ML17055E006
| ML17055E006 | |
| Person / Time | |
|---|---|
| Site: | Nine Mile Point |
| Issue date: | 06/27/1988 |
| From: | Anderson C, Cheung L NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | |
| Shared Package | |
| ML17055E004 | List: |
| References | |
| 50-410-88-08, 50-410-88-8, IEB-79-01, IEB-79-1, IEIN-86-002, IEIN-86-003, IEIN-86-053, IEIN-86-071, IEIN-86-104, IEIN-86-2, IEIN-86-3, IEIN-86-53, IEIN-86-71, IEIN-87-008, IEIN-87-052, IEIN-87-52, IEIN-87-8, NUDOCS 8807200150 | |
| Download: ML17055E006 (42) | |
See also: IR 05000410/1988008
Text
U. S.
-NUCLEAR REGULATORY COMMISSION
REGION I
Report
No.
50-410/88-08
Docket No.
50-410
License
No.
Licensee:
Nia ara
Mohawk Power
Cor oration
301 Plainfield Road
S racuse
13212
Facility Name:
Nine Mile Point Nuclear Station
Unit 2
Inspection At:
S racuse
Inspection
Conducted:
A ril 18-22
1988
da
e
S. Alexander,
EQ Test Engineer,
NRC-NRR/DRIS-VIB
E. Claiborne,
Senior Engineer,
Sandia National
Lab
M.
R. Carpenter,
Senior Engineer,
Idaho National Engineering
Lab
Q. Decker,
Senior
Engineer,
Idaho National Engineering
Lab
.Inspector:
Leonard
Cheung,
Senior
a tor
ngineer
Other participants
and contributors to this report include:
Approved by:
C. J.
nderson,
Chief, Plant
Systems
Section,
EB/DRS
date
Ins ection Summar:
Ins ection of A ril 18-22
1988
Ins ection
Re ort
>>/
Areas Ins ected:
Special,
announced
inspection to review the licensee's
implementation of a program for establishing
and maintaining the qualification
of electrical
equipment within the
scope of 10 -CFR 50.49.
Results:
Based
on the review covered
by this inspection,
the inspectors
determined that the licensee
has
implemented
a program to meet the requirements
of 10 CFR 50.49 except for certain deficiencies listed below:
8807200150
380706
ADOCK 05000410
a)
The qualification of the
Raychem cable splices associated
with three
Rosemount transmitters
in the reactor building was not established
at the
time of the inspection
in tha't the splices did not have the required
seal
length.
This is
a violation of 10 CFR 50.49 paragraph'(f)
(50-410/88-08-01,
report paragraph
13. 1).
b)
The licensee's
activities in response
concerning potential
problems
in Raychem splice installation
was incomplete
in that
NMPC did not specifically select
Raychem splice
samples for verifi-
cation after receipt of Information Notice 86-53.
They relied
on
SWEC's
gC inspection during construction.
The NRC's walkdown samples
indicated
that deficiencies
existed in the
Raychem splice installation.
Following
.
the inspection,
NMPC conducted
a
100'< walkdown
on
Eg Raychem splices
and
identified several
deficiencies.
These deficiencies
were evaluated
and
documented
by the licensee.
This is an unresolved
item (50-410/88-08-03,
report paragraph
15.0).
c)
Three of the six Limitorque operators
(outside the primary containment)
inspected
by
NRC contained
unremoved plastic
caps
(used for shipping)
on
the grease relief valves.
The inspectors
were concerned that
a similar
situation might exist for the Limitorque operators
inside the drywell.
Following the inspection,
the licensee called the inspector
on
May 12,
1988, stating that they had found
6 Limitorque operators
inside the
drywell that contained
unremoved plastic
caps
on the relief valves.
These
plastic caps
were subsequently
removed
and the activities documented
in
the
Eg files.
An engineering
evaluation
was performed for the qualifica-
tion of the affected Limitorque operators.
This is an unresolved
item
(50-410/88-08-02,
report paragraph
13.2).
DETAILS
1.0
Persons
Contacted
Nia ara
Mohawk Power Cor oration
(NMPC)
A.
G
~
- M
G.
J.
- J
L.
R.
"M.
J.
L.
V.
AJ
K.
- D
- A.
Athelii, Senior
EQ Engineer
Dean, Assistant Unit Superintendent,
Eldrige,
EQ Engineer
Eron, Assistant
Engineer,
Electrical Maintenance
Geier,
Lead Material Engineer
Gresock,
Manager,
Nuclear Engineering
Jirousek,
EQ Program
Manager
Kroehler,
Manager, Quality and Reliability Engineering
Lagoe, Site
I&C Supervisor
Main, Training
Hosier,
Lead Engineer,
Safety Analysis
Pace,
Manager,
Material Engineering
Plank, Training
Price,
EQ Engineer
Roy,
I&C Training
Savoca,
Associate
Engineer,
Mechanical
Maintenance
Sweet, Electrical
Maintenance
Superintendent
Weaver,
Lead Material Engineer
Zallnick, Manager,
Nuclear Licensing
1.2
Stone
& Webster
En ineerin
Cor oration
(SWEC)
A.
D.
L.
P.
C.
Dellagreca,
Senior
EQ Engineer
Hobman,
EQ Engineer
Illy, EQ Engineer
Si lverberg,
EQ Engineer
Zehrer,
EQ Engineer
1.3
Other Contractors
J.
R.
J.
J
~
N.
R.
C.
E.
W.
Anderson,
Engineering
Program Manager,, Wyle Lab
Demark,
EQ Consultant,
Gasser
Assoc.
Gleason,
Director, Nuclear Engineering,
Wyle Lab
Konu,
EQ Consultant,
Gasser
Assoc.
Luria, Manager, Quality Engineering,
McClelland, Senior Program Manager,
Nieh, Design Engineer,
Schum,
Senior
EQ Engineer,
Wyle Lab
Shaffer,
EQ Engineer,
PATSCO
Lon
Island Li htin
Com
an
LILCO
M.
J.
Gannattasio,
EQ Section
Head
Kaczor, Senior
EQ Engineer
1.5
United States, Nuclear
Re viator
Commission
C. Anderson,
Chief, Plant
System Section,
EB,
W. Cook, Senior Resident
Inspector
"Denotes
those
not present at the exit meeting at the
NMPC Corporate
Office on April 22,
1988.
2.0
~Pur oae
The purpose of this inspection
was:
( 1) to review the licensee's
implementation of a program to meet the requirements
of 10 CFR 50.49 for
the Nine Mile Point Nuclear Station, Unit 2 (NMP2); (2) to evaluate
the
licensee's
actions
on the Limitorque valve operator
jumper wires
'esulting
from IE Information Notice 86-03 "Potential Deficiencies 'in
Environmental gualification of Limitorque Motor Valve Operator Miring",
and, (3) to evaluate
the licensee's
actions
on the installation of
Raychem cable splices resulting
from IE Information Notice 86-53
"Improper Installation of Heat Shrinkable Tubing."
3.0
~Back round
In February
1980,
the
NRC asked certain near-term operating
license
(OL)
applicants
to review and evaluate
the environmental
quali,fication
documentation
for each
item of safety-related
electrical
equipment
and to
identify the degree
to which their qualification programs
were in
compliance with the staff positions discussed
in NUREG-0588.
A final rule
on environmental qualification of electrical
equipment
important to safety for nuclear
power plants
became effective
on February
22,
1983.
This rule,
10 CFR 50.49, specifies
the requirements
to be met
for demonstrating
the environmental qualification of electrical
equipment
important to safety located in a harsh environment.
In conformance with
10 CFR 50.49, electrical
equipment. for NMP2 may be qualified according
to the criteria specified in Category II of NUREG-0588.
To document
the degree
to which the environmental qualification program
complies with the
NRC environmental qualification requirements
and criteria,
the licensee
provided equipment qualification information by letters
dated January
3, April 22, October
17,
and
November
20,
1985, to supplement
the information in
FSAR Section
3. 11.
Additional information was provided
in letters dated
February 4, April 9, August 18,
and August 21,
1986.
The
NRC staff reviewed the above information for, the adequacy
of the
NMP2 environmental qualification program for electrical
equipment important
to safety
as defined in
In addition, the
NRC staff
conducted
an audit of the licensee's
qualification documentation
and the
installed electrical
equipment
on December
16-19,
1985.
Based
on the
results of the review and audit, the
NRC staff concl'uded that the
licensee
had demonstrated
conformance with the requirements
for
environmental qualification as detailed
and relevant
parts of GDC 1 and 4,
and Sections II, XI, and XVII of Appendix
B to
and with the criteria in NUREG-0588.
By lette'r's dated August
18
and August 21,
1986,
the licensee
informed the staff that all equipment
within the
scope of 10 CFR 50.49
was fully qualified..
4.0
Nine Mile Point
2
E
Pro
ram
The
NRC inspectors
examined
the implementation
and adequacy
of the
licensee's
EQ program for establishing
and maintaining the qualification
of electrical
equipment in compliance with the requirements
of 10 CFR 50.49.
The current Nine Mile 2
EQ program
was developed
by Stone
8
Webster
in accordance
with SWEC procedure
J.O.
No. 15600.09,
"Envir'on-
mental Qualification Document
(EQD)," dated April 9,
1987.
This program
is being transfered
from SWEC to
NMPC.
NMPC has developed
procedure
NEL-052 entitled "Nine Mile Point
2
EQ Program" dated
March 25,
1988 to
supplement
the Stone
5 Webster
EQD.
The Stone
5 Webster
EQD describes
how the
NMP2
EQ program was developed.
Section
2 identifies the plant zones
subject to harsh
environment.
Section
3 defines
the "functional performance
requirements".
This section
also identifies the systems
required for accident mitigation and the
systems
whose
components
require
EQ.
Paragraph
3.3 defines
the post
accident operability period requirements.
Table 3-2 identifies the
systems
subject to various type of accidents,
including
MSLB.
Section
4 establishes
the methodology of equipment qualification,
including qualification basis,
aging, margins, radiation
dose rate
and
synergistic effect.
Section
5 establishes
the requirements
of qualifica-
tion documents
including the environmental qualification list (EQL) and
System
Component Evaluation
Work (SCEW) sheets.
NMPC procedure
NEL-052 supplements
the
EQD to provide guidance
and
control of the
NMP2
EQ program.
Section
6 of this procedure
establishes
the
EQ requirements
as follows:
6.1
6.2
6.3
6.4
6.5
6.6'.7
6.8
6.9
6.10-
For
the
in the
EQ Design Criteria, Preparation
and
Use
Review of Plant Modifications
Determination of
EQ Procurement
Requirements
Review/acceptance
of
EQ Reports/Documentation
Qualification Alternatives
Installation Requirements
Maintenance
Requirements
Equipment Qualification File Requirements
Reevaluation
of Equipment Qualification Criteria
Non-Qualified Equipment.
i
documentation,
the
EQ program manager is responsible
to maintain
file in an auditable
form.
The following documents
are included
EQ file:
i
EQ Master List
EQ Environmental
Design Criteria
(EQEDC)
Equi pment Quali fi cat ion Document
(EQD)
System
Component Evaluation Worksheets
(SCEW)
Qualification Reports,
Suppliers
Document Data
Form (SDDF) file,
Vendor Qualification Reports,
Test Laboratory Reports
Post Accident Operating
Period
(PAOP) data
sheets
Mechanical
Equipment Qualification
(MEQ) Reports
Environmental
Calculations
Equipment Qualification Required Maintenance
(EQRM) and/or
Maintenance
Program
Data Sheet
(EQMPDS)
Vendor Technical
Information
EQ Correspondence
Materials/Parts
Evaluations
Equipment Qualification Studies/Analyses
EQ Field Verification Data
Equipment Qualification Review Checklist
Equipment Qualification Job Books.
Of these
documents,
items
a through i are controlled documents.
These
controlled documents
are subject to change with plant modification or
reevaluation
of
EQ parameters.
The inspectors
reviewed these
procedures
and.did not identify any
deficiencies.
5.0
Environmental
ualification List
E
L
The
NMP2 EQL is
a subset of the
NMP2 Master Equipment List (MEL) database
which is
a functional
module of NMPC's comprehensive
computerized
plant
information management
system for
NMP2.
The
MEL includes all plant
equipment,
including safety-related
and non-safety-related
equipment.
Its
many data fields include coding for numerous
equipment attributes,
some of
which are associated
with
There are three principal sets of fields on which the
MEL data
base is
indexed to generate
the
EQL.
These
are: (1) the Environmental
Zone
( location code);
(2) the Environment (harsh or mild); and,
(3) the
operability
Code
(OP Code).
NMP2
OP Codes
A, B, and
C correspond
to the
EQ functional operability categories
in Regulatory
Guide 1.89 or
categories
2.a,
2.b,
and 2.c, of Appendix
E of NUREG-0588.
Each
equipment
item with environment
code "harsh" is assigned
OP Codes
associated
with each
DBE that exposes it to
a harsh environment in which
it must function.
The
EQL consists of all
OP Code A,
B or
C equipment in a harsh
environment.
This breakdown
covers all equipment within the
scope of
10 CFR 50 '9 in that safety-related
equipment
under
and
post accident monitoring equipment
under
would be
OP
Code
A for harsh
environments
in which it must function.
Non-safety-related
equipment,
the failure of which would be detrimental
to safety,
under
would be
OP
Code
B for DBE harsh
environments
to which
it is exposed.
Non-safety
equipment
in
a harsh environment;
not supplied
with lE power or automatically i solable
from 1E power,
the failure of
which is not detrimental
to safety (including misleading the operator) is
listed in the
MEL with OP Code
C.
Equipment outside
the
scope of 10 CFR 50.49 due to its being in a mild environment is listed as,OP
Code
0 also
requiring qualification only for extremes of its normal service
conditions.
The assignment
of OP Codes
and the required operability times for plant
equipment to determine
EQL inclusion
and
EQ requirements
were based
on:
(1) the Final Safety Analysis Report; (2) Safety Evaluation Reports
(SERs)
and Supplemental
SERs;
(3) the
NMP2 NUREG-0588 submittal; (4) technical
specifications;
(5) emergency
operating
procedures
(EOPs);
and, (6) plant
equipment verification walkdowns.
The walkdowns
had not been
completed
(NMPC estimated 80'.'omplete)
at the time of this inspection
due to equip-
ment accessibility
problems
and
some
equipment with missing
nameplates
~
NMPC was scheduled
to complete the walkdowns
and verify all equipment
not
positively identified by nameplate
during the outage
scheduled
to start
on
May 6,
1988.
EQ engineering
work for NMPC on
NMP2 including development
and
maintenance
of the
MEL (including the
EQL) is done
under the supervision
of the
EQ Coordinator.
The
EQ Coordinator supervises
the efforts of
EQ engineering
personnel
and
NMPC's
EQ contractors/consultants.
Procedure
NEL-052 "NMP2 Equipment Qualification Program" Revision 0,
dated
March 1988,
governs the development
and maintenance
of the
EQL.
The development
and maintenance
of the
MEL are detailed in procedures
SSG-112
"Component Identification" and
SSG-104
"NMP2 Master Equipment
List," Revision 0, dated
Oecember
8,
1987.
Review of these
procedures
indicated that control of the
EQL is adequate.
Records pertaining to
deletion of
EQL items were also reviewed with no unjustified deletions
noted.
As a further validation check
on NMP2's
EQL, the Emergency Operating
Procedures
(EOPs)
were reviewed with NMP2 operations
personnel.
The
inspectors
selected
27 items of equipment required to be used with the
EOPs.
Of these
27 items,
18 were listed in the
EQL as qualified under
OP
Code
A or B, eight were non-safety-related
and
powered
from non-Class
lE
power supplies,
and
one was listed as safety-related,
but,OP
Code
C,
i.e., not required to function in the harsh environment.
The inspector
determined this classification to be acceptable.
6.0
NRC Information Notice
INs
and Bulletins 'EB
NRC INs and bulletins are handled administratively
as part of a program
called the
Commitment Tracking System.
The program is
a module of NMPC's
comprehensive
computerized plant information management
system
(which
includes the
EQL) and provides for distribution, tracking,
and assignment
of responsibility for correspondence
requiring action and/or response
Specific instructions for handling of NRC correspondence
including INs,
IEBs, inspection reports, etc.,
are contained
in
NMPC Procedure
NT-30,
"Control of Licensing Correspondence."
The inspectors
reviewed Procedure
NT-30, Revision
3 dated July 1,
1987.
It specified that all such
incoming material is routed according to
a
standard distribution list.
The inspector verified that the appropriate
EQ personnel
are
on the list.
The
who was included
on the distribution list had established
a special file several
years
ago
of EQ-related
NRC INs and Bulletins.
The file contained all
NRC INs and
Bulletins considered
to be EQ-related
from Bulletin 79-01 through
and reflected that they had
been dispositioned for NMP1 and
reviewed for NMP2 applicability.
They had
been dispositioned
for
NMP2
with the exception of a few that were under review.
Most of this file
had been transfered
to the
Commitment Tracking System.
The inspectors
did not identify any EQ-related
NRC initiatives for which
disposition
was not adequate
and timely with the exception of IN 86-53
discussed
in Section
15.0.
The inspectors
reviewed in detail. the status of actions
on selected
EQ-related
INs and bulletins
and examples
are discussed
below:
IN 86-02 concerns
corrosion of magnesium rotors in Reliance
motors for Limitorque valve actuators.
NMPC had determined that
testing of Limitorque actuators
with magnesium
motor rotors for GE
at Wyle Laboratories,
as reported in GE
EQ Report
NEOC-31049,
was
adequate
to qualify them for NMP2 applications.
All of the
18 such
MOVs at
NMP2 have
a required post,-accident operability time of one
day and are required to operate
only once during the accident/post-
accident
phase.
IN 86-71 deals with problems in Limitorque MOVs associated
with
energized
switch compartment
space
heaters.
NMPC's response
to this
issue
was to add this concern to the Limitorque walkdown checklist
and inspect all
EQL Limitorques for heaters
and wire burn damage.
Review of records
and discussion with NMPC personnel
indicated that
all heater
elements
found were de-energized
and removed,
and all
wiring which showed
any evidence of burn damage 'was replaced.
IN 86-104 concerns
Nylon insulated
crimp type wire joints in dual
voltage
AC Limitorque motors.
NMP2 has
no dual voltage
IN 87-08 alerted
licensees
to degraded
insulation
on Peerless
motor leads in Limitorque actuators.
A comprehensive
audit
performed
by
NMPC in cooperation with the Velan Valve Company,
NMP2's supplier of DC Limitorque motors, disclosed that two MOVs at
NMP2 had the subject
Nomex-Kapton insulated
motor leads.
Review of
maintenance
records
confirmed that both of these
MOVs had qualified
Raychem sleeving applied to each
motor
as
recommended
by
IN 87-52 concerns
insulation
breakdown of silicone rubber insulated
single-conductor
cables
during high-potential testing.
NMPC's
disposition of this issue
was documented
in
a Peter
Si lverberg
memo
to the
IE Notice file dated April 8,
1988.
,NMPC had reviewed
specifications
and procurement
documentation
and determined that
no
silicone rubber cable
had
been
ordered for NMP2 and that the
manufacturer
noted in the IN, American Insulated Wire Corporation,
was not
a supplier to NMP2.
NMPC had identified silicone rubber
insulated wire only as short lead wires in qualified components
such
as
ASCO solenoid operated
valves,
Reliance
fan and
MOV motors
and in
the Comsip hydrogen analyzers.
concerning potential deficiencies
in the
EQ of Limitorque
motor wiring, was reviewed
and discussed
in Section'4.0.
The licensee's
QA audit group conducted
an audit of the
NMP2
EQ program
(Audit No. SY-RG-IN-86-021), at the Stone
& Webster Corporate'ffice
in
Cherry Hill, New Jersey
and
NMP2 plant site
on December
3-10,
1986 'he
audit team consisted
of 3 auditors
and
a technical
specialist.
The
activities audited included:
1.
Stone
& Webster Engineering
processing
of vendor
EQ reports,
SILs, Nonconformance
Reports
and
NRC IE bulletins and INs.
2.
Stone
& Webster Engineering effort related to equipment life
extensions
based
on
EQ requirements.
3.
Stone
& Webster Engineering extraction of maintenance
and
surveillance
requirements
from
EQ documentation.
10
4.
NMPC incorporation of maintenance
and surveillance
requirements
into
the appropriate
procedures.
5.
NMPC performance of EQ related
maintenance
and sur'veillance.
The audit was performed in accordance
18. 10
"Quality Assurance
Department Audits" dated July 3,
1986.
The following
audit checklists
were
used
by the auditors during the audit:
1.
SY-RG-IN-8602-1
Identification and Performance
of Maintenance
and
Surveillance
Required to Maintain Equipment Qualification
2.
SY-RG-IN-86021-2 - Equipment Life Extension
Program
3
~
SY-RG-IN-86021-3 - Review of Modifications, Nonconformance
Reports,
Design
Changes
for Impact on Equipment Qualification
The results of this audit w'ere documented
in audit report SY-RG-IN-86021
dated January
26,
1987.
The report indicates that four findings were
identified.
Three of these findings required revisions of maintenance
procedures
and were resolved before June
18,
1987.
The fourth one
involved numerous
design-changes
and nonconformance
documents
which were
not reviewed
by the
EQ group or were reviewed incorrectly.
The resolution
of this deficiency was verified to be complete
by the
NMPC auditors
on
February
19,
1987.
The inspector
reviewed the audit documents
provided by the licensee.
No
unacceptable
conditions were identified.
8.0
E
Maintenance
Pro
ram
EQ maintenance
at
NMP2 is generally covered
under the
same procedures
described
in Section 5.0 for the discussion
of the
EQL.
Requirements
from the
EQ files relating to installation,
maintenance
and replacement
of qualification equipment
to establish
and maintain qualification status
are transmitted to the
NMP2 site via
EQRMs.
The site
EQ coordinator
and
the Electrical
and
ICC maintenance
engineers
translate
these
maintenance
requirements
into detailed installation,
maintenance
and surveillance
instructions.
They also
schedule
the maintenance
and surveillance acti-
vities to assure
that qualified lives are not exceeded.
They are then
incorporated
in the
NMP2's planned
maintenance
management
system.
NMP2's
computerized
system covers all aspects
of plant maintenance
including
EQ.
In addition to the
EQ program procedures
mentioned
above that include
maintenance
requirements,
the inspector
reviewed the following site
maintenance
procedures
that pertain in particular- to
EQ:
.
NMP2 Procedure
S-IDP-X-GEN-001, "Instruction for Writing, reviewing,
and Revising Instrumentatioa
and Control Procedures"
Revision 4,
dated
March 18,
1988.
NMNPS Maintenance
instruction S-MI-GEN-002, "Maintenance Instruction
for writing Procedures"
Revision 2, dated April, 1988
'dministrative
AP-8. 1, "Preventive Maintenance"
Revision
3 dated
July 27,
1987
NMPNS Electrical Maintenance
Procedure
S-ENP-GEN-003,
"Splice
Installation Procedure",
Revision
1, dated
March 11,
1988.
NMPNS Procedure
S-MI-GEN-004, "Maintenance Instruction for Review
and Implementation of Technical
Requirements
in Maintenance
Procedures"
~
NMNPS Procedure
AP-5.2, "Unit 2 Procedure for Repair," Revision 9,
dated
December 8,
1987
At the plant site,
the inspectors
examined
the computerized
maintenance
management
system.
Maintenance
supervisory
and planning personnel
demon-
strated
how
EQ related
maintenance
and replacement
requirements
from the
EQ files are incorporated
into maintenance
instructions
and schedules.
The inspectors
reviewed selected
samples
of surveillance
and maintenance
instructions for qualified components,
and the records of completed
work
orders.
The inspectors
also interviewed
NMP2 maintenance
superv'isors,
planners
and technicians.
The inspectors
concluded that
NMPC has satis-
factorily implemented their program at
NMP2 for preservation
of the
qualified status of
EQ equipment.
9.
E
Trainin
Pro
ram
During the course of this inspection,
the
EQ training program for
personnel
at
NMP2 was reviewed.
The engineering
department training
procedure
"NEL Procedures
Mod-80-EQ", dated
March 1987 delineates
the
licensee's
training program to provide, maintain
and upgrade
the training
and qualification status of the personnel
performing safety-related
design, modification, review,
and approval,
including
EQ related
activities.
The
EQ training program provides
personnel
training in the
following EQ areas:
NEL-028, Equipment Qualification (EQ Rule,
NEL2-028,
Equipment Qualification Program (Unit 2)
NEL2-028.A,, EQ Design Criteria
NEL2-028.B,
EQ Procurement Activities
NEL2-028.C,
EQ Qualification Alternatives
'EL2-028.D,
EQ Vendor Document
Reviews
12
NEL2-028
~ E,
EQ Installation Requirements
NEL2-028.F,
EQ Maintenance
Requirements
NEL2-028.G,
EQ Documentation
and Files
NEL2-028.H,
EQ Change
Control
In addition,
the training department
has developed .training'procedures
for the Electrical
and
IKC Departments
at the plant site.
For the
Electrical
Maintenance
Department,
procedure
EM 225 dated August 1985,
provides
the
means of ensuring
the proper training for their job acti-
vities.
Also, monthly meetings
are held with the electrical
personnel
to
discuss
any
new issues e.g.,
IE Information Notices
and
IE Bulletins,
industry notifications etc., for EQ equipment.
The electrical
department
also
has
"hands-on" training for their maintenance
personnel.
Procedure
NTP-7 dated October
1986, establishes
training requirements for the
IKC
craftsmen
at the plant site.
This procedure
provides the means of ensur-
ing the proper
and continuing training of the
IKC personnel.
There are
other training courses
to supplement this procedure,
e.g.,
Lesson
plan
IC-201.8 entitled "Equipment Qualification" dated
March 1988.
Also
Instrument Maintenance
Procedures
were incorporated
into the training of
the
I&C personnel
at
NMP2.
The instrumentation
personnel
were included in
the monthly information me'etings with the electrical
department
to keep
informed on current issues
and changes
to
EQ procedures.
The training instructor
attended
outside training courses for Raychem
Splices
and Limitorque MOV's.
From these
courses
a required training
session
was developed
and administered
to all electrical
and
IKC
personnel.
Review of the training records
and discussions
with selected
personnel
administering
the training courses
indicated that quality
control
and design
personnel
performing
EQ related activities are included
in the train.'ng sessions
along with the technicians.
Based
on the above,
the inspector determined that the licensee
has
established
and implemented
an acceptable
EQ training program.
10.
E
Procurement
Pro
ram
The procurement
program for the
NMP2 plant has
been
in'
state of
transition for the past year.
During the construction
phase
ending in
July 1987,
Stone
and Webster
handled all procurement at
NMP2.
From July
1987 through
December
1987 procurement at
NMP2 was conducted
according to
NMPC Nuclear Engineering
and Licensing Procedures.
Procedure
NEL-015.G,
"Commercial
Grade
Procurement
and Dedication" formalized the process
through which NMP2 could purchase
commercial
grade
items
and dedicate
their
use in safety-related
functions at
NMP2;
Starting January
1,
1988,
all procurement at
NMP2 was conducted
according to Niagara
Mohawk
Procedure
Number NEL-015.M, "Procurement
Requirements
Evaluation
and
Dedication Planning
Procedures
"
This procedure'rovides
instruction for
the procurement
of all safety-related
equipment including
EQ equipment at
e
13
NMP2.
This
new procedure
encompasses
NEL-015.G (Commerical
Grade)
and
expands
the
scope
to include the procurement of all safety related
and
quality-related
equipment.
Procedure
NEL-015.M applies to the procurement of items for Nine Mile
Point
1 and
2 categorized
as Safety Related,
Quality Related,
and Non-Safety
or Modification related
items.
This procedure
may also
be applied to the
procurement of services.
The emphasis
of this evaluation is placed
on
items procured for use in Environmental Qualification applications.
The implementation of NEL-015.M is accomplished
by the included
"Procurement
Requirements
Evaluation
Form."
On the first page,
the item,
is identified as safety related,
whether or not it will be procured
as
commercial
grade,
and whether the item is subject to
EQ,
If it is subject
to
EQ, it is reviewed
by a member of the
EQ group that is assigned
to the
procurement
group
and serves
as liaison between
the two groups.
This
trained person
reviews the items according to Procedure
NEL-028, "Equip-
ment Qualification," then determines
the requirements
the item must
satisfy to meet the desired
EQ Level.
These
requirements
are listed in
detail
on the procurement
evaluation
form.
In general, if the item can
be procured
from the original supplier
who is
a qualified supplier of
nuclear grade parts,
and who will certify the part is the
same
as original-
ly purchased
and tested, it will be.
If not,
an attempt will be
made to
purchase
"Nuclear Grade"
from another (preferably) qualified supplier.
If
it becomes
the case that "Commercial
Grade"
must be purchased,
a "dedica-
tion program" must be undertaken
to qualify the item for use in
a safety-
related function.
Procedure
NEL-015.M details
the steps
which must be
followed to dedicatea
commercial
grade
item,
and includes
a Critical
Characteristic
Worksheet.
This worksheet details the attributes
the item
must possess
including:
configuration description,
materials/physical
properties
and appearance,
dimensions,
markings
and identification,
mechanical
and electrical functional requirements
and whatever test infor-
mation and certification is available.
The actual
means
by which
EQ is
established (i.e., type-test,
partial test plus analysis,
etc.) is
determined
by the
EQ group.
Within the
scope of this review,
no deficiencies
or anomalies
in the
NMP2
procurement
program were identified.
11.0 Control of
E
Related Modifications
NMPC uses
SWEC Project Procedure
(PP)'94 to establish
the responsibilities
and methods to control the identification, coordination,
implementation,
and documentation
of all plant modifications that have
an impact on
environmentally qualified equipment.
This procedure is applicable to all
changes
which affect environmental,
mechanical,
and/or seismic/hydrody-
namic qualification of equipment which falls within the following areas:
14
Equipment modifications
Changes
to environmental. parameters
Changes
in the seismic
and dynamic loads
Changes
in the location of equipment
Changes
in design details which affect the structure,
materials,
and
mounting configuration or orientation of the
equipment'hanges
made to the equipment interfaces
Changes
in process
design conditions
Changes
involving safety-related
non-metallic material
Changes
in post accident operability period data.
The
EQ engineer
and the site engineering
group are responsible
,for initiating a change within the
scope of this procedure.
The lead
engineer is responsible
to ensure that the completed
check list (Reviewer
Checklist to Determine Effects of Change
on Category
1 Electrical
and
Mechanical
Equipment Qualification) is technically correct
and consistent
with licensing requirements.
He is also responsible
to provide the Equip-
ment Qualification Action Item (EQAI) forms for concurrence
as applicable;
and when requested,
provide assistance
in completing the checklist 'and
providing technical justification for NO IMPACT statements.
The assistant
to the project Engineer
(ATPE-EQ) is responsible
for
monitoring the review changes
which affect the qualification of equipment
and ensure that all open
and action items identified on the
EQAI are
logged, filed, and properly dispositioned.
In addition, the ATPE-EQ is
responsible
to ensure that the
EQ lists are reviewed
and that
a sequential-
ly numbered
log identifying and tracking the
EQAI has
been established.
The inspectors
reviewed three modification packages.
Each of these
packages
contained
the necessary
documentation
to show that the
modification program is being
implemented.
The three modification
packages
reviewed were
as follows:
~
Modification No.
PN2Y87MX133 (EQAI No, 226) - Elapsed
Time Meters
Added to Control Circuit of 2HVC*FN2A and. 2B Fans
~
Modification No.
PN2Y86MX031 (EQAI No.
233
Rev.
1) - Relocation of
Temperature
Switches
2HVR*TIS31A and
B
~
Modification No.
87MX229 (EQAI No. 246) - Relocation of Transmitters
No.
ZGTS*PDTSA and
B
'll EQ requirements
are addressed
in these modification packages,
such
as
the
EQ master list,
EQ files,
and qualification documentation.
Within the
scope of review of the plant
EQ modification activities,
no
deficiencies
were identified.
A
15
12.0 Detail
Review of
E
Files
The licensee's
EQ files were examined to verify the qualification status
of equipment within the
scope of 10 CFR 50.49.
In addition to comparing
plant service conditions with qualification test conditions
and verifying
the basis for these conditions,
the inspectors
selectively 'reviewed areas
such
as required post-accident
operating
time compared to the duration of
time the equipment
has
been demonstrated
to be qualified; similarity of
tested
equipment to that installed in the plant (insulation class,
component materials,
test configuration versus installed configuration
and documentation for both); evaluation of adequacy of test conditions,
aging calculations for qualified life and replacement
interval
determination;
effects of decrease
in insulation resistance
on equipment
performance;
adequacy
of demonstrated
equipment accuracy;
evaluation of
test anomalies;
and applicability of
EQ problems reported
in IE Bulletins
and Information Notices
and their resolutions.
The inspectors
reviewed fifteen
EQ files,
The types of equipment
covered
by these files included areas
such
as electrical
cables,
terminal blocks,
Limitorque valve operator s, limit switches,
solenoid operated
valves,
electrical
triaxial connectors,
cable splices,
and
radiation detectors.
An equipment
type is defined
as
a specific type of
electrical
equipment,
designated
by manufacturer
and model, which is
representative
of all identical
equipment in the plant area
exposed
to
the
same or less
severe
environmental
service conditions.
The following
were noted during the inspection:
12.1 Limitor ue Valve 0 erators
Job Book PP304R
EQ Job book No.
P304R is the master file containing the environmental
qualification documentation
for all
149 Limitorque MOVs'on the
master list at
NMP2.
Placement of these
MOVs include
23 in the
drywell,
5 in the main
steam tunnel,
and the remainder at various
locations
in the Reactor Building.
During the course of the file review, three
concerns
arose that were
successfully
resolved prior to the exit meeting.
They are discussed
briefly as follows:
a.
Similarit
Anal sis for the Buchanan
0222 Terminal Blocks
Some Limitorques in the drywell and
steam tunnel at
NMP2 utilize
Buchanan
0222 terminal blocks.
NEDC-31049, which documents
a
test performed
by Wyle for General Electric (GE),
was
used
as
the basis for the qualification of these
Buchanan
terminal
blocks in the
NMP2 Limitorques.
The document
does
not spe-
cifically identify the terminal blocks used in the type test
as
0
16
Buchanan
Model 0222.
During the course of the inspection,
personnel
retrieved the terminal block used in the
test, definitely identified as
a Buchanan,
then,-via matching
physical characteristics
with the Buchanan
G'-100 catalog,
identified it as either
a Model 0212 or a Model 0222.
The only
difference is that Model 0212 has
a plain marking area while
Model
0222
has
a painted marking
arear'he
inspector
had
no
further questions.
b.
Terminal Blocks
T
e Tested at 460
Y versus
E ui ment
A
lications at
575 V.
NEOC-31049 type tested
Marathon
300 and
Buchanan
0222 Terminal blocks at 460
V whereas
the
NMP2
Limitorques are operated
at 575 V.
This issue
was successfully
addressed
during the inspection
by the license presenting
evidence
showing the only increase
in failure mechanism
due to
higher voltage is tracking to ground under
100% moisture
conditions.
Both the subject terminal blocks are rated at 600
V and were
UL tested
wetted with a
1% Ammonium Chloride
Solution, which is more conductive
than water, at 600 V. .Both
of these
terminal blocks are
UL rated
PLX ¹1 (400
599.9
V)
indicating that
a material
in this class will perform
identically within the entire
range which includes
both 460
V
and
575
Y.
The inspector
concurred with this analysis
and
concluded
the
575
Y application for the Limitorque terminal
blocks at
NMP2 is acceptable.
Reliance
AC Motors Used
on Limitor ue
MOVs T
e Tested at
460
V and
Used at
NMP2 at 575 V.
The licensee
demonstrated
the
Reliance
AC motors
used at
NMP2 are the
same
as those
type
tested
in NEDC-31049 except the
number of turns in the
NMP2
primary motor windings were increased
in order to maintain the
standard volts per turn in the coil.
Since the horsepower is
the
same,
the normal operating
and locked rotor amperage
is
less for the
575
V motor and the type test results
from
NEDC-31049 for the
460
Y motor conservatively
bound the
575
V
motor application at
NMP2.
The inspector concurred with this
analysis
and considered this issue closed.
12.2 Litton Veam Connector
(Job Book ¹E061A)
The test report
used to qualify the Litton Yearn connectors
was
an
Isomedix document entitled "Test conducted
by Isom'edix Inc. for
Litton Products International," dated
February
1978.
The model
numbers tested
were CIR030-28-51
and CIR06RK-22-23.
Only one Litton
Yearn connector is used at
NMP2. It was installed
on
a bulkhead
inside the primary containment,. connecting
the cable for a
NAMCO
limit switch which sends
a signal to the control
panel
indicating ihe
position of air operated
valve 21CS"AOV157.
This position indication
is required to satisfy the requirements
of Regulatory
Guide
1
~ 97.
17
gualification deficiencies of Litton Veam connectors
had
been
identified at other plant sites
because
of low insulation resistance
issue.
The connector -at
NMP2 is for control application only.
Low
insulation resistance
is not
a serious
concern.
The licensee's
Field Verification Photo erroneously
showed the Litton
Yearn connector
as
an in-line junction box number 21CS*JB1995.
Because of this error, the licensee
has
committed to walking down the
connector during the next power outage to verify the installed con-
nectors
are the
same
as described
in the test report supplied
by
Isomedix.
13.0 Plant
Ph sical
Ins ection
The
NRC inspectors
conducted
a physical
inspection
on April 20,
1988, of
EQ components
in the Reactor Building at various elevations.
No items
were selected
in the primary containment
because
of its inaccessibility
during plant operations.
Items selected for examinations
included
Limitorque valve operators,
limit switches,
solenoids
operated
valves,
cables
and cable splices.
The inspectors
examined characteristics
such
as mounting configuration,
orientation,
connection interface,
model
and instrument type, cleanliness
and physical condition.
The. following deficiencies
were identified:
, 13. 1
Ra
chem Cable
S lices
During the plant walkdown on April 20,
1988, while in the Reactor
building, the inspectors
identified that the
Raychem cable splices
associa.ed
with the following transmitters
had seal
length less than
1 inch:
~
Flow transmitters
CSL*FT126 (GEPE21-N003)
in environmental
zone
SC175102
~
Pressure
transmitter
CSL*PT109(GEP21-N052)
in environmental
zone
SC175102
~
Level transmitter
SFC*LT32A in environmental
zone
SC328197
The qualification documents
in the
Raychem Splice
E(} file indicate
that the minimum seal
length for the
Raychem splices
in these
areas
must be
1 inch to meet <he qualification requirements.
The
inspectors
concluded -that-~he qualification of these
Raychem splices
was not established
at the time of the inspection.
. This is in
violation .of 10 CFR 50.49 paragraph (f) which requires
each
item of
electrical
equipment important to safety
be qualified
(50-410/88-08-01).
18
13.2
During the week of the inspection,
the licensee
was able to show
that the splices
in question
were qualifiable for'heir applications
in their relatively less
severe
environments.
NMPC was able to
obtain Wyle Laboratories
Nuclear Environmental Qualification (NEQ)
Report
No.
17859-02P which documents
a test
sponsored
by
Commonwealth
Edison
Company
(CECo)
and the Nuclear Utility Group
on
Environmental Qualification
(NUGEQ) to qualify numerous
configurations of Raychem splices that deviated significantly from
Raychem specifications
and those qualified by Raychem.
One set of
transmitter splice
specimens
(2-2 and 2-3) with seal
lengths of ',
inch, exhibited
no measurable
leakage current at 37
VDC under
environmental
conditions enveloping
those of NMP2.
This provided
reasonable
assurance
that the splices
found were qualifiable for
their
NMP2 applications.
Limitor ue Valve 0 erators
The inspector physically observed
the installed condition of six
Limitorque valve operators.
They are:
28WP*MOV15A, 2SWP"MOV17AEB,
2SWP*MOV18A, 2SWP*MOV21A8B.
The limit switch covers
were
removed
for close
examinations
In general
the valve operators
were clean,
in good order,
and exhibited
good maintenance
and surveillance
practices.
However,
the inspector noticed that three of the six
operators
inspected
(2SWP*MOV17B, 2SWP"MOV18A, and
2SWP"21A)
contained
unremoved plastic
caps
on the grease relief valves.
Outside the drywell, the
MOV oprators
do not require
a grease relief
at
NMP2 so these
three operators
were not
a concern.
However, inside
the drywell at
NMP2, the
MOV operators
do require
grease reliefs and
the question
arose
as to whether all their plastic
caps
had
been
removed.
NMP2 committed to conduct
an inspection during their next
outage of all Limitorque MOVs in the drywell and the
steam tunnel
and
to remove (if necessary)
all the grease relief dust covers.
On May 12,
1988,
the licensee
called the inspectors
stating that
they had completed
walkdown of all
EQ MOVs in the drywell and in the
steam tunnel during the recent
NMP2 outage.
They found
6
MOVs in
the drywell containing
unremoved plastic caps
on the grease relief
valves.
These plastic caps
were subsequently
removed
and the
activities documented
in the
EQ file.
The licensee
also stated that
engineering
evaluation
was performed for the qualification of the
affected
MOVs and documented
in the
EQ file.
The inspectors
concluded that this issue is not an immediate safety concern.
This
item is unresolved
pending
NRC review of the engineering
evaluation
of the qualification of the affected
MOVs (50-410/88-08-02).
14.0 Licensee's
Actions in Res
onse to Information Notice 86-03
The licensee
reviewed the applicability of Information Notice 86-03
regarding potential deficiencies
in environmental qualification of
Limitorque motor valve operator wiring.
The licensee's
resolution of
this issue
was to walkdown every Limitorque valve operator
on the
Eg
master list.
The walkdown checklist indicated that only Rockbestos
Firewall III or Raychem Flamtrol wire would be acceptable.
If the
internal wire could not be identified as either of these,
a deficiency was
noted
on the
"MOV Deficiency Checklist."
This deficiency checklist,
in
turn, triggered
a formal "Deficiency Report" which required
a "Work
Request" to resolve
the deficiency.
When the work specified
on the "Work
Request"
was completed,
this was noted
on the "Deficiency Report"
and
finally closed out on the original
MOV Deficiency Checklist.
A review of a sample of MOV walkdown sheets
indicated
NMP2 has replaced
all ques
ionable wire and
now only has
the acceptable
Rockbestos
or
Raychem internal wire.
There are
149 Limitorque valve on the
Eg master
list.
Twenty three of these
valves are located inside the primary contain-
ment,
5 are in the main
steam tunnel
and the rest are at various location
in the reactor building.
The inspectors
physically inspected
the follow-
ing six Limitorque valves in the reactor building.
~
2SWP"MOV15A, Isolation valve for the service water to the
pump
room.
~
2SWP*MOV17A and
2SWP'MOV17B, Isolation valves for the service water
inlet to the spent fuel cooling heat exchanger.
~
2SWP*MOV21A and
2SWP*MOV21B, Isolation valves for the service water
emergency
make-up to the spent fuel pool.
~
2SWP"MOV18A, Isolation valve for the service water outlet from the
spent fuel cooling heat exchanger.
The Limit switch compartments
of these
valves were opened for close
inspection.
The inspectors
observed
the installed condition and
identification of the jumper wires.
Only Rockbestos
Firewall III cable
was observed.
Discussion with NMP2 personnel
indicated that of the
149
Eg Limitorque
operators,
approximately
10% required
some internal rewiring. It was
required that only the acceptable
Rockbestos
Firewall III cable or
Raychem cable
be installed in all the
Eg Limitorque 'operators prior to
fuel loading.
20
15.0 Licensee's
Res
onse to Information Notice 86-53
Ra
chem Cable
S lices
NMPCs disposition of this issue
was documented
in
NMPC internal
memorandum
from E.
R. Klein to M. J.
Ray dated July 28,
1986,
in which
NMPC concurs with SWEC's assertion
in their letter 9M2F-17-851 dated
July 24,
1986 that the issue in IN 86-53 was of no concernto
NMP2.
This memorandum states:
"SWEC's letter No. 9M2F-17-851
responds
to this concern.
We are in
agreement
with
SWEC that due to the explicit instructions
provided
in the Electrical Installation Specification
E061A followed by
100%
FgC inspection,
the problem identified in the subject notice is not
applicable
to
NMP2 project."
Construction installation of Raychem splices at
NMP2 had
been
done for
SWEC by Comstock Electric Co.
and installation records
reviewed
referenced
specification
E061A.
However,
the
NRC inspector's
review of
specification
E061A revealed that while it contained
diagrams of various
types of approved
Raychem splice configurations,
there
were
no specific
instructions for the installation of Raychem cable splices other than the
general
statement
to "...use manufacturers
instructions."
The inspectors
also reviewed
SWEC Quality Assurance
(gA) Inspection. Plan
No. N20E061AFA0276,
Rev.
OE,
Change
4.
This comprised
the inspection
checklist that
gA inspection
records
indicated were
used
by
SWEC field
quality control
( FgC) inspectors
for E061A Raychem installations.
The
checklist referenced
E061A and stated that all installations
should
be in
accordance
with manufacturer's
instructions.
The actual
gC inspection
. attributes
in the checklist were incomplete
and did not include specific
sleeve positioning or dimensional
specifications.
Attachment
B to the
checklsit lists
Raychem
preformed kit instructions,
the
"Raychem
WCSF-N
Installation Guide" (Ref.
No.
E061A Inst. 01.690-5022),
and the
Raychem
WCSF-N Splice Application Guide
(E061A Inst. 01.690-5029).
The
Installation Guide is refered to in the checklist under "Optional" and
the Application Guide is not referenced
in the checklist.
Combining all
these facts,
along with the
Raychem cable splice deficencies identified
. by the
NRC inspectors
(see
paragraph
13. 1) and,the fact that
NMPC had not
done specific walkdown inspections for Raychem splice deficiencies after
receipt of IN 86-53, the inspector
concluded that this issue
had not been
given
an adequate
review.
NMPC committed to conduct their own inspection
of all
Raychem cable splices,
immediately for cable splices outside
the
drywell and during the upcoming outage
for cable splices
inside the
drywell.
Following the inspection,
on May 10,
and
May 16,
1988 the licensee called
the inspector s stating that they had completed
a walkdown of all
Raychem
'able
splices
both inside
and outside
the drywell.
The splices
inside
0'
'0
21
the drywel1 all Wad greater
than 2" seal
length.
Of the splices outside
the drywel1, they found 22 instances
of splices
less
than
1" seal
length.
Five splices
had WCSF-.050
only.
This configuratio'n
was considered
by the licensee
as qualified, but not in accordance
with ProcedGre
E061A.
Three splices
had 4" seal
length
and
two were found less
than
~~", i.e.,
7/16" and 3/8" of seal
length.
The licensee
reported that qualification
for these
splices
in their applications
was supported
by Wyle Laboratories
Report
No.
17855-2
and its supplement.
The report
showed 0.3
ma leakage
current at
125
VDC under the accident conditions. 'his information
indicates 'that these
splices
would be considered qualifiable for the
NNP2
applications
in which they were found provided that instrument
loop
accuracy
requirements
were met.
This item is unresolved
pending
NRC.
review of licensee's
documentation
of these findings.
(50-410/88-08-03)
16.0 Unresolved
Items
Unresolved
items are matters
about which more information is required in
order to ascertain
whether they are acceptable
items or violations.
Unresolved
items identified during this inspection
are discussed
in
Details,
Paragraph
13.2
and 15.0.
17.0 Exit Neet~in
The inspectors
met with licensee
corporate
personnel
and licensee
representatives
(denoted
in Details,
section
1.0) at the conclusion of
the inspection
on April 22,
1988.
The inspectors
summarized
the
scope of
the inspection,
the inspection findings and confirmed with the licensee
that the documents
reviewed
by the team did not contain
any proprietary
information.
The licensee
agreed that the inspection report
may be
placed in the Public Document
room without prior licensee
review for
proprietary information.