ML17055D216

From kanterella
Jump to navigation Jump to search
Insp Rept 50-410/87-32 on 870901-08.Five Apparent Violations Identified.Major Areas Inspected:Review of Events Leading to 870902 Shutdown as Required by Tech Specs
ML17055D216
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 09/15/1987
From: Jerrica Johnson
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17055D215 List:
References
50-410-87-32, NUDOCS 8709210225
Download: ML17055D216 (10)


See also: IR 05000410/1987032

Text

U.S.

NUCLEAR REGULATORY COMMISSION

REGION I

Report

No.

87-32

Docket No.

50-410

License

No.

NPF-69

Category

B

Licensee:

Niagara

Mohawk Power Corporation

301 Plainfield Road

Syracuse,

New York

13212

Facility:

Nine Mile Point Unit 2

Location:

Scriba,

New York

Dates:

September

1,

1987 to September

8,

1987

Inspectors:

W.A. Cook, Senior Resident

Inspector

C.S. Marschall,

Resident

Inspector

W.L. Schmidt,

Resident

Inspecto~

J.R. Johnso,

Chief, Reactor

Projects

Section

2C,

DRP

INSPECTION

SUMMARY:

9/Is

/Bp'ate

Areas

~Ins ected:

Special

inspection

by resident

inspectors

to review the

events

leading to the

shutdown

on September

2,

1987 required

by Technical

Specifications.

This inspection

involved 54 hours6.25e-4 days <br />0.015 hours <br />8.928571e-5 weeks <br />2.0547e-5 months <br />

by the inspectors.

Results:

A sequence

of events is discussed

in section

2.

Five apparent

violations are discussed

in section

3.

87Pg210225

87

pDR

AD

K o

pDR

8

DETAILS

l.

~Pur ose

The purpose of this special

safety inspection

was to review the circum-

stances

leading to the

shutdown initiated at Nine Mile Point Unit 2 to

comply with Technical Specifications

(TS) on September

2,

1987

'.

Event Chronolo

The following is

a chronology of the important events:

In early June

1987,

a cumulative count of operating

hours for each

Standby

Gas Treatment

(SBGT) train was conducted,

based

on the run

times documented

in the Chief Shift Operator

(CSO) logs.

This

action

was prompted

by

NRC inspector review during

an Operational

Readiness

Team Inspection (Inspection

Report

No. 50-410/87-16).

The

A train of SBGT was determined to have

440 hours0.00509 days <br />0.122 hours <br />7.275132e-4 weeks <br />1.6742e-4 months <br />

and the

B train to

have

200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> of cumulative

run time at the

end of May 1987.

Both

SBGT trains were operated

during the months of June, July and

August 1987.

The

SBGT trains were operated

for normal surveillance

testing,

venting of the containment drywell and,

on occasion,

due

to spurious actuations.

On September

1,

1987 at 1:20 p.m., the Division II emergency

diesel

generator

(EDG) was

removed

from service

so that modification work

could be performed.

Prior to removing the Division II EDG from

service,

the requirements

of TS Limiting Condition for Operation

(LCO) action statement

3.8. 1. l.e were reviewed

and logged

as

completed in the Station Shift Supervisor

(SSS)

log.

Approximately three

hours after the Division II diesel

was taken out

of service,

on September

1,

1987, calculations for the run time on

SBGT train A indicated that the train had been

run for 785 hours0.00909 days <br />0.218 hours <br />0.0013 weeks <br />2.986925e-4 months <br />,

in

excess

of the

TS 4.6.5.3.c

surveillance limit of 720 hours0.00833 days <br />0.2 hours <br />0.00119 weeks <br />2.7396e-4 months <br />.

This

cumulative

run time was based

on

a review of the

CSO logs through the

end of July 1987.

Subsequent

to the above determination,

Operations

management

immediately contacted

the corporate licensing staff to determine if

the standard

255 variance in surveillance

frequency applied to TS

surveillance 4.6.5.3.c limit.

Operations

was told verbally that the

25% variance

was applicable.

This made the

maximum allowable sur-

veillancee

frequency

900 hours0.0104 days <br />0.25 hours <br />0.00149 weeks <br />3.4245e-4 months <br />.

At that time, Operations

management

did not continue with the

SBGT run time review because it was thought

that the

900 hour0.0104 days <br />0.25 hours <br />0.00149 weeks <br />3.4245e-4 months <br /> limit would not be exceeded.

0

On September

2,

1987,

the review of the cumulative

run time on the A

train of SBGT was continued

and it was determined

to have

exceeded

the 900 hour0.0104 days <br />0.25 hours <br />0.00149 weeks <br />3.4245e-4 months <br /> surveillance

requirement

(1120 actual

hours).

Based

on

this determination,

the A train was declared

inoperable

and Unit

"management

was informed.

At 5:35 p.m.

on September

2,

1987,

a reactor

shutdown

was

commenced

to comply with TS 3.8. l.l.e,

due to train A of SBGT being inoperable

while the Division II EDG was also out of service.

3.

Ins ector Findin

s

Failure to comply with a Technical Specification Surveillance

requirement

to sample

SBGT charcoal filters after -720 hours of operation:

C.

On September

1,

1987, after the Division II emergency diesel

generator

(EDG) was

removed

from service,

Operations

Department

management

became

aware that the limit for accumulated

run time

hours

on train A of SBGT was exceeded.

The licensee

subsequently

determined

on September

2,

1987 that the total

number of run hours

on train. A was greater

than

1100.

The purpose for tracking accum-

ulated run hours is to ensure

a sample of charcoal filter adsorber

medium is drawn and chemically analyzed

in accordance

with TS sur-

vei llance requirement 4.6.5.3.c.,

(after 720, plus or minus

25%,

hours of operation).

The analysis

determines if the charcoal

still has its adsorbing properties for iodine.

The failure to

sample train

A charcoal filter medium after

720 hours0.00833 days <br />0.2 hours <br />0.00119 weeks <br />2.7396e-4 months <br /> of operation

is an apparent violation of T.S. 4.6.5.3.c

~

VIOLATION (50-410/87-32-01)

Failure to inform the Station Shift Supervisor

(SSS) of the potentially

inoperable

SBGT trains:

On September

1,

1987, Operations

management

knew that train A of

SBGT had exceeded

720 hours0.00833 days <br />0.2 hours <br />0.00119 weeks <br />2.7396e-4 months <br /> of cumulative run time, but did not

believe that the total run time exceeded

900 hours0.0104 days <br />0.25 hours <br />0.00149 weeks <br />3.4245e-4 months <br />.

The licensee

was unable to provide

an adequate

reason for the belief.

In addition,

the cumulative

run time for the

B train was uncertain.

T.S. 6.8 and

Regulatory

Guide 1.33 require that the licensee

implement adminis-

trative procedures

for personnel

authorjties

and responsibilities

for

the safe operation of the plant.

Administrative Procedure

1.2,

section

4. 1 states

that under the general direction of the Superin-

tendent of Operations,

the SSS's

function includes

ensuring that the

plant is operated

safely and within the license

and Technical Specifi-

cations.

When the operability of the

SBGT trains

was first in question,

the

SSS

was not informed of. the status of the surveillance testing

requirement,

and therefore,

not afforded the opportunity to make

an

operability determination of the

SBGT system.

This is an apparent-

violation of T.S. 6.8 and procedure

AP 1.2.

VIOLATION (50-410/87-32-02)

From approximately mid-June,

1987 to September

1,

1987,

the licensee

did not know the total

run time on either train of SBGT.

This led

to two apparent violations of TS Limiting Condition for Operation

3.8.l.l.e:

Failure to recognize that that train A of SBGT was inoperable

when the Division II EDG was taken out of service:

When the Division II EDG was

removed

from service,

TS 3.8. 1. 1.e

required that the licensee verify that all systems that depend

on the remaining operable

EDG as

a source of emergency

power

are

also operable.

The

SSS verified that the surveillance tests

in

the surveillance

schedule

computer printout were up-to-date

and

that

no out-of-service

equipment entries

were

made in the

Equipment Status

Log for components

or systems that rely on

Division I

EDG for emergency

power.

In addition, the Division

II EDG outage

was

a preplanned

evolution

and the inspectors

could

find no evidence that

a detailed

management

review was conducted,

in advance,

to ensure

compliance with TS 3.8. 1. l.e.

In that the

licensee

did not verify that surveillance

testing

on the

A train

of SBGT was current,

the lic'ensee failed to comply with the

LCO

requirement of TS 3.8. 1. l.e.

This is an apparent violation of

T.S. 3.8. 1. 1.e.

VIOLATION (50-410/87-32-03)

Failure to be in

HOT SHUTDOWN within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after the

cumulative

run time

on the A SBGT train exceeded

the required

720 hours0.00833 days <br />0.2 hours <br />0.00119 weeks <br />2.7396e-4 months <br />

(+25%) in conjunction with the inoperability of the

Division II EDG.

Shortly after the Division II EDG was

removed

from service

on

September

1,

1987,

the licensee identified that the operabli lity

of train A of SBGT was in question.

Although a

TS interpreta-

tion was

made that

a

25% variance applies to the

720 hours0.00833 days <br />0.2 hours <br />0.00119 weeks <br />2.7396e-4 months <br />

surveillance

frequency,

the licensee did not verify that the plus

25% (900 hours0.0104 days <br />0.25 hours <br />0.00149 weeks <br />3.4245e-4 months <br />) limit was not exceeded.

TS 3.8. 1. l.e requires

that the unit be placed in HOT SHUTDOWN within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

and

COLD

SHUTDOWN in the following 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, if the operability of systems

dependent

on the operable

EDG are not verified.

The licensee

'did not take action within the allowable

TS action statement

to

shutdown the unit when the operability of the

SBGT system

came

into question.

This is an apparent violation of T.S.

3'. 1. l.e.

VIOLATION ( 50-410/87-32" 04)

d.

Failure to take prompt and effective action

on

a previously

identified item:

During the Operational

Readiness

Team inspection

conducted during

the first few weeks in June

1987,

a deficiency was noted in the

licencee's

program for tracking the accumulated

run hours

on the

two redundant

Standby

Gas Treatment

System trains.

During this

inspection, it was not clear by whom or how these

hours were being

tracked.

Prior to the

end of the team inspection,

the inspector

was

shown documentation

on

SBGT system

run hours

accumulated

through

May

1987.

0

Based

on this earlier inspection,

the licensee initiated changes

to

the

SBGT system operating

procedures.

The changes

to the procedures

incorporate

a log sheet to be completed

by the control

room operators

when

a train of SBGT has

been

operated.

These

procedure

changes

were

not incorporated

into the procedure until August 31,

1987.

In addi-

tion,

no interim action was taken

by the licensee

to ensure

a current

status of SBGT train run times was maintained.

10 CFR 50, Appendix

B, Criterion XVI, requires

that conditions adverse

to quality be

promptly identified and corrected.

NMPC Quality Assurance

Program

Topical Report for Nine Mile Point Nuclear Station Operations,

QATR-1, Revision 2; states

that program

and hardware conditions

adverse

to quality are identified promptly and corrected

as

soon

as

.

practical.

Failure to take prompt and appropriate corrective action

for this previously identified deficiency is an apparent violation

of 10 CFR, Appendix B, Criterion XVI, and the

NMPC

QA program.

VIOLATION (50-410/87-32-05)

4. Exit M~eetin

At the conclusion of the inspection,

a meeting

was held with senior

corporate

and station

management

to discuss

the

scope

and findings of

this inspection.

Based

on the

NRC Region I review of this report

and discussions

held with

licensee

representatives, it was determined that this report does

not

contain Safeguards

or 10 CFR 2.790 information.

P

0