ML17058A989

From kanterella
Jump to navigation Jump to search
Insp Rept 50-410/92-15 on 920512-14 & 26-29.Major Areas Inspected:Response to Insp Findings Re Engine Cylinder Liner & Piston Distress in Cooper KSV-16 EDG
ML17058A989
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 07/01/1992
From: Ruland W, Woodard C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17058A988 List:
References
50-410-92-15, NUDOCS 9207170074
Download: ML17058A989 (20)


See also: IR 05000410/1992015

Text

U.S. NUCLEAR REGULATORY COMMISSION

REGION'1

DOCKET NOS.

REPORT NOS.

LICENSE NOS.

LICENSEE:

FACILITYNAME:

92-15

NPF-69

Niagara Mohawk Power Corporation

301 Plainfield Road

Syracuse,

New York

13212

Nine Mile Point Nuclear Power Station, Unit 2

INSPECTION AT:

Scriba, New York

INSPECTION DATES:

May 12-14 and May 26-29, 1992

INSPECTORS:

C. H. Woodard, Reactor Engineer, DRS

C. Bennett, Reactor Engineer, DRS

3. Rajan, Mechanical Engineer, NRR/EMEB

E. Murphy, Consultant Inspector, American Systems Corp.

INSPECTOR:

C. H. Woodard, Reactor Engineer,

Electrical Section, EB, DRS

ate

APPROVED BY:

. Ruland, Acting Chief, Electrical Section,

Engineering Branch, DRS

a

s

y

Date

9207170074

920702

PDR

ADOCK 05000410

PDR

EXECUTIVESUMMARY

This inspection was in response

to the licensee's inspection findings which identified engine

cylinder liner and piston distress in their Cooper KSV-16 emergency diesel generator (EDG) ~

This distress was identified as similar to that found in 1989 at Susquehanna

in their Cooper

KSV-16 engines

as precursors which had led to several crankcase'explosion

events.

The inspectors found that the Cooper EDG users group had developed

a draft inspection

manual in April 1992 to be used as a guide in inspectirig the Cooper KSV engine cylinder

liners and pistons for distress.

This manual included input from the Susquehanna

root cause

evaluations which were concluded late in 1991.

It included color photographs of distressed

and damaged KSV-16 pistons, cylinder liners wrist pins, and wrist pin bearings from

Susquehanna

and told the users how to look, what to look for, and what constitutes the

distress indications which could lead to EDG failure. It also covered corrective actions which

included the removal of piston wrist pin end cap seals and the piston bottom of skirt oil

scraper ring to improve cylinder lubrication.

The inspectors found that the licensee had completed the inspection and changes

to the

Division 11 EDG.

Inspection procedures,

methods,

results and changes were reviewed for

this unit. The inspectors witnessed

the inspection of the Division I unit.

As a consequence

of the distress indications found, the licensee has replaced six of the pistons and liners on the

Division I EDG and nine of the pistons and liners on the Division IIEDG. With Cooper

concurrence,

all of the wrist pin end caps and bottom piston skirt oil scraper rings were

removed in both EDG units in order to improve piston to liner lubrication.

The licensee

f'ound no damage to wrist pins,,wrist pin bearings, crankshaft journals, and connecting rod

bearings.

The inspectors concl'uded that the licensee had aggressively pursued the EDG inspection with

a dedicated

system engineer aided by onsite Cooper representatives

in identifying the

distressed

components,

replacing them and in making engine modifications to overcome the

potential root causes of the problems.

This work was actively supported by upper

management

with much day-to-day direct involvement in the EDG rooms.

Modifications

were made in accordance with approved procedures

and included appropriate QA involvement

in all areas.

Licensee root cause analyses with followup enhanced

inspections are planned to

provide additional confirniation that the basic problems (root causes)

have been corrected.

1.0

BACKGROUND

Niagara Mohawk (NM) Unit 2 Nuclear Power Plant utilizes a Cooper KSV-16 emergency

diesel generator (EDG) unit in each of the Division I and Division II safety-related electrical

power trains.

Cooper KSV-16 EDG units at the Pennsylvania Power and Light (PP&1.)

Susquehanna

Nuclear Power Plants underwent a series of crankcase explosions the last of

which occurred in 1989.

Distress and damage found in the failed Susquehanna

EDG units

included piston and cylinder liner distress in which piston tin coating (bearing material) was

wiped (galled/scraped) off onto the liners.

Piston wrist pins and wrist pin bearings were

damaged

and press-fit piston wrist pin end cap seals had moved out and galled cylinder

chrome-plated liners.

As a consequence of these events, PP&L took corrective actions and made modifications

based

upon suspected

root causes.

These included the replacement of all distressed cylinder

liners, pistons, wrist pins and bearings;

the removal of the piston wrist pin end cap seals and

the piston skirt bottom oil scraper rings to provide for better piston/liner lubrication; the

elimination of cold, dry and unnecessary

fast starts; and modifications to provide for warm

pre-lubricated engines.

PP&L has not reported any evidence of cylinder distress since these

changes were made in 1989.

Since 1989, PP&L conducted extensive root cause evaluations

including extensive proof testing of a similar Cooper KSV engine which was heavily

instrumented and operated

under controlled conditions to confirm the root causes of the

cylinder distress and engine failures.

These evaluations were concluded during late 1991.

Based upon the evaluations, PP&L along with other nuclear utilities which use the Cooper

KSV EDG units prepared

a draft inspection manual.

This inspection manual provided the

details needed for inspection of the EDG units.

It included vivid detailed color photographs

of normal and distressed

pistons and cylinder liners. It provided information as to what to

look for, how to look for it and what constitutes distress which could lead to EDG failure.

The draft inspection manual was received by NM Unit 2 on April 30, 1992.

At this time the

Division I EDG had con>pleted its outage maintenance,

surveillance, testing and was

considered operable.

The Division II EDG was near completion of the same.

Although there

was no requirement for NM to conduct the draft manual inspections, both the Division II and

l EDG units were sequentially declared inoperable and inspected per the draft manual by NM

personnel with the direct assistance of Cooper field service personnel.

(The EDG units each

had started approximately 350 times and had operated approximately 750 hours0.00868 days <br />0.208 hours <br />0.00124 weeks <br />2.85375e-4 months <br />.)

2.0

INSPECTIOÃ DETAILS

2.1

EDG Tin Smearing

The inspectors reviewed the "Draft Inspection Manual for Cooper Bessemer (C-B) Model

, KSV Diesel Engine Cylinder Liners, Pistons and Bearings," dated April 9, 1992.

The

manual was prepared by and for the use of the utilities which comprise the C-B KSV EDG

users group for the 16 nuclear power stations which use this EDG unit. The stated purpose

of this manual is to provide guidance for the evaluation of degradation of cylinder liners,

pistons, main and connecting rod bearings and camshafts.

These components were selected

for inclusion due to the potential for a significant reduction in reliability ifthe degradation

is

not identified, or because

the mode of degradation is relatively unique to C-B KSV diesel

engines.

The intent was to provide general industry guidelines for identifying the various

modes of component degradation.

The manual was incomplete in that it did not yet include

guidance for the evaluation of bearings and camshafts.

However, the inspectors found the

draft manual to be adequate for inspection for the tin smear degradation of the pistons and

cylinder liners.

The information presented

relating to the piston-to-liner tin smearing found

in the inspection

n>anual represents

information not previously available from the EDG

inanufacturer, other users or the NRC.

Al tire time of this inspection, the licensee had completed the inspection and refurbishment of

the Division II EDG by the replacement of nine of sixteen (16) pistons hnd cylinder liners

and by the removal of all 16 cylinders piston wrist pin seal end caps and the piston skirt

bottom oil scraper rings.

Cooper concurred by letter to the licensee in the modification,

including the removal of end cap seals and bottom piston skirt oil scraper rings.

By

conducting a review of the licensee's documentation of the inspection of the Division II

EDG, including color photographs of each of the cylinders and liners, the inspectors

concluded that the licensee had conservatively identified and replaced all distressed

pistons

and cylinder liners.

ln addition, the inspection of the piston wrist pins and piston bronze

insert bearings mei the inspection'riteria.

No indications of damage were evident.

The inspectors witnessed portions of the licensee's

inspections,

replacements

and modification

of the Division I EDG unit including the removal of three of the six pistons and liners that

were replaced.

The inspection and modifications were performed in accordance with the

licensee's

approved NMP 2 simple design change (SDC) Procedure No. SDC 2-0136-92 and

the user's Group Inspection Manual.

Initial inspection of each of the 16 cylinders was

conducted by observing, the upper cylinder liner and piston crown through the fuel injection

port, by means ot'

borescope

and then by inspecting the lower portion of the cylinder liner

and piston skirt via the crankcase

access cover openings.

With the limited visibilityprovided

during this initial inspection, the licensee indicated that as many as 10 cylinders liners and

pistons were suspect.

By the sequential removal of cylinder heads, pistons and liners from

the engine for all 16 cylinders, the licensee was able to thoroughly inspect each cylinder.

As

a consequence,

the licensee found that six of the pistons and liners required replacement.

The licensee found no indications of overheating or damage to any of the wrist pins and wrist

pin bearings.

Since the connecting rod caps were removed to pull the pistons, the licensee

was able to inspect all connecting rod caps and bearings and the crank shaft journals.

There

was no evidence of daniage.

The inspectors found active quality assurance

and management

involvement evident in all of the procedures

and in the EDG rooms on a routine daily basis.

The inspectors also found that the licensee's EDG system engineer had "changed hats" to

become a maintenance

mechanic in order to be able to participate with "hands-on" direct

involvement.

This direct hands-on involvement was considered

to be a positive factor in

conducting this major effort.

Overall, the inspectors concluded that the inspection,

modifications, and replacements

were conducted in a professional manner, by

experienced/trained

professionals who used approved procedures,

and whose efforts were

monitored effectively on an on-going basis by quality assurance

and plant management.

The inspectors tried to determine when some of the tin removal from the pistons occurred.

Since some ot'he iin reiiioved trom the piston will be washed down into the crankcase,

engine oil, analyses were examined for preceding years for tin content.

The licensee

performed no detailed analyses for tin prior to 1990.

These monthly analysis did not disclose

any significant variations in tin content of the lube oil. Therefore, the inspectors could not

identify a specific time during the preceding two years in which significant tin transfer

occurred.

This does not rule out tin transfer during this time.

Flakes of tin transferred from

the piston to the engine crankcase will tend to float in the oil and much of it could be filtered

out by the engine oil tilters.

The licensee had made no periodic analyses of engine oil filters

for collected elements.

Oil samples

had been taken from shutdown units crankcase without

regard to time after shutdown and crankcase location.

The licensee agreed to establish

a

meaningful oil sampling procedure that will permit comparing and trending subsequent

~ samples on known reference basis.

The inspectors found that "pop testing" of fuel.injectors was not routinely performed to verify

proper performance.

(It was not included in the vendors routine periodic maintenance

instructions.)

The "pop test" verifies that the injector will open at the proper fuel oil pressure

and that the injector produces

a conical spray mist of fuel.

The proper operating pressure

and

spray characteristics

are essential

to a balanced combustion engine which produces its peak

operating pressure

in each cylinder at the proper (approximately the same) crank shaft angle.

lnjectors that weep or dribble or pop early or late can be compensated

for by adjusting the

fuel rack for each cylinder; however, this does not resolve the basic engine combustion

problem.

The inspectors found up to eight degrees difference in the fuel pump rack setting

between cylinders.

The licensee is currently addressing

this potential problem.

The inspectors questioned

the licensee's continuing approval as satisfactory the EDG lube oil

based

upon satisfactory viscosity when the monthly analysis received (since February

1991)

show fuel oil dilution in the engine oil ranging between

5 and 6%.

This represents

approximately 20 gallons of fuel contamination in the oil. Fuel dilution in engine oil above

2% is generally considered

to be a problem.

A source of raw fuel oil is from fuel injectors

down past the pistons into the crankcase.

Any liquid fuel oil degrades piston to liner

lubrication as it moves from injectors to the crankcase

and also reduces the lubricity of the oil

in the crankcase.

During the inspection, the licensee obtained information which indicates

that there was an error in the analysis as a consequence of the contract laboratory using an

improper oil standard.

Since the inspection, the inspectors were advised that new analyses

made utilizing the proper standard indicated that the fuel oil dilution was less than 2%.

The

licensee has now established

acceptance

limits on the permissible levels of fuel oil in the

engine oil (the C-8 EDG manual did not provide the licensee with limits). Although this

item is now resolved, the inspectors considered it a weakness in that the high dilution had not

been properly addressed.

2.2

EDG Fuel Oil Receipts

The inspector found that the licensee's procedures permit up to 30.days to accomplish the full

analysis of the EDG t'uel oil after it is added to the EDG fuel tanks.

This procedure is

generally in accordance

with the guidance provided to the licensee in'the NRC Standard

Technical Specifications and in the NRC Regulatory Guide 1.137.

However, the licensee had

not recognized tliat by adding tliis unanalyzed

class

1E material to the class 1E EDG units,

that the operability status ot each of the EDG is in question until the confirming analysis is

received.

In fact, by topping off all of the EDG -fuel tanks from a single tanker (the common

practice), there exists a means for the simultaneous common mode failures of all EDG units.

Prior to the conclusion of this inspection, the licensee had confirmed the analysis of the fuel

oil in each of the EDG tanks and had implemented temporary procedural changes to address

this problein.

Draft procedure N2-PM-015, Diesel Fuel Off Load, was reviewed.

It includes

provisions for holdin< the fuel oil in the tanker until full analysis is made prior to adding it to

the tanks.

According to the licensee, previous procedure N2-DDI-5.19 is to be superseded

by the new procedure et'fective June

I', 1992.

Implementation of the new procedure will

resolve this problem.

2.3

Fast Start and Load

Fast starting and fast loading of cold, dry (not pre-lubed) EDG units is considered to

contribute to the unreliability of the units.

NRC Generic Letter 84-15 requested

that

licensee's

address

this issue by making changes

in their surveillance and testing procedures

to

minimize or eliminate this type of starting and loading.

The inspectors determined that NM

had addressed

this issue except for a 184-day test when the units are dry-fast started and fast

loaded into the grid.

The dry start and fast loading during the six-month test are required by

licensee Technical Specification 4.8.1.1.2.a.5

and are conducted in accordance with EDG test

procedure N2-OSP-EGS-M001.

The inspectors questioned

the need for the six-month dry

start, fast load test.

The licensee plans

to review the need.and, ifnot required, to request a

Technical Specification amendment

to delete this requirement.

3.0

CONCLUSION

The licensee acted responsively to the EDG Draft Inspection Manual and proceeded with

further inspection in which precursors of potential EDG failure were identified and corrected

prior to plant startup.

The inspection was made by the licensee with good management

sup'port, active QA involvement, with the effective utilization of a knowledgeable systems

engineer using approved procedures

and with the support of the EDG manufacturer.

Although the license's high fuel oil concentration in the EDG lube oil proved to be an

analysis error, they failed to properly question the high concentration.

The Cooper-Bessemer

(CB) KSV engine is susceptible to piston-to-liner tin smear degradation in the nuclear power

industry which can lead to EDG failure.

APPENDIX A

PERSONS CONTACTED

Nia ara M hawk Power Co

ra ion

"Q. Brownell, Site Licensing Supervisor

  • G. Thompson, System Engineering Supervisor

"'M. McCormick, Plant Manager

T. Fiorenza, Diesel Generators

Systems Engineer

K. Murray, Engineer

D. Kazyaka, Engineer

K. Coates,

Maintenance Manager

R. Dean, Lead Systems Engineer

J. Blasiack, Plant Chemistry Supervisor

J. Savoca,

Maintenance Support Manager

J. Doherty, Procurement Engineer

.onsultant

E. Murphy, Diesel Generator Specialist, American System Engineering Corporation

Coo er-Bessemer

Co

oration

~

g

J. Horn, Manager, Engineering

.S. Nuclear Re ulator

Commission

E. Tomlinson, Diesel Generator Specialist, NRR

J. Rajan, Supervisor, Mechanical Engineering Branch, NRR

":W. Mattingily, Resident Inspector

"C. Bennett, Inspector

W. Schmidt, Senior Resident Inspector

Asterisk (":) indicates those present at the exit meeting.

J

'

APPENDIX B

DOCUMENTS REVIEWED

1.

Inspection Manual for Cooper-Bessemer

Model KSV Diesel'Engine Cylinder Liners,

Pistons and Bearings.

Draft Issue, dated April 8, 1992.

U.S. NRC Safety Evaluation of the Emergency Diesel Generator (EDG) Crankcase

Overpressurization

Events, Susquehann'a

Steam Electric Station, Units

1 and 2 (TAC

Nos. M81347 and M81348) dated May 11, 1992.

Cooper-Bessemer

instruction Manual ¹93080, KSV Turbo Charged Diesel Generating

Unit, Nuclear Power Plant-Emergency

Standby.

  • 200xx,Rev 9/81

~

Pennsylvania

Power and Light Company (PP&L) Root Cause Investigation.

Piston

Tests at SMLP and Distortion/Contact Patch Analysis, dated September

1991.

5.

Susquehanna

Steam Electric Station EDG Root Cause Investigation Baseline Engine

Test Report Cooper-Bessemer

KSV-12-GT Diesel Engine at Sumner Municipal Light

Plant, MPR-1218, Revision A, dated December

1990.

~

6.

U.S. NRC Region I Inspection Report of Cooper Diesel Generator Failures'at PP&L

Susquehanna

Power Station, Reports 50-387/89-30 and 50-388/89-27.

U.S. NRC Memorandum for Hehl, Region I from Varga, NRR Task Interface

Agreement Regarding Emergency Diesel Generator Failures at Susquehanna

Steam

Electric Station, Units l and 2.

8.

NMPC ¹2 Technical Specification 3/4.8, Electrical Power Sources.

NMPC ¹2 Division I and

11 Diesel Generator Operability Test Procedure N2-OSP-

EGS-M001, Rev. 3, dated 12/22/90.

10.

U.S. NRC Generic Letter 84-15, Proposed Staff Actions to Improve and Maintain

Diesel Generator Reliability.

1 l.

NMPC ¹2 Divisions l,2 and 3 EDG Lube Oil Analysis Summaries (2/17/91-5/24/92).

12.

NMPC ¹2 Chemistry Procedure N2-CSP-17V Hydraulic and Lubrication Oil

Surveillance,

Rev. 4/23/91.

13.

NMPC ¹2 Division l and 2 EDG Operating Logs (Operation through 4/15/92).

14.

NMPC ¹2 Division I and II Diesel Generator Operating Cycle 24-hour Run and Load

Rejection Test Procedure N2-OSP-EGS-R002,

Rev. 2, dated 8/6/90,

Appendix 8

15.

NMPC ¹2 Division I and II Diesel Generator Operating Cycle Simulated Loss of

Offsite Power with ECCS, Test Procedure N2-OSP-EGS-R004,

Rev. 3, dated

8/22/90.

16.

NMPC ¹2 Division I and II Diesel Generator Operating Cycle Simulated Loss of

Offsite Power with No ECCS, Test Procedure N2-OSP-EGS-R003,

Rev. 1, dated

2/7/91.

17.

NMPC ¹2 Division I and II Diesel Generator ECCS Start, Test Procedure

.

N2-OSP-EGS-R001,

Rev.

1, dated 10/26/92.