Forwards Insp Repts 50-220/89-05 & 50-410/89-05 on 890404-0510 & Notice of Violation
ML17056A035
Person / Time
Site: Nine Mile Point  Constellation icon.png
Issue date: 06/06/1989
From: Wenzinger E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Burkhardt L
NIAGARA MOHAWK POWER CORP.
Shared Package
ML17056A036 List:
References
NUDOCS 8906140306
Download: ML17056A035 (8)


See also: IR 05000220/1989005

Text

ACCEMRATED

DISCI'RIBUTION

DEMONSTRXTlON

SYSTEM

REGULATORY INFORMATION DISTRIBUTION SYSTEM (RlDS)

ACCESSION NBR:8906140306

'DOC.DATE: 89/06/06

NOTARIZED:

NO

DOCKET

N

FACIL:50-220 Nip'e Mile Point Nuclear Station,

Unit 1, Niagara

Powe

05000220

50-410 Nine Mile Point Nuclear Station,

Unit 2, Niagara

Moha

05000410

AUTH.NAME

AUTHOR AFFILIATION

ENZINGER,E.C.

Region

1, Ofc of the Director

RECZP.NAME

RECIPIENT AFFILIATION

BURKHARDT,L.

Niagara

Mohawk Power Corp.

SUBJECT:

Forwards

Znsp Repts

50-220/89-05

& 50-410/89-05

on 890512

& notice of violation.

DISTRIBUTION CODE:

ZE01D

COPIES

RECEIVED:LTR

(

ENCL

(

SIZE:

TITLE: General

(50 Dkt)-Insp Rept/Notice of Violation Response

NOTES:

ZNTERNAL:

EXTERNAL:

RECIPIENT

iD CODE/NAME

PD1-1

PD

BENEDiCT,R

ACRS

A"OD/DEZIB

DEDRO

NRR/DEST DIR

NRR/DOEA DIR 11

NRR/DREP/RPB

10

NUDOCS-ABSTRACT

OGC/HDSl

RGN1

FILE

01

LPDR

NSIC

COPiES

LTTR ENCL

1

1

1

2

2

1

'

1

1

1

1

1

2

2

1

1

1

1

1

1

1

1

RECIPIENT

ID CODE/NAME

SLOSSON,M

AEOD

AEOD/TPAD

NRR SHANKMAN,S

NRR/DLPQ/PQEB

NRR/DREP/EPB

10

NRR/PMAS/ILRB12

N,J

G FiLE

02

NRC

PDR

COPIES'TTR

ENCL

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

NOTE K) ALL "RZKS"

RECIPIENIS'ZZASE

HELP US 'ZO REDUCE HASTE!

CONTACT %HE DOCXMWZ CONTI'ESK,

RXN Pl-37

(EXT. 20079)

IO ELXK2QXR KX3R NAME FKH DISTRIBUTXCN

LI8TB FOR IXCIIMENXS KRJ DCH~T NEEDI

TOTAL NUMB"R OF COPIES

R"QUiR"D: LTTR

25

ENCL

25

0

0

Docket No. 50-220

Docket No. 50-410

66 JUh

1889

Niagara

Mohawk Power Corporation

ATTN:

Mr. Lawrence Burkhardt, III

Executive Vice President - Nuclear

301 Plainfield Road

Syr acuse,

New Yor k

13212

Gentlemen:

Subject:

Inspection

Report

No. 50-220/89-05

and 50-410/89-05

This letter transmits

the results of the routine inspection

conducted

by

Messrs.

W. Cook,

R. Laura,

R.

Temps

and others of this office on 4/4/89 through

5/12/89 at Nine Mile Point Units

1 and 2, Scriba,

New York.

A summary of the

findings was presented

to Mr.

R. Abbott and other members of your staff at the

conclusion of the inspection.

Two violations were identified during this period concerning Unit 2,

and

a

Notice of Violation (Appendix A) is attached.

One violation regarding

the

minimum number of operable

Main Steam

Line Radiation Monitors was caused

by

errors

made

by operators

during the process

of recording

and reviewing plant

data.

The other violation was the result of removing the High Pressure

Core

Spray

system

keep fill pumps

from service without performing

a safety evalua-

tion.

These violations

have

been categorized

by severity level according to

10 CFR Part 2, Appendix

C (Enforcement Policy).

You are required to respond to

these violations and in preparing your response

you should follow the instruc-

tions in Appendix A.

The response

required

by this letter is not subject to the clearance

procedures

of the Office of Management

and Budget

as required

by the Paperwork Reduction

Act of 1980,

PL 96-511.

We appreciate

your cooperation.

Sincerely,

Regig] ~

Edward

C. Wenzinger,

Chief

Projects

Branch

No.

2

Division of Reactor Projects

8906i40306

890606

PDR

ADOCK 05000220

8

PNU

OFFICIAL RECORD

COPY

IR NMP1-2 89-05 - 0001.0.0

05/30/89

Niagara

Mohawk Power Corporation

qs cut< %88

Enclosures

1.

Appendix A, Notice of Violation

2.

NRC Region I, Combined Inspection

Report

No. 50-220/89-05

and 50-,410/89-05

. cc w/encls:

Connor

& Wetterhahn

Gary

D. Wilson, Senior Attorney

C.

Mangan,

Senior Vice President

C. Terry, Vice President

Nuclear Engineering

and Licensing

J. Willis, General

Superintendent

K. Dahlberg,

Station Superintendent,

Unit

1

R. Abbott, Station Superintendent,

Unit 2

R. Randall, Unit

1 Superintendent

of Operations

R. Smith, Unit 2 Superintendent

of Operations

J.

Perry,

Vice President 'equality Assurance

D. Palmer, Acting Manager,

equality Assurance

C.

Beckham,

Manager Nuclear equality Assurance

Operations

W. Hansen,

Manager

Corporate (}uality Assurance

Troy B. Conner, Jr.,

Esquire

Gary

D. Wilson, Senior Attorney

John

W. Keib, Esquire

Director,

Power Division

Department of Public Service,

State of New York

James

F. Warden,

New York Consumer Protection

Branch

New York State,

Department of Law

Public Document

Room (PDR)

Local Public Document

Room (LPDR)

Nuclear Safety Information Center

(NSIC)

NRC Resident

Inspector

State of New York

bcc w/encls:

Region'

Docket

Room (with concurrences)

Management Assistant,

DRMA (w/o encls)

S. Collins,

DRP

J.

Johnson,

DRP

M. Conner,

DRP

M. Hiller, SLO

.

K. Abraham,

PAO

R. Bores,

DRSS

J.

Dyer,

EDO

M. Slosson,

NRR

P. Koltay, SRI - IP-3

W. Schmidt,

SRI - JAF

OFFICIAL RECORD

COPY

IR NMP1-2 89-05 - 0002.0.0

06/06/89

0

Niagara

Mohawk Power Corporation

(I,,

06 JUN 18Ih

RIQp

W

ok/mjd

47/ i/89

I:

P

Johnson

/89

OFFICIAL RECORD

COPY

RI

P

E

nger

( /$ /89

IR NMPI-2 89-05 - 0003.0.0

05/30/89

e