ML17056B895

From kanterella
Jump to navigation Jump to search
Ack Receipt of 920513 Response to Violations Noted in Augmented Insp Rept 50-410/92-81
ML17056B895
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 06/02/1992
From: Hodges M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Sylvia B
NIAGARA MOHAWK POWER CORP.
References
NUDOCS 9206090023
Download: ML17056B895 (16)


See also: IR 05000410/1992081

Text

Docket No.

50-410

Mr. B. Ralph Sylvia

Executive Vice President - Nuclear

Niagara Mohawk Power Corporation

¹ine MilePoint

Post Office Box 63, Lake Road

Lycoming, New York 13093

Dear Mr. Sylvia:

Subject:

RESPONSE TO THE NRC REGION I AUGMENTEDINSPECTION TEAM

(AIT) REVIEW OF THE MARCH 23, 1992 NINE MILEPOINT UNIT 2

LOSS OF OFFSITE POWER AND CONTROL ROOM ANI'AJNCIATOR

EVENT, INSPECTION REPORT NO. 50-410/92-81

This refers to your letter dated May 13, 1992, which responded to the AITreport transmitted

to you on April 10, 1992.

Your letter presented

a summary of Niagara Mohawk's corrective

actions relative to the March 23, 1992 event and the findings of the subsequent AIT. You

described the corrective actions that had been accomplished,

and those not yet finished were

assigned specific completion dates.

These actions willbe examined during a future inspection

of your facility

Your cooperation with us is appreciated.

Sincerely,

Marvin W. Hodges, Director

Division of Reactor Safety

920b090023

920b02

PDR

ADOCK 05000410

Q

PDR

ME~ l

lI

B. Ralph Sylvia

JUN 03 1992

2

cc w/encl:

J. Firlit, Vice President - Nuclear Generation

C. Terry, Vice President - Nuclear Engineering

J. Perry, Vice President - Quality Assurance

S. Wilczek, Jr., Vice President - Nuclear Support

K. Dahlberg, Unit 1 Plant Man'ger

M. McCormick, Unit 2 Plant hLu~er

D. Greene, Manager, Licensing

J. Warden, New York Consumer Protection Branch

G. Wilson, Senior Attorney

M. Wetterhahn, Winston and Strawn

Director, Power Division, 'Department of Public Service, State of New York

C. Donaldson, Esquire, Assistant Attorney General, New York Department of Law

K. Abraham, PAO AllInspection Reports

Public Document Room (PDR)

Local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

NRC Resident Inspector

State of New York, SLO Designee

bcc w/encl:

Region I Docket Room (with concurrences)

W. Lanning, DRS

C. Cowgill, DRP

J. Yerokun, DRP

L. Nicholson, DRP

S. Greenlee, DRP

W. Schmidt, SRI - Nine Mile

R. Lobel, OEDO

R. Capra, NRR

J. Menning, NRR

D. Brinkman, NRR

DRS SALP Coordinator

RI:DRS

5/8/92

~c/q

Anderson

98/%92

RI:DRS

Hod

s

6/p /92

OFFICIALRECORD COPY

A:9281.RL

V NIAGARA,

u MOHAWK

NIAGARA~OH +KPOKIER CORPORATION/NINE MILEPOINT. PO BOX 63. LYCOMING,NY 13093/TELEPHQNE {315) 349.288/

8. Ralph Sylvia

May 13, 1992

Executive Vice President

NMP84888

Nuclear

Mr. Marvin W. Hodges

Director, Division of Reactor Safety

United States Nuclear Regulatory Commission

475 Allendale Road

King of Prussia,

PA 19406-1415

RE:

Nine Mile Point Unit 2

Docket No. 50-410

NPF-

Subject:

Response

to the NRC Region I Augmented Inspection Team (AIT) Review of the

March 23, 1992 Nine Mile Point Unit 2 Loss of Offsite Power and Control Room

Annunciator Event.'Inspection Report No. 50%10/92-81

Dear Mr. Hodges:

On March 23, 1992 Nine Mile Point Unit 2 (NMP2) declared an "ALERT," in accordance with

~

~

~

its Emergency Plan criteria, as a result of the loss of all Control Room annunciators.

The loss

of Control Room annunciators was due to the unplanned loss of offsite '1 15 KV power line No.

5, associated

Reserve Transformer 1A, and related Division I loads as a result of an inadvertent

actuation, during restoration from calibration, of an overcurrent protection relay. At the time

of this event, NMP2 was in the Second

Refuel Outage,

and the reactor core was partially

offloaded.

Fuel movements

were not in progress

at the time of the event.

A detailed

description of the sequence

of events is contained in LER 50-410/92-06, dated April 22, 1992.

In response to this event, the NRC formed an Augmented Inspection Team (AIT) on March 24,

1992.

During the period of March 24-28, 1992 the,AIT conducted an independent inspection,

review, and evaluation of, the conditions and circumstances

associated

with this event.

The

AIT had complete access to plant staff and records to support their investigation.

Niagara

Mohawk cooperated'ully with the AIT.

The AIT's inspection report, 50-410/92-81,

was

received by Niagara Mohawk on April 13, 1992.

Niagara Mohawk was requested to respond

to this report within 30 days of receipt, discussing our plan for corrective actions.

This letter summarizes Niagara Mohawk's corrective actions relative to the NRC's findings in

Inspection Report 50-410/92-81.

This letter also includes the corrective actions identified in

LER 50-410/92-06, dated April 22, 1992 and Niagara Mohawk's presentation at the AIT exit

meeting on April 1, 1992.

A complete listing of all corrective actions is=contained. in the

Niagara Mohawk assessment

team report.

TEAM

Immediately following termination of the ALERT, an NMPC assessment

team was formed under

the direction of the Nine Mile Point Unit 2 Plant Manager, to investigate

and evaluate the

circumstances

leading to the declaration of the ALERT, and to evaluate the performance of

equipment and personnel.

A written report, consisting of individual team reports and corrective

actions has been prepared.

Corrective actions have been established for all identified concerns

i

1

Mr. Marvin W. Hodges

May 13,,1992

and will be ti'acked to conclusion

via the Deviation/Event

Report

(DER) process.

The

assessment

report has been reviewed by the Station Operations Review Committee.

A copy

of the assessment

report will be provided to the Senior Resident Inspector at Nine Mile Point.

W R

PRI RITIZATI

ND

HED L N

Correcting the deficiency that prevented UPS-1A from transferring back to the normal power

source from the maintenance

power supply was not given the proper priority by Operations,

Outage IVlanagement, Work Control or System Engineering.

This lack of timeliness allowed the

deficiency to remain uncorrected for 15 days, during which time the plant was vulnerable to

a loss of UPS-1A loads (Control Room annunciator local power supplies) through loss of the

maintenance

power supply.

The root cause

of the failure to properly prioritize this work was that Operations

did not

~

exercise their responsibility for setting work priority and tracking work. Contributing factors

were:

the procedure requires that Work Requests

(WRs) be sent to the Operations

Planning

group (part of the Work Control Center) rather than to Operations

Department

personnel,

responsible

personnel

may have

been distracted

by multiple outage

priorities early in the

outage,

and the potential for the loss of all Control Room annunciators

upon loss of a single

UPS (in this case, UPS-1A) was not widely understood.

Corrective actions are:

Administrative Procedure

(AP) 5.5

~ 1, "Work Requests" willbe revised to clearly require

the Station Shift Supervisor (SSS)/Assistant

SSS establish WR priority. This will be

completed by September

1992.

In the interim, WRs are sent to the Control Room to

establish priority.

A Lessons

Learned Transmittal (LLT) will be sent to all Operations, Work Control and

Technical

Support

personnel

to remind them that Operations

personnel

have the

responsibility to establish work priorities commensurate with the importance to station

operations.

This will be completed by June 1992.

Operations has included the UPS's on a Control Room status board.

Operations is developing a list of important equipment to be included in the daily work

schedule.

This will be completed by September

1992.

A Lessons Learned Transmittal (LLT) will be sent to all NMP2 personnel to stress the

urgency of corrective maintenance

on UPS's,

until the full capability of the UPS is

restored.

This will be completed by June 1992.

Regarding maintenance work control, NMP2 had begun implementing improvements following

NMPl's inadvertent Loss of the Ultimate Heat Sink event of February 1992.

Work packages

were prescreened,

and plant impact was assessed.

However, the plant impact assessment

part

of the overcurrent protection relay work package was inadequate

in that it did not address the

impact of inadvertent relay actuation during the work. Interviews with Control Room super-

vision, Outage Management, Operations Management, and the technicians performing the work

Mr Qarvin W. Hodges

May 13, 1992

onsidered the risk of tripping line No. 5 d

these relays.

This could occur during'calibration when the cover is re-installed on the relay.

following the March 23, 1992 event, all relay work was stopped at NMP2, and plant impact

statements

in relay work packages

were re-assessed

and clarified before allowing work to

continue.

Direction was given by the NMP1 and NMP2 Plant Managers, via memo to Branch

Managers onsite, reinforcing expectations for pre-work job planning of Relay and Control Work

In Progress

(WIP) data, sheets as outlined in Site Administrative Procedure AP-5.2.5, "Work In

Progress."

R LT

I NA D

P

Relay and Control technician job performance leading up to and during the event was not up

to expectations..The

technicians did not have a full understanding of the potential equipment

and plant impact.

Once the inadvertent relay actuation

and line loss had occurred,

the

technicians did acknowledge the error to the Control Room. However, subsequent

evaluation

and communication to the Assistant SSS regarding the use of line No. 6 to reenergize the line

No. 5'bus was inadequate,

resulting in the further loss of line No. 6.

As the AITreport notes,

a human factors issue contributed to the inadvertent relay actuation.

The relay that actuated when the, cover was replaced

is located only inches from the floor,

making cover replacement difficult. The technicians

had not been trained in this particular

configuration.

To address the noted performance deficiencies,

Relay and Control supervision instructed

all

Relay

and

Control technicians

at NMP2 that complete

and

concise

equipment

impact

statements

must be included on the WIP data sheets and that they must provide Operations

with a full functional description of the protective relay or metering logic pertaining to the

system under test.

Improved pre-job briefings will be conducted

and will include sufficient

detail to establish

a full understanding

by all personnel involved in the particular test of the

circuit functions,

including

all auxiliary relays

associated

with the scheme

under test.

Additionally, a training mockup has been developed to certify Relay and Control personnel for

removal/re-installation of relay covers.

A training effectiveness evaluation was conducted by the Operations Training Department to

review and identify operator strengths and weaknesses

resulting from this event. This review

resulted in the nyy{fificationof existing, and the development of new Requalification Lesson

Plans to upgradCIeensed

and non-licensed operator training programs.

The plans include but

are not limited ti7.~

~

The review of the auxiliary boiler relay protection logic and how it affects offsite power

availability.

~

Plant impacts upon loss of individual UPS loads.

~

A technical seminar by the Relay and Control Department on line protection schemes

and relaying.

~

Additionally, simulator evaluations identified that a reproduction of'a similar loss of line No. 5

scenario was not possible.. A Simulator Discrepancy

Report was generated

to correct the

deficiency and completed on April 3, 1992.

- Page 4

tVlr. Marvin W. Hodges

lUlay 13, 1992

op

o

g

t will discuss the miscommunication

aspects

of the M

h 23,

Op

o

personnel,

and develop guidelines for a moie assertive

and

type of communcation between Operations and Support personnel, including Relay and Control

personnel.

These actions will be completed prior to Unit 2'startup from its Second

Refuel

Outage.

Additionally, to aid operators

in correcting alarm conditions resulting from tripped relays,

Operating Procedure

N2-0P-70, "Station Electrical Feed

and 115 KV Switchyard," will be

revised to include protective devices relaying schemes.

The procedure will be revised prior to

Unit 2 startup from its Second Refuel Outage.

WEA NE

E

INMANA EME

PP

T

F

PE

T N

The AIT report addresses

three weaknesses

in management

support of Operations.

The first

is acceptance

of delays in operation of offsite power supply breakers inherent with the use of

, a traveling operator.

In order to minimize this delay, plant operators will be trained to identify

"targets" of tripped devices in the Scriba switchyard, and to communicate this information to

Power Control.

Depending

on the cause for the tripped condition, Power Control will then

remotely operate switchyard equipment to re-energize lines. This training willbe conducted by

December 1992.

The second

weakness

concerned the absence

of a backup air supply during the refue/ing

outage, with air pressure being used in reactor vessel and main steam line'seals.

These seals

have multiple methods of sealing: mechanical as well as an inflatable seal.

Thus, no backup

air supply is needed.

However, Niagara Mohawk had planned to and willassess

the need for

a backup air supply for the Third Refuel Outage for normal maintenance

reasons.

The third weakness,was

acceptance

of cumbersome,

generic

procedures

which require

operators to use, concurrently, several procedures

during a loss of offsite power.

Niagara

Mohawk will be writing new procedures for "Station Blackout." Atthat time, we will review

operating

procedures

to determine if improvements

can

be made.

This will be done by

December 1992.

Due to inadequate

design 'of the Service Water cooling pressure

detection logic, two new

scenarios. have44M-identified that would have the Division III Emergency Diesel Generator

running for a tetjraurveillance, or as a result of a iow reactor water "level two" initiation, with

either situati~'CSSowed

by a sequential

loss of offsite power.

The cooling water to the

Division IIIDiesel Generator would isolate in either scenario.

This would render the Division III

Diesel Generator unavailable for accident mitigation, due to high temperature damage; without

operator action to return service water cooling.

To correct this, a modification will be imp'lemented during the Second

Refuel Outage that

addresses

the scenarios

identified above to prevent the loss of Division III Diesel Generator

during a sequential

loss of offsite power.

This modification will install a time delay for the

service water cooling supply valves to close the valves after receipt of a low pressure signal

on the service water supply header.

This will provide sufficient time for the service water

system to re-establish proper pressure; after power is restored, following loss of divisional or

~

.

Mr. Marvin W. Hodges

May 13, 1992

offsite power. The present time delay, which permitted closing Service Water valves after one

r'ninute of diesel operation, will be disconnected.

Additionally, administrative controls have been established in N2-OP-100B, "High Pressure Core

Spray Diesel Generator," such that during periods when Division I or II Diesel Generators

are

out of service, Division III switchgear will be aligned to an offsite power source protected by

the operable Division I or Division II Diesel Generator.

Niagara Mohawk's assessment,

the significance of design deficiencies identified, and corrective

actions will be reported in a supplement to LER 50-410/92-06.

The expected submittal date

is June 15, 1992.

NTR L

WR

PLIE AND P-

Engineering's evaluation showed that the loss of Control Room annunciation was consistent

with the design.

Presently, ten power supplies are provided to supply the annunciator load for

the NSSS panel.

A minimum of five power supplies are required to,carry the full load (two

125/24/12/VDC power supplies, two 125VDC power supplies, and one 12VDC power supply).

The remaining five provide 100% backup.

However, the majority of the 125VDC power

supplies are fed from UPS-1B. Therefore, a loss of UPS-1B power feed would cause the loss

of all NSSS Plant Monitoring System computer inputs.

All of the 12VDC and 24VDC power

supplies are fed from UPS-1A so loss of this UPS power feed would totally disable the NSSS

annunciator system.

Plant changes are being made which include a rearrangement of the annunciator power supplies

within the annunciator cabinets to preclude loss of all annunciation upon loss of one UPS. This

is to be done in two steps: first, a redistribution of the load in the NSSS panel; and second, an

upgrade

and/or redistribution of the load in the BOP annunciator

panel.

Engineering

has

completed the design for rearrangement

of the NSSS annunciator power supplies,

and field

installation will be completed during the Second

Refuel Outage.

Upgrading the annunciator

power supplies or redistributing the loads in the BOP annunciator panel willbe done during the

Third Refuel Outage.

UPS-1A was out of service on March 23, 1992 due to the UPS being on its maintenance power

supply. Corrective maintenance determined that one of the six sets of internal batteries in the

UPS were degraded which prevented the Unit from being returned to normal service.

The

design life of t~hatteries is 18 months (recently increased from 12 months), but they only

lasted about 7~s in service.

This premature failure is being evaluated at an independent

laboratory.

SubCefaent to a design modification made

in 1991, the batteries

were only

required for startup of the Unit. A design change to eliminate dependence

on the batteries has

been completed and willbe installed in the Second Refuel Outage.

Increased

UPS reliability is

possible through the implementation of this design change.

NMP2 had performed a shutdown safety review of the Second Refueling Outage prior to its

start.

This review was performed following the NUMARC guidelines.

The goal was to

maintain, throughout the outage, at least three sources of power available to the station. On

March 23, 1992 these three sources were the two offsite 115 KV lines, designated

line No.

~

~

Jg

1

Page 6

Mr. Marvin W. Hodges

May 13, 1992

oivision

II Emergency

D'esel Generator.

Th'dequate

defense-in-depth

for the event th t o

d.

After the March 23,

1992

event,

the

Independent

Safety

Engineering

Group's, Safety

Assessment

Report concluded that at no time during the March 23, 1992 loss of offsite power

event was there any danger to the fuel, the plant, or to the health and safety of the public

because

of decay heat loads.

In conclusion, Niagara Mohawk has assessed

the safety aspects associated with the March 23,

1992 ALERTevent, and has taken or willtake the necessary corrective actions to minimize the

potential for loss of all Control Room annunciators and to address other identified deficiencies.

Very truly yours,

.~a~

Exec. Vice President - Nuclear

BRS/JTP/Imc

(A:84888.0oc)

xc:

CSfr~>T:"..T.;Martin",Regional "Administrator"Region~le~

Mr. J, E. Beall, Team Leader, Division of Reactor Safety

Mr. W. L. Schmidt, Senior Resident Inspector

Mr. R. A. Capra, Director, NRR

Mr. J. E. Menning, Project Manager, NRR

IV!r. L. E. Nicholson, Section Chief, Reactor Projects, Branch No. 1B

Records Management

~: