown of the reactor building heating, ventila-

tion, and air conditioning

(HVAC) system

and detailed review of engineering,

licensing,

and plant operations

documents

associated

with mechanical

systems

in

support of the

EDS, including the following:

The

HVAC systems that provide the required operating

environment for the

safety-related

equipment.

This included local air coolers for high-

pressure

coolant injection (HPCI) and core spray

pumps,

the ventilators

for the diesel

generator

rooms

and the pumphouse

[housing the essential

service water

(ESW) and residual

heat

removal service water

(RHRSW)

pumps],

and the battery

room and emergency

switchgear

room

(ESWGR)

HVAC

systems

including the interfacing control structure chilled water system

and the dedicated direct expansion

(DX) units for the Unit 2

ESWGR HYAC.

The power demands for major loads required

by the core spray,

ESW,

residual

heat removal

(RHR), and

RHRSW pumps following a

LOOP.

The ability of the

ESW to provide cooling to safety-related

equipment

following a design-basis

event.

The ability of the diesel generators

to provide the standby

power supply

required to operate

the safety-related

equipment

needed for a safe plant

shutdown following a design-basis

event, including the following auxiliary

systems:

fuel oil supply

lube oil supply

jacket water cooling

air start

combustion air intercooler

In addition, the assumptions,

input data,

design bases,

methodology,

and output

results of selected

calculations

were spot

checked for consistency

between

design

documents

and the thoroughness

of the major electrical

loads

on the

diesel

generator

buses

and

compared to the load lists in the design

documentation.

3.1

Heating, Ventilation, and Air Conditioning Systems

The licensee

found that

a single failure of an

NCC could prevent all venti la-

tors in one train of the

ESW pumphouse.from starting, which would prevent

cooling for the

ESW and two

RHRSW pumps.

However, further analysis

indicated

that if the operator were to manually open the pumphouse

louvre vents within

5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> of the event, natural circulation would remove

enough heat to prevent

motor failures, but the resulting

pumphouse

temperature

would exceed

the limit

in the

FSAR.

Therefore,

pending completion of the Engineering

Work Request

(EWR) H80540, the licensee

plans to update the design documentation

and

FSAR.

15

During a walkdown of local

room coolers,

the team discovered that the thermal

insulation

had been

removed from the

HPCI pump, booster

pump,

and crossover

piping.

The licensee

determined that this insulation was

removed for mainte-

nance in July of 1984

and inadvertently

was not reinstalled.

In addition, the

calculation of the heat

load for the

HPCI

pump room had not been revised to

analyze the effect of the additional heat load.

This item is identified as

Unresolved

Item 90-200-06 in Appendix A to this report.

Limiting conditions for operation

(LCO) are not delineated for HVAC systems

because

these

systems

are not explicitly addressed

in the Technical Specifica-

tion.

The unavailability of an

HVAC system could limit the ability of the

associated

safety-related

equipment to perform its function.

During a walkdown

of the Unit 2

ESWGR

HVAC equipment,

the team noted that the loop

B direct

expansion unit was out of service for maintenance.

Although only one division

was available,

no specific outage times, limiting conditions, or compensatory

measures

had been established.

In addition, although the unavailability of the

reactor building circulation fans could impair the performance of the standby

gas treatment

system,

no procedures

had been generated

which would govern the

acceptable

outage

times for these

components.

The team considered that appt o-

priate procedures

should be provided for the acceptable

outage

times of one or

both trains of support systems,

which are not specifically addressed

by the

plant technical specifications.

During the inspection,

the licensee

provided

Technical Specification Interpretations

(TSI) for the

ESSM ventilation and

Control Structure

HVAC.

A team work plan was also provided which forms the

basis for an internal process

of prioritizing work on critical equipment.

This

is the procedure

used to expedite work on the non-technical

specification

equipment listed above until the TSIs, which are currently under development,

are completed

and issued.

3.2

Power Demands for Major Loads

Although the power demands of the major pump motors powered

by the diesel

generators

following a

LOOP were generally

adequate for the core spray,

ESW,

RHR, and

RHRSW pumps,

the following concerns

were noted.

There are four ESM

pumps,

each of which deliver 50 percent of the required flow.

Two pumps are in

each division of the

ESM system.

Each

ESW pump is powered from one of the four

diesel generators.

The latest revision of FSAR Table 9.2-3 indicates that when

both

pumps are operating in parallel, the system flow is 9800

gpm (4900

gpm per

pump).

Each

pump requires

410 bhp in this mode of operation.

If only one of

the two

ESW pumps in a loop starts,

the flow through the

pump increases

to

approximately

7600

gpm.

The

pump power is about

503 bhp under these

condi-

tions, exceeding

the 450 bhp (rated motor power)

assumed for the diesel

genera-.

tor loading.

Consequently,

the single failure of one

ESM pump could cause

increased

loading on the diesel generator

which supplies

the other

ESW pump.

Although the team felt this oversight should be corrected in the

FSAR diesel

generator

loading tables,

the power demands for other loads were sufficiently

conservative to compensate

for this oversight.

The second

concern

was that

with three out of four ESM pumps operating,

a required

mode of operation,

the

motor is at 110 percent of its rated capacity of 450 bhp.

Although this

operating

mode is considered

marginal, it is acceptable

because

the motor is

designed with a minimum 15 percent

margin and the motor protective devices

are

16

~

~

set at

a minimum of 132 percent of the maximum load at rated voltage

and are

not expected to trip under this load.

The four core spray

pumps are arranged

in two loops, with two pumps that can

each deliver 50 percent of required flow in each

loop. If only one

pump in a

loop starts, it is estimated that the

pump would produce approximately

150 percent of its normal flow.

The net positive suction

head

(NPSH) required

by the

pump increases

to about

17 feet, which exceeds

the

HPSH available in the

system.

Operation of this large

pump (700 bhp) under cavitating conditions

could result in excessive

pump vibration and extensive

damage to the piping

supports,

and the potential for damage is increased

by the relatively low

operating

temperatures

of less than 250'F.

However, Operating

Procedure

OP-151-001

does caution the operator against the high system flow rates

and

instructs the operator to throttle the

pump discharge

valve to limit system

flows to 7900

gpm with two pumps

and 3950

gpm with one

pump per loop.

The team

agreed that the damage, if any, would be limited to one loop only, which is

within the design basis of the plant.

3.3

Emergency Service Water System

The

ESW system

draws water from a reservoir .to provide cooling to Class

1E

equipment.

Little can be done to control the water chemistry in an open-loop

cooling water system.

Furthermore,

the

ESW system is normally in a standby

condition; therefore,

sedimentation

can occur

as

a result of stagnant

cooling

water left in the piping and heat exchangers.

As a result,

excessive

fouling

of the heat transfer surface

(0.003 hr-ft'-'F/Btu versus

0.002

as originally

specified)

and tube plugging of tubes

(due to wall thinning caused

by erosion,

corrosion,

and buildup of sediments),

can decrease

the capacities

of the heat

transfer equipment serviced

by ESW.

The licensee

has evaluated

the maximum allowable

number of plugged tubes in

procedure

t31453

on the basis of the actual

heat exchanger

performance at the

site.

When the number of plugged tubes for the

D emergency

diesel generator

jacket water cooler

exceeded

the allowable limit of 4 percent,

the licensee

issued

Nonconformance

Report

HCR 90-0117

and stated that the tube bundle will

be replaced

next year (1991).

The licensee

did not evaluate

the allowable

number of plugged holes for the condensers

that were purchased

as part of a

commercial

package to account for the increased fouling, which was in excess of

the fouling assumed

in the original design.

Increased fouling is of particular

concern in applications with two-phase

heat transfer in which fouling can be

the dominant parameter

in the relatively high overall heat transfer coeffi-

cient.

Currently,

5 to 6 percent of the tubes in the

CSCW system

condenser

are

plugged,

and 4 percent of the tubes in the direct expansion unit condenser for

the Unit 2

ESWGR

HVAC system are plugged.

The effects of increased fouling and

the reduction of available surface

area

as

a result of tube plugging could

affect the operability of these

components

and hence the operability of the

Class

lE equipment

supported

by them.

The licensee

has

committed to evaluating

the surface

area available in the

CSCW

system

condenser

and assessing

the operability of the equipment affected

by the

number of tubes

plugged to date.

In addition, if the assessment

of CSCW

condenser

proves to be marginal or unacceptable,

the licensee

committed to

perform a similar assessment

of the equipment affected

by the direct expansion

17

unit condenser for the Unit 2

ESMGR HVAC.

This item is identified as

Unresolved

Item 90-200-07 in Appendix A to this report.

The sections of ESW piping between

the supply

and return isolation valves to

each diesel generator

and the secondary

side of the emergency

diesel

generator

(EDG) auxiliary coolers (intercoolers,

jacket water cooler,

lube oil coolers,

fuel oil cooler) are not protected

from overpressurization

as required

by the

ASHE Code Section III, ND-7000.

The

ESM system

has capacity to provide cooling

to four of the five EDGs.

As

a result, the standby unit is isolated from main

ESM piping and the isolation valves are normally closed.

Under the following

operating conditions,

energy is added to the isolated section of the system

and

overpressurization

could occur.

To minimize the time required to place

an

EDG back in service,

the standby

lube oil and jacket water heaters

and circulating

pumps are operated

to

prewarm the equipment while the

ESW valves are closed to isolate the

cooling water.

Overpressurization

of that section of the piping has the potential to impair

both loops of the

ESW system since

common connections

from both the A and

B

loops are provided to each diesel generator.

The license

has committed to

performing procedural

or hardware modifications as necessary

to eliminate the

overpressure

concerns.

This item is identified as

Open Item 90-200-08 in

Appendix A to this report.

The

FSAR states that the two independent

loops of ESW are separated

by barriers

and trenches.

The PAID shows

two pipe trenches,

each with a supply and return

line for one loop, running outside the diesel

generator

rooms

and branch lines

from each

loop entering

each diesel generator

room.

However, during

a walkdown

of the diesel generator

rooms, the team noted that this

1oop separation

had not

been provided.

The four pipes

(two supply and two return lines) run beside

each other from one diesel generator

room to the other in the basement of the

diesel generator

rooms.

The licensee

stated that the design documentation

and

FSAR would be updated to reflect the as-built configuration.

3.4

Diesel Generator

and Auxiliary Systems

An actuated

control valve with a temperature

feedback

loop was recently

added

to the

ESW return line from the diesel generator intercooler.

A downstream

butterfly valve is used

as

a throttling valve.

The butterfly valve flapper is

fixed in a permanent position to ensure that other

ESW loads are not affected

if the temperature

control valve fails open.

During

a walkdown of this modifi-

cation, the team heard cavitation noise in the piping near

the throttling

valve.

The vibration and erosion associated

with the cavitation process

could

result in potential failures in these

valves

and downstream piping.

The

licensee

is planning to disassemb'le

this section of piping and to inspect the

temperature

control valves

(TV-01124A-E), the butterfly valves

(011042, 44, 46,

68,

and 011509),

and the associated

downstream piping for indications of

excessive

erosion

and to inspect the butterfly valve stem for fatigue damage.

18

The licensee

was in the process

of revising the Technical Specifications

and

associated

operating

and surveillance

procedures

to ensure

the instrumentation

setpoints

and normal

day tank fuel levels were in accordance

with NRC

Regulatory

Guide 1.137

and ANSI Standard

N195

(ANS 59.51).

The ANSI standard

requires that the day tank have

enough fuel below the fuel transfer

pump start

level setpoint to allow the diesel generator to operate for a minimum of 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />

at 110 percent of its rated capacity.

The team identified two areas of concern

with the calculations for the level setpoints.

The required fuel capacities

are based

on

a specific fuel consumption rate

(BTU/BHP-hr) as verified by the manufacturer's

test results.

The quantity of

chemical

energy required for 1-hour operation at 110 percent rated capacity is

converted to an equivalent

volume that can be verified in the field.

The

licensee

advised that the fuel oil can range in specific gravity from 0.82 to

0.95, with an associated

range of heat content,

BTU/gallon.

The day tank

capacities

have

been calculated

using

a median specific gravity of 0.87 which

is not conservative.

Furthermore,

the quoted specific gravities are for fuel

at 60'F.

Accounting for thermal

expansion of the fuel to typical operating

room temperatures

(100-105'F)

could require another

2 percent in the required

capacity.

The licensee

committed to a thorough review of the day tank calcula-

tions and setpoints

to resolve these

issues.

During

a walkdown of the five diesel generators,

the team identified inconsis-

tencies

on the nameplates

of the diesel

motors

and the generators.

For exam-

ple, the 2000-hour rating was not given on the nameplates for diesel

generators

A through

D.

The Instruction and Operating

Manual states

the

2000-hour rating is 4700

kW.

The licensee

was able to confirm with the manu-

facturer that the peaking

power for the A through

D diesel

motors is equivalent

to the 2000-hour rating.

The manufacturer also provided information to justify

the 4700-kM 2000-hour rating for generators

A through

D.

Although the name-

plate data

was incomplete

and did not reflect the design requirements for the

equipment,

the actual capabilities

of the components

were satisfactory.

The

FSAR shows diesel generator

loading following an accident

as high as

4400

kW, (which is 110 percent of the rated capacity of diesels

A through D).

The team felt that the intent of the day tank sizing criteria in ANSI Standard

N195 was not satisfied

by calculating the fuel requirements

based

on the

nameplate rating when the normal operating condition exceeds

the rated value.

The team expressed

their opinion that the 2000-hour rating (i.e., the nominal

rating applicable for the post-accident

operating conditions) or, as

a minimum,

the maximum diesel

loading to be sustained for at least

1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />, should be used

instead of the nameplate rating for determining the day tank capacity.

Although the team disagreed

with the way the diesel

day tank levels were deter-

mined,

no specific safety concern

could be identified with this issue.

The Technical Specification

bases for diesel fuel testing includes the guidance

of Regulatory

Guide 1.137.

Regulatory

Guide 1.137 states that prior to adding

fuel to the fuel storage

tanks, testing should

be performed to evaluate

the

fuels specific gravity, water content,

sediment content,

and viscosity.

The

licensee

s technical specification (4.8.1.1)

and diesel fuel oil handling

procedures

(SC-023-001)

did not include the requirement for testing the

specific gravity of the sample.

The licensee

has agreed to update the testing

requirements.

19

The portion of the diesel

generator

fuel supply system below ground level and

in the diesel generator

room is seismically qualified and protected

from damage

by a tornado.

However, the fuel storage

tank vent and its associated

flame

arrester is not qualified for these

design-basis

events.

There are two failure

modes of concern:

1.

If the vent is crushed,

a vacuum would be created

in the tank as fuel is

transferred

to the day tank.

As the available

NPSH falls, the transfer

pump cavitates

preventing further flow of fuel to the engine.

2.

If the vent is broken off, debris would enter the opening into the tank

and block the transfer

pump inlet.

In addition, there would be

a poten-

tial fire/explosion hazard

because

of the loss of the flame arrester.

In response

to this concern,

the licensee

said that the overflow line from the

day tank to the storage

tank would provide

a vent for the storage tank.

In the

case of diesel generator

E, there is a 2-foot trap in the overflow line.

Even

with the partial

vacuum required in the storage

tank to clear this trapped

fuel, there is sufficient NPSH available for continued transfer

pump operation.

The licensee believed that the probabi lity of debris entering the storage

tank

through

a broken vent stack

was very low and the layout of pump suction line

would inhibit debris from enter ing the

pump suction line, which is further

protected

by a strainer.

In addition,

a temporary flame arrester

would be

installed over the opening before trucks or other ignition sources

were allowed

in the vicinity of the storage

tanks.

The team found this explanation

acceptab le.

Contrary to the

FSAR, the level indication and low level annunciators for the

diesel fuel oil storage

tanks are not being continuously monitored or indicated

in the diesel generator building.

The licensee is currently using

a dip-stick

method to check level in the five diesel fuel oil tanks monthly and following

each diesel start.

This item identified as Unresolved

Item 90-200-09

and is

discussed

in further detail in Appendix A.

3.5

Fire Protection

System

The fire protection

system is not seismically qualified.

Although the sprin-

kler pipes are normally air filled, the deluge valves

and related controls are

not seismically qualified and can be assumed

to fail.

Therefore,

nonqualified

sprinkler systems

could spray Class

1E electrical

equipment following a seismic

event.

The team requested

that the licensee

demonstrate

that the fire protec-

tion system would not impair the operation of the diesel generators

following a

seismic event.

The licensee

provided

a summary sheet of the activities conducted

in accordance

with Bechtel Specification 8856-f)-388, which was

a guide for assessing

the"

effect of failures of equipment that is not safety-related

on Class

1E equip-

ment.

The diesel generator

room signoff sheet stated that the fire protection

system

was designed

and installed in accordance

with Bechtel Specification

N-343, which thus ensured

the integrity of the piping.

However, the team

found, that the spacing of many pipe supports

exceeded

the allowable spans

given in Appendix

B of the specification

by 50 to 100 percent.

The licensee

performed calculations for these

nonconforming sections of pipe, taking into

20

I

0

account the water filled pipes,

the stress

intensification for threaded joints,

the seismic accelerations

with 2 percent

damping,

and the as-built spacing.

These calculations

indicated the stresses

to be below the maximum allowable.

The team was concerned that the guideline practices

used to design

a system

were not followed for many of these

pipe supports.

The licensee

confirmed that

an engineering

discrepancy

report

(EDR G00154)

had been

issued to revise the

specifications

and drawings to reflect the as-built layout.

This item is

identified as Unresolved

Item 90-200-10 in Appendix A to this report.

4.0

ELECTRICAL EQUIPMENT TESTING AND SURVEILLANCE

As part of its overall evaluation of the electrical distribution system,

the

team performed

a review of selected

testing

and surveillance

procedures

related

to the diesel generators,

the batteries,

the Class

1E inverters, circuit

breakers,

and relays.

In addition,

a review was conducted of the licensee's

fuse control.

Details of these

reviews are contained

below.

4.1

Diesel Generator Testing

The diesel generator testing procedure for classifying starts

as valid or not

valid did riot specifically address

the case of a maintenance

run.

The licensee

currently classifies

successful

maintenance

runs

as valid tests to reduce the

number of starts that the diesel is subjected to.

This is acceptable

as

long

as failures of maintenance

runs are also classified

as valid tests if the

failure results from a problem not related to the maintenance activity and if

the failure would have prevented

the diesel

from performing its emergency

function.

A failure of a maintenance

run should not automatically

be classi-

fied as

a non-valid test simply because it was

a failure.

A review should

be

conducted of test failures of maintenance

runs

and otherwise to determine if

the failure was part of a valid test or not valid, and this review should

be

adequately

documented

in the diesel start logs.

The licensee

has

agreed to

revise its diesel test procedures

to clarify this issue.

The readings of insulation resistance

and polarization index from insulation

resistance

tests

on the generator windings were compared to the minimum accept-

able values

and recorded.

However, there

was

no trending of the results,

which

could be beneficial to tracking insulation life deterioration

and predicting

remaining life.

4.2

Setpoint Calculation

and Control

The licensee's

program for establishing

and controlling safety-related

instru-

ment setpoints

is described

in Nuclear Department Instruction NDI-QA-15.2.9,

"Setpoint Selection

and Control." It delineates

the responsibilities of the

groups responsible for establishing

and controlling setpoints.

The nuclear

plant engineering

and system operation

groups

share

the responsibility for

establishing

setpoints for various instruments

depending

on the system voltage

level.

Setpoint

changes

are required to be evaluated for their effect on the

FSAR, Technical Specifications,

and design description

documents.

Setpoint

change

packages

(SCPs)

were developed

as

a means of controlling instrument

setpoint

changes.

Relaying setting

change notices

(RSCNs)

wer e the design

21

E

~

l

~

output documents that provide the controlling means for ensuring that setpoints

are maintained in accordance

with their bases.

Setpoint criteria for electrical devices

were established

and described

in

various relay section calculations

(DBC-1,2,3).

These calculations specified

the setpoint criteria for protective devices to protect electrical equipment,

such

as motors, timers,

and undervoltage

and overcurrent relays,

through

selective tripping of loads.

These criteria were used to establish

setpoints

in setpoint calculations.

The calculation results

were transferred

to relay

setting

change notices

(RSCNs) that are

used to maintain

and control instrument

setpoints.

Once

a device requires testing or calibration, the applicable

RSCN is reviewed

to note the previously calculated

required relay setpoint.

This information,

along with applicable tolerances,

is translated

into the applicable calibration

procedure

data sheet before calibration.

The data sheet requires that as-found

and as-left data

be recorded.

The team reviewed relay calibration records to verify that the device setpoints

conformed to the specified setpoints

in setpoint calculations.

The setpoints

were specified along with a tolerance

band for acceptable

values.

The as-left

setpoints

were within this specified tolerance

band.

However,

8 of 16 data

sheets

reviewed for both undervoltage

timers

and overcurrent relays indicated

that. the as-found settings

were outside the setpoint tolerance

band.

These

settings

ranged from+2.8 to -21 percent

beyond the tolerance

band.

Although

these

readings

were outside the specified tolerances,

there

was

no evaluation

to determine the cause for the instrument drifts.

The licensee

stated that

there

was

no formal program for evaluating

instrument drifts to identify

instruments that may require more frequent calibrations.

Additionally,

operability determinations

have not been

made for those instruments

in which

the excessive drifts could have

compromised their safety functions.

This item

is identified as Unresolved

Item 90-200-11 in Appendix A to this report.

The setpoint for all 27A undervoltage

relays is required to be 24 volts.

One

of the 27A relays installed in the Unit 2 4160-Vac bus 20104

was of a different

type and had

a manufacturer's

setpoint

band of 36-45 volts.

The licensee

installed this relay and adjusted

the setpoint to 24 volts.

The manufacturer's

setpoint

band envelopes

the settings at which the relay can be set

and still

perform as desired with accuracy

and repeatability.

Although the licensee

knew

the relay setpoint

was outside the manufacturer's

band,

the relay was evaluated

as being satisfactory.

The team asked the licensee

to provide an evaluation

for setting the relay outside the manufacturer's

specified setting

band.

Instead of providing an evaluation,

the licensee

replaced

the installed relay

with one with an appropriate

band of 18-30 volts.

Although this issue is

closed, it is identified as Unresolved

Item 90-200-12 in Appendix A to this

report.

4.3

Circuit Breaker Testing

The team reviewed the licensee's

program for periodic testing of Mestinghouse

4160-Vac

1200A switchgear breakers,

Brown Boveri

K600S 480 Vac load center

breakers

and

GE AK-2-25 250-Vdc load center breakers.

The team identified that

Procedure

NT-GE-006, "Load Center Breaker Relay Logic and Primary Current

Testing,"

does not provide adequate

information for testing

dc circuit breakers

and there is no acceptance

criteria specified in the procedure

except for a

22

data

sheet to record the test values.

During the review of test

documents for

250-Vdc breakers

72-66222

and 72-662013,

the team noted that the licensee

was

using

an ac test current source to test the dc circuit breakers.

Discussions

with the manufacturer

revealed that the breaker trip response

would be differ-

ent if they are tested with an ac current.

In response

to the team's

concern,

the licensee

sent

two sample

GE AK breakers

to the manufacturer's facility (GE)

for testing with ac and dc current.

The preliminary assessment

of the test

results

indicated that the time-current characteristics

of the breakers

varied

significantly between

the ac and dc tests.

This item is identified as Unre-

solved Item 90-200-12 in Appendix A to this report.

A complete overhaul of 4160-Vac breakers

is performed every

3 years in accor-

dance with Procedure

HT-GE-005, "Circuit Breaker

and Switchgear Inspection

and

Maintenance of 5 and

15

kV Breakers."

A routine relay logic and system'func-

tional test also is performed every refueling cycle.

This procedure reflects

all the necessary

maintenance

suggested

by the manufacturer.

However, the

existing maintenance

program does not require

any periodic overcurrent trip

testing of 480-Vac breakers

or requirements

to perform this test after

a

breaker

overhaul is performed.

The team noted that

a lack of maintenance

testing of circuit breakers

related to fire protection equipment

(10 CFR Part 50, Appendix R) was identified during

a previous

NRC inspection,

Inspection Report (88-21/88-24).

The licensee

stated that

a formal breaker

maintenance

testing

program to address all of load center

and motor control

center breakers

480-Vac and below is being developed to ensure

proper breaker

operation.

This program will determine

the appropriate

frequency of future

preventive maintenance

from trending past test results

and proposed

sample

tests.

It will also consider industry and manufacturer's

recommendations

and

procedures

to be revised accordingly.

A pilot test program consisting of

approximately

10 percent of Unit 1 and

common (to both units) Class

1E breakers

of 480-Vac and below is scheduled

to be conducted

during the next refueling

outage.

This program is scheduled

to be in place at the end of 1991.

4.4

Fuse Control

During a walkdown (control

room panel

IC614; dc panels

1D631, 632, 634, 661,

662 and 274; switchgear

1A203; load center

)B230 and motor control center

1B236), the team noted that the ampere rating of the fuses

agreed with the

applicable design

documents

except for the fuses

(ID Nos.

6A and 7A) for

inverter 821B-K801A in control panel

1C614.

These fuses

were 20-ampere

Bussman

type KTK-20 and did not agree with the 10-ampere

fuse rating identified in

Design

Document E16, Sht.

11, and vendor Drawing N1-B21-98.

The licensee

issued

NCR 90-0174 to address this discrepancy

and determined that the

installed fuses

are correct for the inverter application.

The design drawings

were never updated to reflect the as-built condition.

The licensee

took

appropriate

actions to update

the affected drawings before the end of the

inspection.

Control schematic

drawings reviewed typically specified only the current rating

and not the type of fuse.

The licensee

stated that during the pre-operational

phase of the plant, the engineering

department

performed

a walkdown to verify

as-built conditions.

However, the walkdown documents

did not include an

evaluation of the acceptability of various types of installed fuses.

Without

verification that the proper type of fuse is used,

a loss of electrical

23

~

~

~

~

coordination could occur.

In response

to this concern,

the licensee

stated

that Operation

Procedure

OI-AD-037 establishes

administrative control of fuse

removal

and replacement.

In addition, the licensee

stated that it is taking

steps to implement

a formal fuse control program that will include creating

a

database,

conducting walkdowns, verifying engineering

design,

and revising

applicable administrative procedures.

The fuses installed in 250-Ydc control centers

and load centers

are rated for

250-Vac.

This equipment is operated at

a higher dc voltage of 264-285

Vdc

because

of battery float/equalizing requirements.

The affected fuses

are Gould

OT fuses,

BUSS

NON fuses,

and

GE CF6 fuses.

In response

to the team's

concern

about the acceptability of these fuses,

the licensee

provided documentation

of

the qualification of these

fuses for a 250-Vdc rating.

However,

no documenta-

tion was available for the qualification of these

fuses at higher voltages.

The licensee

issued

an engineering

discrepancy

report

(EDR G00107) to have all

existing underrated

250-Ydc fuses

replaced with fuses of a higher voltage

rating.

This item is identified as

Open Item 90-200-03 in Appendix A to this

report.

4.5

Inverter Testing

The preventive maintenance

work authorizations

(MA) written to calibrate

and

test Topaz inverters in accordance

with procedures

IC-dc-100 and 400 and the

operating

and instruction manuals for static inverters

appeared

adequate.

This

testing is performed to verify inverter low- and high-voltage trip setpoints

and includes calibrations

every refueling cycle.

During initial installation,

the inverters were subjected

to a performance test from no-load to full-load

conditions to verify the output response.

The inverter setpoints

are selected

so that inverters will not trip at input voltages

between

100 and

140 Vdc to

provide 115-Vac output.

The low- and high-voltage trips are set at 95-Vdc and

147-Vdc, respectively, with resets at 108 Vdc and

132 Vdc.

The dc input

voltages to the inverter during battery float and equalize periods are

132 Vdc

and 142.8 Vdc, respectively.

The calibration

and trip setpoint records also

seemed

adequate.

Significant Operating

Occurrence

Report 1-90-177

was initiated to address

an

inverter trip which occurred while the batteries

were

on equalizing voltages.

The licensee

concluded that the dc overvoltage,

which caused

the inverter trip,

appeared

to be the result of the battery charger

response

to a voltage dip

during the start of a heavy ac load or a possible potential inverter drift.

As

a result, the corresponding

battery charger

was returned to float operation.

This caused

the inverter to reset

and reenergize

the lost instrumentation.

The

licensee is planning to trend the setpoint calibration data from the next

scheduled

preventive maintenance

tests

and determine whether the setpoints

or

battery equalizing voltage

have to be changed to address

this issue.

The team

concluded that the licensee

has

a program in place to monitor and test the

inver ter adequately.

4.6

Battery Testing

The team reviewed service testing procedures

SN-102-A04,A03

and SM-188-103-2

for Class

1E 125-Vdc and 250-Vdc batteries.

The test procedures

were adequate

to verify the design function capability of the Class

1E battery

system.

24

~

~

r

However, the procedures

did not account for the inaccuracies

of instruments

used during testing.

The licensee

believed the test procedures

have

enough

margin to account for instrumentation

inaccuracies,

but said it would revise

the procedures.to

address test instrumentation

inaccuracies.

The completed

test records for the Class

1E 125-Vdc battery bank 10610

had conservative test

acceptance

criteria and were in accordance

with requirements

of the station

Technical Specifications

and

IEEE Standard

450.

5.0

ENGINEERING AND TECHNICAL SUPPORT

5.1

Equipment Modifications

The team found the engineering

and technical

support associated

with selected

modifications related to the electrical distribution system to be of high

quality.

These modifications are discussed

below.

l.

Addition of a Fifth Diesel

The modification package for the addition of the fifth diesel generator

and the

team's

walkdown of the related installation were adequate.

Cable length and

separation,

compliance with the single-failure criterion,

and the short circuit

ratings of the associated

equipment

were also adequate.

2.

Temperature

Control Valve for Diesel Generator

Super charger Intercooler

The combustion air supplied to the diesel

generator is cooled downstream of the

supercharger

before entering the engine manifold.

The cooler was sized for ESW

at 95'F

and maximum outside air temperature.

A butterfly valve was adjusted to

establish

the required flow for these

bounding rated conditions

and locked in

position.

In the winter months,

excessive

heat

was

removed from the combustion

air and the temperature fell below the recommended

range of 95 to 125'F.

The

manufacturer felt that low air temperature

was

a contributing factor to recent

diesel failures.

The licensee

decided to add

a temperature

control valve and

a temperature

feedback control loop to modulate the

ESW flow and maintain inlet air tempera-

ture within the specified range.

The modification had been

completed in two of

the five diesels at the time of the inspection.

The design

change

package

(DCP-3009) for this modification describes

the changes

to be implemented

and

provides the supporting calculations

and setpoint evaluations.

The team was

impressed with the quality of the engineering

process

in preparing the design

documentation.

Although several

questions

were raised

concerning

the input

data

and boundary conditions,

the root source of the discrepancies

were easily

identified and corrected

because

the calculations

were well referenced

and the

excerpts

from the relevant design

documents

were included in the modification

package.

3.

120-Vac lE Inverter Addition

The primary function of the inverters

was to supply power to post-accident

monitoring

(PAN) instrumentation.

The calculated

load per inverter was below

1450

VA.

The inverters were energized

from the 125-volt Class

1E batteries,

channels

A and B.

Each inverter was rated at 2000

VA and consisted of two

25

1000

VA inverters in a master-slave

configuration.

The units were of the

ferroresonant

transformer output type.

The team found the input voltage with

the minimum and maximum values available from the 125-volt dc system

and output

voltage regulation acceptable for the application.

The rating of the invert-

ers, current limits for overload

and short circuit conditions,

and the protec-

tive fusing in the distribution system energized

from those inverters

were

adequate.

4.

Replacement

of Class

lE Battery

Modification package

DCP 87-9128 for the Unit 2 125-Vdc station battery capaci-

ty upgrade

was issued to replace the old 742-ampere-hours

Class lE batteries

with new 825-ampere-hours

CLD batteries.

The

new batter ies were installed

on

the old battery racks, which were seismically reanalyzed.

The safety evalua-

tion, post-modification testing,

and installation instructions

were technically

acceptable.

5.

Relay Replacement

Modifications

,Two plant modifications

(DCP 89-9017 A,B,C,D and 89-9132)

were associated

with

the replacement

of instrument relays

used in safety-related

applications.

Both

modifications required the dedication of commercial

grade relays for the

intended safety-related

application.

The associated

design

change

packages

verified the critical characteristics

required to ensure

the desired perfor-

'ance.

In addition, these relays were to be functionally tested after instal-

lation.

The licensee's

dedication

process

appeared

to adequately

address

the

critical characteristics

for these relays.

5.2

Discrepancy

Management

System

As part of the team's

review of the licensee's

engineering

and technical

support,

a review was conducted of the discrepancy

management

system

used to

identify, document,

evaluate,

and report deficiencies at Susquehanna.

5.2.1

Deficiency Control System

The licensee's

mechanisms

to control deficiencies at Susquehanna

include

nonconformance

reports,

engineering

discrepancy

reports, significant operating

occurrence

reports, audit findings, quality assurance

surveillance findings,

and deficiency reports.

1.

Nonconformance

Reports

Nonconformance

Reports

(NCRs) are

used to identify, document,

process,

and

control deficiencies with regard to a characteristic,

documentation,

or proce-

dure that renders

the quality of an item unacceptable

or indeterminate.

Nonconformances

include physical defects, test failures, incorrect or inade-

quate documentation,

and fai lure to comply with prescribed

processing,

inspec-

tion, or test procedures.

HCPs

document the cause of the nonconformance,

the

evaluation of its effect on plant operability, the determination of its report-

abi lity to the

HRC, and the corrective actions taken

and to be taken to pre-

clude recurrence.

26

Procedure

AD-gA-120 requires

NCRs to be evaluated

to determine if the noncon-

fornance affects plant operability and if it has to be reported to the

NRC

within 2 days.

The procedure also requires that the report be dispositioned

within 45 days of the date of issue.

Contrary to these

requirements,

the

following open

NCRs, which were issued before June 7, 1990, were, evaluated for

operability and reportability from 4 to 86 days after their date of issue:

NCR Number

Number of Da s from Issue to Evaluation Dates

86-0931

86

86-0930

85

87-0883

,

31

90-0003

27

88-0660

19

89-0435

15

89-0362

11

88-0524

10

89-0066

8

89-0473

6

87-0453

5

87-0021

4

90-0117

Evaluation undated

Two PP&L audits of corrective action (Audit Report 90-019, Finding No. Ol, and

Audit Report 88-100, Observation. No. 5) identified similar conditions.

To control the "hold" placed

on a nonconforming item, authorization is needed

to have the item conditionally released

to permit its use before obtaining

a

disposition or completion of corrective action.

The conditional release

is

authorized for a specific length of time and is based

on an engineering justi-

fication that includes the extent to which the nonconforming item may be

installed,

used, or operated.

Although no nonconforming

items were currently installed in the plant beyond

their conditional release

expiration dates,

several

nonconforming

items

(NCRs

87-0021

and -0336; 88-0085,

-0327, -0328,

and -0493;

and 89-0659

and -0660)

had

been previously installed in the plant beyond their conditional release

expira-

tion dates.

This problem

may have

been

caused

because

there

was

no procedural

~

requirements

to designate

who is responsible for tracking

NCR conditional

release

expiration dates

and, specifically, to designate

what action is to be

taken before the

NCR conditional release

expiration date is reached.

2.

Engineering Discrepancies

A fairly new program is in place to control engineering

discrepancies (i.e.,

differences

between

an engineering

requirement

and its implementation or a

conflict between

engineering

documents).

The governing procedure,

EDM-(A-122,

Engineering Discrepancy

Management,

was originally issued

on December

12, 1989.

Revision

1 was issued

on June

29

ai>d Revision

2 on July 19, 1990.

The latest

procedure revision requires

engineering-discrepancy

items to be documented

by

using either an engineering

discrepancy

report

(EDR) or by assigning

an

EDR

type classification

and priority classification to an existing deficiency

control mechanism or an engineering

wor k request

(Eh'R).

The item, its assigned

27

EDR type classification

and priority classification, is entered

in the computer

tracking system for engineering

work requests.

However, several

items with a

priority 2

EDR classification (to be dispositioned within 14 days from the

origination date) did not have the "Date Disposition Needed" block on the

EDR

form completed

and

no date

had been entered

in the "Date Needed"

column of the

EWR tracking system.

Thus, ft was unclear

when the disposition

was needed.

The

EWR tracking report, titled "Weekly Engineering

Discrepancy

Report," sorts

entries

by priority class.

The issue of August 7, 1990, contained

138 entries,

and

no date

had been entered

in the "Date Needed"

column for 75 of those

54 percent).

This "Date Needed"

column is apparently

the disposition

due date

based

on the

EDR priority classification)

and not the implementation

due date.

Procedure

EPM-gA-122 requires

EDRs classified

as "Nuclear Safety" or

"Regulatory" to be reviewed within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to determine if a reportabi lity,

operability,

and plant safety assessment

is required.

Procedure

EPH-gA-122,

requires

the Discrepancy

Review Committee

(DRC) to document the results of its

reportability, operability,

and plant safety assessments,

and the basis for its

conclusions,

but does not specify where and

how these

assessments

are to be

documented.

These reportability, operability, and plant safety

assessments

were not being documented

on the

EDR form but in the minutes of the

DRC meet-

ings, which were not indexed

by

EDR number.

The minutes

and other appropriate

documents

are not being filed with the associated

EDR and are not readily

retrievable.

During the inspection, reportability, operability,

and plant

safety

assessments

could not be retrieved from the

DRC meeting minutes,

was not

on the

EDR Form, or elsewhere

in the

EDR files for EDRs G-00036

and G-00039.

Although the procedure

states that engineering action to close

EDRs be

completed within 180 days of the disposition date,

several "old" EWRs,

designated

and tracked

as

EDRs, remain

open (e.g., H-50612, October 4, 1985;

M-60758, June 23, 1986; M-71248, October 6, 1987; H-79310,

May 28, 1987).

EWR,

ID No. EIR-100304,

dated

September

15, 1982, containing

a "Disposition

Required

By" date of October 15, 1982,

was still open,

had been designated

as

an

EDR, and was being tracked in the

EWR tracking system

as

EDR X-03186.

3.

Significant Operating Occurrence

Reports

Significant Operating Occurrence

Reports

(SOORs) are used to identify and

document significant, potentially significant, or near miss occurrences

that

may negatively affect operation of the plant, adversely affect personnel

safety,

be of significant interest to the public, and require

management

attention.

Procedure

AD-gA-424 requires

a timely resolution of SOORs.

The

team identified several

old SOORs that have remained

open since

1987 (e.g.,

1-87-179, July 8,

1987

1-87-209,

August 4, 1987; 2-87-076, April 29, 1987;

and

2-87-104, July 4, 1987I.

4.

guality Assurance Audit Findings

and Surveillance

Findings

equal ity assurance

audit finding sheets

(AFSs) are used to document

adverse

findings identified during operational quality assurance

audits that require

corrective action.

They contain the controlling document

and requirement,

a

description of the deficient finding, the action required to correct the

28

L E

~

~ I

~

~

~

deficiency, the corrective actions

taken to resolve the deficiency,

and

verification of the adequacy of the corrective actions

completed.

The audit report that includes the AFSs contains observations

and recommenda-

tions and

an assessment

of the effect each audit finding has

on quality as

a

means of signifying the importance of each finding as well as

an overall

assessment

of the effectiveness

of the program being audited.

guality assurance

surveillance findings (gASFs) are used to document deviations

from specified requirements

or procedures.

(ASFs contain

a description of the

requirement,

the nonconforming activities or items,

a description of the action

required to correct the condition and to prevent recurrence,

and action per-

formed to verify the implemented corrective action.

The reviewed

gA audit reports

and surveillance

reports

appeared

to be well

written and effective in identifying problem areas.

5.

Deficiency Reports

Deficiency Reports

(DRs) are used to identify, document, control, and disposi-

tion significant conditions adverse

to quality.

Significant conditions adverse

to quality include major program breakdowns,

license

and regulation violations,

repetitive nonconforming conditions, trends

adverse

to quality, and adverse

generic conditions.

The processing

of DRs includes reporting significant

adverse

conditions to appropriate

levels of management,

correcting deficient

conditions, determining root causes

of the conditions,

and implementing correc-

tive and preventive actions to preclude recurrence

of the condition.

Of the five DRs that have been issued,

the team had concerns

about

DRs89-001

and 89-002.

DR 89-001

was issued

on April 24, 1989, to identify that adequate

configuration control requirements for safety-related

cable

and raceway design

drawings

have not been defined

and implemented.

This deficiency was identified

during the performance of gA Surveillance 88-184.

Cable

and raceway design

data were contained

in circuit and raceway

schedules

that were outputs of an

architect/engineer

computer program.

The architect/engineer's

computer was not

compatible with PPAL's computer equipment,

had

no calculation ability, and did

not maintain data related to 10 CFR Part 50, Appendix R.

The licensee's

computer program, which currently is used to determine

the as-engineered

or

as-built status of these

drawings,

was inadequate

because

the appropriate

software

gA controls

had not been applied to the program.

Furthermore,

the

process

required to accurately

determine

the as-engineered

or as-built status

of these

drawings

had not been defined.

The existing drawing update

process

in

use at the plant was not compatible for revising these

drawings.

The responsi-

bilities and special

process

required to revise these

drawings

had not been

established

and documented.

Thus, these

drawings were not being revised

on

a

routine basis.

Updated

FSAR Section 8.3.3.1 requires

a review to be performed

when

a cable

tray becomes

more than

30 percent full by cross-sectional

area to determine the

adequacy

of the design.

gA Surveillance

88-184 identified instances

where this

review (engineering

calculations)

was not performed

when the 30-percent-full

limit was exceeded.

Other instances

were identified where results of the

design

adequacy

review were questionable

as

a result of errors in the computer

29

program database.

These errors include cables

and raceways

having duplicate

identification numbers,

cable lengths not provided,

cable size

codes

not

defined,

and invalid cable size codes.

The conditions identified in QA Sur-

veillancee

88-184

have existed since

1984 when the licensee

assumed

responsibi l-

ity for the design of cable

and raceway from the architect/engineer.

The

licensee

established

an interim cable

and raceway tracking plan to correct

these conditions.

However, only part of this plan has

been

implemented.

The

licensee currently is re-evaluating

the required corrective actions

necessary

to resolve this issue.

DR 89-002 was issued

on November 11, 1989, to identify repetitive nonconforming

conditions with regard to the implementation of key elements of the Susquehanna

Equipment Qualification (EQ) Program.

These conditions were identified during

the performance of the

1989 annual

QA audit of the

EQ Program (Audit 89-075).

Several audit findings identifying EQ deficiencies

remained unresolved,

includ-

ing one

open finding from Audit 86-034

and three

open findings from Audit

88-021.

These conditions include as-qualified verses as-installed

configura-

tion control; identified

EQ maintenance

and surveillance

requirements

not

having been adequately

implemented;

and previously identified conditions/

deficiencies

reported

via NCRs, equipment qualification evaluation

requests

(EQERs), audit findings; and at least

one

NRC commitment.

These previously

identified

EQ deficiencies

remain unresolved

and more are continuing to

accumulate.

Specific deficiencies

include

Hardware found installed in the plant in an unqualified configuration.

This hardware

included standby

gas treatment

damper actuators

and

Rosemount transmitters.

Conflicting, obsolete,

and inaccurate

information that exists in

EQ

binders

as

a result of over 400 unincorporated

change notices

posted

against

89

EQ binders.

Inconsistences

between actual

EQ binder configuration and the design

document

management

system,

which contains

the official record of the

plant configuration.

Maintenance

requirements

specified in qualification test reports not being

identified to the Maintenance

Department.

Implementation of several

EQERs that provide

a mechanism to request

improvements or corrections to

EQ maintenance

requirements

were postponed

by as

much as 2-1/2 years.

Correction of these identified

EQ program deficiencies

are being addressed

by a

special action team.

6.

NCRs Related to Environmental Qualification

Three of the

NCRs reviewed pertained to the lack of qualification for numerous

Limitorque motor actuators

and target rock solenoid valves.

Of specific

30

I

0

concern

were

NCRs 88-0181

and 88-0520, which were originated

on March 24 and

July ll, 1988, respectively.

NCR 88-0181 identifies the concern that 21 motor actuators

in each unit are

equipped with Reliance

dc motors that were not subjected

to Limitorque qualifi-

cation testing.

The qualification testing related to these

motor actuators

was

performed

on Porter/Peerless

dc motors, which have not been

shown to be similar

to the Reliance

dc motors installed at Susquehanna.

Although the evaluation to

NCR 88-0181 identified a similarity analysis

performed

by Myle Labs for the

Shoreham nuclear plant, which compared

Reliance

125 Vdc and Reliance

480 Vac

motors, the licensee

had not shown its applicability to their 250-Vdc Reliance

motors.

In addition, the licensee

had not shown qualification for motor

actuators fitted with Peerless

Class

8 motors.

NCR 88-0520 identifies the concern that

31 motor actuators

in each unit are

operated with 250-Vdc control power, which is twice as

much as the 125-Vdc

control power used in the Limitorque qualification testing of these actuators.

The 250-Vdc control power is routed though the motor actuator limit and torque

switches that have exposed terminal connections.

In an accident environment,

these

connections

could be subject to insulation breakdown

as

a result of

moisture intrusion.

Although the licensee

provided

some evidence that these

components

could be environmentally qualified, the evaluation

was found to be

weak because

It relied partially on

a test report (F-C3271) that included

no

pre-accident

aging or radiation.

Low-resistance

readings

have

been recorded for fibrite torque switches,

even at 120-Vdc.

the Limitorque motor actuator is not a sealed

device

and

some moisture

intrusion is expected.

Although both

NCRs 88-0181

and 88-0520

have

been evaluated,

over 2 years

has

elapsed without resolution of these

issues.

Furthermore,

extensions

to both

NCRs cited

a lack of resources

as the reason resolution of these

NCRs has not

been accomplished.

As a result,

numerous Limitorque motor actuators

have still

not been qualified and are currently in an indeterminate

status.

This issue

has

been

documented

in Region I

NRC Inspection Report 50-387/90-17

and

50-388/90-17.

In addition, the three

NCRs discussed

below identified nonconforming environ-

mentally qualified equipment installed beyond their conditionally released

expiration dates.

NCR 88-0493 identified two installed, environmentally qualified electrical

relays that had not been replaced

by a qualified life expiration date specified

in their preventive maintenance

schedule.

These relays were installed for

17 days beyond their conditionally released

expiration date until a reanalysis

indicated that the relays could remain installed until a new date that was

specified in a revised preventive maintenance

schedule.

This

NCR was verified

closed

on November 17, 1988.

31

~

~

NCR 88-0659 identified

1 of 2 primary containment

hydrogen/oxygen

analyzer

sample

pumps installed in Unit 2 contained nonqualified

Buna-N rather

than

Neoprene 0-rings.

This condition constituted

an

EQ nonconformance

since

Buna-N

0-rings

had not been tested or analyzed for use under post-accident

conditions.

NCR 88-0660 'identified a similar condition on 2 of 2 primary containment

hydrogen/oxygen

analyzer

sample

pumps installed in Unit 1.

The three installed

pumps were permitted to operate for 2 months beyond their conditionally

released

expiration date which were documented

on the NCR's.

This condition

was identified during the performance of the 1989 annual

QA Audit of the

EQ

Program, Audit 89-075.

The nonconforming Unit 2 pump was replaced with an

acceptable

spare

pump on 'October 13,

1989

and

NCR 88-0659

was verified closed

on November 24, 1989.

Eight spare

hydrogen/oxygen

analyzer

sample

pumps were

determined

unacceptable.

Five were sent out for repair; the remaining

3 were

retired from service.

The

NCR for the Unit 1 pumps

was reevaluated.

It was determined that these

pumps could remain installed for an indefinite period of time.

These Unit 1

pumps are scheduled

to be replaced with qualified pumps during the upcoming

refueling outage

scheduled

to begin in September

1990.

DR 89-002 was issued

on

November 30, 1989, to inform SSES

management

personnel

of this condition.

5.2.2

Su+nary of Discrepancy

Management

System

Review

Although the licensee

has effectively identified and documented

the deficien-

cies at Susquehanna,

the deficiencies

have not been evaluated,

controlled,

processed,

and resolved in a timely and effective manner.

To address

and improve this situation,

PPKL issued

Nuclear Department Policy

Letter Number 90-003, Revision 0, on August 13, 1990,

on the subject of Defi-

ciency Control.

This policy letter

includes

PPSL standards

of performance for

the identification, control, and closure of deficiencies at the Susquehanna

plant.

Conditions adverse

to quality, plant safety,

and reliability are to be

promptly identified, reported,

and corrected.

All work activities associated

with the identification and closure of

deficiencies will receive proper management

attention

and priority.

These

activities include determinations

of operability and reportability,

disposition,

and corrective action implementation.

PPSL

has established

a Deficiency Control and Corrective Action Program.

As

part of this program,

PPKL will review the backlog of open deficiencies

issued

before August 13, 1990, to determine

the need for an accelerated

and/or differ-

ent disposition plan for all open nonconformance

reports,

engineer ing discrep-

ancy reports, significant operating

occurrence

reports, quality assurance

audit

findings, quality assurance

surveillance findings,

and deficiency reports

by

the target date of November 15, 1990.

PPSL will integrate provisions into its deficiency control processes

to ensure,

with limited exceptions,

that the lifetime of any corrective action is limited

to one cycle of operation.

32

'l

e

~

~

If this program is properly implemented,

the teams

concerns with the

PPEL

discrepancy

management

program should

be resolved.

6. 0

GENERAL CONCLUSIONS

The inspection

team concluded that generally the

SSES electrical distribution

system would be capable of performing its intended safety functions.

With the

exception of the

14 specific findings identified in the report; the batteries,

emergency

diesel generators,

switchgear,

and other components within the

EDS

were found to be adequately

sized

and configured.

Separation

between

redundant

trains or divisions was found to have

been adequately

maintained,

and

an

adequate

design basis exists

and is being upgraded

and maintained for the SSES.

The general quality of engineering

and technical

support appeared

to be good,

and the licensee

had

a good self-assessment

(quality assurance

audit) program.

Weaknesses

were identified by the inspection

team in voltage regulation at the

lower ac voltage levels,

and in timeliness of corrective actions to self-

identified deficiencies.

33

APPENDIX A

Ins ection Findin

FINDING CATEGORY AND NUMBER:

OPEN

ITEM 90-200-01

FINDING TITLE:

Calculation Errors and Discrepancies

DESCRIPTION OF CONDITION:

The team identified several

problems

concerning calculations

and the control of

calculations.

Some of these

problems

are discussed

below.

1.

The licensee

does not have

a calculation index or other system for con-

trolling the use of non-valid or superseded

calculations.

As

a result,

three calculations

were found to be in effect for the short circuit rating

of Class

lE switchgear.

The three calculations

did not have the

same

assumptions

and results.

Even so, the licensee

considered

them valid and

had put them into effect simultaneously.

These calculations

contained

several

nonconservative

features,

including those listed below.

There were errors in the multiples used for breaker interrupting

times.

Maximum possible voltage

was improperly considered.

The installation of new

ESF transformers

before plant startup

had not

been accurately

considered

in modeling of the system.

One of the calculations

had been designated

"non-g" and lacked proper

review and auditabi lity.

In response

to the team's

concern,

the licensee

proceeded

to perform a

fourth calculation

(SC-1), which was given to the team for review in

preliminary form on August 31,

1990.

The team's

review of this calcula-

tion indicated that most of the

comments

and concerns

had been addressed.

However, the available margin between

the duty and the rated values for

the switchgear short circuit capability

was practically nonexistent.

The

licensee

committed to perform formal calculations to allow for proper

evaluation of this issue.

The team was not concerned with the safety implications of the minimal

available

margin because

the conditions

when the short circuit rating

could be exceeded

are not continuously present.

These conditions are only

present

when the diesel generator is in test

and is paralleled with the

grid.

2.

The team determined that cable losses

were not included in the loading

tabulations for the emergency

diesel generators.

These

losses

were

calculated

by the licensee to be approximately

8

kW.

Although the team

did not have

an immediate safety

concern

because

approximately

a 326-kW

margin exists for the diesel capacity,

the team considered

these

losses

sufficiently important to warrant revision of the loading tabulations.

The licensee

has

committed to perform complete calculations

and revise the

loading tables accordingly.

REQUIREMENTS

ANSI NQA-1-1979, Supplement 6S-l, requires that design inputs

and documents

be

properly prepared, filed, and controlled.

ANSI Std C37.010-1972,

requires that circuit breakers

be rated

above the

required interrupting duty.

10 CFR Part 50, Appendix B, Criterion III, Design Control, requires

design

control measures

to be provided for verifying of checking the adequacy of

design.

Criterion III of 10 CFR Part 50, Appendix B, requires that measures

be estab-

lished to ensure

the design basis is correctly translated

into specifications,

drawings,

procedures,

and instructions.

REFERENCES:

2.

4 ~

Calculation E2004-01,

"System Fault Duty Calculations,"

Revision 3,

Narch 17, 1981, performed

by Bechtel.

Calculation GP-19, "Calculation for Minimum ES Transformer

Impedance,"

Revision 1, October 22, 1982, performed

by PP&L System Operating

Department.

Calculation GP-18,

"4

8

13

kY Swgr. Units

1

E

2 Duty Gale.," Revision 1,

October 2, 1980, performed

by PPhL.

Calculation SC-l, preliminary, August 31, 1990, performed

by PPSL.

A-2

FINDING CATEGORY AND NUMBER:

UNRESOLVED ITEM 90-200-02

FINDING TITLE:

Emergency Diesel Generators

Over load Alarm

DESCRIPTION

OF CONDITION:

The diesel generators

incorporate

an inverse time overcurrent relay to provide

an alarm in the control

room to alert operators

of a diesel overload condition.

The team found that the overcurrent relay settings

were not adequate for diesel

generator

E and that all diesel relays exhibited excessive drifting, not

properly accounted for in the relay setting calculations.

For diesel generator

E, the relay minimum pickup was

105 percent

above the maximum generator rating,

which would mean that overloading of up to 5 percent

could be present for an

indefinite period of time without any alarm to indicate this condition.

In

addition, review of the surveillance report for the overload relays disclosed

that excessive drifting was occurring in the pickup value of the relays,

as

depicted

by the following examples:

Ref.

MAP83526,

November 4, 1989,

51 relay for DGA, drift from previous

test

on September

9,

1985 was 250 percent of setpoint.

Ref.

MAP00555, March 16,

1990,

51 relay for DGC, drift from previous test

on October 31,

1988 was

100 percent of setpoint.

Ref.

HAP83528,

November 18, 1988,

51 relay for

DGC, drift from previous

test

on February 22,

1984 was 25 percent of setpoint.

Ref. HAP83527,

February 21, 1989,

51 relay for DGB, drift from previous

test

on February

15,

1984 was

50 percent of the setpoint.

The

51 relay instruction sheets

(GEI-28818D) indicated that the above drifting

values

are not unexpected for values

close to minimum pickup.

Despite the very

high level of drifting found in the periodic surveillance, drifting had not

been considered

in the relay setpoint calculation.

The team was concerned that improper settings

and drifting of setpoints

could

prevent initiation of the overload alarm if the diesel generator

was

overloaded.

REIEIIIREIIEHTE:

IEEE Standard

308, Alternating Current Power Systems,

requires that protective

devices

be provided to limit the degradation of the Class

1E power systems.

10 CFR Part 50, Appendix A, Criterion 17, requires

the design of the electric

power system to be capable of permitting functioning of components

important to

safety.

10 CFR Part 50, Appendix B. Criterion III requires

measures

be established

to

ensure

the design basis is correctly translated

into specifications,

drawings,

procedures,

and instructions.

A-3

REFERENCES:

~

~

~

~

1.

PPSL System Operating

Department

Relay Setting

Change Notice 1381(,

January

31, 1981.

2.

Calculation 1-20204-5,

"Relay Setting Calculation for Diesel

Gen A

(B,C,D,E) T.O.C. Alarm 5 Diesel

Gen

E Def. T.O.C. Alarm," Revision 1,

January

14, 1987,

performed by PPSL.

3.

Relay Surveillance

Work Authorizations, for Card 4DGA-1-A4, Card

ODGB-I-A4, Card fDGC-l-A4, Card fDGD-l-A4, Card EDGE-l-A4.

4.

Relay Instructions,

GEI-28818D, Applicable to Type

IAC66A Relay.

5.

PP8L Single Line Heter

5 Relay Diagram 4.16

kV Diesel Generator

Common,

Dwg. No. E-5, Sheet 4, Rev. 9, January ll, 1988.

FINDING CATEGORY AND NUMBER:

OPEN

ITEN 90-200-03

FINDING TITLE:

Overvoltage

On 250-Vdc System During Battery Float/Equalize

Conditions

DESCRIPTION OF CONDITION:

The licensee's

fuse control program

showed that several

control fuses installed

in 250-Vdc load centers

and motor control centers

(MCCs) are rated only for

250 Vdc.

This equipment is operated at

a higher dc voltage of 264 to 285 Vdc

during the application of a battery float voltage

and equalizing

charge.

The

250-Vdc rated fuses that were verified during the field walkdown in load

centers

and

l'ICCs are Gould

OT fuses,

Bussman

NON fuses,

and

GE CF6 fuses.

The

team raised

concerns

regarding

the acceptability of these

fuses at higher

voltages

and the licensee

issued

engineering

Discrepancy

Report

G00107 to

address

this issue.

Preliminary assessment

of overvoltage

on fuses

showed that during short circuit

fault conditions greater

than

375 amperes,

the battery charger would regulate

the output voltage to the battery

and would eliminate any potential overvoltage

problems.

However, the licensee

could not provide sufficient justification for

the 250-Vdc fuses capability to interrupt during normal overloads at higher

voltages.

The licensee's

preliminary analyses

showed that if a sustained

overload existed for a long period of time, the upstream breakers

or fuses

would interrupt to protect the circuit, causing

a loss of one division of dc

power.

The licensee

stated that it is planning to replace all underrated

fuses in the 250-Vdc system

as

soon

as possible.

REIEII REIIRIIE:

10 CFR Part 50, Appendix B, Criterion III, "Design Control," requires in part

that measures

be established for the selection

and review for suitability of

materials

and equipment that are essential

to the safety-related

functions of

the systems.

REFERENCES:

1.

FSAR Section 8.3.2,

"DC Power Systems."

2.

NRC Information Notice 83-08,

"Component Failures

Caused

By Elevated

DC

Control Voltage."

3.

Engineering

Discrepancy

Report G100107.

A-5

FINDING CATEGORY AND NUYiBER:

UNRESOLVED ITEtl 90-200-04

FINDING TITLE:

Questionable

Seismic Qualification of 250/125

Vdc Load

Center Breakers

In Racked-Out Position

DESCRIPTION

OF CONDITION:

During a walkdown, the team found all the spare breakers

in the 250/125-Vdc

load centers

were in a partially drawn-out position, which led the team to

question

the seismic qualification of this equipment in this configuration.

The licensee

stated that the effect on the seismic qualification of the

affected

load centers

is indeterminate

because

the test configuration was with

the breakers

racked in.

The licensee

subsequently

reported this unanalyzed

condition to

NRC in accordance

with 10

CFR 50.9.

As a result of the team's

concerns, all spare circuit breakers

were racked in until the analysis to

determine

the acceptability of the seismic qualification is completed.

RE UIREHENT:

GDC 2, "Design Bases for Protection Against Natural

Phenomena,"

requires that

structures,

systems,

and components

important to safety

be designed to with-

stand the effects of earthquakes.

REFERENCES:

None

A-6

~

g

~

FINDING CATEGORY AND NUMBER:

UNRESOLVED ITEM 90-200-05

DEFICIENCY TITLE:

Degraded Grid Relay Setpoints

DESCRIPTION

OF CONDITION:

The current setpoints for the undervoltage

relays to actuate

under degraded

grid conditions

do not provide adequate

protection for safe operation of all

Class

1E loads at the 480-Vac and 120-Vac voltage levels.

The setpoints for

the relays are at 84 percent of rated

bus voltage for the 4160-Vac buses.

To

ensure

adequate

protection

and operation of all Class

1E loads, calculations

indicate that the system voltage must not drop below approximately

93 percent

of rated voltage at the 4.16-kV bus.

As a result,

should the 4160-Vac bus

voltage fall below 93'percent,

but remain

above the degraded

grid relay

setpoints of 84 percent,

adequate

operation of numerous

Class

1E loads could

not be ensured.

The licensee is in the process of developing

new relay setpoints to provide

greater protection of'quipment and to ensure that sufficient voltage is

available at the required

loads.

These

new settings require that the facility

Technical Specifications

be changed

and these

changes

require

NRC approval.

The licensee

has

committed to submitting

a technical specification

change

request for raising these setpoints

by September

30, 1990.

REIEUERBiENTS:

~

~

~

Criterion III of 10 CFR Part 50, Appendix B, requires that measures

be estab-

lished to ensure the design basis is correctly translated

into specification,

drawings, procedures,

and instructions.

Criterion XVI of 10 CFR Part 50, Appendix B, requires

measures

be established

to ensure that deviations

and deficiencies

are promptly identified and

corrected.

REFERENCES:

1.

FSAR Section 8.3.1.3.6,

"l1anual

and Automatic Interconnections

Between

Buses,

Buses

and Loads,

and Buses

and Supplies."

2.

Technical Specifications,

Section 3/4.3.3,

"Emergency

Core Cooling System

Actuation Instrumentation."

A-7

~

~

~

~

E 'g'INDING

CATEGORY AND NUMBER:

UNRESOLVED ITEN 90-200-06

FINDING TITLE:

HPCI

Pump Thermal Insulation

Removal

DESCRIPTION

OF CONDITION:

During

a walkdown of the reactor building HVAC system,

the team found that the

thermal insulation

on the

HPCI pump, booster

pump,

and crossover piping had

been

removed.

This insulation

was

removed during July 1984 for a maintenance

activity and inadvertently

was not reinstalled.

In addition, the reactor

building

HVAC calculations

had not been revised to consider the result of the

insulation removal.

During the inspection,

the licensee

performed

a calcula-

tion and determined that there

was

a sufficient margin in the

HPCI room coolers

to handle the additional

heat load.

Two nonconformance

reports

were generated

as

a result of this concern,

and the licensee is planning to reinstall the

insulation in the near future.

REEEIIIREIIERTR:

Criterion

V of 10 CFR Part 50, Appendix B, requires activities affecting

quality be performed in accordance

with appropriate

procedures.

The procedures

should contain appropriate

acceptance

criteria for determining the activities

have

been satisfactorily accomplished.

REFERENCES:

i.

2.

3.

Calculation 176-18,

"Reactor Building Heat Load," Revision 4, performed

by

Bechtel.

PPKL Nonconformance

Report No. 90-0185,

August 27, 1990.

PP8L Nonconformance

Report No. 90-0186, August 27, 1990.

~

I

FINDING CATEGORY AND NUMBER:

UNRESOLVED ITEN 90-200-07

FINDING TITLE:

Insufficient Heat Transfer Surface

Area in Condensers

DESCRIPTION

OF CONDITION:

The essential

service water

(ESW) system

draws water from a reservoir to

provide cooling to Class

lE equipment.

Little can

be done to control the water

chemistry in an open-loop cooling water system.

Furthermore,

the

ESW system is

normally in a standby condition; therefore,

sedimentation

occurs

as

a result of

stagnant

cooling water left in the piping and heat exchangers.

As a result,

excessive fouling of the heat transfer surface

(0.003 hr-ft'-'F/btu versus

0.002

as originally specified)

and plugging of tubes

due to wall thinning,

decreases

the capacity of the heat transfer equipment serviced

by

ESW.

Currently, 5,to

6 percent of the tubes in the control structure chilled water

(CSCW) system

condenser

are plugged,

and

4 percent of the tubes in the direct

expansion unit condenser for the Unit 2

ESWGR

HVAC system are plugged.

The

effects of increased

fouling and the reduction of available surface

area

as

a

result of tube plugging could affect the operability of these

components

and

hence the operability of the Class

1E equipment

supported

by them.

As a result

of this finding, the licensee is performing

an evaluation using

a fouling

factor of 0.002

on the refrigerant side

and of 0.003 (hr-ft'-'F/BTU) on the

ESW

side.

Should the assessment

of CSCW condenser

prove to be marginal or unac-

~

~

ceptable,

the licensee

has agreed to perform a similar assessment

of the

DX

units for the Unit 2

ESWGR HVAC.

REIERIREMERI:

Criterion III of 10 CFR Part 50, Appendix B requires that measures

be estab-

lished for the selection

and review for suitability of materials

and equipment

that are essential

to the safety-related

functions of the systems.

REFERENCE:

1.

PPEL Specification

N1453 General Specification for Heat Exchanger

Tube

Plugging.

A-9

FINDING CATEGORY AND NUMBER:

OPEN ITEN 90-200-08

FINDING TITLE:

Lack of Overpressure

Protection for ESM Side of Diesel

Generator Auxiliary Heater Exchangers

DESCRIPTION

OF CONDITION:

The sections of emergency

service water

(ESM) system piping providing cooling

water to the auxiliary coolers of each diesel generator

(intercoolers,

water

jacket,

lube oil and fuel oil coolers)

can be isolated from the main system

piping.

Overpressure

protection

has not been provided for this piping and the

secondary

side of the heat exchangers

as required

by ASHE Code Section III,

ND-7000.

The plant has five diesel generators,

four of which are aligned to Class

1E

buses while the fifth is on standby.

The

ESW system

has sufficient capacity to

provide cooling to only four diesel generators

at one time.

Therefore,

the

isolation valves in

ESW lines to the standby diesel generator

are normally

closed,

which allows for the following potential

source of overpressurization:

1.

To minimize the time required to place

a diesel generator

back in service,

the standby

lube oil and jacket water

pumps

and heaters

are operated to

prewarm the equipment while the cooling water is isolated.

This condition introduces

energy

sources

to the primary side of the auxiliary

heat exchangers

with no heat sink available.

There is a potential for

common-mode failure of both divisions of the safety-related

ESW because

both

loops of ESW are connected

to each diesel generator.

The licensee

has

committed to perform procedural

or hardware modifications

as

required to eliminate the overpressure

concerns.

REIEUIRE ~ENT:

ASME BPV Code,Section III, ND-7000, requires that "a system shall

be protected

from the consequences

arising from the application of conditions of pressure

and coincident temperature

that would cause

the Design Pressure

specified in

the Design Specification to be exceeded"

(where system refers to a component or

group of components for which overpressure

protection is provided).

REFERENCES:

l.

ASNE Boiler and Pressure

Vessel

Code,Section III, ND-7000,

1971 Edition

up to and including Minter 1972 addenda.

2.

E106216 Sheet (H-ill) Emergency Service Mater System

PAID.

A-10

FINDING CATEGORY AND NUMBER:

UNRESOLYED ITEN 90-200-09

FINDING TITLE:

Diesel

Fuel Oil Storage

Tank Level Indication Inoperable

DESCRIPTION

OF CONDITION:

During a walkdown of the diesel generators,

the team observed that the alarm

for low level in the diesel fuel oil storage

tanks

was annunciated

in two of

the five diesel generator

rooms.

The licensee told the team that there are

currently

no level indicators or low-level annunciators

in service for the five

diesel fuel oil storage

tanks

because

incorrect assumptions

were

made in

calculating the instrument setpoints

and, with the high-error rate in the

instruments,

they could not be properly calibrated.

Although two of the five

level instruments

have been replaced with new, more accurate

instruments,

they

are not operating properly because

of elevated

temperatures

in the cabinet

where they are located.

The licensee

is currently using

a dip-stick method to

check the level in the tanks monthly and after diesel starts.

This condition

has existed for over a year with tank

E and for several

months with tanks

A

thr ough D.

This condition is inconsistent with the

FSAR, which states that the fuel oil

storage

tank level is continuously monitored

and indicated at the local control

panel in the diesel

generator building.

By the current method of monitoring

level,

a fuel oil leak between diesel starts

would go undetected.

The licensee

plans to replace

the three remaining old level indicators

and to make

a modifi-

cation to the

new instruments

so that they will be operable.

The licensee

has

committed to check the diesel fuel oil storage

tank levels

every

7 days by the dip-stick method until the

new instruments

are operable for

all five tanks.

The team found this acceptable.

RE IEII R El l EIII:

SSES

FSAR, Chapter 9.5.4.4, states

in part:

"The fuel oil inventory in the

storage

tanks

and day tanks is continuously monitored

and the level is

indicated at the local control panel in the diesel generator building."

10 CFR Part 50, Appendix B, Criterion XVI, requires

measures

be established

to

ensure that deviations

and deficiencies

are promptly identified and corrected.

REFERENCES:

1.

FSAR, Chapter 9, Revision 40.

FINDING CATEGORY AND NUMBER:

UNRESOLVED ITEM 90-200-10

FINDING TITLE:

Fire Protection Piping in Diesel Generator

Room

DESCRIPTION

OF CONDITION:

The fire protection

system is not seismically qualified.

Although the sprin-

kler pipes are normally air filled, the deluge valves

and related controls are

not seismically qualified and

can

be assumed

to fail.

Therefore,

the

nonqualified sprinkler systems

could spray Class

1E electrical

equipment

following a seismic event.

The team requested

that the licensee

demonstrate

that the fire protection

system would not impair the operation of the diesel

generators

following a seismic event.

The licensee

provided

a summary

sheet of the activities conducted

in accordance

with Bechtel Specification 8856-M-388,

Engineering

Program for the Job Site

Review and Disposition of Safety Impact Items,"

a guide for assessing

the

effect of failures of equipment that is not safety qualified on Class

1E

equipment.

The diesel

generator

room signoff sheet stated that the fire

protection

system

was designed

and installed in accordance

with Bechtel Speci-

fication M-343, which thus ensured

the integrity. of the piping.

However, the team found that the spacing of many pipe supports

exceeded

the

allowable spans

given in Appendix

B of the specification

by 50 to 100 percent.

As a result of this finding, the licensee

performed calculations for these

nonconforming sections

of pipe, taking into account the water filled pipes,

the

stress

intensification for threaded joints, the seismic accelerations

with

2 percent

damping,

and the as-built spacing

and found the stresses

to be below

the

maximum allowable.

However, the team was concerned that the guideline

practices

used to design

a system,

were not followed for many of these

pipe

supports.

The licensee

confirmed that an engineering

discrepancy

report

(EDR

G00154)

had been

issued to revise the specifications

and drawings to reflect

the as-built layout.

Rtt ENTS:

Criterion III of 10 CFR Part 50, Appendix B requires

measures

be established

to

ensure

the design basis is correctly translated

into specifications,

drawings,

procedures,

and instructions.

Criterion

V of 10 CFR Part 50, Appendix B requires activities affecting quality

be accomplished

in accordance

with appropriate

procedures.

USNRC Regulatory

Guide 1.29, "Seismic Design Classification," Section

C-2

requires that "those portions of structures,

systems,

or components

whose

continued function is not required but whose failure could reduce the function-

ing of any plant feature

included in items l.a through 1.q above to an unac-

ceptable

safety level or could result in incapacitating injury to occupants

of

the control room should be designed

and constructed

so that the

SSE would not

cause

such failure."

~

S

FSAR Section 9-5.1.1-19 requires structural integrity of the portions of the

~

~

~

~

~

~

~

~

fire protection

system in the vicinity of safety-related

structures,

systems,

and

components

during

a safe-shutdown

earthquake.

REFERENCES:

1.

Bechtel Specification 8856-M-388, "Engineering

Program for the Jobsite

Review and Disposition of Safety

Impact Items."

2.

Bechtel Specification 8856-M-387, "Safety Impact List for SSES."

3.

Bechtel Specification 8856-M-343, "Technical Specification for Deluge and

Sprinklers for SSES," Appendix B, specifies

the type of pipe supports to

be used

and the

maximum spans

between supports.

4.

FF 108930-8856-M343-74-5,

Fire Protection

System Layout Drawings.

5.

FF 108930-8856-M343-75-5,

Fire Protection

System Layout Drawings.

6.

FF 108930-8856-M343-76-5,

Fire Protection

System Layout Drawings.

7.

E-106227

(M-122), Sheets

1, 2, 3, and 10, Fire Protection

System

P&ID.

8.

Design Description,

Chapter 44, Fire Protection

System.

9.

FSAR Section 9.5.1, Fire Protection

System.

A-13

~

~

~

FINDING CATEGORY AND NUMBER:

UNRESOLVED ITEM 90-200-11

FINDING TITLE:

Instrument Drift and Lack of Trending

DESCRIPTION

OF CONDITION:

The team identified several

relays

and timers that were found to be out of

calibration during testing.

These relays included overcurrent relays

and

protective circuit timers.

These

instruments

are calibrated currently

on a

3-year interval.

The team reviewed the data sheets for 16 instruments

and identified 8 of them

with as-found readings

outside the instrument tolerance

band.

Bus

1A 27A

UV Relay (+2.9 percent)

Bus

1B 27A UV Relay (+3.3 percent)

CS

Pump lA 50/51 Alarm Relay (+4.6 percent)

CS

Pump

1B 50/51 Relay (+2.8 percent)

RHR Pump

1A 50/51 Relay (+6.3 percent)

62-27-A IX1-20201 Timer (-7. 5

ercent)

62B1-20102 Timer (-21 percent

62Bl-20202 Timer (-21 percent

Although, during the calibration testing the instruments

were reset to within

the acceptable

band, there

was

no formal program to evaluate

"as-found" data

~

~

which was outside the tolerance

band or to trend the associated

instrument

drift.

As a result,

instrument drift values

used in,setpoint calculations for

these

instruments

have not been validated,

and

may be nonconservative.

Additionally, operability determinations

have not been

made for those

instruments

in which the excessive drifts could have

compromised their safety

functions.

R ttUIR IIERTS:

10 CFR Part 50, Appendix B, Criterion III requires that measures

be established

for establishing

the adequacy of a design.

10

CFR Part 50, Appendix 8, Criterion XI requires that testing which is

designed to demonstrate

system or component

performance

be performed in accor-

dance with written test procedures

that incorporate

the acceptance

limits

contained

in the applicable design

documents.

REFERENCES:

None

A-14

c I ~

J

I

~

4

FINDING CATEGORY AND NUMBER:

UNRESOLVED ITEM 90-200-12

FINDING TITLE:

Improper Application of Undervoltage

Relay

DESCRIPTION

OF CONDITION:

The team identified an installed undervoltage

relay for which the dropout

setting

was outside the manufacturer's

specified range.

The relay setpoint

calculation indicated that the installed

27A relay had

a manufacturer's

setpoint

band of 36-45 volts.

The licensee installed this relay and adjusted

the setpoint to 24 volts, which is outside the manufacturer's

operating

band.

The manufacturer's

setpoint

band envelopes

the settings at which the relay can

be set

and still perform as desired with accuracy

and repeatabi lity.

The

licensee

replaced

the installed relay with one with an appropriate

band of

18-30 volts.

RE UIREMENT:

10 CFR 50, Appendix B, Criterion III, "Design Control", requires in part, that

measures

be established for the selection

and review for suitability of appli-

cation of equipment that are essential

to the safety-related

functions of the

structures,

systems

and components.

REFERENCES:

1.

Calculation 1-20200-2,

"27A Relays,

March 4, 1982, performed

by PPGL.

2.

Work Authorization V00492, August 24, 1990.

A-15

~ a5 +

~

r

a

~

FINDING CATEGORY AND NUMBER:

UNRESOLVED ITEYi 90-200-13

FINDING TITLE:

Inadequate

Testing of 250/125-Vdc

GE AK Circuit Breakers

DESCRIPTION

OF CONDITION:

The General Electric AK 2-25 250-Vdc circuit breakers

are tested

using

a

multi-ampere

ac current source.

The team questioned

the accuracy of testing

dc

circuit breakers with an ac current source.

Subsequent

discussions

with the

licensee

and the manufacturer

indicated that the breaker trip response

would be

different if they are tested with an ac current source.

In response

to the

team's

concern,

the licensee

sent two breakers to the manufacturer to perform

an overcurrent trip test using ac and dc currents.

Preliminary test results

showed that when

a breaker is tested

using dc current, the trip unit will pick

up 15-40 percent

sooner than with an equivalent

ac current.

The

iicensee

has

not analyzed

how coordination of the existing 250/125-Vdc breakers will be

affected

by the difference in the actual

pickup values.

In addition, the

licensee

does not have adequate

data to indicate that the dc trip curve main-

tains the

same

shape

and size as the ac trip curve.

Furthermore,

the existing

maintenance

procedure,

NT-GE-006,

does not provide adequate

information for

testing the circuit breakers

and there is no acceptance

criteria mentioned in

the procedure

except for the data sheet to record the test values.

The

licensee

has

committed to a complete evaluation of this issue.

REIEUI RE I ERIE:

10 CFR Part 50, Appendix B, Criterion XI, "Test Control", requires,

in part,

that

a test program be established

to assure that all testing require to

demonstrate

that structures,

systems

and components will perform satisfactorily

in service is identified and performed in accordance

with written test proce-

dure which incorporate

the requirements

and acceptance

limits contained

in

applicable

design

documents.

SSES Technical Specification, Section 6.8.1 states

in part, "that written

procedures

shall

be established,

implemented

and maintained

covering the test

activities of safety related equipment."

REFERENCES'.

Procedure

NT-GE-006, "Load Center Breaker Relay Logic and Primary Current

Testing," Revision 7.

2.

Test data for circuit breakers

1D662-022

and 1D662-013,

December

12,

1989

and July 15, 1982.

4

~ 4$ )t ~ g 4

~

~

(4

APPENDIX

B

Persons

Contacted

The following list contains

those

persons

contacted

by the team during the

inspection.

Those persons

marked with an asterisk also attended

the exit

meeting.

PP&L

J.

P.

  • J
  • R.
  • B
  • p
  • S.
  • R.
  • P
  • C.
  • D

'K.

  • P

E.

  • P
  • C

M,

  • 'g
  • P

M.

  • F
  • P

S.

G.

G.

  • A.

D.

+G.

  • C
  • P

T.

  • R.
  • V

P.

  • J

J.

D..

  • J

A.

  • M.
  • B

Sleva

A.

Personnel

A

s

Bartel

Berger

Bogar

Bozarth

Brady

Bry 1 ins ky

Byram

Cardinale

Coddington

Davis

Deange

1 i s

Dyckman

Eustice

Filchner

Galbrai th

Gulliver

Hecht

Heffelfinger

Hiedorn

Jones

Koste1 ni k

Kuhn

Kuzynski

Maertz

Male

McGann

Morris

Myers

Nudge

Oldenhage

Paley

Reel a

Riley

Rimsky

Robinson

Roth

Rothe'abol

She lbner

Skorus

ND, Electrical

Operations

Site Engineering

Electrical Maintenance

EDSFI

Team

EDSFI Team

Electrical Testing

VP, Nuclear Operations

NPE,

I&C

Licensing

Bechtel

Electrical

Al1egheny E1ectri c

Coordinator,

NQA

ND Electrical

EDSFI Team

Supervising

Engr.

NQA

Exec.

VP, Operations

NQA

EDG

Bechtel

EDSFI Team

EDG

Technical Supervisor

Operations

Manager,

Nuclear Plant Engineering

Compliance

Consultant

Manager,

Nuclear Projects

ND, Electrical

QA

Tech Section

Tech Section

Super visor,

NQA

Tech/Site

Transmission

Senior Compliance Engineer

Electrical Supervisor

Manager,

NQA

Site Engineering

NP Electrical

Electrical

l

~

~ /y

PPKL Personnel

(cont.)

  • G. Stanley
  • B. Veazie

D. Weatherly

  • R. Wehry
  • G. Wetel
  • C. Whirl

NRC Personnel

AAA

<<C. Anderson

  • S. Athavale
  • G. Barber
  • J. Beaton
  • R. Gramm
  • W. Hodges
  • J. Jacobson
  • R. Jolliffe
  • A. Josefowicz

",J. Lara

"B. Liaw

  • R. Hathew
  • 0. Hazzoni
  • J. Stone

Plant Superintendent

EDSFI Team

Relaying

Compliance

Nuclear Plant Engineer

Asst. Hanager,

NgA

NRR

Region I

NRR

Senior Resident

Inspector

Consultant

NRR

Region I

NRR

AEOD

Consultant

Region I

NRR

Region I

Consultant

NRR

B-2

'+W

~ QQ-

f. '*