ML17138A744

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Repts 50-387/79-15 & 50-388/79-09 on 790402-27 & Notice of Violation
ML17138A744
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 06/12/1979
From: Robert Carlson
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Curtis N
PENNSYLVANIA POWER & LIGHT CO.
Shared Package
ML17138A742 List:
References
NUDOCS 7908200280
Download: ML17138A744 (2)


See also: IR 05000387/1979015

Text

t

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

631 PARK AVENUE

KING OF PRUSSIA, PENNSYLVANIA19406

Docket Nos. 50-387

50-388

'am i281~

Pennsylvania

Power

& Light Company

ATTN:

Mr. Norman W. Curtis

Vice President

Engineering

and Construction

(N-4)

2 North Ninth Street

Allentown, Pennsylvania'8101

Gentlemen:

Subject:

Combined Inspection.50-387/79-15

and 50-388/79-09

This refers to the inspection conducted

by Mr. R.

M Gallo of this office on

April 2-27,

1979 at Susquehanna

Steam Electric Station, Units 1 and 2, Berwick,

Pennsylvania of activities authorized by NRC License Nos.

CPPR-101

and

CPPR-102

and to the discussions

of our findings held by Mr. Gallo with Mr. Green of your

staff at the conclusion of the inspection.

Areas examined'ring this inspection. are described in the Office of Inspection

and Enforcement, Inspection, Report. which is enclosed with this letter.

Within

these

areas,

the inspection consisted of selective

examinations

of procedures

and representative

records,

interviews with personnel,

and observations

by the

inspector.

Based

on the results of this. inspection, it appears

that certain of your activities

were not conducted in full compliance with NRC requirements,

as set forth in the

Notice of Violation, enclosed herewith as Appendix A.

These items of noncompliance

have been categorized into the levels as described in our correspondence

to you

dated

December

31,

1974.

This notice is sent to you pursuant to the provisions

of Section 2.201 of the NRC's "Rules of Practice,." Part 2, Title 10,

Code of

Federal Regulations.

Section 2.201 requires

you to submit to this office,

within thirty (30) days of your receipt of this notice,

a written statement

or

explanation in reply including:

(1} corrective steps

which have been taken by

you and the results achieved;

(2) corrective steps

which will,be taken to avoid

further items of noncompliance;

and (3) the date when full compliance will be

achieved.

In accordance with Section 2.790 of the NRC's "Rules of Practice," Part 2, Title

10,

Code of Federal Regulations,

a copy of this letter and the enclosures will

be placed in the NRC's Public Document

Room. If this report contains

any infor-

mation that you (or your contractor) believe to be proprietary, it is necessary

that you make

a written application within 20 days to this office to withhold

V 9089 00 L~

Pennsylvania

Power

6 Light Company

such information from public disclosure.

Any such application must be accompanied

by an affidavit executed

by the owner of the information, which. identifies the

document or part sought to be withheld, and which contains

a statement

of reasons

which addresses

with specificity the items which will be considered

by the

Commission as listed in subparagraph

(b) (4) of Section 2.790.

The information

sought to be withheld shall be incorporated

as far as possible into a separate

part, of the affidavit. If we do not hear from you in this regard within the .

specified period, the report will be placed in the Public Document

Room.

Should you have any questions

concerning this inspection,

we will be pleased

to

discuss. them with you.

Sincerely,

Robert T. Garison,

Chief

Reactor Construction

and Engineering

Support Branch

Enclosures:

l.

Appendix,A, Notice of Violation

2.

Office of Inspection

and, Enforcement

Combined Inspection

Report: Numbers 50-387/79-15

and 50-388/79-09

cc w/encls:

A. R. Sabol,

Manager,

Nuclear Quality Assurance

W. E., Barberich, Licensing Engineer

R. W. Dunn, Superintendent

of Plant