ML17083B634

From kanterella
Jump to navigation Jump to search
Forwards Insp Repts 50-275/85-27 & 50-323/85-24 on 850211-0717.No Violations or Deviations Noted
ML17083B634
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 07/19/1985
From: Kirsch D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Shiffer J
PACIFIC GAS & ELECTRIC CO.
Shared Package
ML17083B635 List:
References
NUDOCS 8508080584
Download: ML17083B634 (26)


See also: IR 05000211/2007017

Text

Docket Nos. 50-275

and 50-323;,'i,':"> fan&.",

Pacific Gas

and Electric Company

77 Beale Street,

Room 1451

San Francisco,

California 94106

Attention:

Hr. J.

D. Shiffer, Vice President

Nuclear Power Generation

Gentlemen:

Subject:

NRC Inspection of Diablo Canyon Units

1 and 2

This refers to the special inspecti'ons

conducted

by ILAIL inspectors

under

contract to this office during the period of February ll through July 17,

1985, of activities authorized

by NRC I,icense Nos.

DPR-80 and DPR-81.

Areas

examined during this inspection are described in the enclosed

inspection

report.

Within these

areas,

the inspection consisted of selective

examinations of procedures

and representative

records,

interviews with

personnel,

and observations

by the inspectors.

No violations of NRC requirements

were identified within the scope of this

inspection.

In accordance

with 10 CFR 2.790(a),

a copy of this letter and the enclosure

will be placed in the

NRC Public Document

Room.

E

Should you have any questions

concerning this inspection,

we will be glad to

discuss

them with you.

Sincerely,

.

>.'.

~ t~(;1

c>r s1C8 Ef

D. $'e Ci.'rsih, Acting Director

Divisio'n of Reactor Safety

S Projects

Enclosure:

Inspection Report Nos. 50-275/85-27

and 50-323/85-24

CC;

Jim Knight, NRR

S. D. Skidmore,

PG&E

R.

C. Thornberry,

(Diablo Canyon)

P. A. Crane, Jr.,

PGEZ

D. Taggart,

(Diablo Canyon)

R. Weinberg,

(Diablo Canyon)

Sandra Silver (report only)

State of CA

bcc:

RSB/Document Control Desk

(RIDS)

Hr. J. Hartin

Resident Inspector

RV

JBu

n:dh

MMendonca

ds

7/i

/85

7/g/85

7//f /85

DKir ch

7/y /85

Diablo Canyon

SSER-33

8508080584

8507f9

PDR

hDQCK 05000275

Q

PDR

B. 5-1

Appendix

B

U. S.

NUCLEAR REGULATORY COMMISSION

REGION U

Report Nos.

50-275/85-27

and 50-323/85-24

Docket Nos.

50-275

and 50-323

License

Nos.

DPR-76 and

DPR

Licensee:

Pacific Gas

and Electric Company

77 Beale Street,

Room 1451

San Francisco,

California 94106

Facility Name:

Diablo Canyon Units

1 and

2

Inspection at:

Diablo Canyon Site,

San Luis Obispo County, California

Inspection

conducted:

February

11 - July 17,

1985

Inspectors:

LLNL Contract Inspectors

Approved By:

R. T.

Do ds, Chief

Reactor Projects Section

1

7z

Pr-

ate Signed

Summary:

Ins ection from Februar

11 throu h Jul

17

1985

(Re ort Nos. 50-275/85-27

and 50-323 85-2

Areas Ins ected:

Followup of various allegations pertaining to plant

construction.

Results:

No violations or deviations

were identified.

Diablo Canyon

SSER-33

B.5-2

Appendix B

DETAILS

1.

Persons

Contacted

M. Tressler,

Project Engineer

D. Rockwell, Unit 2 Construction Superintendent

J. Bratton,

PGSZ Allegation Coordinator

D. Dunham,

PGSE

QC Engineer

T. Pierce,

QC Engineer

S. Pascal,

PTGC Electrical Department Engineer

W. Cadwell,

PTGC Electrical Inspector

R. Ortega,

PTGC Electrical Department Engineer

C. Warne,

PTGC Instrument

and Control Department Supervisor

J. Gisclon,

PGSE Assistant Plant Manager

K. Doss,

PGGE Onsite Safety Review Group Mer,'r

H. Karner, Pullman,

QA/QC Site Manager

J. Guyler, Pullman, Internal Auditor

C. Neary, Pullman,

QC Supervisor

C. Gunderson,

PGSZ Allegation Coordinator

C. Dougherty,

PTGC, Pipe Support Group, Engineer

D. McGrew,

PPP, Engineering,

Engineer

G. Thomas,

PTGC, Pipe Support

Group, Supervisor

G. Vincent,

QC Hotline

G. Morrison,

PTGC Electrical Department Engineer

R. Cook,

PGSZ Allegation and Rate-Case

Supervisor

M. Lepke,

PGSE Onsite Engineering Supervisor

G. Klemm,

PTGC Mechanical Department Piping Engineer

R. Seewald,

PTGC Mechanical Engineer

G. Johnson,

PGSZ,

PTGC Special Projects

Engineer

R. McBay, BCI,

PTGC QA/QC Records

Supervisor

D. Delfino, Pullman Power Products,

Mechanical Engineer

NOTE:

The allegation characterization

statements

contained in this

report are either

a paraphrasing

of the staff's understanding

of the

allegers

concern or statements

taken from the allegation source

document.

The characterization

statements

do not represent

a staff assessment,

conclusion or position.

2.

Task:

Alle ation or Concern Nos.

200 and

201

ATS No:

RV-84-A"030

a.

Characterization

The

PGSE nondestructive

examination

(NDE) weld inspection reports

are inconsistent with Foley inspection reports and/or the

NDE

reports

were changed

by Foley without the approval of the

PGEZ

inspection

team.

b.

Im lied Si nificance to Desi

n

Construction or

O eration

The allegation implies that the

NDE inspection results

maybe

compromised

due to record falsification which may allow uninspected

or defective welds to exist in a safety-related

structure.

Diablo Canyon

SSER-33

B.5-3

Appendix

B

c ~

Assessment

of Safet

Si nificance

The staff reviewed the original NDE reports related to this

allegation referenced

by PG&E response

DCL-84-186.

Changes

in the

weld NDE identification numbers

were noted by a single line

cross-out with the initials of the person performing the change.

No

changes

were

made that totally obliterated the original.

The

changes

were for identification only because

each

NDE report

identifies the weld joint by connection

number, detail drawing

number

and reference

drawing, eliminating the possibility that the

wrong joint was inspected

and/or repaired.

For example,

a full penetration

V-groove butt joint is identified by

Foley by two separate

weld numbers.

One number is, for the face

and

one is for the root.

In certain instances

on vertical or horizontal

weldments

these

weld numbers

were inadvertently reversed

due to the

inspectors orientation while inspecting the weld. If the inspector

was on the outside looking into the fuel handling building he may

call the face of the weld No.

1 and the root No. 2. If he was

oriented from the "inside looking out" these

numbers

were reversed.

This situation

was rare

due to Foley's

QCP-6 requirement that the

inspectors participate in a continuing training program at least

once every three months.

This training, emphasized

orientation of

prints and weld inspection sheets.

d.

-Conclusion

and Staff Position

The allegation that

PG&E inspection reports

are inconsistent with

Foley's inspection reports is substantiated

in rare instances,

but

the inconsistencies

are of weld identification number only and

present

no adverse

safety significance.

The staff, upon review of

the

NDE REPORTS found no evidence of unauthorized alterations of the

reports.

e.

None.

3.

Task: Alle ation or Concern

No.

0219

ATS No:

RV-84-A"045

a

~

Characterization

Construction work on the

PAM-2 panel in Unit 2 was transferred

from

HP Foley to PGGE.

It is alleged that this action was contrary to

procedures

and was

done to bypass Quality Control inspections.

b.

Im lied Si nificance to Desi

n

Construction

and

eration

Bypass of procedures

in this case

could result in inoperability of

this portion of the Post-Accident Monitoring System

when called upon

to operate

and could indicate the possibility of a more general

failure 'to fully implement the Diablo Canyon

QC program.

Diablo Canyon

SSER-33

B. 5-4

Appendix

B

c ~

Assessment

of Safet

Si nificance

The process for PG&E modifications to equipment during construction

was reviewed.

Modifications of this nature are controlled by QC

procedures

DCP-10 and DCP-19.

Both procedures

are applicable to

work on safety-related

equipment

and require

QC review of the work

plans

and

QC inspection

and sign off of modifications to

safety-related

equipment.

Documentation of activities conducted

under these

procedures

is maintained via form E-72 for DCP-10 and

E-53 for DCP-19.

In order to determine if these

procedures

were correctly applied to

the

PAM-2 panel in Unit 2, the E-72 and E-53 logs were examined to

identify modifications

made by PG&E.

This examination

looked for

log entries identified as being associated

with PAM or with Design

Change Notices that affected

PAM-2, as determined

from the revision

description for the

PAM-2 wiring diagrams

435796

Rev.

2 and 435797

Rev. 2.

This process identified

a number of E-53's

and E-72's that

may have been related to the Unit 2 PAM-2 panel.

Each of these

candidate

records

were reviewed;

E-72 number

642 and E-53 number

2082 were identified as the only PG&E conducted modifications

on the

Unit 2 PAM-2 panel during construction.

In both cases,

the work was

identified as Class

1 and the required

QC approvals

were obtained.

d.

Position

Modifications to the Unit 2 PAM-2 panel that were done during

construction by the

PG&E Project

Team General Construction

and the

Dry Run Test Group were performed in accordance

with approved

and

applicable

PG&E procedures.

Documentation

generated

by these

modifications provide evidence that the

QC inspections

and reviews

required by the procedures

were conducted.

e.

None.

4.

Task:

Alle ation or Concern No. 0378

ATS No: RV-84-A-062

a ~

Characterization:

A QC inspector alleges that he was never provided with support to

perform his duties,

nor was he provided with proper training.

b.

Assessment

of Safet

Si nificance

Staff reviewed the affidavit to determine

when the alleger

was

employed by the H. P. Foley Company

as

a

QC inspector.

The staff

subsequently

examined

copies of QC inspector training records

encompassing

the indicated time period.

Diablo Canyon

SSER-33

B.5-5

Appendix

B

The staff review of the documented training records

shows that

H. P. Foley Company conducted

over 750 quality related training

sessions

from January

1981 to December

1983.

The number of people

attending

each session

ranged

from one to twenty.

A review of specific training records indicate that the individual

involved received

classroom training in at least twelve different

gA/QC Procedures,

as

documented

on H. P. Foley "equality

Indoctrination and Training Records"

dated

March 25,

1981, April 1,

1981, February

16,

1983 and March 8,

1983.

The training records

are

all signed by the alleger.

In addition to classroom training, the

alleger also received

over 90 days of on-the-job training.

C.

Conclusions

and Staff Position

The allegation that

a

QC inspector

was not provided with adequate

training cannot

be substantiated.

Staff review of H. P. Foley

training records provide evidence that extensive

gA/(}C training was

indeed conducted.

The portion of the allegation that implies the

inspector

was "not provided with support" lacks specificity, and

cannot

be substantiated.

The allegation

has

no safety significance.

d.

Actions Re uired

None.

5.

Task:

Alle ation or Concern

No.

0624

ATS No:

RV-84-A-052

a

~

Characterization

PG&E officials failed to correct

a false statement

to the

NRC that

the

Company

was ignorant of inaccuracies

in the plant manual for

operators.

b.

Assessment

of Safet

Si nificance

Staff review of the allegers affidavit indicates that,

an inaccuracy

in Volume 16 of the Plant Manual is the source of the allegation.

The necessary

correction involved a hi-lo level alarm on the reactor

coolant

pump lube oil system which was incorrectly identified as

a

lo-level alarm only.

Volume 16 of the Plant Manual is discussed

on

three separate

occasions

in the affidavit, specifically:

1)

Page

13: "...I had repeatedly notified PG&E management

(including a

memo to Mr. Thornberry,

the Plant Manager,

which

is enclosed

as exhibit 8) of an error in Plant Manual

Volume 16...."

2)

Page

14: "...PG&E claimed ignorance of any errors in Plant

Manual,

Volume 16,

even though I had written memo's

on the

subject to both John Gisclon and Mr. Thornberry,

the Plant

Diablo Canyon

SSER-33

B.5-6

AppendixB

Manager,

and given copies of these

memos to the

NRC the

previous August."

3)

Page

31: "...I had complained to the

NRC that an error which I

discovered in the Plant Manual,

Volume 16,

'Annunciator

Response'as

still uncorrected

eight months after I had

reported it.

NOTE: this problem was ultimately not corrected

until January of 1983, over 20 months after I identified the

problem...."

GAP letter dated February 2,

1984,

page

49, paragraph

170 states

that "at a 1982 meeting,

PGSE failed to correct

a false statement

to

the

NRC staff that the

company

was ignorant of inaccuracies

in its

Plant Manual for Operators."

PGSZ's

response

to this allegation dated

March 29,

1984,

substantiates

that the subject of inaccuracies

in the Plant Manual

were not discussed

at the exit interview on January

7,

1984,

and

that Mr. Gisclon and Mr. Thornberry did not have the opportunity to

correct this impression.

The

PGSE response

further stated, "...in

fact, however, corrective action was already underway."

The "Corrective Action that was already underway" consisted

of:

Response

to the alleger's

memo dated

June 9,

1981 acknowledging

the problem and indicating that it would be corrected.

Copies of the proposed

changes

were sent to the alleger by

Rob Fisher

on January ll, 1982.

"An on-the-spot

change" to Volume

16 of the Plant Manual was

issued

on January 5,

1983, at the request of NRC.

Permanent

revisions to Volume 16 of the Plant Manual, including

correction of the annunciator

response

problem were

incorporated in Revision 3, dated July 15,

1983.

c

Conclusions

and Staff Position

The allegation that inaccuracies

in the Plant Manual were not

discussed

at

a 1982 meeting

can be substantiated.

However,

PG&E has

taken the appropriate

action to correct the Manual (Ref:

Rob Fisher

letter dated January

11,

1982).

The manual

was corrected in

September

1983 prior to loading fuel in Unit

1 in November of 1983.

The staff concludes that this allegation

has

no safety significance.

d.

Action Re uired

None.

Diablo Canyon

SSER-33

B.5-7

Appendix

B

6.

Task:

Alle ation or Concern

No.

0789

ATS No:

RV-84-A-064

a

~

Characterization

Welded extension bars at the

119 level in Unit 2 were inspected

and

bought off, but did not meet specifications

or drawing requirements.

b.

Im lied Si nificance to Desi

n

Construction or 0 eration

Welded extension for decking supports not meeting specifications

or

drawings

may present

a safety hazard

due to failure upon loading.

c ~

Assessment'of

Safet

Si'ificance

The staff on another allegation (reference

allegation

995,

ATS:

RV-84-A-064) conducted

an investigation to establish its validity

and as

a consequence,

examined inspection records for the

119

foot level.

Several inspection discrepancies

were found.

One of

the three corrective actions

taken by Guy F. Atkinson,

Co.

(GFA) was

to reinspect all related field work at the

119 level.

Of the 900

items to be reinspected,

42 were found inaccessible

due to status of

the construction work.

The remainder

were either found acceptable

or minor repairs

were made.

The inaccessible

items were accepted

without reinspection

by PG&E following an evaluation by the

PG&E

engineering staff.

d.

Staff Position

Based

on the significance of identified discrepancies,

the staff

concludes that there is reasonable

assurance

that the welded

extensions

meet the specifications

and drawings.

e.

Action Re uired

None.

7.

Task:

Alle ation or Concern

No. 0833

ATS No:

RV-84-A-064

a ~

Characterization

A welder disregarded

the

ISO drawing, field installation

instructions,

process

sheet instructions,

weld rod requisition

instructions

and then incorporated his

own welding procedure.

b.

Im lied Si nificance to Desi

n

Construction or

eration

The failure of a welder to weld in accordance

with the qualified

weld procedure

could result in a defective pipe weld and the

inability of a safety-related

pipe system to perform its intended

function.

Diablo Canyon

SSER-33

8.5-8

Appendix

B

c.

Assessment

of Safet

Si nificance

The staff reviewed the Pullman Power Products

(PPP) internal audit

number

85 for 1981, which was the basis for the allegation.

Audit

number

85 was performed

on 10 CFR 50'Appendix B, Criterion XVI,

Corrective Action.

Audit action request

No. 4-4 was the specific

finding in the audit report.

The original documentation

was retrieved

and reviewed from the

records vault and all procedures

or specifications in effect at the

time of the audit were obtained.

The field work was

shown

on

PPP

isometric drawing No. 23-21 Revision "F".

Field welds

477 and 478

attach

a stainless

steel valve FCV 658 to a 4-inch, schedule

40

carbon steel pipe.

These welds were

made

on February

10 and ll,

1981.

The first of the three-part audit finding stated that the welder

disregarded

the

GTAW/SMAW weld procedure

(WP 149). and continued to

use

GTAW for the weld-out

(WP 150).

This statement is incorrect.

It misrepresents

the requirements

of weld procedure

149, which

permits

1 to 3 passes

of GTAW after the root pass.

In this case,

a

consumable insert was used to weld the 0.237 inch wall thickness

pipe to the valve.

In a weld of this configuration,

no more than

three

GTAW cover passes

would be required to complete the weld.

Hence,

the complete

GTAW geld-out per procedure

WP 149 is identical

to

WP 150.

The weld procedure

change to the process

sheet

was

made

by the field engineer

on February

10,

1981, which means

the

change

was prior to or at the time of the welding.

There

was

no attempt

made by the welder 'to use "his own" procedure.

In this case,

the design of the pipe is not affected by use of

either

WP 149 or

WP 150.

The weld procedure specifications,

procedure qualification records,

and welder 'qualification records

for both procedures

were found acceptable.

The, second part of the audit finding was that according to the weld

rod requisition sheets,

welding occurred

on February ll, 1981, while

the process

sheet

noted welding was completed

on February

10,

1981.

ESD-264 requires

the

PPP inspector to fillall the blocks

on the

field process

sheets

and not the individual performing the operation

(the preferred method).

The method used required the welder to

notify the inspector

when welding was complete

and to enter it on

the process

sheet.'SD-202

required the weld foreman to fillout

the weld rod requisition sheets

the dsy ~rior" to the weld heing

made.

A detailed review of the field process

and weld rod

requisition sheets

for both

FW 477 and 478 showed that the

inspector,

not the welder, filled in the completion date

as

February

10,

1981,

a day earlier than the filler requisition date.

The process

sheet indicated that no welding was performed after the

final inspection by the

PPP inspector.

All welds were subsequently

visually inspected

and radiographed

before acceptance.

The third part of the finding states

that the field engineer did not

initial, date

and explain changes

made

on the process

sheets.

After

Diablo Canyon

SSER-33

B.5-9

Appendix B

reviewing the

FW 477 and 478 process

sheets, it was found that the

field engineer did sign and date the weld procedure

change

on both

process

sheets.

The field engineer did not initial and date where

the

same

change

occurred redundantly

on the

same form.

There

was

no

written explanation of the

change but it was clearly evident the

change

was from WP 149 to

WP 150.

ESD-264 paragraph

7.2 only

requires explanation of changes

and not the reason for the change.

Again, from the foregoing evaluation,

there

was no need to make this

change to the process

sheet.

The staff reviewed several

subsequent

audits for the follow-up

actions to this audit.

1982 Internal Audit Number

31 dated July 6,

1982,

on 10 CFR 50 Appendix B, Criterion XVI, Corrective Action and

1982 Internal Audit Number 35 dated

December

1,

1982

on Criterion

IX, Special

Processes

were reviewed to see if similar problems noted

in 1981 Audit Number

85 were still detected.

Audit 31 was

an

"unscheduled" audit. It was never completed

and

was voided by the

internal auditor on approximately July 6,

1982.

The checklist for

Audit 35 has

an item No.

4 which was to verify that there were no

deviations

from the required weld procedures.

However, the audit

results did not indicate whether the status of work performed

was

acceptable

or not.

Subsequent

audits

examined,

such as Audit 118

dated

May 27,

1983 on Criterion X, Inspection

and Audit 131 dated

April 24-30,

1984 on Criterion IX, Special Processes,

were complete,

accurate

and had

a checklist of reported results.

For example,

the

response

to Audit Action Request

No.

5 of Audit 118 showed the

corrective action and steps

taken to prevent reoccurrence

were

appropriate

and consistent with the finding.

d.

Conclusions

and Staff Position

The allegation that

a welder disregarded

the weld procedure

and

process

sheet

cannot

be substantiated.

The staff has

concluded that

Audit Action Request

No. 4-4 of PPP Internal Audit Number

85

appeared

to misrepresent

the situation

as evidenced

by the original

documentation.

-The weld procedure

was correctly implemented.

It

appears

that the inspector errored in his entry of the weld

completion date,

not the welder.

The changes

made to the process

sheet

were not necessary

but,

even having been

made,

they still met

the intent of the requirements.

There is no apparent

safety

significance to this allegation.

e.

Actions Re uired

None.

Diablo Canyon

SSER-33

B.5-10

Appendix B

8.

Task:

Alle ation or Concern

No.

0995

ATS No:

RV-84-A-064

a

~

Characterization

Inspection work performed under Atkinson's control in 1978 in the

northwest corner roof area of turbine building was performed by a

questionable

inspector.

b.

Im lied Si nificance to Desi

n

Construction or

eration

An unqualified inspector

could permit unsatisfactory

construe'tion

work to go unrepaired resulting in structural failure.

c ~

Assessment

of Safet

Si nificance

Upon disclosure of the identity of the alleged unqualified

inspector,

the staff proceeded

to investigate

the individual's

qualifications

and the extent of his participation in the inspection

of the construction of the Turbine Building roof.

In accordance

with the

Guy F. Atkinson Company

(GFA) Diablo Canyon

Project Specification No. 5442, Quality Assurance

- Personnel

Q.8-9,

the inspector

was indoctrinated,

trained

and certified (effective

August 2,

1978)

as

a Structural Steel Welding and Erection Inspector

by GFA's Quality Assurance

Manager consistent with GFA's Quality

Control Procedure

13.

The supporting documentation

(references

2,

3,

and 4) was reviewed

and found acceptable.

Contrary to the allegation,

the inspector did not perform any work

of record in the turbine building roof area.

Inspection records for

the roof structure

generated

by GFA during the period of the

inspectors

employment at Diablo Canyon were examined

and his

signature

did not appear.

Although the foregoing clearly resolves

the specific allegation,

further investigation

was conducted to establish

the validity of the

allegation with respect

to the work actually performed by the

inspector.

As

a consequence,

inspection records for the

119 foot

level (location derived from reference

1) were examined for the

period of the inspector's

employment.

Several inspection

discrepancies

were identified that had also been found and

documented

by NCR 293 dated April 17,

1979, during an audit of

inspection records

performed by GFA.

The audit was conducted in

accordance

with GFA - QCP-15 (reference 5).

Virtually all of the

discrepancies

described

by the

NCR were attributed to the inspector

in question.

The corrective actions taken by GFA were to:

1)

conduct

a thorough review of all of this inspector's

documentation,

2) reinspect all related field work and,

3) not rehire the

individual who had already terminated to return to college.

The inspector

was found to have been involved with 900 items

and

750

(83@ of these

were reinspected

and found acceptable

(reference

7).

Diablo Canyon

SSER-33

B.5-11

Appendix

B

10

Of the remainder

108 (12$ ) were found to have minor deficiencies

that were quickly repaired

and 42 (5'j) 'were inaccessible

due to the

advanced

state of construction at the time of the

GFA audit.

Half

of the inaccessible

items had been ultrasonically tested

and

accepted

by another inspector

and, therefore,

also accepted

by PG&E

based

upon the availability of test records.

The remaining

21 items

were accepted

by the

PGGE engineering staff on the basis that "welds

were either not critical to resist loads, or margins between weld

size

shown on design drawings

and weld size required to resist

design loads were more than adequate

considering limited

deficiencies that might exist."

d.

Conclusions

and Staff Position

The allegation

as stated

could not be substantiated

to the extent

that the inspector

met all of the requirements

established

for the

job and that no evidence

could be found that he had performed

inspection work in the northwest roof area.

However, further

investigation did validate significant deficiencies in the

inspector's

performance in another location which had been

identified by the licensee's

gA program

and properly dispositioned,

including the evaluation of inaccessible

welds.

e.

Actions Re uired

None.

9.

Task:

Alle ation or Concern

No.

1062

ATS No:

RV-84-A-064

a ~

Characterization

Missized or improperly installed

beam

clamps

have been

used to

fasten

raceway support struts to structural

beams.

b.

Im lied Si nificance to Desi

n

Construction

and 0 eration

Inadequately

supported safety-related, raceway could result in

degradation

or failure of critical power, control or instrumentation

circuits during events (e.g.,

earthquake)

that cause

abnormal

loading of the raceway supports.

C ~

Assessment

of Safet

Si nificance

The sketches

provided

as part- of the allegation indicate that the

Unistrut F2785

and P2786 style beam

clamps are the items of concern.

This is the predominate

beam

clamp style in use at Diablo Canyon.

This type of clamp is

a angled piece of plate steel that captures

the foot of a beam between it and the framing channel.

The plate is

held in place

and tightened against

the beam by a U bolt which is

installed around the framing channel

and through the plate

(see

Diablo Canyon

SSER-33

8.5-12

Appendix 8

Sketch)-.

Vendor catalogs

and

PGSE drawing 50030 Revision

30 require

that these

clamps always

be used in

pairs'eview

of the Unistrut, Power Strut and Super Strut catalogs

shows

that Unistrut produces

two clamp sizes in this style,

Super Strut

three sizes

and Power Strut two sizes.

In all cases,

the only

difference between the different size

clamps of each vendor is the

U-bolt length. If a clamp with too short of a U-bolt is selected,

the clamp will not fit in the application because

U-bolt threads

will not extend sufficiently beyond the clamping plate to allow

installation of the U-bolt nuts. If a clamp with too long of a

U-bolt's selected,

then it is possible that the U-bolt nuts would

reach the end of the threads

before the clamp was completely tight.

The selection of the wrong size clamp will not, in and of itself,

result in a loose attachment of strut to beam.

Loose

clamps will

only occur if the U-bolt nuts are not properly tightened.

The results of previous

NRC raceway support inspections

were

reviewed

and additional inspection 'of beam

clamp installation was

conducted.

As

a part of the

NRC inspection of the seismic

reverification program,

300 raceway supports

were inspected

including 24 supports

whose design allowed for the use of beam

clamps.

No loose

beam clamps

were identified during these

inspections.

d.

In response

to this allegation

an additional

200 beam

clamps

on

raceway supports in both Unit

1 and Unit 2 were inspected for

tightness.

During this inspection

one loose

beam

clamp was

identified.

In this case,

the proper size U-bolt was employed,

however,

the nuts were simply not sufficiently tightened.

PGSE

issued Minor Variation Report No.

3281

on April 2,

1985, to tighten

the clamp.

H

Conclusions

and Staff Position

The review of vendor information establishes

that the size of beam

clamp used

does not directly affect the tightness of the clamp. It

is further concluded

from the results of 'raceway support inspections

that loose

beam

clamps

has not been

a generic problem at Diablo

Canyon.

e.

None.

10.

Task:

Alle ation or Concern

No.

1270

ATS No:

RV-84-A-071

a ~

Characterization

PGGE response

that an individual was not aware of orders to stop

working on hangers is misleading.

Another individual" gave the stop

Diablo Canyon

SSER-33

/

B.5-13

Appendix B

work order, but the individual who claims to be unaware of the order

should have

known about it.

b.

Im lied Si nificance to Desi

n

Construction

and

eration

The allegation is not sufficiently detailed to allow an assessment

of its significance to design,

construction

and operation.

Generally,

stop work orders

are issued to hold construction while

problems with design, materials or procedures

are resolved

so the

amount of rework required is minimized.

In this regard, failure to

be aware of or to comply with a stop work order would be more likely

to have economic significance

than safety significance.

c.

Assessment

of Safet

Si nificance

The portion of the allegation provided to the investigation

team did

not specifically identify the subject or time period of the order to

stop work that is in question.

It is assumed

that the order in

question

was

a formal stop work order

on pipe support installation

and that the order could have occurred

between

March 1983 and April

1984.

The general

subject of stop work orders

on pipe supports

was

discussed

with a pipe support supervisor

and

a group engineer of

PTGC.

They stated that one significant stop work order issued

during this interval involved supports that were being evaluated

by

engineering

as part of the seismic reverification program.

Pullman

Power Products

(PPP)

was instructed to stop construction

on these

supports

by a

memo from G. A. Thomas to H.

W. Karner dated August 8,

1983.

The intent of this order was to stop work on supports that

might be subject to

a design

change

as

a result of the

reverification program.

It was stated that

PPP issued

stop work

orders

on the supports in question

and hung hold tags

on each

support.

Failure to stop work on any support in this case

would

have

no safety significance,

as

any design

change to a support would

be implemented whether or not construction

on the support

was

continued.

The

PPP Pipe Support stop work orders

were reviewed for the interval

in question to audit Pullman's

performance in response

to stopping

work on the supports

discussed

above

and to determine if other

irregularities exist that might be the source of the allegation.

A

sample of the supports identified in the August 8,

1983

memo

was

selected

and it was verified that for each

sample

case,

a

corresponding

PPP stop work order

was issued.

During the review of

the stop work orders it was noted that one

PTGC

memo dated

September

15,

1983,

was referenced

by stop work orders

through March

1984.

This apparent

discrepancy in dates

was investigated

and it

was determined that the September

15,

1983

memo instructed

PPP of a

policy change that could also be the source .of the allegation

as

discussed

below.

Pullman Power Products

procedures

require that construction

work on

a support

be stopped

when

a new revision of the drawing for that

Diablo Canyon

SSER-33

B.5-14

Appendix

B

13

support is received.

When

a new revision is received

a stop work

order is issued,

the old construction

package is pulled back from

the field, a new construction

package is issued

and the construction

hold is removed.

As

a result of problems

encountered

in

construction,

PTGC instituted

a pipe support preinspection

program

that evaluated

new designs for constructibility before they were

turned over to PPP.

During the time new drawing revisions

were

under review by the preinspect

group,

PPP

was not formally aware of

the new revisions

thus construction work on the affected supports

continued

even though

new drawing revisions

were onsite.

This

apparent violation of PPP procedures

was noted by preinspect

group

inspectors.

However, since

PPP had not received

the

new revision,

their actions

were in accordance

with written procedures.

Initially, no action was taken

on this problem because

PG&E judged

that

a minimal amount of rework would be required

as

a result of

construction continuing while the new design revisions

were under

consideration

by the preinspect

group.

After an instance

was

identified where significant rework would have been required

had

construction continued during preinspection,

PPP

was instructed to

stop work on any support

when the

PTGC preinspect

group received

a

new revision of drawings for that support.

This policy change

was

transmitted

by the September

15,

1983

memo from G. A. Thomas to

H.

W. Karner.

Review of the

PPP stop work orders

from the time of

the

memo forward indicated that

PPP consistently

implemented this

policy.

Even if this were not the case,

failure on the part of PPP

to stop work on

a support would have

no safety significance since

the support would eventually have to be reworked to comply with the

latest drawing revision.

d.

Conclusions

and Staff Position

No irregularities were noted in the

PPP pipe support stop work

orders during the interval of March 1983 through April 1984.

The

two issues

that resulted in the majority of stop work orders during

this interval were investigated

and appear to have been handled

properly by PGSZ and

PPP.

Therefore,

an allegation that stop work

orders during this were not properly implemented or that key

individuals were not aware of stop work orders

cannot

be supported.

Furthermore, failure to take proper action on the stop work orders

reviewed would have

had economic impact, but no safety impact.

e.

None.

ll.

Task:

Allegation or Concern

No.

1381

ATS No:

RV-84-A-073

a

~

Characterization

A nut could not be properly installed

on an embedded

stud that

attaches

a main feedwater pipe support to the containment wall.

The

Diablo Canyon

SSER-33

B.5-15

Appendix

B

14

nut was cut in half and tack welded to the base plate.

This problem

is described in Diablo Canyon Problem Report 1-2335-P.

b.

Im lied Si nificance to Desi

n

Construction

and

eration

An improperly supported

feedwater pipe could result in a loss of

feedwater, during

a transient that places

abnormal. loads

on the

support.

The pipe support in question is upstream of the main

feedwater

check valves

so that problems with this support would not

impair the ability to provide auxiliary feedwater.

Nevertheless,

the support in question is classified

as safety-related

by PG&E.

c ~

Assessment

of Safet

Si nificance

Diablo Canyon Problem Report DP-1-2335-P contains

a detailed

description of the condition that is the source of this allegation.

The embedded

mounting studs for support

1048/8SL were too short to

allow complete thread

engagement

for the base plate nuts.

As

a

field fix, the nuts were cut in half longitudinally, installed

on

the studs

and tack welded to the base plate.

Engineering approval

of this configuration was provided

on February

14,

1979, in response

to the problem report.

.Approval was based

upon

a determination that

enough threads

were engaged

to allow the full bolt strength to be

developed.

The unusual configuration of the base plate attachment

was again

noted during final gC inspection of the support.

The discrepancy

report generated

as

a result of this inspection

(PPP

DR 5734)

questions

the suitability of the nut tack welds since neither the

nut material or the welding procedure

used could be established.

This item was resolved by memo from J.

A. Longworth to J. Arnold and

R. Tinkle dated January

20,

1984, which recommended

that the nut

welds be accepted

as is, since the welds serve only to prevent the

nuts from backing off and are not assumed

to add any structural

strength to the support.

The partial engagement

of the base plate nuts is documented

on the

as-built drawing for the support

and the as-built configuration was

accepted

by PG&E engineering.

Some confusion about

PG&E's ultimate acceptance

of the nut tack

welds

may have resulted

from the fact that

DR 5734 also identified a

number of undersized structural welds

on the support.

Pipe Support

Design Tolerance Clarification Form No. TC-1-14461 indicated that

some of these

welds were unacceptable

as is and should be reworked.

The rework required by TC-1-14461

was completed

and the resulting

support configuration was incorporated into the as-built drawings.

TC-1-14461

does not address

the nut tack welds.

d.

Conclusions

and Staff Position

The condiiion described in the allegation exists in the field.

This

condition was documented

as

a discrepancy

on two separate

occasions

and was properly dispositioned

on both occasions.

Diablo Canyon

SSER-33

B. 5-16

Appendix

B

e.

Action Re uired

None.

12.

Task:

Alle ation or Concern

No.

1264

ATS No:

RV-84-A-071

a

~

Characterization

PG&E response

to

GAP allegation No.

259

on walkdown by personnel

who

marked-up

drawings

used by equality Control is misleading.

The

people were not qualified.

b.

Assessment

of Safet

Si nificance

The implied safety significance of this allegation is that the

quality of safety-related

systems

may be compromised if they were

analyzed

and constructed

using improper drawings.

C.

Assessment

of Safet

Si nificance

The source of this allegation

was

GAP submittal No.

120 dated

June

21,

1984, attachment

10, page

12, which states

that PGSE's

response

to

GAP allegation

No. 259 is misleading regarding

qualification of personnel

performing walkdowns.

The alleger is concerned

that unqualified personnel

worked on the

drawings

and that "those drawings were used for gC inspection work

throughout the plant and for engineers

to make decisions

on the

acceptability of design changes."

It is not apparent that the alleger understands

the use of drawings

that are marked-up

as

a result of walkdowns

~

Marked drawings that

result from walkdowns are used for updating as-built drawings which

are later analyzed

and used for gC inspection.

The

NRC staff examined

the concern regarding qualification of

walkdown personnel

by: reviewing PG8Z instructions

and procedures

for walkdown inspections;

reviewing

a sample of ISO drawings

used

for the walkdowns;

and verification of training of individuals who

signed the drawings

used for walkdowns.

PGSE instruction entitled "Field Reverification Procedure for Piping

Isometrics"

was prepared

in response

to

NRC Bulletin 79-14

on

March 10,

1982,

and was revised

on April 12,

1982.

On May 6,

1982,

PG&E engineering

assumed

control of the procedure,

and re-issued it

as instruction numbers I-17 for large bore pipe and I-18 for small

bore pipe.

The

NRC staff randomly selected

seven isometric drawings that were

marked-up during walk-downs,

and recorded

the

names of individuals

who signed the drawings.

Diablo Canyon

SSER-33

B. 5-17

Appendix

16

Training records

were later reviewed,

and, in all cases,

personnel

who performed the walk-downs

and signed the drawings

had been

previously trained in the walkdown procedure.

Review of PGSZ's

79-14 Training File indicates that over 50 people

have been trained

in the walkdown procedures.

No violations were identified.

d.

Staff Position

The staff concludes that personnel

who performed walk-downs were

adequately

trained

and qualified to do the work.

None.

13.

Task:

Alle ation or Concern

No.

1397

ATS No:

RV-84-A"073

a

~

Characterization

On diesel generator fuel oil transfer

system pipe support (support

number 20/85R),

a nut is bearing

on a weld and half of a shim plate.

This condition is not shown on the as-built drawings, but is shown

on pipe support tolerance clarification form TC-1-11497.

b.

Im lied Si nificance to Desi

n

Construction

and

0 eration

A improperly supported

pipe in the diesel fuel oil transfer

system

could result in eventual failure of one diesel generator

following

conditions

(such as

a seismic event) that imposed

abnormal

loads

on

the piping system.

c ~

Assessment

of Safet

Si nificance

A copy of the drawings for support

20/85R was obtained

and the

support

was inspected

against

the drawing.

The inspection

confirmed

that the condition described

by the allegation exists.

Specifically:

Line 1-2-J-2599-2" rests

on

a shim plate that is welded to one

of the support cross

members.

A U-bolt is installed around the

line and through holes that were drilled partially through the

shim plate

and partially through the weld material.

U-bolt

nuts are installed

on the top side of the ship plate to provide

for the design spacing between the pipe and the U-bolt.

The

U-bolt is secured

from underneath

by a nut and

a lock nut on

each side.

The top nuts rest partially on the shim plate

and

partially on the weld.

These nuts are the source of the

allegation.

Contrary to the allegation,

the correct version of the hanger

drawing for this support details this configuration

(Drawing 049318

sheet

110B Section

D-D in conjunction with section

E-E on sheet

Diablo Canyon

SSER-33

B.5-18

Appendix

B

17

llOH).

These details

were added

by either revision

3 or revision

4

of the drawing.

In both cases,

the Field Correction Transmittal

form documents that the as-built configuration has either been

factored into the support calculations

or that the calculations

have

been reviewed to verify that the condition does not affect the

adequacy of the support.

d.

Conclusions

and Staff Position

The condition described

by the allegation exists in the field,

however,

PG&E has

documented,

assessed

and accepted

the

configuration described.

More than enough weld material remains after drilling holes for the

U-bolt to insure secure

attachment

of the shim plate to the support.

The incomplete seating provided for the top U-bolt nuts is of no

consequence

since the nuts are only used to support the U-bolt in

order to provide the designed

gap between the U-bolt and the pipe.

Therefore,

the staff agrees

that the condition observed

does not

adversely affect the adequacy of the support.

e.

None.

14.

Task:

Alle ation or Concern

No.

1486

ATS No:

RV-84-A-113

a

~

Characterization

An individual questions

the acceptability of capped'ff lines coming

from the reactor vessel

support pads.

b.

Im lied Si nificance to Desi

n

Construction

and 0 eration

C.

Capped lines could be indicative of incomplete construction work.

Assessment

of Safet

Si nificance

The piping and Mechanical Drawing (Drawing 50152

Change

3) of the

rea'ctor vessel

support block was examined to identify pipes

coming

from the support pads.

Twenty four pipes were identified.

Inspection of this piping in the Units 2 containment

confirmed that

lines 2K1696,

2K3003,

2K391,

2K1,702,

2K2947,

2K400, 2K1700,

2K2254,

2K395,

2K1698,

2K3008 and 2K393 are capped.

The piping and instrument diagram for the Component Cooling Water

System

(Drawing 108014 sheet

7) shows these lines as Cooling Water

lines to spare Reactor Vessel support coolers

and that they are

capped per design.

Diablo Canyon

SSER-33

B. 5-19

Appendix B

18

d.

Conclusions

and Staff Position

The capped lines coming from the reactor vessel

support, pads

are for

spare

equipment

and are

capped per design.

e.

None.

15.

Task:

Alle ation or Concern

Nos.

1566 and

1567

ATS No:

RV-84-A-115

a

~

Characterization

Welders worked without shielding

gas flow meters

and incompatible

meters.

b.

Im lied Si nificance to Desi

n

Construction "or 0 eration

Welds

made without shielding

gas flow rate information or inaccurate

information could possibly result in oxidized weldments, with lower

mechanical

and physical properties of the base material,

thus not

meeting the original design criteria.

C.

Assessment

of Safet

Si nificance

During an audit of welder performance

by Pullman Power Products

equality Assurance

on June 4,

1984, it was discovered that

a welder

was using

a flowmeter that

was not identified as

an acceptable

flowmeter in weld procedures

ESD-213 and ESD-219.

Further

investigation by Pullman revealed that improper and uncalibrated

pressure

regulators

were also in use.

These deficiencies

were

documented

by Pullman Power Products

on Deficient Condition Notice

(DCN) Number 96-058,

dated

June

7,

1984.

Pullman Power then

prepared Deficiency Reports

(DR's)

8657

and 5946,

and submitted

them

to PGRE for disposition.

PG&E's investigation resulted in a revision to PPP Procedures

ESD-213 and ESD-219.

The revisions included

a description of and

instructions for the use of additional types of flowmeters,

including those

found during the audit.

Supplementary

instructions

were issued to all welders

and

(}C personnel

were indoctrinated in

proper flowmeter and regulator use.

PGScE investigated'egulator

calibration requirements

with the

manufacturer,

and reviewed the

ASME code,

Sectio'n IX.

The

ASME code

addresses

the shielding

gas flow rate

as

a "non-essential" variable.

Because

of this,

changes in gas-flow were deleted

from the

PPP

ESD's,

and the existing welds were accepted.

Diablo Canyon

SSER-33

B.5-20

Appendix B

19

d.

Conclusions

and Staff Position

'The allegation that welders

were using improper flowmeters

and

uncalibrated

regulators is substantiated.

However, the staff

further concludes that

PG&E acted properly in the .corrective action

taken to resolve the situation of the use of uncalibrated

weld

shielding

gas pressure

regulators

and incorrectly matched

flowmeters

to regulators

by revising PPP's

welding procedures

ESD-213

and

ESD-219 to reflect conformance to ASME code Section IX which

considers

the shielding

gas flow rate for manual

gas tungsten

arc

welding as

a non-essential

variable.

All welds performed required

NDE assuring

weld soundness.

This allegation, therefore,

has

no

safety significance.

e.

Actions

Re uired

None.

16.

Task:

Alle ation or Concern

No.

416

ATS No:

RV-84-A-062

a

~

Characterization

Inconsistent

weld acceptance

standards

were used by day and night

shift inspectors

inspecting structural steel welds for the

Guy F. Atkinson Company.

b.

Im lied Si nificance to Desi

n

Construction

and

eration

Inconsistent

standards

could have resulted in unacceptable

welds

being accepted.

This could cause structural steel welds to fail

under abnormal

loads if weld strength is less

than

assumed

by the

design.

c ~

Assessment

of Safet

Si nificance

Exhibit

1 of Attachment

10 to the

GAP letter indicates that one

example of the night shift requiring rework on welds accepted

by day

shift inspectors is excess

reinforcement

on stiffener plates

3 and

5

on column 14.

Review of weld inspection

records indicated that

column 14-A was inspected

on the date in question by the inspector

identified in Exhibit 1.

Stiffener plates

1 through

16 on

column 14-A and" stiffener plates

7, 8,

15 and

16 on column 12.1-A

were inspected

as part of the investigation into this allegation,

No evidence of excess

reinforcement

was" noted,

Thus, the example

cited does not support the allegation.

To address

the question of inconsistent

inspection standards,

two thousand

two hundred

and fifty (2250) structural steel weld

inspection

records

were reviewed for 1855 welds reflecting the work

of 22 different weld inspectors

to determine if any groups of

'nspectors

had significantly different weld reject rates

than other

groups.

The records

reviewed were from two groups.

One group was

Diablo Canyon

SSER-33

B.5-21

Appendix

B

20

randomly selected

from the structural steel welding records for the

turbine building.

The second

group was selected

to include the

records for the stiffener plate welding referred to in exhibit

1 of

the allegation.

The records

encompassed

the time period June

1978

through August 1979, thus spanning several

months before

and several

months after the date of exhibit l.

Of the 2250 inspection records

reviewed,

126 (5Q were rejects.

Five inspectors

accounted for all

of the rejects.

The bases

for these rejections

were reviewed to

determine if they were attributable to different inspection

standards.

Of the

126 rejects

found in the sample, ill resulted

from

reinspection of 395 welds that had been originally accepted

but

which subsequently

cracked at the ends

as

documented

by NCR's 243

and 313.

The resolution of these

NCR's required grinding out the

weld cracks, visually inspecting the welds

and conducting liquid

penetrant testing to insure

no cracked weld material

remained to

serve

as

a starting point for further crack growth.

All welds that

were reinspected

were visually acceptable.

The rejects resulted

from the liquid penetrant testing.

Since the circumstances

surrounding

these rejections

are significantly different from the

other weld inspections

reviewed,

the high reject rate in these

cases

clearly result from circumstances

other than acceptance

criteria.

The reject rates for the two inspectors

who conducted

the

reinspection

were roughly the

same.

'The remaining

1855 weld inspections

reviewed resulted in 15 rejects

((1'j) by three inspectors.

Seven of the rejections

were by a single

inspector

who conducted

906 of the inspections

in the sample.

This

represents

a rejection rate of less

than one percent,

which is not

clearly inconsistent with the other inspectors

rejecting

no welds

out of a much smaller number of inspections.

The eight remaining

rejects

were by two inspectors

who inspected

a total of 52 welds.

It could not be determined if both of these

inspectors

were on the

night shift.

The eight rejects

occurred

on three joints, therefore,

it appears

that the relatively large percentage

of rejects for these

two inspectors

resulted

from the

same welder making more than one

reject weld on

a joint.

To verify that different acceptance

criteria did not result in welds

being more readily accepted

by one group than another,

the

productivity rate for two of the inspectors

that inspected

a large

percentage

of the welds in the sample,

were examined to verify that

no more than

a credible number of welds per day had been inspected

by these individuals. It was determined that one inspector

had

accepted

a very large number of welds in one day.

Review of these

welds,

however, indicated that all of the welds were grouped

together

so that it was possible to inspect the number of welds

indicated.

d.

Conclusions

and Staff Position

The specific column referred to in the allegation

as

an example of

unaccept'able

work being accepted

by day shift showed

no indication

Diablo Canyon

SSER-33

B.5-22

Appendix B

21

of excess

weld reinforcement

as alleged.

Review of a large

sample

of weld inspection records did show differing weld rejection rates

by different inspectors,

but in all cases

the higher rejection rates

noted could be attributed to factors other than different acceptance

standards.

No evidence

was noted that different standards

resulted

in inspection of more than

a credible number of welds per day by an

inspectors

Therefore, it was not clear that there

was any group of

inspectors

(day or night shift) that had higher rejection rates

due

to differing acceptance

criteria.

Thus, the allegation of differing

acceptance

criteria between

day and night shifts cannot

be

substantiated.

e.

None.

17.

Task:

Alle ation or Concern No.

1543

ATS No:

RV-84-A-114

a

~

Characterization

An individual feels that

PGEZ made false statements

that led to the

resolution of previous allegations

regarding welder qualification

test surveillance.

Specifically, the existence

of., welder

'qualification records

referenced

by a J.

P.

Watson affidavit

presented

before the Atomic Safety

and Licensing Appeal Board is

questioned.

b.

Im lied Si nificance to Desi

n

Construction

and 0 eration

Lack of adequate

welder qualification test records

would impair the

traceability of weld quality for any welds

made by welders lacking

adequate

qualification records, invalidating the acceptance

of these

welds.

As a result

some of the accepted

welds might fail under

abnormal loading conditions because

they lack the structural

strength

assumed

by the design.

c ~

Assessment

of Safet

Si nificance

The allegation

stems

from apparently conflicting testimony regarding

welder qualification records that was given by J.

P. Watson

on two

different occasions.

In the ASLB affidavit, it was indicated that

records of fitup, root pass, filler pass, final visual and bend test

had been

reviewed for a group of welders.

In subsequent

testimony

during

a Department of Labor hearing Mr. Watson indicated that there

were no permanent

records of examinations

conducted at qualification

weld hold points.

The process

used by -Pullman Power Products

(PPP) to conduct

and

document welder qualification tests

was reviewed to determine

what

documentation of qualification tests

was generated

and maintained.

Welder performance qualification is controlled by PPP procedure

ESD 216.

This procedure

requires

the

gC Welding Supervisor to

Diablo Canyon

SSER-33

B.5-23

Appendix

B

22

supervise

welder performance qualification testing

and document the

results of>the guided bend tests or radiography

used to determine

the acceptability of the qualification weld.

These

requirements

and

the documentation

generated

and maintained

by PG&E fulfillthe

welder qualification requirements

of ASME Code Section IX

Article III, gW 301.4.

Discussions

with a

PPP mechanical

engineer indicate that it was also

standard practice for PPP

QC Welding Supervisors

to inspect the

qualification weld progression at selected

hold points, usually fit

up, root pass

and final visual inspection.

The results of these

inspections

were maintained in informal notes

by the Welding

Supervisor,

but were not maintained

as permanent

formal Diablo

Canyon

gC documents.

d.

Conclusions

and Staff Position

The apparent conflict in testimony

seems

to result from Mr. Watson

referring on one hand to records consisting of informal notes

and

on

the other hand to formal permanent

records.

Therefore,

no real

inconsistency

between the statement

that (informal) records of gC

inspection for fitup, root pass, filler pass, final visual and bend

test were reviewed

and the statement that (formal) permanent

records

of these

inspections

do not exist.

Therefore,

the allegation that

PG&E made false statements

regarding welder qualification test

documentation

cannot

be substantiated.

Furthermore,

the welder qualification records maintained

by PG&E

fully comply with the

ASME requirements for such records.

Therefore, failure to maintain records of inspections

conducted at

hold points during the qualification testing

has

no safety

significance.

The specific questions

raised in the alleger's affidavit are

addressed

as follows:

Are inspection

records of welder qualification testing required at

nuclear power facilities?

Yes, however,

the

ASME code only requires that the essential

variables,

test results

and background

data

be maintained

as

'ecords of welder qualification.

The welder qualification

records maintained

by PG&E satisfy these

requirements.

Does the welder qualification test have hold points that must be

inspected

before the test

can be allowed to proceed?

Ão, although inspection at hold points

was standard practice

by

the

PPP

gC Welding Supervisors, it is not requir'ed by either

the

ASME Code or by the written PPP procedures;

If a gC inspector performed

an inspection of a mandatory hold point,

would that inspector

be required to document

the results of such

an

inspection?

Diablo Canyon

SSER-33

B.5-24

Appendix B.

No, as discussed

above neither the inspection hold points nor

documentation of the results of hold point inspections is

mandatory.

e.

None.

18.

Task

Alle ation or Concern

No.

169

ATS No:

RV-84"A-022

a ~

Characterization:

Pullman failed to conduct support welds

as required by procedure

and

QA wrongfully approved

the technique.

b.

Im lied Si nificance to Desi

n

Construction

or 0 eration

Welds

made without the proper procedure

could result in improperly

made welds in critical areas.

Ci

Assessment

of Safet

Si nificance

The alleger stated that two W14x90 wide flange beams

were welded

together

on support nos.

2/45R and 2/49R by use of an unqualified

welding technique.

It was stated that Pullman welding procedure

specification

(WPS) 7/8 was used to join steel

shapes

without the

required backing bar in place of which back-gouging

was performed

and the Pullman

QA/QC Manager wrongly approved

the technique

utilized.

The staff reviewed packages

from support nos.

2/45R and 2/49R and

Pullman's

WPS 7/8 to evaluate

welds in question.

The joint type is

a groove butt in which a backing bar is placed to ensure full

penetration

when welding.

Pullman's

General Field Support Process

Sheets for these

supports indicate

a hold point after back-gouging

to verify sound weld metal was attained

from the back side before

welding the back side.

Both techniques

are approved

by the

AWS and

ASME codes.

Both techniques

achieve

the

same purpose:

to obtain

full penetration at the root.

The

AWS Code has both of these

particular weld joint types

as prequalified in their Structural

Welding Code Dl.l, but the omission or inclusion of a backing bar is

an essential

variable in which a

WPS has to be requalified if the

weld joint was not prequalified.

ASME Section IX addresses

backing

bars

as nonessential

variables requiring no requalification of a

WPS.

Pullman's

WPS 7/8 closely resembles

ASME Section IX but does not

state that Section IX is to be used

as

a supporting

document

when

a

interpretation is required.

Therefore, technically the alleger

was

correct in stating that the support welds

made without a backing bar

was performed without a properly qualified procedure

because

back

Diablo Canyon

SSER-33

B.5-25

Appendix

B

24

gouging was not addressed

on

WPS 7/8.

On March 12,

1984,

WPS 7/8

was revised to allow for back grinding and back welding.

Pullman's

gA/gC Manager has

no recollection in approving the use of

backgouging

as

an alternative to the use of a backing bar for welds

in question.

d.

Staff Position

The staff concludes that

no structural deficiencies

resulted

from

the change of welding technique

because. full penetration of the root

was achieved in both cases.

None.

19.

Exit Interview

Mr. M. Tressler,

was informed of the results of these inspections

by

telephone

on July 17,

1985.

Diablo Canyon

SSER-33

B.5-26

Appendix B