ML17059B100

From kanterella
Jump to navigation Jump to search
Insp Repts 50-220/96-05 & 50-410/96-05 on 960217-0311.No Violations Noted.Major Areas inspected:LER-95-05,applicable Tss,Ufsar & IPE Sections,Portions of Related Calculations, Procedures,Ders,Sorc Meeting Minutes & Other Documentation
ML17059B100
Person / Time
Site: Nine Mile Point  Constellation icon.png
Issue date: 03/29/1996
From: Conte R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17059B099 List:
References
50-220-96-05, 50-220-96-5, 50-410-96-05, 50-410-96-5, NUDOCS 9604080091
Download: ML17059B100 (46)


See also: IR 05000220/1996005

Text

U.S.

NUCLEAR REGULATORYCGNiNISSIN

REGIN I

Report Nos.:

96-05

96-05

Docket Nos.:

50-220

50-410

License Nos.:

DPR-63

NPF-69

Licensee:

Niagara

Hohawk Power Corporation

P. 0.

Box 63

Lycoming,

NY 13093

Facility:

Nine Nile Point, Units

1 and

2

Location:

Scriba,

New York

Dates:

February

17 to Harch ll, 1996

Inspectors:

B. S. Norris, Senior

Resident

Inspector

H. J. Buckley, Resident

Inspector

R. A. Skokowski, Resident

Inspector

Approved by:

Richard J.

Conte,

ief

Projects

Branch

5

Division of Reactor Projects

Date

Results:

See Executive

Summary

960408009l

960329

PDR

ADQCK 05000220

8

PDR

'

EXECUTIVE SQOQLRY

Nine Mile Point Unit 1

50-220/96-05

February

17 to Narch 11,

1996

The purpose of this special

inspection

was to review concerns identified

during the review of the Nine Mile Point Unit

1 (Unit 1) Licensee

Event Report

(LER) 95-05, "Building Blowout Panels

Outside the Design Basis

Because of

Construction Error," dated

November 30,

1995.

These

concerns

involved NMPC's

application of their safety

assessment

processes,

design control measures,

and

reportability requirements,

and corrective action measures.

For the time period from initial operations

(December

1969) to October

1993,

a

safety problem existed,

in that, the reactor

and turbine building blowout

panels

would not have relieved until a pressure

in excess of the structural

design pressure for the buildings stated

in the Updated Final Safety Analysis

Report

(UFSAR).

This condition was caused

by an original plant construction

error involving the installation of oversized

blowout panel

fasteners (i.e.,

bolting) that occur red in a period that preceded

the use of quality measures

required to be implemented

under the requirements

of 10 CFR 50, Appendix B.

However, the inspection determined that the safety problem continued

from

October

1993 until March 1995 due to inadequate

implementation of 10 CFR 50,

Appendix

B design control measures

that resulted in a calculation error and

an

inadequate

design review of that calculation that allowed the oversized

fasteners

to remain in place.

This condition was identified as

an apparent

violation of 10 CFR 50, Appendix B, Criterion III "Design Control."

Furthermore,

the inspection identified concerns with the safety

assessment

process that:

(1) allowed

a change to the facility as described

in the

UFSAR

(i.e., leaving the oversized

fasteners

in place in lieu of correcting the

condition) to exist in the plant for approximately

an 18-month period without

the conduct of a required

10 CFR 50.59 safety evaluation;

and (2) upon

determining that the facility was being operated with blowout panel relief

capabilities in excess of the structural

design value prescribed

in the

UFSAR,

altered the design of structures

described

in the

UFSAR (i.e.,

removing every

other fastener)

without the conduct of a

10 CFR 50.59 'safety evaluation.

This

condition was identified as

an apparent violation of 10 CFR 50.59.

Regarding reportability of events to the

NRC, the inspection identified

a

concern with NMPC's process that resulted in two occasions

(October

1993

and

March 1995) where

NMPC should

have identified that the plant was operated

outside of it s design basis,

and in fact did not perform,the required

reporting.

This failure on two occasions

to perform the requisite reporting

was identified as

an apparent violation of 10 CFR 50.72

and 50.73.

Also, the

inspection identified that when

NMPC ultimately reported the matter to the

NRC

in LER 95-05, the submitted report was weak in describing corrective actions

and significance of conditions.

The inspection identified

a concern involving procedural

adherence,

which

involved the failure of NMPC to enter the design control measure

inadequacies

identified in March 1995 into their corrective action system (i.e., the

Deviation/Event Report).

This condition is an apparent violation of the Nine

Mile Point Nuclear Station Unit

1 Technical Specification 6.8.1,

which

requires

procedures

to be. implemented.

The above four (4) apparent violations are being considered for escalated

enforcement.

The inspection identified inconsistencies

within and between the

UFSAR and the

Individual Plant Examination that involved the stated

value of the pressure

relief capabilities of the blowout panels.

There were also inconsistencies

within the

UFSAR regarding the design basis for the blowout panels

and

specific high energy line breaks.

The

NRC Staff plans to discuss this matter

further at the Enforcement

Conference.

In addition, while the inspection

had not identified any immediate safety

concerns with the manner in which the March 1995 modification of the blowout

fasteners

had resolved

NHPC's safety problem, the

NRC staff has initiated

actions to perform a confirmatory independent

review of NMPC's calculations

that formed the basis for this modification.

'

TABLE OF CONTENTS

EXECUTIVE SUMMARY .

1. 0

INTRODUCTION

1.1

Purpose of Inspection

1.2

Event Overview

1.3

Scope of Inspection

.

1

1

1

1

2.0

DETAIL DESCRIPTION

OF THE EVENT..................

2

3.0

ASSESSMENT

OF THE EVENT

.

3,1

Design Control

3. 1. 1 Root Cause of the Installation of Oversized Bolts

during Construction

.

3. 1.2 October

1993 Calculational

Error

3. 1.3 Corrective Actions to Address the Calculational

Erroi

3.2

10 CFR 50.59 Safety Evaluations

.

3.2. 1

10 CFR 50.59 Safety Evaluation

October

1993

.

.

.

.

3.2.2

10 CFR 50.59 Safety Evaluation - March 1995

.

.

.

.

.

3.3

10 CFR 50.72

and 50.73 Reportability

3.3. 1

10 CFR 50.72

and 50.73 Reportability

October

1993

.

3.3.2

10 CFR 50.72

and 50.73 Reportability - March 1995

.

.

3.4

Procedural

Compliance

.

.

.

.

. '.

.

.

.

.

.

.

.

.

.

.

.

.

.

4

5

5

5

6

6

6

7

7

8

4.0

REVIEW OF

LER 95-05,

"BUILDING BLOWOUT PANELS OUTSIDE THE

BASIS BECAUSE OF CONSTRUCTION

ERROR,"

DESIGN

9

5.0

SAFETY SIGNIFICANCE

.

5. 1

Review of the Unit

1 Individual

5.2

Review of the

UFSAR Commitments

5.3

Safety Assessment

and

Summary

.

6.0

MANAGEMENT MEETINGS

.

~

~

~

~

~

~

~

~

~

~

Plant Examination

.

~

~

~

~

~

~

~

~

9

9

10ll

12

0

DETAILS

1. 0

INTRODUCTION

1.1

Purpose of Inspection

t

The purpose of this special

inspection

was to review concerns identified by

.

the

NRC staff during the review of the Nine Mile Point Unit

1 (Unit 1)

Licensee

Event Report

(LER) 95-05, "Building Blowout Panels

Outside the Design

Basis

Because of Construction Error," dated

November 30,

1995.

1.2

Event Overview

On October 25,

1993, with the reactor at

IOOX power, Unit

1 engineering staff

determined that the safety-related

blowout panels in the reactor

and turbine

buildings would not blowout at the design relief pressure

of 45 pounds per

square foot (psf).

The purpose of the blowout panels is to provide pressure

relief to prevent collapse of the superstructure

due to a break of an

emergency cooling system,

or other primary coolant system line in the reactor

building,

and

a steam line break in the turbine building.

Unit

1 found that

the existing shear bolts

on the blowout panels

were larger than those

identified on the design drawings.

This was documented

in a Deviation/Event

Report

(DER 1-93-2526).

The initial engineering

evaluation indicated that the

turbine

and reactor building blowout panels

would relieve at

a pressure

greater

than the design basis value,

but less

than the design basis fail

pressure for the reactor

and turbine buildings.

The

1993 engineering

evaluation

recommendation

and

NMPC resolution

was to leave the as-found

condition in place.

On March 27,

1995, during the completion of the recommended

actions

included

in the

DER,

an engineering

review determined that the blowout panels

would

actually not relieve until pressures

in excess of the structural

design of 80

psf for both buildings.

At this time, Niagara

Mohawk Power Corporation

(NMPC)

completed

a design

change to bring the relief pressures

back in conformance

with the

UFSAR.

During subsequent

reviews of the issue,

NMPC determined that

the condition was reportable

under Title 10 of the

Code of Federal

Regulations

Part 50.73,

(10 CFR 50.73)

"Licensee

Event Report System,"

and issued

LER

95-05.

1.3

Scope of Inspection

During this inspection,

the inspectors

reviewed

LER 95-05, applicable

Technical Specifications

(TSs),

Updated Final Safety Analyses

Report

(UFSAR)

and Individual Plant Examination

(IPE) sections,

portions of related

calculations,

procedures,

DERs, Station Operations

Review Committee

(SORC)

meeting minutes

and other licensee

documentation.

The inspectors

also

conducted interviews with various

members of the

NMPC staff and management,

and conducted

walkdowns of the applicable

areas of the facility.

The

inspectors

focused their review on the following aspects

of the issue:

~ Engineering

Support/Design

Control

~ Reportability/LER Adequacy

~ Safety Review and Assessment

~ Proper

Procedure

Implementation

0

0

Additionally, the inspector

assessed

the accuracy of the applicable

UFSAR

sections.

2.0

DETAIL DESCRIPTION

OF THE EVENT

Attachment

1 to this report is

a time line of events for this review.

During NMPC's effort to resolve contradictions identified in the

UFSAR

regarding the blowout panel relief pressure,

Calculation

S7-RX340-WOl, dated

August 23,

1993, was'enerated.

Due to a lack of documentation

regarding the

material properties of the bolts identified on the design drawings,

NMPC

determined to test

a sample of the installed bolts to obtain actual material

properties.

After initial calculations

were performed,

a number of bolts were

replaced with new 3/16" diameter American Society for. Testing

and Materials

(ASTM) A-307 bolts.

The previously installed bolts were tested to determine

their strength.

Upon receipt of the test results,

the structural

engineer

identified that the bolts were 1/4",

and not 3/16" as specified

on plant

drawings

(C-18713-C).

Furthermore,

the test results indicated that the

strength of the bolts to be higher than that used in Calculation

S7-RX340-W01.

Therefore,

the structural

engineer initiated Revision

1 to the calculation,

which indicated that the relief pressure for the reactor building to be

53

psf,

and

60 psf for the turbine building.

On October 28,

1993,

DER 1-93-2526

was written to address

the difference

between the size of the installed blowout panel bolts and the size indicated

on the plant drawings.

When the

DER was reviewed

by the

SSS

on November

1,

1993,

an operability determination

was attached that indicated the relief

pressures

of blowout panels for both the reactor

and turbine buildings would

exceed the value described

in the

UFSAR.

Because

the calculated relief

pressures

were less

than the buildings internal failure pressure,

engineering

recommended

that the blowout panels still be considered

operable.

The

SSS

accepted this recommendation.

Additionally, the

SSS did not consider the

condition to be reportable.

As part of DER 1-93-2526 Action Plan, Unit

1 was to complete

a calculation to

identify exactly which bolts were required to be replaced to restore the

blowout panels

in. conformance with the

UFSAR relief pressure

of 45 psf.

This

calculation

was scheduled

to be completed

by June 30,

1995.

The calculation

was completed

on March 27,

1995, during the Unit

1 refueling outage

13.

Based

upon the results of this calculation,

the licensee

determined different relief

pressures

for the as-installed

configurations.

These

new relief pressures

were in excess of the fail pressure for both the reactor

and turbine buildings

as stated in the

UFSAR.

According to the engineering

supervisor,

there

was

an error in the assumptions

used during the October

1993 calculation that caused

the previous incorrect

results.

Particularly, loading of the panels

was

assumed to be equally

distributed in both the horizontal

and vertical directions.

Therefore,

the

engineer incorrectly concluded that

a failure of the sheet

metal at the top of

the panels

would be sufficient to relieve pressure

as required.

To provide

'ufficient

pressure relief,

a failure of the bolts connecting the sides

of. the

panels to the supports

would have

been required.

Based

on the

new

3

calculations

the correct relief pressure for the reactor building was

91 psf,

and 89 psf for the turbine building.

No DER was written at this time to

address

the

human performance

issues

associated

with the design control

deficiencies

inherent in the calculation error and the independent

design

review (this area is described further in Section 3.3).

During the re-

disposition of the

DER in March 1995,

NMPC indicated that the event

was not

- reportable

under

10 CFR 50.72 or 50.73 for the following reasons:

~

UFSAR Section XVI.D.2.0 states

that Unit

1 was designed prior to 10 CFR 50 Appendix A, General

Design Criterion 4,

and that it was not designed

for the dynamic effects of a double-ended guillotine pipe rupture,

and

that the probability of this kind of occurrence

is extremely low.

The above

assumption

was substantiated

by a 1984 leak-before-break

analysis.

This analysis

concluded that

a full double-ended

pipe break

need not,be postulated

as

a design

basis for defining loads at Unit 1.

The results of this study were

used to define the Unit

1 design basis

for masonry walls at Unit 1,

and were submitted to the

NRC via letter

dated

June 8,

1984.

The leak-before-break

analysis eliminates the need

for the blowout panels,

because

the high energy line break

(HELB) event

would be preventable

by detection of the leak,

and timely shutdown would

follow.

Therefore,

the condition was not outside the Unit

1 design

bases.

During the

1995 refueling outage,

Unit

1 evaluated

the situation

and decided

to remove every other bolt used to hold each of the blowout panels

in place

due to the higher relief pressures.

This would provide

a relief pressur e of

approximately

45 psf as per the

UFSAR.

DER 1-93-2526

and associated

oper ability determinations

were updated

and the blowout panels

were declared

inoperable,

on March 27,

1995.

Modification Nl-95-001

LG329 was initiated,

and the bolts were removed prior to plant restart

from the refueling outage in

1995.

The Structure

Engineering Supervisor determined that because

NMPC was

completing the design

change to place the relief pressure

back in accordance

with the

UFSAR,

no additional

analyses

were needed;

such

as analyses

to

determine the actual

internal fail pressures

of the reactor

and tur bine

buildings, the events that would exceed

these fail pressures

or the subsequent

consequences

of exceeding

these failure pressures.

During the closeout

SORC review of DER 1-93-2526,

on June

22,

1995, the

SORC

questioned

the reportability of the issue,

and requested

that engineering re-

evaluate

the reportability of the events.

Nuclear Engineering confirmed the

bases for the earlier decision not to report the condition.

This information

was documented

in

NMPC Memorandum

ESB1-S95-0039 to file, and presented

to

SORC

on July 6,

1995.

On October 31,

1995,

DER 1-95-3012

was written to prompt another evaluation of

the condition for reportability.

This

DER was generated

as

a result of a non-

required review of original condition performed

by NMPC personnel.

As a

result,

NMPC determined to report the condition under

10 CFR 50.73(a)(2)(ii).

LER 95-05 was submitted to the

NRC on November 28,

1995.

According to

LER 95-

05, the use of engineering, judgement

was improperly credited in the previously

0

concluding that this condition was not reportable

and that the

UFSAR inferred

that the relief panels

were credited with functioning for certain events.

DER 1-95-3012 identified the failure to properly report the condition to be

caused

by inadequate

engineering

reviews,

and inadequate

investigation of the

reportability requirements

when the error was identified.

Based

on these

causes,

NNPC initiated the following corrective actions:

~

Emphasis to be given to the Structural

Engineering

Group to perform an

adequate

review of documentation

and verification of assumptions

used in

calculation before final issue.

(Completed shortly after the end of

Refueling Outage

13.)

~

Engineering to write a lessons

learned transmittal to address

the

responsibility of engineering staff to promptly inform operations

when

, new information is identified that could affect reportability.

(Scheduled for completion October 1996.)

~

Provide

a training session

to certain engineering

and plant personnel

regarding reportability (NUREG-1022,

and

10 CFR 50.72,

and 50.73),

and

include .this training in the

NHPC continuous training cycle.

(Scheduled

for completion October 1996.)

3.0

ASSESSMENT

OF THE EVENT

Based

on the inspectors'eview,

concerns

were identified in the following

areas:

Design Control;

50.59 safety evaluations;

Reportability;

Procedure

compliance;

and

Root Cause

and Corrective actions

as described

in the

LER.

3.1

Design Control

The inspectors

reviewed the following facets of design control:

~

the root cause for the installation of the oversized bolts during

construction;

~

the October

1993 calculational

err or;

and

~

the corrective actions to address

the calculational error.

3. 1.1 Root Cause of the Installation of Oversized Bolts during Construction

The cause of the oversized bolts used to install the reactor

and turbine

building blowout panels

was documented

in LER 95-05 to be inadequate

quality

control measures

in place during construction.

The corrective action credited

in the

LER is additional quality control

and quality assurance

requirements

that have

been

im'plemented for the design

and construction activities since

r

'

initial construction,

which should prevent similar. deficiencies.

NMPC

reported that, Unit

1 was designed

and constructed prior to the implementation

of 10 CFR 50 Appendix 6, "guality Assurance Criteria for Nuclear Power Plants

and

Fuel Reprocessing

Plants."

The inspectors

acknowledged

NMPC statement

ia

this regard,

but did not focus

on the performance

problems in the construction

period.

Those

same quality assurance

requirements

referenced

to by

NMPC were

in effect during the performance

problems since

1993.

The inspectors

focused

their review on the time period from 1993.

3.1.2 October

1993 Calculational

Error

In October

1993, after the oversize bolts were identified, the engineer

made

an error in his assumptions

leading to the determinations of the. incorrect

relief pressure

fo} the safety-related

reactor

and turbine building blowout

panels.

Specifically, the assumption

that the loading of the panels

was

equally distributed in both the horizontal

and vertical directions resulted

in

the incorrect determination that the reactor

building blowout panels

would

relieve at 60 psf and the turbine building blowout panels

would relieve at 53

psf.

This error was not caught

by the checker or the approver of the

calculation

as part of design review.

As determined

in March 1995, the actual

relief pressures

would be

91 psf for the reactor building and 89 psf for .the

turbine building.

According to the

UFSAR, the reactor building and turbine

building blowout panels

were designed to relieve at 45 psf to prevent failure

of the building superstructures

at pressures

in excess of 80 psf.

This is an apparent violation of 10 CFR 50 Appendix 8 Criterion III, "Design

Control," in that Calculation

S7-RX340-W01 incorrectly determined

the blowout

panel relief pressures

to be less than the 80 psf failure pressure

of the

reactor

and turbine buildings,

and the calculation. was inadequately

design

reviewed.

3. 1.3 Corrective Actions to Address the Calculational

Error

The inspectors

reviewed Modification Nl-95-001

LG329, which initiated the

removal of every other blowout panel bolt,

and identified no immediate

concerns.

The inspectors verified that the applicable drawings

and

calculations

wer e updated.

Additionally, the inspector s also

"walked down"

the blowout panels for the reactor building and verified through sampling that

the installed configuration was consistent with the plant drawings.

However,

the

NRC did not complete

a detail review of the calculations

as of the close

of the inspection period.

Region I is performing

a confirmatory independent

review of the calculations.

This is considered

an unresolved

item pending the

completion of NRC staff's review.

(URI 50-220/96-05-01)

3.2

10 CFR 50.59 Safety Evaluations

The inspectors

evaluated

the licensee's

implementation of 10 CFR 50.59

"Changes,

Tests

and Experiments," for the relief pressures

exceeding

the

values stated

in the

UFSAR identified in October

1993,

and for the

modification to remove every other bolt used to install the blowout panels

completed in March 1995.

0

'

3.2.1

10 CFR 50.59 Safety Evaluation - October

1993

In October

1993, during NMPC's evaluation of the installed oversized bolts,

NHPC determin'ed

the blowout panels to be operable.

With respect to the

original relief pressure of 45 psf and the new calculated relief pressures

of

approximately

60 psf both being less

than the structural

design value

(80

psf), clearly the safety margin was reduced in these facts.

Unit

1 decided to

leave the oversized bolts installed until the completion of their corrective

actions,

scheduled

to be completed

June 30,

1995.

When this decision

was

made,

no

10 CFR 50.59 evaluation

was completed.

A delay or partial correction

of a condition adverse to safety or quality for a structure,

system,

or

component described

in the

UFSAR is considered

by the

NRC staff to be

a change

in the facility, which is subject to a 10 CFR 50.59 review.

Additionally, the

above facts indicated

a reduced safety margin that needed to be evaluated

in

accordance

with 10 CFR 50.59.

h

The inspectors

considered

the failure to complete

a

10 CFR 50.59 evaluation,

to allow for the approx'imately

one

and

a half year delay in resolving the

differences

between

the

UFSAR stated

design relief pressures

and the

installed/calculated relief pressures

for the reactor

and turbine building

blowout panels,

an apparent violation on

10 CFR 50.59.

3.2.2

10 CFR 50.59 Safety Evaluation

March 1995

During the evaluation of Modification N1-.95-001

LG329,

an applicability review

was completed

by the Unit

1 staff indicating no need for the conduct of a

10 CFR 50.59 safety evaluation.

The inspectors

noted that the

NHPC documented

basis in the applicability review for not completing

a

10 CFR 50.59 safety

evaluation

was because

the proposed

change

would bring the, facility back onto

compliance with the

UFSAR.

The inspector s acknowledged this basis in the

applicability review,

and also verified that the size

and spacing of the

blowout panel bolting were not described

in the

UFSAR.

However,

changes

in

~

the facility as described

in the

UFSAR are considered

by the

NRC staff

(NRC

Manual Chapter Part

9900) to pertain to any changes

in the facility which

alter the design,

function, or method of performing the function of a

component,

system

or structure described

in the

UFSAR.

Accordingly, the

NHPC

Modification Nl-95-001

LG329 made in March 1995, which consisted of the

removal of every other blowout panel bolt, is considered

by the

NRC staff to

be

an .alteration to the design of a structure described

in the

UFSAR.

Therefore,

the failure of NHPC to perform

a safety evaluation for the subject

modification is considered

another

example of an apparent violation of 10 CFR 50.59.

3.3

10 CFR 50.72 and 50.73 Reportability

The inspectors

evaluated

the licensee's

implementation of 10 CFR 50.72

and

50.73,

"Immediate notification requirements for operating

nuclear

power

reactors,"

and "Licensee. event report system," for the relief pressures

exceeding

the design values stated

in the

UFSAR identified in October

1993,

and for the relief pressures

exceeding

the structural

design pressures

of the

reactor

and turbine buildings values stated

in the

UFSAR identified in March.

1995.

"

7

The inspectors

reviewed the applicable revisions of the licensee's

procedure

regarding reportability and determined it to provided appropriate, requirements

to ensure that

10 CFR 50.72

and 50.73 reportability regulations related to

conditions that are outside of the design basis of the plant.

3.3. 1 10 CFR 50.72 and 50.73 Reportability October

1993

The inspectors

discussed

with the licensee their reasoning for not declaring

the event reportable

under

10 CFR 50.72,

50.73 in October

1993,

and was

informed, that even though the relief pressure

of the blowout panels

exceeded

the design basis

values stated in the

UFSAR, the structural

design basis

pressure of the reactor

and turbine buildings would not be exceeded.

Additionally,

NMPC reviewed their design basis

and determined that

HELBs were

outside their design basis that there

was

no credible postulated

event that

would cause

pressures

to challenge

the failure pressure of the reactor or

turbine buildings.

Based

on these

reasons,

NHPC determined that they were not

outside the design basis; therefore,

the condition was not reportable.

The inspectors

evaluated

the reportability decision

made

by NHPC.

Based

on

the definition of Design Basis

as provided in 10 CFR 50.2,

"Design bases

means that information which identifies specific functions to be performed

by

a structure,

system,

or component of a facility, and the specific values or

ranges of values

chosen for controlling parameters

as reference

bounds for

design...."

Since the specific values

chosen for controlling the relief

pressures

of the reactor

and turbine building blowout panels

were exceeded

as

stated in the

UFSAR, the inspectors

considered

Unit

1 to be in a condition

outside their design basis.

The inspectors

concluded that the Unit

1 failure to complete the reports,

as

required in October

1993, is an apparent violation on

10 CFR 50.72

and 50.73.

3.3.2

10 CFR 50.72

and 50.73 Reportability Narch

1995

During the period of March through July 1995,

NHPC evaluated

the reportability

of the blowout panel relief pressures

on several

occasions.

Through

discussions

with NHPC staff and management,

the inspectors

ascertained

that

NHPC understood that they were outside their design basis relief pressures

of

45 psf as stated

in the

UFSAR.

Furthermore,

they understood that the

calculated relief pressures

exceeded

the 80 psf failure pressure for the

reactor

and turbine buildings,

as stated in UFSAR Sections

VI-C.1.2 and III-

A.l.2, respectively.

However,

NHPC decided that the condition was not outside

the Unit

1 design

bases,

since the

UFSAR Sections

XVI.D.2.0 describes

that

HELB events

are not part of the Unit

1 design basis;

and, therefore,

no

postulated

pressure-related

event would challenge

the reactor building blowout

panels.

The inspectors

evaluated

the reportability decision

made

by

NHPC for this time

period.

Unit

1

UFSAR Sections

VI-C.1.2,

"Pressure

Relief Design," describes

specifically, that the reactor building pressure relief is provided to prevent

collapse of the superstructure

due to a break of an emergency cooling system,

or other primary coolant system line in the reactor building.

Further,

the

pressure relief function is provided by the blowout panels,

that were designed

0

to fail at

an internal

pressure

of approximately .45 psf, to prevent excessive

internal pressure

on the superstructure

walls, roof, and their supports,

which

would fail at

an internal pressure

in excess of 80 psf.

A similar description

is provided for the turbine building in UFSAR Section III-A.1.-2, specifying

the initiating event

as

a steam line break.

Since the specific values

chosen for controlling the relief pressures

of the

reactor

and turbine building blowout panels

as stated in the

UFSAR were

exceeded,

and the specific values

chosen for the reactor

and turbine building

failure pressure

as stated in the

UFSAR were exceeded,

the inspectors

considered

Unit

1 to be in a condition'utside their design basis.

Furthermore,

the detailed description of the emergency cooling system line

break

and the steam line break provided in the

UFSAR as the events for which

the. blowout panels

were installed to protect against,

indicated that there

are

analyzed pressure-related

events

would challenge

the reactor

and turbine

building blowout panels.

The inspectors

concluded that Unit

1 failure to complete the reports,

as

required in March 1995, is an apparent violation on

10 CFR 50.72

and 50.73.

3.4

Procedural

Compliance

The inspectors

reviewed the applicable revisions of the licensee's

DER

procedure to verify the completion of DER 1-93-2526

was in accordance

with the

procedure.

Although the inspectors

found the

DER completed

as required

by the

procedure,

the inspectors

noted that the length of time taken

between the

identification of the problem until the review of the

SSS

was longer than

expected

considering

the potential significance of the condition.

Particularly, the condition was identified on October 25,

1993, the

DER was

initiated on October 28,

1993,

and signed

by the

SSS

on November 1,

1993.

Discussion with NHPC management

indicated that the length of time taken for

the condition to receive

SSS review did not meet their expectations.

During the engineering

review of the design control deficiencies

involving the

calculational error and the independent

design review that allowed the

oversized bolts to remain in place from October

1993 until March 1995, the

inspectors identified that no

DER was written in March 1995 to document

and

initiate root cause

and corrective actions.

NHPC Procedure

NIP-ECA-Ol,

"Deviation Event Report," Revision 8, requires

a

DER be written to address

human performance

and personnel

performance

problems

adverse to quality.

The

failure to write a

DER is an apparent violation of the Nine Mile Point Nuclear

Station Unit

1 Technical Specification 6.8. 1, which requires

procedures

to be

implemented.

The inspectors

noted that even though

NHPC did not write a

DER to address

the

human/personnel

performance

concerns

related with the design control

deficiencies,

they did initiate some corrective actions

by provided emphasis

to the Structural

Engineering

Group on the need to perform an adequate

review

of documentation

and verification of assumptions

used in calculation before

final issue.

According to NHPC, this discussion

was completed shortly after

the completion of Refueling Outage

13, prior to the initiation of DER 1-95-

3012.

However, the inspectors

did not .consider this review of the design

control deficiencies to be

a sufficient evaluation of the root cause to

develop appropriate corrective actions to preclude recurrence.

4.0

REVIEW OF LER 95-05,

"BUILDING BLOWOUT PANELS OUTSIDE THE DESIGN BASIS

BECAUSE OF CONSTRUCTION ERROR"

The inspectors

reviewed

LER 95-05,

and found it to accurately describe

the

event associate'd

with the oversized bolts installed in the reactor

and turbine

building blowout panels.

However, the following weaknesses

were identified:

~

the

LER did not adequately

address

the failure to report the condition

in October

1993,

or in Parch

1995;

~

the

LER did not provide sufficient details regarding the

1993

calculational error to allow for an adequate

assessment

of the

licensee's

corrective actions to prevent recurrence;

and

~

the

LER did not address

the potential for, and the significance of a

reactor building failure.

Based

on these

weaknesses,

LER 95-05 will remain open,

pending further

NRC

staff review..

5. 0

SAFETY SIGNIFICANCE

5. 1

Review of the Unit 1 Individual Plant Examination

The inspectors

reviewed the applicable sections of the Unit

1 Individual Plant

Examination

(IPE) related to the reactor building pressure relief design.

The

information provided in Section

4.'1,

"NMP1 Containment

Design Description

and

Data," of the

IPE was consistent with that provided in UFSAR Section VI.C.1.2

"Pressure

Relief Design" for the reactor building.

These sections

from the

UFSAR and the

IPE basically described that pressure relief is provided to

prevent collapse of the superstructure

due to a break of an emergency cooling

system,

or other primary coolant system line in the reactor building.

The

relief is 'provided

by the blowout panels that were designed to fail with an

internal pressure

of approximately

45 psf.

Relief of pressure

through the

panels

in case of an energy release will prevent excessive

internal pressure

on the superstructure

walls, roof, and their support that would fail at

an

internal pressure

in excess of 80 psf.

The inspectors

also noted that the Unit

1

IPE describes

in Table 4.5-1,

"Overall Level

2 Success Criteria," the reactor building integrity and

effectiveness

to be successful, if either

one of the following two criteria

are met:

1)

Reactor building integrity is maintained if the reactor building

pressurizes

to no more than 36 psf. If not, then the reactor

building blowout panels

are to assumed

to have opened.

2)

The reactor building is assumed effective in removing

radionuclides if the following criteria are met:

10

~

No structural

breach to the reactor, building, allowing free

communication with the environment,

caused

by events

such

as

hydrogen detonation

in the reactor building.

~

No natural circulation paths with chimney effects are

established

within the reactor building that could

drastically reduce residence

time and retention within the

reactor building.

Additionally, Section 4. 1.2,

"Summary of Secondary

Containment Features,"

contains

a list of the safety design basis for the secondary

containment

system.

Included in this list as Item 5,

"The reactor building is designed to

contain

a maximum positive internal

pressure

of 80 pounds per square foot

(0.56 psig).

Blowout panels

in the refuel floor are

used to release

at

a

pressure

of approximately

40 pounds per square foot (0.28 psig) to relieve

internal reactor building pressure."

The information pertaining to the Unit

1 design basis

as described

in the

IPE

substantiated

the information provide in the

UFSAR, indicating that Unit

1 was

outside their design basis for the reactor building blowout panel relief

pressure.

Additionally, the inspectors

noted inconsistencies

within the

IPE

with respect to the relief pressure

of the blowout panels.

These

inconsistencies

indicate blowout panel relief pressures

of 36 psf,

40 psf and

45 psf.

Some of these inconsistencies

are similar to those originally

identified in the UFSAR'by NMPC.

The inspectors

considered

the resolution of

these inconsistencies

an inspector follow item (IFI) to be reviewed during

a

future inspection.

(IFI 50-220/96-05-02)

5.2

Review of the

UFSAR Commitments

A recent discovery of a licensee

operating their facility in a manner contrary

to the

UFSAR description highlighted the need for additional verification that

licensees

were complying with UFSAR commitments.

During an approximate

two

month time period,

February through March 1996, all reactor inspections will

provide additional attention to UFSAR commitments

and their incorporation into

plant practices,

procedures

and procedures.

While performing the inspection,

which are discussed

in this report, the

inspectors

reviewed the applicable portions of the

UFSAR that related to the

areas

inspected.

During discussions

with NMPC personnel,

the following

apparent

inconsistency

was noted in the

UFSAR between

Section XVI.D.2.0 "Plant

Design for Protection Against Postulated

Piping Failure in High Energy Lines,"

and Sections

VI.C.1.2,

and III.A.1.2 "Pressure

Relief Design" for the reactor

and turbine buildings respectively:

Specifically,Section XVI.D.2.0 states that Unit

1 was design

and constructed

prior to 10 CFR 50 Appendix A, "General

Design Criteria,"

(GDC) Criterion 4,

and was not designed

accordance

with this criterion dealing with the effects

of pipe whips from HELBs, vs,Section VI.C.1.2, which states that "breaks in

all primary coolant systems

piping has

been

analyzed

since accidents of this

type result in the highest pressure,

temperature

and humidity condition in the

building.

A break in the emergency

cooling system is the most serious

since

it releases

the most coolant at the highest rate."

Furthermore,

Technical Specification Basis Section 5.4 "Containment," states,

"Pressure relief is

provided to prevent

damage to the superstructure

due to the break of any

primary system line the reactor building.

In this event,

blowout panels will

fail, relieving pressure

in the event of a major line rupture."

Also Section III.A.1.2, states that "to prevent failure of the superstructure

due to a steam line break,

a wall area of 1800 square feet has

been attached

with bolts [blowout panel] will fail due to an internal pressure of

approximately

45 psf; thus relieving the internal pressure."

The inspectors

used the most conservative

design basis for their review.

These inconsistencies

regarding the design basis for Unit

1 with respect to

specific high energy line breaks will be discussed

further during the

enforcement

conference

pertaining to the apparent violations described

in this

report.

Furthermore,

the resolution of these

inconsistencies

is considered

part of the inspector follow item identified in Section 5.1.

(IFI 50-220/96-

05-02)

Additionally, the licensee identified that there

was

a discrepancy

between the

UFSAR Sections III.A.1.2 and VI.C.1.2, which state that the pressure relief

panels

in the tur bine and reactor buildings blow out at 45 psf.

Contrary to

this,

UFSAR Table XVI-31 and discussion

on the subsequent

pages

state that the

pressure relief panels

blow out at 40 psf.

This contradiction led to Unit

1

identifying the discrepancy

between the design

and installed configuration.

NNPC has initiated

a change to the

UFSAR to correct this discrepancy.

5.3

Safety Assessment

and

Summary

The

NNPC organization

has concluded that their March 1995 modification of the

blowout panel bolting had resolved their safety problem.

However, while the

NRC has

no immediate safety concerns

pertaining to the supporting calculations

for this modification, confirmatory independent

review of these calculations

is currently being performed

by the

NRC staff.

During this review, the inspectors

noted that

a general

safety objective for

the reactor building and the turbine building blowout panels is to relieve

internal building pressure prior to structural failure for anticipated

transients/challenges

inside the building.

The inspectors'ocus

was

on the

reactor building since it houses

safety structures,

systems

and components.

If such

an event were to occur, radiation doses

at the site boundary appear to

be accounted for and are of minimal consequences.

However,

two areas

remain

unclear

as

a result of this review:

How much design margin existed for the structural

design value of 80 psf

or what actual

internal building pressure

would result in failure

(collapse)

and the obvious impact on safety related

equipment

such

as

emergency

core cooling systems

being used in response

to the anticipated

transients/challenges.

The highest pressure

in the reactor building for design basis

anticipated transients/challenges.

12

For the time period from initial operations to March 1995,

a vulnerability

existed,

the significance of which is dependent

on resolution of the above

two

areas.

Notwithstanding the fact that no actual

challenges

occurred to the

reactor building internal pressure

relieving system,

the potential existed

which is not addressed

in the related

LER.

More importantly,

NHPC resolution

,of the issue

from October

1993 to March 1995,

was weak in thoroughly

establishing,

understanding,

and evaluating the safety design basis for the

reactor building internal pressure

relieving system;

The weak safety

assessment

coupled with the calculation error,

inadequate

design review of

that calculation,

and apparent failure to follow the

DER procedure

led to the

untimely resolution of this problem commensurate

with its safety significance.

Although this problem was eventually reported to the

NRC, the event report

does not fully address

the safety significance of the potential for (in

distinction to actual)

challenges

to the internal building internal relieving

system for the time period from initial operations

to March 1995.

As a

result, licensee corrective actions

do not address

apparent

weaknesses

in

their technical,

and safety review process.

6.0

HANAGEHENT HEETINGS

At periodic intervals

and at the conclusion of the inspection period, meetings

were held with senior station

management

to discuss

the scope

and findings of

this inspection.

The final exit meeting occurred

on March ll, 1996.

During

the exit meeting,

Richard Abbott, Vice President

and General

Manager,

Nuclear

for NHPC questioned

the inspector's

statements

regarding

NHPC basis for not

reporting the condition under

10 CFR 50.73,

in March 1995.

Subsequent

conversations

between the inspectors

and

NMPC management,

clarified

NMPC

.basis,

and

was considered

in this report.

Based

on the

NRC Region I review of

this report,

and discussions

held with NHPC representatives, it was determined

that this report does not contain safeguards

or proprietary information.

Attachment

2 to this report is listing key personnel

contacted

during this

review.

ATTACHNENT 1

TINE LINE

October 20,

1993

.

.

. During the removal of bolts for testing,

technicians

identified that 1/4" bolts used to install the blowout

panels.

october 22-27,

1993

. Test results

were available to the structural

engineer.

August 23,

1993

.

.

.

. Calculation

S7-RX340-W01,

Revision

0 was approved.

October 25,

1993

.

.

. The identification of reactor

and turbine building blowout

panel bolts stronger

than required

by design drawings

as

documented

on

DER 1-93-2526.

October 28,

1993

. Originator signed

DER 1-93-2526.

October 29,

1993

.

.

. Supervisor

signed

DER 1-93-2526.

November

1,

1993

.

.

~ . Station Shift Supervisor

signed

DER 1-.93-2526.

November

5,

1993

February 8,

1995

March 27,

1995

March 30, 31,

1995

April 4,

1995

.

.

. Calculation

S7-RX340-WOl, Revision

1 was approved.

. Refueling outage

13 began.

. Calculation error was identified.

. Every other bolts was from the blowout panels

removed in

accordance

with Modification Nl-95-001

LG329.

. Unit

1 connected

to the grid following refueling outage

13.

=April 5,

1995

.

.

.

. Structure

engineers

training on the verification of

assumptions.

June

22, 1995....

July 6,

1995

October 31,

1995

November 28,

1995

.

November 30,

1995

.

SORC mee'ting discussing

the safety evaluation

associated

with the

UFSAR change to correct the originally identified

UFSAR contradiction,

and the need to document the basis

for not reporting the condition in DER 1-93-2526.

SORC meeting approving the implementation of DER 1-93

-2526,

and the issuance of NHPC memorandum

documenting

bases for not reporting the condition.

. Origination of DER 1-95-3012, "Reportability Review of DER

1-93-2526."

.

SORC meeting approving the disposition of DER 1-95-3012,

and

LER 95-05.

.

NHPC Issued

LER 95-05.

'

Nia ara

Mohawk Power Cor oration

ATTACHMENT 2

PERSONS

CONTACTED

R. Abbot, Vice President

and General

Manager,

Nuclear

H. Alvi, Supervisor,

Structural

Design, Unit

1

D. Baker,

Engineer,

Licensing

M. Balduzzi, Operations

Manager,

Unit

1

C.

Beckham,

Manager, Quality Assurance

G. Corell, Manager,

Chemistry, Unit

1

K. Dahlberg,

General

Manager,

Projects

M. McCommick, Vice President,

Nuclear Safety Assessment

8 Support

N. Rademacher,,Plant

Manager,

Unit

1

K. Sweet,

Manager,

Technical

Support, Unit

1

C. Terry, Vice President,

Nuclear Engineering

G. Wierzbowski, Supervisor,

Technical

Support,

Unit

1

G. Wilson, Counsel

D. Wolniak, Manager,

Licensing

W. Yaeger,

Manager,

Engineering,

Unit

1

A. Zallnick, Licensing Engineer

U;S. Nuclear

Re ulator

Commission

  • R. Conte, Chief, Reactor Projects

Branch

(RPB) No.

5

~

~

~

~

~

~

~

  • H. Eichenholz,

Project Engineer,

RPB No.'

  • M. Hartzman,

Mechanical

Engineering

Branch,

NRR

  • D. Hood, Project Manager,

NRR

  • W. Rothman,

Structural

Engineering

Branch,

NRR

S.

Sanchez,

Resident

Inspector

All of the above personnel

were present at the exit meeting

on March ll, 1996.

  • Telephonic presence

at the exit meeting.

Enclosure

2

DESIGN/LICENSING BASIS QUESTIONS

ON NNP-1

REACTOR BUILDING BLOWOUT PANELS

The

LER discusses

use of blowout panels to protect the secondary

containment

structure.

However,

as discussed

in "GE Design Specifications for 'Reactor

Containment,"

blow-out panels

are also sometimes

used to protect primary

.

containment

from excessive

reverse differential pressure

that could occur-in

the event of a high energy line break in a compartment

adjacent to the

primary containment.

Is this generic design objective applicable to the

NMP-1 facility and what

is the documented

basis if it is7

2.

s.

4.

5.

With respect to page

11 of Nine Mile Point

1 License

Event Report

(LER),

titled, "Building Blowout Panels

Outside

Design Basis

Because of

Construction Error," what are the key assumptions

and engineering

analysis/calculations

performed in late October

1993 which led to the

initial determination that the turbine and reactor building panels

would

blow out at 60 and

53 psf, respectively,

to relieve internal pressure.

[Provide engineering calculations

which support the above stated

blowout

pressures.]

Two design internal

pressures

of 40 and

45 psf are

shown in different

locations of the'SAR for Nine Mi,le Point

1 pressure relief panels

(PRPs)

for the reactor

and turbine buildings.

Please clarify the ambiguity about the two pressure

values

and indicate the

correct licensing basis

design pressure for the

PRPsl

Has

an assessment

been

made

on the error in the design

assumptions

for load

distribution which was identified during the March 1995 refueling outage'

Also explain what assumptions

for load distribution were used in conjunction

with the consideration of the 1/4" bolts with higher ultimate strength

(78

ksi) which led to the determination of the revised

panel

blowout pressures

of 92 and 88 psf for the reactor

and turbine buildings, respectively

(pages

ll and

13 of DER No. 1-93-2526).

With respect to the above referenced

DER, provide

a detailed discussion of

the key assumptions,

panel/bolt configurations

(including pertinent

drawings)

and bolt ultimate strength

used in concluding that the revised

panels

would blowout at about

45 psf with the use of the 1/4" diameter bolts

and the removal of every other bolt from the existing panels.

0

'-

e.

The Reactor Building Blowout panel revised calculations

are based

on certain

assumptions,

the conservatism of which cannot

be determined

unless

compared

to a more rigorous analysis

or test.

It is not clear

how NMPC demonstrated

conformance with FSAR commitments

by

reevaluating

the panel

pressure

capacity using

a more exact methodology,

or

revising the analysis

and stating clearly the conservatism of each

assumption

used in the analysis.

The staff has identified the following effects which appear'to

have not been

considered

in the analysis or are not clearly stated:

'a ~

b.

C.

d.

The calculation of the pressure

capacity of the top and bottom

connections

do not consider the membrane effect of the panel

in the

longitudinal (vertical) direction

and the effect of the flexibilityof

the side connections

between the flutes and the columns.

In addition,

the effect of friction between the bolts and the sheetmetal

surfaces,

due to bolt pre-loading,

has not been considered.

The calculation of the pressure

capacity of the side connections

are

based

on the assumption of a simply supported

beam.

This is not valid

if the panel is rigidly bolted to the angle

members,

in which case the

analysis

should

be based

on

a beam with elastically built-in ends.

The calculation of the pressure

capacity of the side connections

was

determined

from the analysis of a typical flute, without considering

the in-plane

membrane

forces acting

on the flutes.

The calculation of the sheet-metal

shear capacity is based

on one

shear

area.

It should

be based

on two shear

areas.

e.

The effect of the panel

dead-weight

on the connections

has not been

considered.

0'hat

are results of these effects

on the calculation of the panel

pressure

capacities,

as demonstrated

by detailed calculations,

or by the conservatism

of the existing calculations2

Also,

a weakness

of the

1995 modification evaluation for the blowout panel

interim corrective actions

appears

to be the implied assumption of imminence

of failure of the 1/4 " diameter

shear

bolt with a computed "unity" value

for the "shear-tension

interaction" equation.

What is the pertinent analytical or test-supported

basis for such

an

assumption7

[As appropriate,

a more realistic, non-linear finite element analysis of the

PRPs with rigorous modeling of the

PRP elements

including proper

representation

of the combined shear/tension

stiffness of the bolts

and the

supporting

steel

frame may be performed to demonstrate

the adequacy of the

current

PRP eyaluation.]

With respect to Nine Mile Point

1 Calculation

Nos.

S7-RX340-WOI Revisions

0

and 1, in support of bolt strength:

0

a.

What is the basis for selecting

the revised bolt ultimate tensile

strength of 78 ksi in the latest

panel

blowout capacity calculation2

b.

What is the test verified ultimate shear strength of the

same set of

'bolts tested2

c.

Are the strengths

(both the ultimate tensile

and shear strengths)

based

on ultimate strength tests of an adequate

sample size of the

I/4" bolts2

d.

Is the 78 ksi

a mean ultimate tensile strength2

e.

What is. the corresponding

mean ultimate shear strength

used in the

assessment2

C

If they represent

mean ultimate strengths,

what are their

corresponding

standard

deviations2

g.

If the values represent

nominal lower-bound strengths

and they were

used in your latest calculation which confirmed the revised blowout

capacity of approximately

45 psf,

how can one be sure that the panels

would blowout approximately at 45 psf and not at

a higher value2

h.

Given the above mentioned uncertainties

in ultimate tensile

and shear

strengths

and load distribution assumptions

used in the analysis,

has

NHPC, established

a conservatively

determined

upper-bound

panel

blowout

pressure

and demonstrated

that the computed pressure

capacity is lower

than the

45 psf pressure

stipulated in the licensing basis

document2

With respect to the

same calculations

noted

above,

discuss

the

appropriateness

of using conservative

engineering

assumptions

including

conservative

modeling (e.g.,

one way horizontal action for Robertson's

panels)

and use of mean or non-upper-bound

ultimate bolt tensile

and shear

capacities

to determine

a realistic upper-bound

internal

pressure

which will

cause failure. of the

PRPs.

Such

an approach

could underestimate

the real

panel

blowout pressure,

thus,

resulting in a non-conservative

conclusion.

Specifically,

use of a lower-

bound or mean bolt ultimate tensile strength

and

an assumed

ultimate bolt

shear strength of 0.6

F (instead of a test verified shear strength)

would

lead to a unrealistic

PRP failure pressure

and potentially unsafe

conclusion.

Discuss the safety implications of such

a practice in light of the objective

of the

PRP evaluation

and the need-to modify the evaluation

and demonstrate

that the physical

panel disposition proposed is still valid.

0

34386

Federal Register / Vol. 60, No. 126 / Friday, June,30,

1995 / Notices

'

factors in arriving at the appropriate

is not held, the licensee willnormaliy

severity level willbe dependent on tho

be requested to provide a written

circumstances oftho violation.

response to an inspection report, if

However. ifa licensee refuses to conect

issued, as to the licensee's views on the

a minor violation within a reasonable

apparent violations and their root

time such that itwillfullycontinues, the

causes and a description ofp]armed or

violation should be categorized at least

implemented corrective action.

at a Severity Level Di.

During the predecisional enforcement

conference, the licensee, vendor, or

D. Violations ofRePorting Requiremezits

other persons willbe gven an

The NRC expects licensees to prov]de

opportunity to provide information

complete, accurate, and timely

~ consistent with the pmpose ofthe

information and reports. According]yi

conference, including an explanation to

unless otherwise categorized in the

the NRC ofthe immediate corrective

Supplements, tho severity level ofa

actions (ifany) that were taken

violation involving the failure to make

followingident]fication oftho potential

a required report to the NRC willbe

violation or nonconformance and the

based upon the significance ofand the

long-term comprehensive actions that

circumstances surrounding the matter

were taken or willbe taken to prevent

that should havo been reported..

recurrence. Licensees, vendors, or other

However, the sevority lovel ofan

persons willbe told when a meeting is

untimely report, in contrast to no report,

a pzedecisiona] enforcement conference.

may be reduced depending on the

A predecisional enforcement

circumstances surrounding the matter.

conference is a meet]ng between the

A ]icensee wi]lnot norma]]y be cited for

NRC and the licensee. Conferences are

a failure to report a condition or event

normally held in the~lone] offices

unless the licenseo was actually aware

and are not norma]]y open to public

oftho condition or event that it failed

observation. However, a tna] program is

to report. A liconsee will,on the other

being conducted to open approximately

hand, normallY bo cited for a failure to

25 percent ofa}] e]igible conferences for

report a condition or event ifthe

public observation, Le., every fourth

licensee knew ofthe information to be

e]ig]b]e conference invo]ving one of

reportod, but did not recogn]ze that it

three categories of ]icensees (reactor,

was requirea to make a report.

hospital, and other materials licensees)

V. Predecisional Enforcement

wi]Ibe open to tho public. Conferences

Conferences

willnot normally be open to the public

e

th NRC ha

]earned oftho

ifthe enforcement actionbeing

onever

e

as carne

o

o

contem~]ated:

existence ofa Potential violation for

(1) ~ou]d be taken against an

which escalated enforcement action

indiv]dua], or ifthe action, though not

aPPe~ to be anted, or ~umng

taken against an individua];turns on

nonconformance on the part ofa

whethor an individual has committed

vendor, the NRC may provide an

wron doing:

opportunity for a predecisional

(2) fnvo]ves significant personnel

entorcement conference with the

failures where the NRC has requested

licensee, vendor, or other person before

that the individua](s) invo]ved be

taking enforcement action. The purpose

pnisent at the conference.

oftho conference is to obtain

(3) Is based on the findings ofan NRC

information that willassist the NRC in

Office ofinvest]gat]ons report; or

determining the appropriate

(4) Involves safeguards information,

enforcement action, such as: (1) A

pnvacy Act information, or information

common understanding offacts root

which could be considered proprietary;

causes and missed opportunities

In addi'tion, conferences willnot

associated with the apparent v]o]at]onsi

normally be open to the public if:

(2) a common understanding of

(5) The conference involves medical

corrective action taken or planned, and

misadministrations or overexposures

(3) a common understanding ofthe

and the conference cannot be conducted

significance ofissues and the need for

without disclosing the exposed

lasting comprehensive corrective action.

individual'a name; or

Ifthe NRC concludes that ithas

(6) The conference wi]]be conducted

sufficient information to make an

by telephone or the conference willbe

informed enforcement decision, a

conducted at a relatively small

conference willnot normally be held

licensee's facility.

unless the licensee requests it. However,

Notwithstanding meeting any ofthese

an opportunity for a conference will

criteria, a conference may. still be open

normally bo provided before issuing an

ifthe conference involves issues related

order based on a violation of the rule on

to an ongoing adjudiwtory proceeding

'eliberate Misconduct or a civilpenalty

with one or moro intervenors or where

to an unlicensed person. Ifa conference

the evidentiary basis for the conference

is a matter ofpublic zecozd, such as an

adjudicatory:dec]sion by the

Department of Labor. In addition, with

the approva] ofthe Executive Director

forOperations, conferences willnot be

open to the public where good cause has

been shown after ba]anc]ng the benefit

ofthe public observation a(]ainst the

potential impact on the agency's

~

enforcement action in a particular case.

As soon as it is determined that a

conference willbe open to public

observation, the NRC willnotify the

licensee that the conference willbe

open to public observation as part ofthe

agency's trial program. Consistent with

the agency's policy on open meetings,

"StaffMeetings Open to Public,"

published Se ptember 20, 1994 (59 FR 48340), the NRC intends to announce

open conferences normally at least 10

working days in advance ofconferences

through (1) notices'posted in the Pub]ic

Document Room, (2) a toll-free

telephone recording at 800-952-9674,

and (3) a toll-free electronic bulletin

board at 800-952-9676. In addition, the

NRC willalso issue a press release and

notify appropriate State liaison officers

that a predecisional enforcement

conference has been scheduled

and that

it is open to public observation.

Tho public attonding open

conferences under the trial program may

observo but not participate in the

conference. It is noted that the purpose

ofconducting open conferences under

the trial program is not to maximize

public attendance, but rather to

determine whether providing the pub]]c

with opportunities tobe informed of

NRC activities is compatible with the

NRC's ability to exercise its regulatory

and safety responsibilities. Therefore.

members ofthe public willbe allowed

access to the NRC regional ofiices to

attend open enforcement conferences in

accordance with the "Standard

Operating Procedures For Providing

Security Support For NRC Hearings And

Meetings," published November 1, 1991

(56 FR 56251), These procedures

provide that visitors may be subject to

personnel screening, that signs, banners,

posters, etc., not larger than 18" be,

permitted, and that disruptive persons

may be removed.

Members ofthe public attending open

conferences willbe reminded that (1)

the apparent violations discussed at

predecisional enforcement conferences

aro subject to further review and may be

subject to change prior to any resulting

enforcement action and (2) the

statements ofviews or expressions of

opinion made by NRC employees at

predecisional enforcement conferences,

or the lack thereof, are not intended to

represent final determinations or beliefs.

NUREG-1600

Federal Register / Vol. 60, No. 126 / Friday, June 30, 1995 / Notices

34387

'

Persons attending open conferences will

be provided an opportunity to submit

written comments concerning'the trial

program anonymously to the regional

office. These comments willbe

subsequently for'warded to the Diiector

ofthe Office ofEnforcement forreview

and consideration.

When needed to protect the public

health and safety or common defense

and security, escalated enfozcement-

action, such as the issuance ofan

immediately effective order, willbe

taken before the conference. In these

cases, a conference may be held alter the

escalated enforcement action is taken.

VLEnforcement Actions

This section describes the

enforcement sanctions available to the

NRC and specifies the conditions under

which each may be used. The basic

enforcement sanctions aze Notices of

Violation, civilpenalties, and orders of

various types. As discussed further in

Section VI.D,related administrative

actions such as Notices of

Nonconformance, Notices ofDeviation.

Confirmatory Action Letters, Letters of

Reprimand, and Demands for

Information are used to supplement the

enforcement program. In selecting the

enforcement sanctions or administrative

actions, the NRC willconsider

enforcement actions taken by other

Federal or State regulatory bodies

having concurrent jurisdiction, such as

in transportation matters. Usually,

whenever a violation ofNRC

requirements ofmore than a minor

concern is identified, enforcement

action is taken. The nature and extent of

the enforcement action is intended to

reflect the seriousness ofthe violation

involved. For the vast majority of

violations, a Notice ofViolation or a

Notice ofNonconformance is the normal

action.

A. Notice ofViolation

A Notice ofViolation is a written

notice setting forth ono or more

violations ofa legally binding

requirement. The Notice ofViolation

normally requires the recipient to

rovide a written statement describing

1) the reasons for the violation or, if

contested, the basis for disputing the

violation; (2) corrective steps that have

been taken and the results achieved; (3)

corrective steps that willbe taken to

prevent recurrence; and (4) the date

when fullcompliance willbe achieved.

The NRC may waive all or portions of

a written response to the extent relevant

information has already been provided

to the NRC in writingor documented in

an NRC inspection report. Tho NRC may

require responses

to Notices ofViolation

to be under oath. Normally, responses

under oath willbe required only in

connection with Severity Level I, H,

or'I

violations or orders.

The NRC uses the Notice ofViolation

as the usual method forformalizing the

existence ofa violation. Issuance ofa

Notice ofViolation is normally the only

enforcement action taken, except in

cases where the criteria for issuance of.

civilpenalties and orders, as set forth in

Sections VLBand VI.C, respectively, are

met. However, special circumstances

regarding the violation findings may

warrant discretion being exercised such

that the NRC refrains from issuing a

Notice ofViolation. (See Section VH.B,

"MitigationofEnforcement Sanctions.")

In addition, licensees are not ordinarily

cited for violations resulting from

matters not withintheir control, such as

equipment failures that were not

avoidable by reasonable licensee quality

assurance

measures or management

controls. Generally, however, licensees

are held responsible for the acts oftheir

employees. Accordingly, this policy

should not be zxinstrued to excuse

personnel errors.

B. CivilPenalty

Acivilpenalty is a monetary penalty

that may be imposed for violation of (1)

certain specified licensing provisions of

the Atomic Energy Act or-

supplementary NRC rules or orders; (2)

any requirement for which a license

tnay be revoked; or (3) reporting

requirements under section 206 ofthe

Energy Reorganization Act. Civil

penalties are designed to deter futuro

violations both by the involved licensee

as well as by other licensees conducting

similar activities and to emphasize the

need for licensees to identify violations

and take prompt comprehensive

corrective action.

Civilpenalties are considered for

Severity Level HIviolations. In addition,

civilpenalties willnormally be assessed

for Severity Level I and H violations and

knowing and conscious violations ofthe

reporting requirements ofsection 206 of

the Energy Reorganization Act.

Civilpenalties are used to encourage

prompt identification and prompt and

comprehensive correction ofviolations,

to emphasize compliance in a manner

that deters future violations, and to

serve to focus licensees'ttention

on

violations ofsignificant regulatory

concern.

Although management involvement,

direct or indirect, in a violation may

lead to an increase in the civilpenalty.

the lack ofmanagement involvement

may not be used to mitigate a civil

enalty. Allowingmitigation in the

atter case could encourage the lack of

management involvement in licensed

activities and a decrease in protection of

the public health and safety.

1. Base CivilPenalty

The NRC imposos different levels of

penalties fordifferent severity level

violations and different classes of

licensees, vendors, and other persons.

Tables 1A and 1B show the base civil

penalties for various reactor, fuel cyclo,

materials, and vendor programs. (Civil

penalties issued to individuals are

determined on a case-by~se

basis.) The

structure of these tables generally takes

into account the gravity ofthe violation

as a primary consideration and the

abilityto pay as a secondary

consideration. Generally, operations

involvinggreater nuclear material

inventories and greater potential

consequences

to the public and licensee

employees receive higher civil

penalties. Regarding the secondary

factor ofabilityofvarious classes of

licensees to pay the civilpenalties, it.is

not the NRC's intention that the

economic impact ofa civilpenalty be so

severe that it puts a licensee out of

business (orders. rather than civil

penalties, are used when the intent is to

suspend or terminate licensed activities)

or adversely affects a licensee's ability

to safely conduct'icensed activities.

The deterrent effect ofcivilpenalties is

best served when the amounts ofthe

penalties take into account a licensee's

ability to pay. In determining the

amount ofcivilpenalties for licensees

for whom the tables do not reflect the

ability to pay or the gravity ofthe

violation, the NRC willconsider as

necessary an increase or decrease on a

case-by~so basis. Normally, ifa

licensee can demonstrate financial

hardship, the NRC willconsider

payments over time, including interest,

rather than reducing the amount ofthe

civilpenalty. However, where a licensee

claims financial hardship, the licensee

willnormally be required to address

why it has sufficient resources to safely

conduct licensed activities and pay

license and inspection fees.

2. CivilPenalty Assessment

.

Inan effort to (1) emphasize the

importance ofadherence to

requirements and (2) reinforce prompt

self-identification ofproblems and root

causes and prompt and comprehensive

correction ofviolations, the NRC

reviews each proposed civilpenalty on

its own merits and, alter considering all

relevant circumstances, may adjust the

base civilpenalties shown in Table 1A

and 1B for Severity Level I, H, and Hi

violations as described below.

~ .