Text
t
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION I
631 PARK AVENUE
KING OF PRUSSIA, PENNSYLVANIA19406
Docket Nos. 50-387
50-388
'am i281~
Power
& Light Company
ATTN:
Mr. Norman W. Curtis
Vice President
Engineering
and Construction
(N-4)
2 North Ninth Street
Allentown, Pennsylvania'8101
Gentlemen:
Subject:
Combined Inspection.50-387/79-15
and 50-388/79-09
This refers to the inspection conducted
by Mr. R.
M Gallo of this office on
April 2-27,
1979 at Susquehanna
Steam Electric Station, Units 1 and 2, Berwick,
Pennsylvania of activities authorized by NRC License Nos.
CPPR-101
and
CPPR-102
and to the discussions
of our findings held by Mr. Gallo with Mr. Green of your
staff at the conclusion of the inspection.
Areas examined'ring this inspection. are described in the Office of Inspection
and Enforcement, Inspection, Report. which is enclosed with this letter.
Within
these
areas,
the inspection consisted of selective
examinations
of procedures
and representative
records,
interviews with personnel,
and observations
by the
inspector.
Based
on the results of this. inspection, it appears
that certain of your activities
were not conducted in full compliance with NRC requirements,
as set forth in the
Notice of Violation, enclosed herewith as Appendix A.
These items of noncompliance
have been categorized into the levels as described in our correspondence
to you
dated
December
31,
1974.
This notice is sent to you pursuant to the provisions
of Section 2.201 of the NRC's "Rules of Practice,." Part 2, Title 10,
Code of
Federal Regulations.
Section 2.201 requires
you to submit to this office,
within thirty (30) days of your receipt of this notice,
a written statement
or
explanation in reply including:
(1} corrective steps
which have been taken by
you and the results achieved;
(2) corrective steps
which will,be taken to avoid
further items of noncompliance;
and (3) the date when full compliance will be
achieved.
In accordance with Section 2.790 of the NRC's "Rules of Practice," Part 2, Title
10,
Code of Federal Regulations,
a copy of this letter and the enclosures will
be placed in the NRC's Public Document
Room. If this report contains
any infor-
mation that you (or your contractor) believe to be proprietary, it is necessary
that you make
a written application within 20 days to this office to withhold
V 9089 00 L~
Power
6 Light Company
such information from public disclosure.
Any such application must be accompanied
by an affidavit executed
by the owner of the information, which. identifies the
document or part sought to be withheld, and which contains
a statement
of reasons
which addresses
with specificity the items which will be considered
by the
Commission as listed in subparagraph
(b) (4) of Section 2.790.
The information
sought to be withheld shall be incorporated
as far as possible into a separate
part, of the affidavit. If we do not hear from you in this regard within the .
specified period, the report will be placed in the Public Document
Room.
Should you have any questions
concerning this inspection,
we will be pleased
to
discuss. them with you.
Sincerely,
Robert T. Garison,
Chief
Reactor Construction
and Engineering
Support Branch
Enclosures:
l.
Appendix,A, Notice of Violation
2.
Office of Inspection
and, Enforcement
Combined Inspection
Report: Numbers 50-387/79-15
and 50-388/79-09
cc w/encls:
A. R. Sabol,
Manager,
Nuclear Quality Assurance
W. E., Barberich, Licensing Engineer
R. W. Dunn, Superintendent
of Plant