ML17059B100
| ML17059B100 | |
| Person / Time | |
|---|---|
| Site: | Nine Mile Point |
| Issue date: | 03/29/1996 |
| From: | Conte R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | |
| Shared Package | |
| ML17059B099 | List: |
| References | |
| 50-220-96-05, 50-220-96-5, 50-410-96-05, 50-410-96-5, NUDOCS 9604080091 | |
| Download: ML17059B100 (46) | |
See also: IR 05000220/1996005
Text
U.S.
NUCLEAR REGULATORYCGNiNISSIN
REGIN I
Report Nos.:
96-05
96-05
Docket Nos.:
50-220
50-410
License Nos.:
NPF-69
Licensee:
Niagara
Hohawk Power Corporation
P. 0.
Box 63
Lycoming,
NY 13093
Facility:
Nine Nile Point, Units
1 and
2
Location:
Scriba,
Dates:
February
17 to Harch ll, 1996
Inspectors:
B. S. Norris, Senior
Resident
Inspector
H. J. Buckley, Resident
Inspector
R. A. Skokowski, Resident
Inspector
Approved by:
Richard J.
Conte,
ief
Projects
Branch
5
Division of Reactor Projects
Date
Results:
See Executive
Summary
960408009l
960329
ADQCK 05000220
8
'
EXECUTIVE SQOQLRY
Nine Mile Point Unit 1
50-220/96-05
February
17 to Narch 11,
1996
The purpose of this special
inspection
was to review concerns identified
during the review of the Nine Mile Point Unit
1 (Unit 1) Licensee
Event Report
(LER) 95-05, "Building Blowout Panels
Outside the Design Basis
Because of
Construction Error," dated
November 30,
1995.
These
concerns
involved NMPC's
application of their safety
assessment
processes,
design control measures,
and
reportability requirements,
and corrective action measures.
For the time period from initial operations
(December
1969) to October
1993,
a
safety problem existed,
in that, the reactor
and turbine building blowout
panels
would not have relieved until a pressure
in excess of the structural
design pressure for the buildings stated
in the Updated Final Safety Analysis
Report
(UFSAR).
This condition was caused
by an original plant construction
error involving the installation of oversized
blowout panel
fasteners (i.e.,
bolting) that occur red in a period that preceded
the use of quality measures
required to be implemented
under the requirements
However, the inspection determined that the safety problem continued
from
October
1993 until March 1995 due to inadequate
implementation of 10 CFR 50,
Appendix
B design control measures
that resulted in a calculation error and
an
inadequate
design review of that calculation that allowed the oversized
fasteners
to remain in place.
This condition was identified as
an apparent
violation of 10 CFR 50, Appendix B, Criterion III "Design Control."
Furthermore,
the inspection identified concerns with the safety
assessment
process that:
(1) allowed
a change to the facility as described
in the
(i.e., leaving the oversized
fasteners
in place in lieu of correcting the
condition) to exist in the plant for approximately
an 18-month period without
the conduct of a required
10 CFR 50.59 safety evaluation;
and (2) upon
determining that the facility was being operated with blowout panel relief
capabilities in excess of the structural
design value prescribed
in the
altered the design of structures
described
in the
UFSAR (i.e.,
removing every
other fastener)
without the conduct of a
10 CFR 50.59 'safety evaluation.
This
condition was identified as
an apparent violation of 10 CFR 50.59.
Regarding reportability of events to the
NRC, the inspection identified
a
concern with NMPC's process that resulted in two occasions
(October
1993
and
March 1995) where
NMPC should
have identified that the plant was operated
outside of it s design basis,
and in fact did not perform,the required
reporting.
This failure on two occasions
to perform the requisite reporting
was identified as
an apparent violation of 10 CFR 50.72
and 50.73.
Also, the
inspection identified that when
NMPC ultimately reported the matter to the
NRC
in LER 95-05, the submitted report was weak in describing corrective actions
and significance of conditions.
The inspection identified
a concern involving procedural
adherence,
which
involved the failure of NMPC to enter the design control measure
inadequacies
identified in March 1995 into their corrective action system (i.e., the
Deviation/Event Report).
This condition is an apparent violation of the Nine
Mile Point Nuclear Station Unit
1 Technical Specification 6.8.1,
which
requires
procedures
to be. implemented.
The above four (4) apparent violations are being considered for escalated
enforcement.
The inspection identified inconsistencies
within and between the
UFSAR and the
Individual Plant Examination that involved the stated
value of the pressure
relief capabilities of the blowout panels.
There were also inconsistencies
within the
UFSAR regarding the design basis for the blowout panels
and
specific high energy line breaks.
The
NRC Staff plans to discuss this matter
further at the Enforcement
Conference.
In addition, while the inspection
had not identified any immediate safety
concerns with the manner in which the March 1995 modification of the blowout
fasteners
had resolved
NHPC's safety problem, the
NRC staff has initiated
actions to perform a confirmatory independent
review of NMPC's calculations
that formed the basis for this modification.
'
TABLE OF CONTENTS
EXECUTIVE SUMMARY .
1. 0
INTRODUCTION
1.1
Purpose of Inspection
1.2
Event Overview
1.3
Scope of Inspection
.
1
1
1
1
2.0
DETAIL DESCRIPTION
OF THE EVENT..................
2
3.0
ASSESSMENT
OF THE EVENT
.
3,1
Design Control
3. 1. 1 Root Cause of the Installation of Oversized Bolts
during Construction
.
3. 1.2 October
1993 Calculational
Error
3. 1.3 Corrective Actions to Address the Calculational
Erroi
3.2
10 CFR 50.59 Safety Evaluations
.
3.2. 1
10 CFR 50.59 Safety Evaluation
October
1993
.
.
.
.
3.2.2
10 CFR 50.59 Safety Evaluation - March 1995
.
.
.
.
.
3.3
and 50.73 Reportability
3.3. 1
and 50.73 Reportability
October
1993
.
3.3.2
and 50.73 Reportability - March 1995
.
.
3.4
Procedural
Compliance
.
.
.
.
. '.
.
.
.
.
.
.
.
.
.
.
.
.
.
4
5
5
5
6
6
6
7
7
8
4.0
REVIEW OF
LER 95-05,
"BUILDING BLOWOUT PANELS OUTSIDE THE
BASIS BECAUSE OF CONSTRUCTION
ERROR,"
DESIGN
9
5.0
SAFETY SIGNIFICANCE
.
5. 1
Review of the Unit
1 Individual
5.2
Review of the
UFSAR Commitments
5.3
Safety Assessment
and
Summary
.
6.0
MANAGEMENT MEETINGS
.
~
~
~
~
~
~
~
~
~
~
Plant Examination
.
~
~
~
~
~
~
~
~
9
9
10ll
12
0
DETAILS
1. 0
INTRODUCTION
1.1
Purpose of Inspection
t
The purpose of this special
inspection
was to review concerns identified by
.
the
NRC staff during the review of the Nine Mile Point Unit
1 (Unit 1)
Licensee
Event Report
(LER) 95-05, "Building Blowout Panels
Outside the Design
Basis
Because of Construction Error," dated
November 30,
1995.
1.2
Event Overview
On October 25,
1993, with the reactor at
IOOX power, Unit
1 engineering staff
determined that the safety-related
blowout panels in the reactor
and turbine
buildings would not blowout at the design relief pressure
of 45 pounds per
square foot (psf).
The purpose of the blowout panels is to provide pressure
relief to prevent collapse of the superstructure
due to a break of an
emergency cooling system,
or other primary coolant system line in the reactor
building,
and
a steam line break in the turbine building.
Unit
1 found that
the existing shear bolts
on the blowout panels
were larger than those
identified on the design drawings.
This was documented
in a Deviation/Event
Report
(DER 1-93-2526).
The initial engineering
evaluation indicated that the
turbine
and reactor building blowout panels
would relieve at
a pressure
greater
than the design basis value,
but less
than the design basis fail
pressure for the reactor
and turbine buildings.
The
1993 engineering
evaluation
recommendation
and
NMPC resolution
was to leave the as-found
condition in place.
On March 27,
1995, during the completion of the recommended
actions
included
in the
DER,
an engineering
review determined that the blowout panels
would
actually not relieve until pressures
in excess of the structural
design of 80
psf for both buildings.
At this time, Niagara
Mohawk Power Corporation
(NMPC)
completed
a design
change to bring the relief pressures
back in conformance
with the
During subsequent
reviews of the issue,
NMPC determined that
the condition was reportable
under Title 10 of the
Code of Federal
Regulations
Part 50.73,
"Licensee
Event Report System,"
and issued
LER
95-05.
1.3
Scope of Inspection
During this inspection,
the inspectors
reviewed
LER 95-05, applicable
Technical Specifications
(TSs),
Updated Final Safety Analyses
Report
(UFSAR)
and Individual Plant Examination
(IPE) sections,
portions of related
calculations,
procedures,
DERs, Station Operations
Review Committee
(SORC)
meeting minutes
and other licensee
documentation.
The inspectors
also
conducted interviews with various
members of the
NMPC staff and management,
and conducted
walkdowns of the applicable
areas of the facility.
The
inspectors
focused their review on the following aspects
of the issue:
~ Engineering
Support/Design
Control
~ Reportability/LER Adequacy
~ Safety Review and Assessment
~ Proper
Procedure
Implementation
0
0
Additionally, the inspector
assessed
the accuracy of the applicable
sections.
2.0
DETAIL DESCRIPTION
OF THE EVENT
Attachment
1 to this report is
a time line of events for this review.
During NMPC's effort to resolve contradictions identified in the
regarding the blowout panel relief pressure,
Calculation
S7-RX340-WOl, dated
August 23,
1993, was'enerated.
Due to a lack of documentation
regarding the
material properties of the bolts identified on the design drawings,
determined to test
a sample of the installed bolts to obtain actual material
properties.
After initial calculations
were performed,
a number of bolts were
replaced with new 3/16" diameter American Society for. Testing
and Materials
(ASTM) A-307 bolts.
The previously installed bolts were tested to determine
their strength.
Upon receipt of the test results,
the structural
engineer
identified that the bolts were 1/4",
and not 3/16" as specified
on plant
drawings
(C-18713-C).
Furthermore,
the test results indicated that the
strength of the bolts to be higher than that used in Calculation
S7-RX340-W01.
Therefore,
the structural
engineer initiated Revision
1 to the calculation,
which indicated that the relief pressure for the reactor building to be
53
psf,
and
60 psf for the turbine building.
On October 28,
1993,
DER 1-93-2526
was written to address
the difference
between the size of the installed blowout panel bolts and the size indicated
on the plant drawings.
When the
DER was reviewed
by the
on November
1,
1993,
was attached that indicated the relief
pressures
of blowout panels for both the reactor
and turbine buildings would
exceed the value described
in the
Because
the calculated relief
pressures
were less
than the buildings internal failure pressure,
engineering
recommended
that the blowout panels still be considered
The
accepted this recommendation.
Additionally, the
SSS did not consider the
condition to be reportable.
As part of DER 1-93-2526 Action Plan, Unit
1 was to complete
a calculation to
identify exactly which bolts were required to be replaced to restore the
blowout panels
in. conformance with the
UFSAR relief pressure
of 45 psf.
This
calculation
was scheduled
to be completed
by June 30,
1995.
The calculation
was completed
on March 27,
1995, during the Unit
1 refueling outage
13.
Based
upon the results of this calculation,
the licensee
determined different relief
pressures
for the as-installed
configurations.
These
new relief pressures
were in excess of the fail pressure for both the reactor
and turbine buildings
as stated in the
According to the engineering
supervisor,
there
was
an error in the assumptions
used during the October
1993 calculation that caused
the previous incorrect
results.
Particularly, loading of the panels
was
assumed to be equally
distributed in both the horizontal
and vertical directions.
Therefore,
the
engineer incorrectly concluded that
a failure of the sheet
metal at the top of
the panels
would be sufficient to relieve pressure
as required.
To provide
'ufficient
pressure relief,
a failure of the bolts connecting the sides
of. the
panels to the supports
would have
been required.
Based
on the
new
3
calculations
the correct relief pressure for the reactor building was
91 psf,
and 89 psf for the turbine building.
No DER was written at this time to
address
the
human performance
issues
associated
with the design control
deficiencies
inherent in the calculation error and the independent
design
review (this area is described further in Section 3.3).
During the re-
disposition of the
DER in March 1995,
NMPC indicated that the event
was not
- reportable
under
10 CFR 50.72 or 50.73 for the following reasons:
~
UFSAR Section XVI.D.2.0 states
that Unit
1 was designed prior to 10 CFR 50 Appendix A, General
Design Criterion 4,
and that it was not designed
for the dynamic effects of a double-ended guillotine pipe rupture,
and
that the probability of this kind of occurrence
is extremely low.
The above
assumption
was substantiated
by a 1984 leak-before-break
analysis.
This analysis
concluded that
a full double-ended
pipe break
need not,be postulated
as
a design
basis for defining loads at Unit 1.
The results of this study were
used to define the Unit
1 design basis
for masonry walls at Unit 1,
and were submitted to the
NRC via letter
dated
June 8,
1984.
analysis eliminates the need
for the blowout panels,
because
(HELB) event
would be preventable
by detection of the leak,
and timely shutdown would
follow.
Therefore,
the condition was not outside the Unit
1 design
bases.
During the
1995 refueling outage,
Unit
1 evaluated
the situation
and decided
to remove every other bolt used to hold each of the blowout panels
in place
due to the higher relief pressures.
This would provide
a relief pressur e of
approximately
45 psf as per the
DER 1-93-2526
and associated
oper ability determinations
were updated
and the blowout panels
were declared
on March 27,
1995.
Modification Nl-95-001
LG329 was initiated,
and the bolts were removed prior to plant restart
from the refueling outage in
1995.
The Structure
Engineering Supervisor determined that because
NMPC was
completing the design
change to place the relief pressure
back in accordance
with the
no additional
analyses
were needed;
such
as analyses
to
determine the actual
internal fail pressures
of the reactor
and tur bine
buildings, the events that would exceed
these fail pressures
or the subsequent
consequences
of exceeding
these failure pressures.
During the closeout
SORC review of DER 1-93-2526,
on June
22,
1995, the
SORC
questioned
the reportability of the issue,
and requested
that engineering re-
evaluate
the reportability of the events.
Nuclear Engineering confirmed the
bases for the earlier decision not to report the condition.
This information
was documented
in
NMPC Memorandum
ESB1-S95-0039 to file, and presented
to
SORC
on July 6,
1995.
On October 31,
1995,
DER 1-95-3012
was written to prompt another evaluation of
the condition for reportability.
This
DER was generated
as
a result of a non-
required review of original condition performed
by NMPC personnel.
As a
result,
NMPC determined to report the condition under
LER 95-05 was submitted to the
NRC on November 28,
1995.
According to
LER 95-
05, the use of engineering, judgement
was improperly credited in the previously
0
concluding that this condition was not reportable
and that the
UFSAR inferred
that the relief panels
were credited with functioning for certain events.
DER 1-95-3012 identified the failure to properly report the condition to be
caused
by inadequate
engineering
reviews,
and inadequate
investigation of the
reportability requirements
when the error was identified.
Based
on these
causes,
NNPC initiated the following corrective actions:
~
Emphasis to be given to the Structural
Engineering
Group to perform an
adequate
review of documentation
and verification of assumptions
used in
calculation before final issue.
(Completed shortly after the end of
Refueling Outage
13.)
~
Engineering to write a lessons
learned transmittal to address
the
responsibility of engineering staff to promptly inform operations
when
, new information is identified that could affect reportability.
(Scheduled for completion October 1996.)
~
Provide
a training session
to certain engineering
and plant personnel
regarding reportability (NUREG-1022,
and
and 50.73),
and
include .this training in the
NHPC continuous training cycle.
(Scheduled
for completion October 1996.)
3.0
ASSESSMENT
OF THE EVENT
Based
on the inspectors'eview,
concerns
were identified in the following
areas:
Design Control;
50.59 safety evaluations;
Reportability;
Procedure
compliance;
and
Root Cause
and Corrective actions
as described
in the
LER.
3.1
Design Control
The inspectors
reviewed the following facets of design control:
~
the root cause for the installation of the oversized bolts during
construction;
~
the October
1993 calculational
err or;
and
~
the corrective actions to address
the calculational error.
3. 1.1 Root Cause of the Installation of Oversized Bolts during Construction
The cause of the oversized bolts used to install the reactor
and turbine
building blowout panels
was documented
in LER 95-05 to be inadequate
quality
control measures
in place during construction.
The corrective action credited
in the
LER is additional quality control
and quality assurance
requirements
that have
been
im'plemented for the design
and construction activities since
r
'
initial construction,
which should prevent similar. deficiencies.
reported that, Unit
1 was designed
and constructed prior to the implementation
of 10 CFR 50 Appendix 6, "guality Assurance Criteria for Nuclear Power Plants
and
Fuel Reprocessing
Plants."
The inspectors
acknowledged
NMPC statement
ia
this regard,
but did not focus
on the performance
problems in the construction
period.
Those
same quality assurance
requirements
referenced
to by
NMPC were
in effect during the performance
problems since
1993.
The inspectors
focused
their review on the time period from 1993.
3.1.2 October
1993 Calculational
Error
In October
1993, after the oversize bolts were identified, the engineer
made
an error in his assumptions
leading to the determinations of the. incorrect
relief pressure
fo} the safety-related
reactor
and turbine building blowout
panels.
Specifically, the assumption
that the loading of the panels
was
equally distributed in both the horizontal
and vertical directions resulted
in
the incorrect determination that the reactor
building blowout panels
would
relieve at 60 psf and the turbine building blowout panels
would relieve at 53
psf.
This error was not caught
by the checker or the approver of the
calculation
as part of design review.
As determined
in March 1995, the actual
relief pressures
would be
91 psf for the reactor building and 89 psf for .the
turbine building.
According to the
UFSAR, the reactor building and turbine
building blowout panels
were designed to relieve at 45 psf to prevent failure
of the building superstructures
at pressures
in excess of 80 psf.
This is an apparent violation of 10 CFR 50 Appendix 8 Criterion III, "Design
Control," in that Calculation
S7-RX340-W01 incorrectly determined
the blowout
panel relief pressures
to be less than the 80 psf failure pressure
of the
reactor
and turbine buildings,
and the calculation. was inadequately
design
reviewed.
3. 1.3 Corrective Actions to Address the Calculational
Error
The inspectors
reviewed Modification Nl-95-001
LG329, which initiated the
removal of every other blowout panel bolt,
and identified no immediate
concerns.
The inspectors verified that the applicable drawings
and
calculations
wer e updated.
Additionally, the inspector s also
"walked down"
the blowout panels for the reactor building and verified through sampling that
the installed configuration was consistent with the plant drawings.
However,
the
NRC did not complete
a detail review of the calculations
as of the close
of the inspection period.
Region I is performing
a confirmatory independent
review of the calculations.
This is considered
an unresolved
item pending the
completion of NRC staff's review.
(URI 50-220/96-05-01)
3.2
10 CFR 50.59 Safety Evaluations
The inspectors
evaluated
the licensee's
implementation of 10 CFR 50.59
"Changes,
Tests
and Experiments," for the relief pressures
exceeding
the
values stated
in the
UFSAR identified in October
1993,
and for the
modification to remove every other bolt used to install the blowout panels
completed in March 1995.
0
'
3.2.1
10 CFR 50.59 Safety Evaluation - October
1993
In October
1993, during NMPC's evaluation of the installed oversized bolts,
NHPC determin'ed
the blowout panels to be operable.
With respect to the
original relief pressure of 45 psf and the new calculated relief pressures
of
approximately
60 psf both being less
than the structural
design value
(80
psf), clearly the safety margin was reduced in these facts.
Unit
1 decided to
leave the oversized bolts installed until the completion of their corrective
actions,
scheduled
to be completed
June 30,
1995.
When this decision
was
made,
no
10 CFR 50.59 evaluation
was completed.
A delay or partial correction
of a condition adverse to safety or quality for a structure,
system,
or
component described
in the
UFSAR is considered
by the
NRC staff to be
a change
in the facility, which is subject to a 10 CFR 50.59 review.
Additionally, the
above facts indicated
a reduced safety margin that needed to be evaluated
in
accordance
with 10 CFR 50.59.
h
The inspectors
considered
the failure to complete
a
10 CFR 50.59 evaluation,
to allow for the approx'imately
one
and
a half year delay in resolving the
differences
between
the
UFSAR stated
design relief pressures
and the
installed/calculated relief pressures
for the reactor
and turbine building
blowout panels,
an apparent violation on
3.2.2
10 CFR 50.59 Safety Evaluation
March 1995
During the evaluation of Modification N1-.95-001
LG329,
an applicability review
was completed
by the Unit
1 staff indicating no need for the conduct of a
10 CFR 50.59 safety evaluation.
The inspectors
noted that the
NHPC documented
basis in the applicability review for not completing
a
10 CFR 50.59 safety
evaluation
was because
the proposed
change
would bring the, facility back onto
compliance with the
The inspector s acknowledged this basis in the
applicability review,
and also verified that the size
and spacing of the
blowout panel bolting were not described
in the
However,
changes
in
~
the facility as described
in the
UFSAR are considered
by the
NRC staff
(NRC
Manual Chapter Part
9900) to pertain to any changes
in the facility which
alter the design,
function, or method of performing the function of a
component,
system
or structure described
in the
Accordingly, the
NHPC
Modification Nl-95-001
LG329 made in March 1995, which consisted of the
removal of every other blowout panel bolt, is considered
by the
NRC staff to
be
an .alteration to the design of a structure described
in the
Therefore,
the failure of NHPC to perform
a safety evaluation for the subject
modification is considered
another
example of an apparent violation of 10 CFR 50.59.
3.3
10 CFR 50.72 and 50.73 Reportability
The inspectors
evaluated
the licensee's
implementation of 10 CFR 50.72
and
50.73,
"Immediate notification requirements for operating
nuclear
power
reactors,"
and "Licensee. event report system," for the relief pressures
exceeding
the design values stated
in the
UFSAR identified in October
1993,
and for the relief pressures
exceeding
the structural
design pressures
of the
reactor
and turbine buildings values stated
in the
UFSAR identified in March.
1995.
"
7
The inspectors
reviewed the applicable revisions of the licensee's
procedure
regarding reportability and determined it to provided appropriate, requirements
to ensure that
and 50.73 reportability regulations related to
conditions that are outside of the design basis of the plant.
3.3. 1 10 CFR 50.72 and 50.73 Reportability October
1993
The inspectors
discussed
with the licensee their reasoning for not declaring
the event reportable
under
50.73 in October
1993,
and was
informed, that even though the relief pressure
of the blowout panels
exceeded
the design basis
values stated in the
UFSAR, the structural
design basis
pressure of the reactor
and turbine buildings would not be exceeded.
Additionally,
NMPC reviewed their design basis
and determined that
HELBs were
outside their design basis that there
was
no credible postulated
event that
would cause
pressures
to challenge
the failure pressure of the reactor or
turbine buildings.
Based
on these
reasons,
NHPC determined that they were not
outside the design basis; therefore,
the condition was not reportable.
The inspectors
evaluated
the reportability decision
made
by NHPC.
Based
on
the definition of Design Basis
as provided in 10 CFR 50.2,
"Design bases
means that information which identifies specific functions to be performed
by
a structure,
system,
or component of a facility, and the specific values or
ranges of values
chosen for controlling parameters
as reference
bounds for
design...."
Since the specific values
chosen for controlling the relief
pressures
of the reactor
and turbine building blowout panels
were exceeded
as
stated in the
UFSAR, the inspectors
considered
Unit
1 to be in a condition
outside their design basis.
The inspectors
concluded that the Unit
1 failure to complete the reports,
as
required in October
1993, is an apparent violation on
and 50.73.
3.3.2
and 50.73 Reportability Narch
1995
During the period of March through July 1995,
NHPC evaluated
the reportability
of the blowout panel relief pressures
on several
occasions.
Through
discussions
with NHPC staff and management,
the inspectors
ascertained
that
NHPC understood that they were outside their design basis relief pressures
of
45 psf as stated
in the
Furthermore,
they understood that the
calculated relief pressures
exceeded
the 80 psf failure pressure for the
reactor
and turbine buildings,
as stated in UFSAR Sections
VI-C.1.2 and III-
A.l.2, respectively.
However,
NHPC decided that the condition was not outside
the Unit
1 design
bases,
since the
UFSAR Sections
XVI.D.2.0 describes
that
HELB events
are not part of the Unit
1 design basis;
and, therefore,
no
postulated
pressure-related
event would challenge
the reactor building blowout
panels.
The inspectors
evaluated
the reportability decision
made
by
NHPC for this time
period.
Unit
1
UFSAR Sections
VI-C.1.2,
"Pressure
Relief Design," describes
specifically, that the reactor building pressure relief is provided to prevent
collapse of the superstructure
due to a break of an emergency cooling system,
or other primary coolant system line in the reactor building.
Further,
the
pressure relief function is provided by the blowout panels,
that were designed
0
to fail at
an internal
pressure
of approximately .45 psf, to prevent excessive
internal pressure
on the superstructure
walls, roof, and their supports,
which
would fail at
an internal pressure
in excess of 80 psf.
A similar description
is provided for the turbine building in UFSAR Section III-A.1.-2, specifying
the initiating event
as
a steam line break.
Since the specific values
chosen for controlling the relief pressures
of the
reactor
and turbine building blowout panels
as stated in the
UFSAR were
exceeded,
and the specific values
chosen for the reactor
and turbine building
failure pressure
as stated in the
UFSAR were exceeded,
the inspectors
considered
Unit
1 to be in a condition'utside their design basis.
Furthermore,
the detailed description of the emergency cooling system line
break
and the steam line break provided in the
UFSAR as the events for which
the. blowout panels
were installed to protect against,
indicated that there
are
analyzed pressure-related
events
would challenge
the reactor
and turbine
building blowout panels.
The inspectors
concluded that Unit
1 failure to complete the reports,
as
required in March 1995, is an apparent violation on
and 50.73.
3.4
Procedural
Compliance
The inspectors
reviewed the applicable revisions of the licensee's
DER
procedure to verify the completion of DER 1-93-2526
was in accordance
with the
procedure.
Although the inspectors
found the
DER completed
as required
by the
procedure,
the inspectors
noted that the length of time taken
between the
identification of the problem until the review of the
was longer than
expected
considering
the potential significance of the condition.
Particularly, the condition was identified on October 25,
1993, the
DER was
initiated on October 28,
1993,
and signed
by the
on November 1,
1993.
Discussion with NHPC management
indicated that the length of time taken for
the condition to receive
SSS review did not meet their expectations.
During the engineering
review of the design control deficiencies
involving the
calculational error and the independent
design review that allowed the
oversized bolts to remain in place from October
1993 until March 1995, the
inspectors identified that no
DER was written in March 1995 to document
and
initiate root cause
and corrective actions.
NHPC Procedure
NIP-ECA-Ol,
"Deviation Event Report," Revision 8, requires
a
DER be written to address
human performance
and personnel
performance
problems
adverse to quality.
The
failure to write a
DER is an apparent violation of the Nine Mile Point Nuclear
Station Unit
1 Technical Specification 6.8. 1, which requires
procedures
to be
implemented.
The inspectors
noted that even though
NHPC did not write a
DER to address
the
human/personnel
performance
concerns
related with the design control
deficiencies,
they did initiate some corrective actions
by provided emphasis
to the Structural
Engineering
Group on the need to perform an adequate
review
of documentation
and verification of assumptions
used in calculation before
final issue.
According to NHPC, this discussion
was completed shortly after
the completion of Refueling Outage
13, prior to the initiation of DER 1-95-
3012.
However, the inspectors
did not .consider this review of the design
control deficiencies to be
a sufficient evaluation of the root cause to
develop appropriate corrective actions to preclude recurrence.
4.0
REVIEW OF LER 95-05,
"BUILDING BLOWOUT PANELS OUTSIDE THE DESIGN BASIS
BECAUSE OF CONSTRUCTION ERROR"
The inspectors
reviewed
LER 95-05,
and found it to accurately describe
the
event associate'd
with the oversized bolts installed in the reactor
and turbine
building blowout panels.
However, the following weaknesses
were identified:
~
the
LER did not adequately
address
the failure to report the condition
in October
1993,
or in Parch
1995;
~
the
LER did not provide sufficient details regarding the
1993
calculational error to allow for an adequate
assessment
of the
licensee's
corrective actions to prevent recurrence;
and
~
the
LER did not address
the potential for, and the significance of a
reactor building failure.
Based
on these
weaknesses,
LER 95-05 will remain open,
pending further
NRC
staff review..
5. 0
SAFETY SIGNIFICANCE
5. 1
Review of the Unit 1 Individual Plant Examination
The inspectors
reviewed the applicable sections of the Unit
1 Individual Plant
Examination
(IPE) related to the reactor building pressure relief design.
The
information provided in Section
4.'1,
"NMP1 Containment
Design Description
and
Data," of the
IPE was consistent with that provided in UFSAR Section VI.C.1.2
"Pressure
Relief Design" for the reactor building.
These sections
from the
UFSAR and the
IPE basically described that pressure relief is provided to
prevent collapse of the superstructure
due to a break of an emergency cooling
system,
or other primary coolant system line in the reactor building.
The
relief is 'provided
by the blowout panels that were designed to fail with an
internal pressure
of approximately
45 psf.
Relief of pressure
through the
panels
in case of an energy release will prevent excessive
internal pressure
on the superstructure
walls, roof, and their support that would fail at
an
internal pressure
in excess of 80 psf.
The inspectors
also noted that the Unit
1
IPE describes
in Table 4.5-1,
"Overall Level
2 Success Criteria," the reactor building integrity and
effectiveness
to be successful, if either
one of the following two criteria
are met:
1)
Reactor building integrity is maintained if the reactor building
pressurizes
to no more than 36 psf. If not, then the reactor
building blowout panels
are to assumed
to have opened.
2)
The reactor building is assumed effective in removing
radionuclides if the following criteria are met:
10
~
No structural
breach to the reactor, building, allowing free
communication with the environment,
caused
by events
such
as
hydrogen detonation
in the reactor building.
~
No natural circulation paths with chimney effects are
established
within the reactor building that could
drastically reduce residence
time and retention within the
reactor building.
Additionally, Section 4. 1.2,
"Summary of Secondary
Containment Features,"
contains
a list of the safety design basis for the secondary
containment
system.
Included in this list as Item 5,
"The reactor building is designed to
contain
a maximum positive internal
pressure
of 80 pounds per square foot
(0.56 psig).
Blowout panels
in the refuel floor are
used to release
at
a
pressure
of approximately
40 pounds per square foot (0.28 psig) to relieve
internal reactor building pressure."
The information pertaining to the Unit
1 design basis
as described
in the
substantiated
the information provide in the
UFSAR, indicating that Unit
1 was
outside their design basis for the reactor building blowout panel relief
pressure.
Additionally, the inspectors
noted inconsistencies
within the
with respect to the relief pressure
of the blowout panels.
These
inconsistencies
indicate blowout panel relief pressures
of 36 psf,
40 psf and
45 psf.
Some of these inconsistencies
are similar to those originally
identified in the UFSAR'by NMPC.
The inspectors
considered
the resolution of
these inconsistencies
an inspector follow item (IFI) to be reviewed during
a
future inspection.
(IFI 50-220/96-05-02)
5.2
Review of the
UFSAR Commitments
A recent discovery of a licensee
operating their facility in a manner contrary
to the
UFSAR description highlighted the need for additional verification that
licensees
were complying with UFSAR commitments.
During an approximate
two
month time period,
February through March 1996, all reactor inspections will
provide additional attention to UFSAR commitments
and their incorporation into
plant practices,
procedures
and procedures.
While performing the inspection,
which are discussed
in this report, the
inspectors
reviewed the applicable portions of the
UFSAR that related to the
areas
inspected.
During discussions
with NMPC personnel,
the following
apparent
inconsistency
was noted in the
UFSAR between
Section XVI.D.2.0 "Plant
Design for Protection Against Postulated
Piping Failure in High Energy Lines,"
and Sections
VI.C.1.2,
and III.A.1.2 "Pressure
Relief Design" for the reactor
and turbine buildings respectively:
Specifically,Section XVI.D.2.0 states that Unit
1 was design
and constructed
prior to 10 CFR 50 Appendix A, "General
Design Criteria,"
(GDC) Criterion 4,
and was not designed
accordance
with this criterion dealing with the effects
of pipe whips from HELBs, vs,Section VI.C.1.2, which states that "breaks in
all primary coolant systems
piping has
been
analyzed
since accidents of this
type result in the highest pressure,
temperature
and humidity condition in the
building.
A break in the emergency
cooling system is the most serious
since
it releases
the most coolant at the highest rate."
Furthermore,
Technical Specification Basis Section 5.4 "Containment," states,
"Pressure relief is
provided to prevent
damage to the superstructure
due to the break of any
primary system line the reactor building.
In this event,
blowout panels will
fail, relieving pressure
in the event of a major line rupture."
Also Section III.A.1.2, states that "to prevent failure of the superstructure
due to a steam line break,
a wall area of 1800 square feet has
been attached
with bolts [blowout panel] will fail due to an internal pressure of
approximately
45 psf; thus relieving the internal pressure."
The inspectors
used the most conservative
design basis for their review.
These inconsistencies
regarding the design basis for Unit
1 with respect to
specific high energy line breaks will be discussed
further during the
enforcement
conference
pertaining to the apparent violations described
in this
report.
Furthermore,
the resolution of these
inconsistencies
is considered
part of the inspector follow item identified in Section 5.1.
(IFI 50-220/96-
05-02)
Additionally, the licensee identified that there
was
a discrepancy
between the
UFSAR Sections III.A.1.2 and VI.C.1.2, which state that the pressure relief
panels
in the tur bine and reactor buildings blow out at 45 psf.
Contrary to
this,
UFSAR Table XVI-31 and discussion
on the subsequent
pages
state that the
pressure relief panels
blow out at 40 psf.
This contradiction led to Unit
1
identifying the discrepancy
between the design
and installed configuration.
NNPC has initiated
a change to the
UFSAR to correct this discrepancy.
5.3
Safety Assessment
and
Summary
The
NNPC organization
has concluded that their March 1995 modification of the
blowout panel bolting had resolved their safety problem.
However, while the
NRC has
no immediate safety concerns
pertaining to the supporting calculations
for this modification, confirmatory independent
review of these calculations
is currently being performed
by the
NRC staff.
During this review, the inspectors
noted that
a general
safety objective for
the reactor building and the turbine building blowout panels is to relieve
internal building pressure prior to structural failure for anticipated
transients/challenges
inside the building.
The inspectors'ocus
was
on the
reactor building since it houses
safety structures,
systems
and components.
If such
an event were to occur, radiation doses
at the site boundary appear to
be accounted for and are of minimal consequences.
However,
two areas
remain
unclear
as
a result of this review:
How much design margin existed for the structural
design value of 80 psf
or what actual
internal building pressure
would result in failure
(collapse)
and the obvious impact on safety related
equipment
such
as
emergency
core cooling systems
being used in response
to the anticipated
transients/challenges.
The highest pressure
in the reactor building for design basis
anticipated transients/challenges.
12
For the time period from initial operations to March 1995,
a vulnerability
existed,
the significance of which is dependent
on resolution of the above
two
areas.
Notwithstanding the fact that no actual
challenges
occurred to the
reactor building internal pressure
relieving system,
the potential existed
which is not addressed
in the related
LER.
More importantly,
NHPC resolution
,of the issue
from October
1993 to March 1995,
was weak in thoroughly
establishing,
understanding,
and evaluating the safety design basis for the
reactor building internal pressure
relieving system;
The weak safety
assessment
coupled with the calculation error,
inadequate
design review of
that calculation,
and apparent failure to follow the
DER procedure
led to the
untimely resolution of this problem commensurate
with its safety significance.
Although this problem was eventually reported to the
NRC, the event report
does not fully address
the safety significance of the potential for (in
distinction to actual)
challenges
to the internal building internal relieving
system for the time period from initial operations
to March 1995.
As a
result, licensee corrective actions
do not address
apparent
weaknesses
in
their technical,
and safety review process.
6.0
HANAGEHENT HEETINGS
At periodic intervals
and at the conclusion of the inspection period, meetings
were held with senior station
management
to discuss
the scope
and findings of
this inspection.
The final exit meeting occurred
on March ll, 1996.
During
the exit meeting,
Richard Abbott, Vice President
and General
Manager,
Nuclear
for NHPC questioned
the inspector's
statements
regarding
NHPC basis for not
reporting the condition under
in March 1995.
Subsequent
conversations
between the inspectors
and
NMPC management,
clarified
.basis,
and
was considered
in this report.
Based
on the
NRC Region I review of
this report,
and discussions
held with NHPC representatives, it was determined
that this report does not contain safeguards
or proprietary information.
Attachment
2 to this report is listing key personnel
contacted
during this
review.
ATTACHNENT 1
TINE LINE
October 20,
1993
.
.
. During the removal of bolts for testing,
technicians
identified that 1/4" bolts used to install the blowout
panels.
october 22-27,
1993
. Test results
were available to the structural
engineer.
August 23,
1993
.
.
.
. Calculation
S7-RX340-W01,
Revision
0 was approved.
October 25,
1993
.
.
. The identification of reactor
and turbine building blowout
panel bolts stronger
than required
by design drawings
as
documented
on
DER 1-93-2526.
October 28,
1993
. Originator signed
DER 1-93-2526.
October 29,
1993
.
.
. Supervisor
signed
DER 1-93-2526.
November
1,
1993
.
.
~ . Station Shift Supervisor
signed
DER 1-.93-2526.
November
5,
1993
February 8,
1995
March 27,
1995
March 30, 31,
1995
April 4,
1995
.
.
. Calculation
S7-RX340-WOl, Revision
1 was approved.
. Refueling outage
13 began.
. Calculation error was identified.
. Every other bolts was from the blowout panels
removed in
accordance
with Modification Nl-95-001
LG329.
. Unit
1 connected
to the grid following refueling outage
13.
=April 5,
1995
.
.
.
. Structure
engineers
training on the verification of
assumptions.
June
22, 1995....
July 6,
1995
October 31,
1995
November 28,
1995
.
November 30,
1995
.
SORC mee'ting discussing
the safety evaluation
associated
with the
UFSAR change to correct the originally identified
UFSAR contradiction,
and the need to document the basis
for not reporting the condition in DER 1-93-2526.
SORC meeting approving the implementation of DER 1-93
-2526,
and the issuance of NHPC memorandum
documenting
bases for not reporting the condition.
. Origination of DER 1-95-3012, "Reportability Review of DER
1-93-2526."
.
SORC meeting approving the disposition of DER 1-95-3012,
and
LER 95-05.
.
NHPC Issued
LER 95-05.
'
Nia ara
Mohawk Power Cor oration
ATTACHMENT 2
PERSONS
CONTACTED
R. Abbot, Vice President
and General
Manager,
Nuclear
H. Alvi, Supervisor,
Structural
Design, Unit
1
D. Baker,
Engineer,
Licensing
M. Balduzzi, Operations
Manager,
Unit
1
C.
Beckham,
Manager, Quality Assurance
G. Corell, Manager,
Chemistry, Unit
1
K. Dahlberg,
General
Manager,
Projects
M. McCommick, Vice President,
Nuclear Safety Assessment
8 Support
N. Rademacher,,Plant
Manager,
Unit
1
K. Sweet,
Manager,
Technical
Support, Unit
1
C. Terry, Vice President,
Nuclear Engineering
G. Wierzbowski, Supervisor,
Technical
Support,
Unit
1
G. Wilson, Counsel
D. Wolniak, Manager,
Licensing
W. Yaeger,
Manager,
Engineering,
Unit
1
A. Zallnick, Licensing Engineer
U;S. Nuclear
Re ulator
Commission
- R. Conte, Chief, Reactor Projects
Branch
(RPB) No.
5
~
~
~
~
~
~
~
- H. Eichenholz,
Project Engineer,
RPB No.'
- M. Hartzman,
Mechanical
Engineering
Branch,
- D. Hood, Project Manager,
- W. Rothman,
Structural
Engineering
Branch,
S.
Sanchez,
Resident
Inspector
All of the above personnel
were present at the exit meeting
on March ll, 1996.
- Telephonic presence
at the exit meeting.
Enclosure
2
DESIGN/LICENSING BASIS QUESTIONS
ON NNP-1
REACTOR BUILDING BLOWOUT PANELS
The
LER discusses
use of blowout panels to protect the secondary
containment
structure.
However,
as discussed
in "GE Design Specifications for 'Reactor
Containment,"
blow-out panels
are also sometimes
used to protect primary
.
containment
from excessive
reverse differential pressure
that could occur-in
the event of a high energy line break in a compartment
adjacent to the
Is this generic design objective applicable to the
NMP-1 facility and what
is the documented
basis if it is7
2.
s.
4.
5.
With respect to page
11 of Nine Mile Point
1 License
Event Report
(LER),
titled, "Building Blowout Panels
Outside
Design Basis
Because of
Construction Error," what are the key assumptions
and engineering
analysis/calculations
performed in late October
1993 which led to the
initial determination that the turbine and reactor building panels
would
blow out at 60 and
53 psf, respectively,
to relieve internal pressure.
[Provide engineering calculations
which support the above stated
blowout
pressures.]
Two design internal
pressures
of 40 and
45 psf are
shown in different
locations of the'SAR for Nine Mi,le Point
1 pressure relief panels
(PRPs)
for the reactor
and turbine buildings.
Please clarify the ambiguity about the two pressure
values
and indicate the
correct licensing basis
design pressure for the
PRPsl
Has
an assessment
been
made
on the error in the design
assumptions
for load
distribution which was identified during the March 1995 refueling outage'
Also explain what assumptions
for load distribution were used in conjunction
with the consideration of the 1/4" bolts with higher ultimate strength
(78
ksi) which led to the determination of the revised
panel
blowout pressures
of 92 and 88 psf for the reactor
and turbine buildings, respectively
(pages
ll and
13 of DER No. 1-93-2526).
With respect to the above referenced
DER, provide
a detailed discussion of
the key assumptions,
panel/bolt configurations
(including pertinent
drawings)
and bolt ultimate strength
used in concluding that the revised
panels
would blowout at about
45 psf with the use of the 1/4" diameter bolts
and the removal of every other bolt from the existing panels.
0
'-
e.
The Reactor Building Blowout panel revised calculations
are based
on certain
assumptions,
the conservatism of which cannot
be determined
unless
compared
to a more rigorous analysis
or test.
It is not clear
how NMPC demonstrated
conformance with FSAR commitments
by
reevaluating
the panel
pressure
capacity using
a more exact methodology,
or
revising the analysis
and stating clearly the conservatism of each
assumption
used in the analysis.
The staff has identified the following effects which appear'to
have not been
considered
in the analysis or are not clearly stated:
'a ~
b.
C.
d.
The calculation of the pressure
capacity of the top and bottom
connections
do not consider the membrane effect of the panel
in the
longitudinal (vertical) direction
and the effect of the flexibilityof
the side connections
between the flutes and the columns.
In addition,
the effect of friction between the bolts and the sheetmetal
surfaces,
due to bolt pre-loading,
has not been considered.
The calculation of the pressure
capacity of the side connections
are
based
on the assumption of a simply supported
beam.
This is not valid
if the panel is rigidly bolted to the angle
members,
in which case the
analysis
should
be based
on
a beam with elastically built-in ends.
The calculation of the pressure
capacity of the side connections
was
determined
from the analysis of a typical flute, without considering
the in-plane
membrane
forces acting
on the flutes.
The calculation of the sheet-metal
shear capacity is based
on one
shear
area.
It should
be based
on two shear
areas.
e.
The effect of the panel
dead-weight
on the connections
has not been
considered.
0'hat
are results of these effects
on the calculation of the panel
pressure
capacities,
as demonstrated
by detailed calculations,
or by the conservatism
of the existing calculations2
Also,
a weakness
of the
1995 modification evaluation for the blowout panel
interim corrective actions
appears
to be the implied assumption of imminence
of failure of the 1/4 " diameter
shear
bolt with a computed "unity" value
for the "shear-tension
interaction" equation.
What is the pertinent analytical or test-supported
basis for such
an
assumption7
[As appropriate,
a more realistic, non-linear finite element analysis of the
PRPs with rigorous modeling of the
PRP elements
including proper
representation
of the combined shear/tension
stiffness of the bolts
and the
supporting
steel
frame may be performed to demonstrate
the adequacy of the
current
PRP eyaluation.]
With respect to Nine Mile Point
1 Calculation
Nos.
S7-RX340-WOI Revisions
0
and 1, in support of bolt strength:
0
a.
What is the basis for selecting
the revised bolt ultimate tensile
strength of 78 ksi in the latest
panel
blowout capacity calculation2
b.
What is the test verified ultimate shear strength of the
same set of
'bolts tested2
c.
Are the strengths
(both the ultimate tensile
and shear strengths)
based
on ultimate strength tests of an adequate
sample size of the
I/4" bolts2
d.
Is the 78 ksi
a mean ultimate tensile strength2
e.
What is. the corresponding
mean ultimate shear strength
used in the
assessment2
C
If they represent
mean ultimate strengths,
what are their
corresponding
standard
deviations2
g.
If the values represent
nominal lower-bound strengths
and they were
used in your latest calculation which confirmed the revised blowout
capacity of approximately
45 psf,
how can one be sure that the panels
would blowout approximately at 45 psf and not at
a higher value2
h.
Given the above mentioned uncertainties
in ultimate tensile
and shear
strengths
and load distribution assumptions
used in the analysis,
has
NHPC, established
a conservatively
determined
upper-bound
panel
blowout
pressure
and demonstrated
that the computed pressure
capacity is lower
than the
45 psf pressure
stipulated in the licensing basis
document2
With respect to the
same calculations
noted
above,
discuss
the
appropriateness
of using conservative
engineering
assumptions
including
conservative
modeling (e.g.,
one way horizontal action for Robertson's
panels)
and use of mean or non-upper-bound
ultimate bolt tensile
and shear
capacities
to determine
a realistic upper-bound
internal
pressure
which will
cause failure. of the
PRPs.
Such
an approach
could underestimate
the real
panel
blowout pressure,
thus,
resulting in a non-conservative
conclusion.
Specifically,
use of a lower-
bound or mean bolt ultimate tensile strength
and
an assumed
ultimate bolt
shear strength of 0.6
F (instead of a test verified shear strength)
would
lead to a unrealistic
PRP failure pressure
and potentially unsafe
conclusion.
Discuss the safety implications of such
a practice in light of the objective
of the
PRP evaluation
and the need-to modify the evaluation
and demonstrate
that the physical
panel disposition proposed is still valid.
0
34386
Federal Register / Vol. 60, No. 126 / Friday, June,30,
1995 / Notices
'
factors in arriving at the appropriate
is not held, the licensee willnormaliy
severity level willbe dependent on tho
be requested to provide a written
circumstances oftho violation.
response to an inspection report, if
However. ifa licensee refuses to conect
issued, as to the licensee's views on the
a minor violation within a reasonable
apparent violations and their root
time such that itwillfullycontinues, the
causes and a description ofp]armed or
violation should be categorized at least
implemented corrective action.
at a Severity Level Di.
During the predecisional enforcement
conference, the licensee, vendor, or
D. Violations ofRePorting Requiremezits
other persons willbe gven an
The NRC expects licensees to prov]de
opportunity to provide information
complete, accurate, and timely
~ consistent with the pmpose ofthe
information and reports. According]yi
conference, including an explanation to
unless otherwise categorized in the
the NRC ofthe immediate corrective
Supplements, tho severity level ofa
actions (ifany) that were taken
violation involving the failure to make
followingident]fication oftho potential
a required report to the NRC willbe
violation or nonconformance and the
based upon the significance ofand the
long-term comprehensive actions that
circumstances surrounding the matter
were taken or willbe taken to prevent
that should havo been reported..
recurrence. Licensees, vendors, or other
However, the sevority lovel ofan
persons willbe told when a meeting is
untimely report, in contrast to no report,
a pzedecisiona] enforcement conference.
may be reduced depending on the
A predecisional enforcement
circumstances surrounding the matter.
conference is a meet]ng between the
A ]icensee wi]lnot norma]]y be cited for
NRC and the licensee. Conferences are
a failure to report a condition or event
normally held in the~lone] offices
unless the licenseo was actually aware
and are not norma]]y open to public
oftho condition or event that it failed
observation. However, a tna] program is
to report. A liconsee will,on the other
being conducted to open approximately
hand, normallY bo cited for a failure to
25 percent ofa}] e]igible conferences for
report a condition or event ifthe
public observation, Le., every fourth
licensee knew ofthe information to be
e]ig]b]e conference invo]ving one of
reportod, but did not recogn]ze that it
three categories of ]icensees (reactor,
was requirea to make a report.
hospital, and other materials licensees)
V. Predecisional Enforcement
wi]Ibe open to tho public. Conferences
Conferences
willnot normally be open to the public
e
th NRC ha
]earned oftho
ifthe enforcement actionbeing
onever
e
as carne
o
o
contem~]ated:
existence ofa Potential violation for
(1) ~ou]d be taken against an
which escalated enforcement action
indiv]dua], or ifthe action, though not
aPPe~ to be anted, or ~umng
taken against an individua];turns on
nonconformance on the part ofa
whethor an individual has committed
vendor, the NRC may provide an
wron doing:
opportunity for a predecisional
(2) fnvo]ves significant personnel
entorcement conference with the
failures where the NRC has requested
licensee, vendor, or other person before
that the individua](s) invo]ved be
taking enforcement action. The purpose
pnisent at the conference.
oftho conference is to obtain
(3) Is based on the findings ofan NRC
information that willassist the NRC in
Office ofinvest]gat]ons report; or
determining the appropriate
(4) Involves safeguards information,
enforcement action, such as: (1) A
pnvacy Act information, or information
common understanding offacts root
which could be considered proprietary;
causes and missed opportunities
In addi'tion, conferences willnot
associated with the apparent v]o]at]onsi
normally be open to the public if:
(2) a common understanding of
(5) The conference involves medical
corrective action taken or planned, and
misadministrations or overexposures
(3) a common understanding ofthe
and the conference cannot be conducted
significance ofissues and the need for
without disclosing the exposed
lasting comprehensive corrective action.
individual'a name; or
Ifthe NRC concludes that ithas
(6) The conference wi]]be conducted
sufficient information to make an
by telephone or the conference willbe
informed enforcement decision, a
conducted at a relatively small
conference willnot normally be held
licensee's facility.
unless the licensee requests it. However,
Notwithstanding meeting any ofthese
an opportunity for a conference will
criteria, a conference may. still be open
normally bo provided before issuing an
ifthe conference involves issues related
order based on a violation of the rule on
to an ongoing adjudiwtory proceeding
'eliberate Misconduct or a civilpenalty
with one or moro intervenors or where
to an unlicensed person. Ifa conference
the evidentiary basis for the conference
is a matter ofpublic zecozd, such as an
adjudicatory:dec]sion by the
Department of Labor. In addition, with
the approva] ofthe Executive Director
forOperations, conferences willnot be
open to the public where good cause has
been shown after ba]anc]ng the benefit
ofthe public observation a(]ainst the
potential impact on the agency's
~
enforcement action in a particular case.
As soon as it is determined that a
conference willbe open to public
observation, the NRC willnotify the
licensee that the conference willbe
open to public observation as part ofthe
agency's trial program. Consistent with
the agency's policy on open meetings,
"StaffMeetings Open to Public,"
published Se ptember 20, 1994 (59 FR 48340), the NRC intends to announce
open conferences normally at least 10
working days in advance ofconferences
through (1) notices'posted in the Pub]ic
Document Room, (2) a toll-free
telephone recording at 800-952-9674,
and (3) a toll-free electronic bulletin
board at 800-952-9676. In addition, the
NRC willalso issue a press release and
notify appropriate State liaison officers
that a predecisional enforcement
conference has been scheduled
and that
it is open to public observation.
Tho public attonding open
conferences under the trial program may
observo but not participate in the
conference. It is noted that the purpose
ofconducting open conferences under
the trial program is not to maximize
public attendance, but rather to
determine whether providing the pub]]c
with opportunities tobe informed of
NRC activities is compatible with the
NRC's ability to exercise its regulatory
and safety responsibilities. Therefore.
members ofthe public willbe allowed
access to the NRC regional ofiices to
attend open enforcement conferences in
accordance with the "Standard
Operating Procedures For Providing
Security Support For NRC Hearings And
Meetings," published November 1, 1991
(56 FR 56251), These procedures
provide that visitors may be subject to
personnel screening, that signs, banners,
posters, etc., not larger than 18" be,
permitted, and that disruptive persons
may be removed.
Members ofthe public attending open
conferences willbe reminded that (1)
the apparent violations discussed at
predecisional enforcement conferences
aro subject to further review and may be
subject to change prior to any resulting
enforcement action and (2) the
statements ofviews or expressions of
opinion made by NRC employees at
predecisional enforcement conferences,
or the lack thereof, are not intended to
represent final determinations or beliefs.
Federal Register / Vol. 60, No. 126 / Friday, June 30, 1995 / Notices
34387
'
Persons attending open conferences will
be provided an opportunity to submit
written comments concerning'the trial
program anonymously to the regional
office. These comments willbe
subsequently for'warded to the Diiector
ofthe Office ofEnforcement forreview
and consideration.
When needed to protect the public
health and safety or common defense
and security, escalated enfozcement-
action, such as the issuance ofan
immediately effective order, willbe
taken before the conference. In these
cases, a conference may be held alter the
escalated enforcement action is taken.
VLEnforcement Actions
This section describes the
enforcement sanctions available to the
NRC and specifies the conditions under
which each may be used. The basic
enforcement sanctions aze Notices of
Violation, civilpenalties, and orders of
various types. As discussed further in
Section VI.D,related administrative
actions such as Notices of
Nonconformance, Notices ofDeviation.
Confirmatory Action Letters, Letters of
Reprimand, and Demands for
Information are used to supplement the
enforcement program. In selecting the
enforcement sanctions or administrative
actions, the NRC willconsider
enforcement actions taken by other
Federal or State regulatory bodies
having concurrent jurisdiction, such as
in transportation matters. Usually,
whenever a violation ofNRC
requirements ofmore than a minor
concern is identified, enforcement
action is taken. The nature and extent of
the enforcement action is intended to
reflect the seriousness ofthe violation
involved. For the vast majority of
violations, a Notice ofViolation or a
Notice ofNonconformance is the normal
action.
A. Notice ofViolation
A Notice ofViolation is a written
notice setting forth ono or more
violations ofa legally binding
requirement. The Notice ofViolation
normally requires the recipient to
rovide a written statement describing
1) the reasons for the violation or, if
contested, the basis for disputing the
violation; (2) corrective steps that have
been taken and the results achieved; (3)
corrective steps that willbe taken to
prevent recurrence; and (4) the date
when fullcompliance willbe achieved.
The NRC may waive all or portions of
a written response to the extent relevant
information has already been provided
to the NRC in writingor documented in
an NRC inspection report. Tho NRC may
require responses
to Notices ofViolation
to be under oath. Normally, responses
under oath willbe required only in
connection with Severity Level I, H,
or'I
violations or orders.
The NRC uses the Notice ofViolation
as the usual method forformalizing the
existence ofa violation. Issuance ofa
Notice ofViolation is normally the only
enforcement action taken, except in
cases where the criteria for issuance of.
civilpenalties and orders, as set forth in
Sections VLBand VI.C, respectively, are
met. However, special circumstances
regarding the violation findings may
warrant discretion being exercised such
that the NRC refrains from issuing a
Notice ofViolation. (See Section VH.B,
"MitigationofEnforcement Sanctions.")
In addition, licensees are not ordinarily
cited for violations resulting from
matters not withintheir control, such as
equipment failures that were not
avoidable by reasonable licensee quality
assurance
measures or management
controls. Generally, however, licensees
are held responsible for the acts oftheir
employees. Accordingly, this policy
should not be zxinstrued to excuse
personnel errors.
B. CivilPenalty
Acivilpenalty is a monetary penalty
that may be imposed for violation of (1)
certain specified licensing provisions of
the Atomic Energy Act or-
supplementary NRC rules or orders; (2)
any requirement for which a license
tnay be revoked; or (3) reporting
requirements under section 206 ofthe
Energy Reorganization Act. Civil
penalties are designed to deter futuro
violations both by the involved licensee
as well as by other licensees conducting
similar activities and to emphasize the
need for licensees to identify violations
and take prompt comprehensive
corrective action.
Civilpenalties are considered for
Severity Level HIviolations. In addition,
civilpenalties willnormally be assessed
for Severity Level I and H violations and
knowing and conscious violations ofthe
reporting requirements ofsection 206 of
the Energy Reorganization Act.
Civilpenalties are used to encourage
prompt identification and prompt and
comprehensive correction ofviolations,
to emphasize compliance in a manner
that deters future violations, and to
serve to focus licensees'ttention
on
violations ofsignificant regulatory
concern.
Although management involvement,
direct or indirect, in a violation may
lead to an increase in the civilpenalty.
the lack ofmanagement involvement
may not be used to mitigate a civil
enalty. Allowingmitigation in the
atter case could encourage the lack of
management involvement in licensed
activities and a decrease in protection of
the public health and safety.
1. Base CivilPenalty
The NRC imposos different levels of
penalties fordifferent severity level
violations and different classes of
licensees, vendors, and other persons.
Tables 1A and 1B show the base civil
penalties for various reactor, fuel cyclo,
materials, and vendor programs. (Civil
penalties issued to individuals are
determined on a case-by~se
basis.) The
structure of these tables generally takes
into account the gravity ofthe violation
as a primary consideration and the
abilityto pay as a secondary
consideration. Generally, operations
involvinggreater nuclear material
inventories and greater potential
consequences
to the public and licensee
employees receive higher civil
penalties. Regarding the secondary
factor ofabilityofvarious classes of
licensees to pay the civilpenalties, it.is
not the NRC's intention that the
economic impact ofa civilpenalty be so
severe that it puts a licensee out of
business (orders. rather than civil
penalties, are used when the intent is to
suspend or terminate licensed activities)
or adversely affects a licensee's ability
to safely conduct'icensed activities.
The deterrent effect ofcivilpenalties is
best served when the amounts ofthe
penalties take into account a licensee's
ability to pay. In determining the
amount ofcivilpenalties for licensees
for whom the tables do not reflect the
ability to pay or the gravity ofthe
violation, the NRC willconsider as
necessary an increase or decrease on a
case-by~so basis. Normally, ifa
licensee can demonstrate financial
hardship, the NRC willconsider
payments over time, including interest,
rather than reducing the amount ofthe
civilpenalty. However, where a licensee
claims financial hardship, the licensee
willnormally be required to address
why it has sufficient resources to safely
conduct licensed activities and pay
license and inspection fees.
2. CivilPenalty Assessment
.
Inan effort to (1) emphasize the
importance ofadherence to
requirements and (2) reinforce prompt
self-identification ofproblems and root
causes and prompt and comprehensive
correction ofviolations, the NRC
reviews each proposed civilpenalty on
its own merits and, alter considering all
relevant circumstances, may adjust the
base civilpenalties shown in Table 1A
and 1B for Severity Level I, H, and Hi
violations as described below.
~ .