ML17055B021

From kanterella
Jump to navigation Jump to search
Insp Rept 50-220/85-13 on 850819-23.Major Area Inspected: Implementation of Program for Establishing & Maintaining Qualification of Electric Equipment within Scope of 10CFR50.49.Deficiencies Noted
ML17055B021
Person / Time
Site: Nine Mile Point 
Issue date: 12/19/1985
From: Potapovs U, Wilson R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To:
Shared Package
ML17055B019 List:
References
50-220-85-13, NUDOCS 8601090566
Download: ML17055B021 (36)


See also: IR 05000220/1985013

Text

U.S.

NUCLEAR REGULATORY COMMISSION

OFFICE

OF INSPECTION AND ENFORCEMENT

Report No.:

Docket No.:

License

No.:

Licensee:

Facility Name:

Inspection At:

Inspection

Conducted:

50-220/85-13

50-220

DPR-63

Niagara

Mohawk Power Corporation

300 Erie Boulevard West

Syracuse,

New York

13202

Nine Mile Point, Unit No.

1

Syracuse

and Scriba,

New York

August

19 to 23,

1985

Inspector:

R.

C. Wilson

Equipment gualification 5 Test Engineer

Date

Also participating in the inspection

and contributing to the report were:

U. Potapovs,

Chief, Equipment gualification Inspection Section,

I&E

S. Alexander,

Engineer,

ISE

A. Masciantonio,

Engineer,

NRR

R. 0. Karsch,

Reactor Engineer,

NRR

E.

H. Richards,

Member of Technical Staff, Sandia

National Laboratories

J.

Fehringer,

Consultant

Engineer,

Idaho National Engineering Laboratory

L. Cheung,

Reactor Inspector,

RI

M. Schaeffer,

Reactor Inspector,

RI

C. Anderson,

Section Chief,

RI

Approved by:

Ul is Potapovs,

Chic

Equipment gualification Inspection Section

Vendor Program Branch

Office of Inspection

and Enforcement

Ih -,

h

k

I

INSPECTION

SUMMARY:

~Ins ection

on

Au ust

19 to 23,

1985

Ins ection

Re ort No. 50-220/85-13

A~d:

p

PP,

dd

p

.P

P

P

implementation of a program per the requirements

of 10 CFR 50.49 for

establishing

and maintaining the qualification of electric equipment within

the

scope of 10 CFR 50.49.

The inspection also included evaluations of the

implementation of equipment qualification (Eg) corrective action commitments

made

as

a result of deficiencies identified in the

December

30,

1982 Safety

Evaluation Report

(SER)

and the August 6,

1982 Franklin Research

Center

(FRC)

Technical

Evaluation Report (TER).

The inspection

involved 269 inspector

hours onsite.

Results:

The inspection

determined that the licensee

has

implemented

an

interim program to meet the requirements

of 10 CFR 50.49, except for the

deficiencies listed below,

and is developing

a long-range

program.

No

deficiencies

were found in the licensee's

implementation of corrective

action commitments

made

as

a result of SER/TER identified deficiencies.

Name

Potential

Enforcement/Unresolved

Items:

Re ort Para

ra

h

Item Number

2.

3.

4.

5.

6.

7.

qualification file deficiencies

Static-0-Ring pressure

switches

Valcor solenoid valves

General Electric EB-25 terminal

blocks

General Electric EB-5 terminal

blocks

Fisher

304 position switches

Rosemount

1151 transmitters

4.A. (1)

4.D. (1)

4.0.(2)

4.D.(3)

4.D.(4)

4.D.(5)

4.D.(6)

50-220/85-13-01

50-220/85-13-02

50-220/85-13-03

50-220/85-13-04

50-220/85-13-05

50-220/85-13-06

50-220/85-13-07

Name

~0en

Items:

Re ort Para

ra

h

Itern Number

1.

2.

3.

4.

Implementation of Eg procedures

Closed loop cooling motor

lubrication

Acoustic monitor coaxial cable

Laurence solenoid valve

4.A.(2)

4.A.(4)

4.D.(7)

4.D.(8)

50-220/85-13-08

50-220/85-13-09

50-220/85-13-10

50-220/85-13-11

t'

1.

Persons

Contacted:

DETAILS

1. 1

Nia ara

Mohawk Power Cor oration

NMPC

  • T. E.

Lempges,

Vice President,

Nuclear Generation

  • C. V. Mangan,

Senior Vice President

  • J.

K. Jirousek,

Project Manager,

Equipment Qualification

  • T. J. Perkins,

Gen. Supt., Site

  • G. D. Wilson, System Attorney
  • K. Sweet, Electrical Maintenance

Supt., Site

  • H. T. Master III, Asst.

QA Engineer, Site

QA, Nuclear

  • M. G. Mosier, Assoc.

Sr. Nuclear Engineer

  • R. J.

Pasternak,

Sr. Nuclear Engineer

  • S. Loveland,

NMP No.

2 Lead

EQ Engineer

R. Main, Assoc.

Generation

Spec., Training

N. Rademacher,

Nuclear Design Coordinator

K. Dahlberg,

Maintenance

Supt., Site

1.2

NMPC Consultants

  • L. W. Price,

EQ Engineer,

Gasser

Assoc.

  • G. F. Eldridge, Engineer,

Gasser

Assoc.

  • P. Brunsgaard,

Engineer,

Gasser

Assoc.

  • T. Patterson,

Senior Staff Engineer,

Wyle Laboratories

  • H. A. Zadeh,

Engineer,

Wyle Laboratories

  • R. K. Ho,

EPM, Consultant to Nuclear Utility Group on

Equipment Qualification

1.3

Nuclear

Re ulator

Commission

  • R. A. Hermann,

NRR, Project Manager

S.

D. Hudson,

Resident

Inspector

  • Denotes those present at exit interview at Syracuse

on August 23,

1985

l

2.

PURPOSE

The purpose of this inspection

was to review the licensee's

implementation

.of the requirements

of 10 CFR 50.49

and the implementation of committed

corrective actions for SER/TER identified deficiencies.

3.

BACKGROUND

On March 15,

1984, the

NRC held

a meeting with NMPC officials to discuss

NMPC's proposed

methods

to resolve the

Eg deficiencies identified in the

December

30,

1982

SER and August 6,

1982

FRC TER.

Discussions

also

included

NMPC's general

methodology for compliance with 10 CFR 50.49

and

justification for continued operation for those

equipment

items for

which environmental qualification was not completed.

The minutes of the

meeting

and proposed

method of resolution for each of the

Eg deficiencies

were documented

in a May 31,

1984 submittal

from the licensee.

The

TER

and

May 31 submittal

were reviewed

by inspection

team

members

and were

used in planning

and conducting the inspection.

4.

FINDINGS

A.

E

Pr'o

ram

Com liance with 10 CFR 50.49

The

NRC inspectors

examined the licensee's

program for establishing

the qualification of electric equipment within the scope of 10 CFR 50.49.

The program was evaluated

by examination of the licensee's

qualification documentation files; review of procedures

and other

means for controlling the licensee's

Eg effort; verification of

the adequacy

and accuracy of the licensee's

10 CFR 50.49 equipment

list; and examination of the licensee's

program for maintaining the

qualified status of the covered electrical

equipment.

Based

on the inspection findings, which are discussed

in more

detail

below, the inspection

team determined that the licensee

has

implemented

an interim program to meet the requirements

of

10 CFR 50.49, although

some deficiencies

were identified.

The

licensee

is also developing

a long range

plan to more formally

control

Eg activities.

(1)

g

life

i

Fil

During the entrance

meeting

NMPC described its Equipment

gualification File as being maintained

under the cognizance

of the

Eg Coordinator for the life of the plant for the

covered items.

The following data were listed

as included

in the file:

Equipment gualification Master List

Eg List Basis

Documentation

System

Component Evaluation Worksheets

(SCEW)

Environmental

Conditions Basis

Documentation

0)

Eg Field Verification Data Including Photographs

Eg Reports

Eg Studies/Analyses

Eg Calculations

EQ Maintenance

5 Spare

Parts

Requirements

Eg Checklists

Eg Location Drawings

Eg Correspondence

(Chronological

Order)

Some supporting information was identified as located elsewhere.

For example, installation,

procurement,

and receipt inspection

records

are maintained at the site with microfilm copies

available for engineering

reference.

The

Eg Master List and

SCEW sheets

are computerized.-

The

NRC inspectors

reviewed the files for 16 equipment

items,

where

an item is defined

as

a specific type of electrical

equipment,

designated

by manufacturer

and model, which is

representative

of all identifical equipment in

a plant area

exposed

to the

same

environmental

service conditions.

The

types were selected

in advance

by the inspection

team and

identified to the licensee

during the entrance

meeting.

Common deficiencies

in the files are described

in this

section of the inspection report,

and specific component-

related

concerns

are discussed

in paragraph

4.D. below.

The inspectors

found that traceability of references

important

to qualification of equipment

was accomplished

by reference

numbers

provided

on the

SCEW sheets

and

on component gualification

Summary Sheets.

Typically the inspector

had to search

the entire

reference

to locate the pertinent information.

File auditabi lity

was degraded

by lack of specific citations to pertinent material

in reference

documents.

All of the major references

inspected

such

as test reports

and

analyses

had rubber stamps

on the cover sheet.

Each

stamp

had

spaces

for "originator," "checker,"

and "approved" signatures,

as well as the reference

number

and

a date for each signature.

The licensee

explained that these

signatures

documented

NMPC

review and acceptance

of the document.

NMPC provided the

inspectors with copies of a five page

memo to file dated

August

22 (near the end of the inspection)

which retrospectively

defined the bases for the

NMPC review and signoff.

The inspecto'rs

conclude that the

NMPC file review process

is deficient for

reasons

that include the following:

The basis for a single set of acceptance

signatures

is not

clear when placed

on

a volume of, Limitorque test reports

involv'.ng several different tests of various operator

types

in various environments,

applicable to multiple types of

operators

with varying service conditions in Nine Mile Point

Unit No. l.

(0

For most components

the files including

SCEW sheets

did not specifically document the required level of

qualification

(DOR Guidelines,

IEEE 323-1974, etc.) nor

did the inspectors find evidence that the signers

addressed

that information for each application.

NMPC

did have

an "Environmental gualification Checklist" with

boxes for checking the appropriate level; however,

the

inspectors

were informed that the

Eg Checklist

was only

issued for components

whose qualification documentation

including maintenance

requirements

is complete.

Since

only a few of the

Eg Required Maintenance

packages

were complete at the time of inspection,

few Eg

Checklists

were issued.

Acceptance

signatures

were found on several

analysis

reports for components

whose functional performance

requirements

in the plant were not defined:

Rockbestos

control cable,

SOR pressure

switches,

and Rosemount

1151

transmitters,

for example.

guestions

raised

by the inspectors

resulted

in the

response

by the licensee that plant service conditions

had been improperly defined for some

components

(see

section

4.D. of this report).

The deficiencies cited above,

considered

in context with the

component-specific file deficiencies

described

in section

4.D.

of this report, collectively comprise

a Potential

Enforcement/

Unresolved

Item, gualification File Deficiencies,

50-220/

85-13-01.

(2)

E

Pro

ram Procedures

NMPC's overall equipment qualification program is addressed

in

Nuclear Engineering

and Licensing Procedure

NT-100.C,

"Equipment

gualification."

Preliminary Rev.

0 dated July 15,

1985 was

provided before the inspection,

and

an August 22,

1985

Preliminary Rev.

0 was given to the inspectors

during the

inspection.

This procedure

has not been

approved or issued;

NMPC is addressing

Eg with an interim program described

below.

A preliminary review of draft procedure

NT-100.C

by the

inspectors

revealed

no deficiencies.

Its scope

includes

the

following:

I

,

~l

References

Definitions

Responsibi

1 ities.

Eg rev iew of pre 1 imi nary des i gn

Determination of Eg procurement

requirements

Determination of qualification alternatives

Development of a qualification test program

Review/acceptance

of Eg reports

Installation requirements

Maintenance

requirements

Eg master list

Eg file requirements

~ Plant environmental

conditions analysis/documentation

Review of manufacturer

and

NRC Bulletins/Notices

Review of changes

to

NMP-1 "g" list

Review of changes

to tech

specs

and operating

procedures

Failure/trend analysis of Eg equipment

Reevaluation of Eg criteria

Verification of engineering

and plant

Eg compliance

At the time of the inspection

the following Eg-related

procedures

had

been issued:

Nl-EMP-44.2

.

Installation Procedure for Class

1 Electrical

Equipment

Nl-EMP-44.4

Installation Procedure for Sealing of Selected

Electrical Connections with Kaowool or Flameseal

and Bisco Locaseal

NI-EMP-44.22

Installation Procedure for Insulating

and Taping

Medium and

Low Voltage

Power Connections

N1-EMP-44.24

Installation Procedure for Namco Limit Switches

Nl-EMP-45.96

Equipment gualification Examination of Limitorque

Valve Actuators

and Associated

Motors, Type

SMB

and

SB

Nl-FMP-45.97

Equipment gualification Inspection for Electromatic

Relief Valves

During-the entrance

meeting,

NMPC provided the following schedule

for completing its

Eg program:

Eg Procedures

Complete

Eg Procedures

Implementation

Eg Required Maintenance

Reviews

Site Maintenance

Procedures

Updates

Training Program

Implementation

October

1985

January

1986

October,

1985

March 1986

January

1986

l

This schedule

is keyed to implementing the long term

EQ program

by a refueling outage

scheduled for March, 1986.

A future

inspection will review the approved

issue of NMPC's

EQ

procedure

and completion

o

the schedule listed above.

Implementation of EQ procedures

comprises

Open Item 50-220/

85-13-08.

I

The inspectors

reviewed

NMPC's interim program for implementation

of the requirements

of 10 CFR 50.49 including:

definitions of

harsh

and mild environments;

equipment qualified life; service

conditions; periodic testing; maintenance;

and surveillance.

NMPC's interim program was also reviewed for requirements

to

establish,

evaluate

and maintain auditable

EQ documentation

including

EQ summary sheets,

test reports,

maintenance

records

and other supporting documentation

to justify equipment

qualification; training of personnel

in the environmental

qualification of equipment;

control of plant modifications

such

as installation of new and replacement

equipment;

and

provisions for updating replacement

equipment to

10 CFR 50.49

cri ter ia.

NMPC's interim

EQ program is intended to control

EQ activities

until the long term program is implemented.

Interim practice

essentially

depends

on routing all EQ-related matters

through

the

EQ project manager,

who ensures

that proper action is taken.

Previous submittals to the

NRC and

a computerized

equipment

master list were used

as

a data

base.

Interim control of the

EQ files, Master List, and maintenance

is discussed

in detail

in other paragraphs

of section

4.A of this inspection report.

The inspectors

reviewed the Quality Assurance/Quality

Control

(QA/QC) organization

and activities.

The

QA/QC organization

consists of a director of QA and five section

managers.

The

nuclear

QA section

manager

has direct control over the nuclear

QA supervisor,

who in turn directs the Quality Engineering

and

QC Inspection functions.

EQ activities requiring

QC coverage--

such

as maintenance,

receipt inspection,

and procurement

specification requirements

review -- are covered

by the nuclear

QA supervisor.

In addition, the

QC inspectors

review all

EQ work

requests.

The inspectors

examined

NMPC

QA Services Audit No. SP-IN-SY-84001

dated

December

6,

1984.

The audited organization

was Nuclear

Design Engineering.

The purpose of the audit was to verify

control of contractor activities

and compliance with Engineering

Procedures,

the

QA program,

and the following:

10 CFR 50 Appendix

B

10 CFR 50 Appendix

R

The

EQ Master List (document

M.O. F1927)

i'd/ ll

Four of the

14 audit findings dealt with Eg and were reviewed

by the inspectors.

Treatment of the findings, dispositions,

and closeouts

were found to be acceptable

to the inspectors.

The inspectors

reviewed the licensee's

Eg training procedure,

intended to train maintenance

personnel

in properly maintaining

environmentally qualified equipment.

The procedure

was approved

August 16,

1985.

It covers the following topics,

intended to

make maintenance

personnel

cognizant of NMPC's requirements

for

meeting

10 CFR 50.49:

Basis for Equipment gualification regulation

Methods of qualifying equipment

Types of analysis

used to extend qualified life of

equipment

Differences

between

Nine Mile 1 and Nine Mile 2

Equipment gualification Standards

Types of accidents

defining

Eg scope

Use of a

SCEN sheet

Systems that have equipment which must

meet Equipment gualification standards

Environmental

map of the station

Equipment gualification procurement

standards

Controls applicable to installation of

Eg equipment

Maintenance

requirements for Eg equipment

Use of an Equipment qualification required

maintenance

sheet

Subsequent

discussions

with the electrical

maintenance

supervisor

on October 3,

1985 disclosed that eight of his electricians

successfully

completed the training course

on September

27,

1985.

The passing

grade for the written exam was

80 percent.

The

supervisor also stated that forty electricians

were scheduled

to

complete

the

Eg training within eight weeks.

During the site visit, the inspectors

reviewed the

training records of 16 maintenahce

electricians, all

of whom are certified to ANSI N45.2.6-78.

Verification that the licensee

completes

implementation

of his training program by January

1986 is included in

the

Open Item identified at the beginning of this report

section 4.A.(2).

10 CFR 50.49 List

E

Master List

The licensee is required to maintain

an up-to-date list of the

equipment that must

be qualified under

10 CFR 50.49.

This list

is entitled "Nine Mile Point No.

1 Equipment Qualification M.O.

81927" dated August 15,

1985.

For ease of access

and control,

this list is part of a computer controlled environmental

qualification data

base.

Considered

in the preparation of this

list are environmental

effects resulting from all postulated

design-basis

accidents

documented

in the licensee's. Final

Safety Analysis Report,

Technical Specification limiting

conditions of operation,

emergency operating

procedures,

piping and instrumentation

diagrams,

and electrical

distribution diagrams.

The licensee

is aware that when

emergency

procedures

are rewritten as

symptom oriented

procedures,

new items will be added to the

EQ Master List.

The

EQ Master List was produced

as detailed

by the licensee'

submittal

"Equipment Qualification Program"

dated

May 31,

1984.

This procedure

and Engineering

Procedures

NT-100.2,

NT-110 and

HD-100 provide guidance

and control

n.

the

EQ Master List to

maintain its accuracy.

It was suggested

that ND-100 be

modified to more clearly define responsibility for screening

plant modifications for impact on the

EQ Master List.

Pending full implementation of the long term

EQ program,

NMPC

has

addressed

possible additions of equipment to the Master List

via

a letter from the

EQ project manager to all lead design

engineers.

The letter states

that all design

changes

should

be reviewed

by .the

EQ staff for EQ impact.

Eleven items were used

as

an audit sample to verify the complete-

ness of the current

EQ Master List.

In order to compile this

audit sample,

review was conducted of the following piping and

instrumentation

drawings

(P&IDs) and emergency

procedures.

10

4

J'>

Emer enc

Procedure

"Emergency Cooling Systems

05,

39

& 60" revision

15

P&IDs

18002-C

18007-C

18014-C

18014-C

18014-C

18018-C

18020-C

18022-C

18041-C

Sheet

¹1 rev 20

Rev

28

Sheet

¹1 rev 33

Sheet ¹3 rev

9

Sheet ¹4 rev ll

rev

6

rev

10

Sheet

¹4 rev

2

Sheet

¹7 rev

4

"Main Steam

& High Pressure

Turbine"

"Reactor Core Spray"

"Reactor Containment

N2 Purge

& Fill

Drywell Cooling System"

"Reactor Containment

N2 Supply"

"Reactor Containment

N2 Supply"

"Reactor

Shutdown Cooling"

"Reactor Recirculation

Loops"

"Service Hater Reactor

& h~aste

Bldgs"

"Reactor Vessel

Post Accident Sample

Points"

The audit sample

was selected

to verify that those

items required

to be on the list are in fact on the list.

The sample also

included

one item required for implementation of R.G.

1.97 (High

Range Radiation Monitor including cable).

All sample

items required to be

on the

Eg Master List were in

fact on the list.

To test the thoroughness

of the licensee's

review

a sample

item not required to be

on the

Eg Master List

was questioned;

the item was not on the list and the licensee

provided

a satisfactory explanation

why it was not.

Based

on this review the licensee's

Eg Master List is considered

satisfactory.

E

Maintenance

Pro

ram

The inspectors

determined that

NMPC has

an interim program which

covers

Eg maintenance

requirements

until the next outage,

scheduled for March,

1986.

The interim program is defined in

a March 29,

1985 letter from the

Eg Project Manager to maintenance

supervisors.

The letter summarizes

the ongoing activities for

developing the formal program; transmits

the computerized

Eg

Master List, which also identifies any action required for

qualification through March 1986 and the status of that action;

and states

that all modifications required to be complete

by

March. 31,

1985 were completed.

The inspectors

noted that,

except for the deferred

items discussed

in paragraph

4.B of this

inspection report, all required actions

were recorded

as completed

by August 14,

1985.

11

f

The March 29 letter also stated that any planned

change involving

qualified equipment would have to be assessed

to ensure that

qualification is not jeopardized;

and specified that the

responsible

maintenance

supervisor or designee

is to review

work requests

against

the

Eg master list, identify the work

request

as Eg-related if applicable,

and either use formal

Eg

maintenance

requirements

where existent or contact the

Eg staff

for guidance.

Finally, the letter called for Eg staff review

prior to performance of any preventive maintenance

and

surveillance test procedures

not previously reviewed,

and

advised guality Control to verify that

Eg Master List items

are identified on work requests.

The inspectors

interviewed the

ISC and electrical

maintenance

supervisors,

who demonstrated

that they were familiar with the

March 29 letter and stated that it is being observed.

The

Eg

project manager stated that

an additional

backup exists to

ensure that the interim program is effective; namely,

he

receives

and reviews

a monthly printout listing the status of

all Eg-related

work requests.

The inspectors

randomly selected

from the Master, List two

components

requiring corrective action to maintain qualification

until the next outage,

and reviewed the applicable

work packages

to verify completion of the corrective action.

The selected

items are (1) MSIV pilot solenoid valve SOV-01-04C,

ASCO model

206-381-2RU,

which required replacement

by a qualified

NP series

solenoid valve;

and (2)

PORV solenoid actuator

POS-NR-108D,

Unimax model

KBL711B-5, which required coil replacement.

Khe following documents

in the work packages

were reviewed:

Work Request

WR¹25985 for Replacing

ASCO Model

206-381-2RU

by ASCO Model

NP 206-381-2RU,

dated

May 4, 1984.

Installation Instruction from J.

K. Jirousek to

T.

W.

Roman.

Description of Work for Eg Work Package

No. 01-21.

Electrical

Connection

Seal Installation

Check List

dated

June

1,

1984.

Inspection

Report

No.

840593 dated

June

1, 1984.

Work Request

WR¹25689 Inspect

and Replace

Wire

(Coil) per

EOWP¹01-6 dated April 18,

1984.

Equipment gualification Inspection for Electromatic

Relief Valve (ENR¹122) dated

May 4, 1984.

12

I'

Review of these

documents

demonstrated

that the modifications

were performed using detailed

approved instructions

and were

inspected

by licensee guality Control Inspectors.

No

unacceptable

conditions were found in this review.

The licensee

stated that all

Eg Required Maintenance

reviews

would be completed

by October

1985,

and all site maintenance

procedures

would be updated to include

Eg requirements

by

March 1986.

At that time the

Eg maintenance

program is

scheduled

to be fully implemented.

Maintenance

program

implementation is included in the

Open Item identified in

section 4.A.(2) of this inspection report.

'uring

the plant physical

inspection of the reactor building

closed loop cooling motors M70-01, 02,

and

03 the inspectors

found evidence of oil spillage

under

each motor and

pump.

guestioning of the electrical

maintenance

supervisor during

and after the inspection (in an August 29 telephone

conversation)

revealed that the

pumps

and motors

had

been

overfilled during

a requi red weekly lubrication maintenance

check.

Overfilling was said not to interfere with equipment

functioning because

the excess oil drains through vent holes.

The licensee

stated that corrective action

was taken

by

lowering the oiler fillers.'erification of this action

and

inspection of maintenance

records will be accomplished

in a

future

NRC inspection.

Closed loop cooling motor lubrication

constitutes

Open Item 50-220/85-13-09.

B.

SER/TER Commitments

The

NRC inspectors

evaluated

the implementation of Eg corrective

action commitments

made

as

a result of SER/TER-identified

deficiencies

as stated

in a licensee

submittal

dated

May 31,

1984.

This submittal states

that all equipment

on the

10 CFR 50.49 Master List is qualified except for certain

eauipment for which Justifications for Continued Operation

(JCOs)

were submitted.

The final SER, transmitted

January

10,

1985 identified that the

JCOs

were acceptable.

Licensee letters

dated

December

13,

1984 and February 5,

1985 stated that further

extension

beyond March 31,

1985

was needed for only two groups

of equipment,

four Limitorque operators

and two shutdown

supervisory

panels.

NRC letter dated

March 15,

1985 extended

the qualification deadline for this equipment until November 30,

1985.

Based

on review of files and of the

10 CFR 50.49 Master List, the

NRC inspectors

identified no failure to implement

SER/TER

commitments.

13

0

~

~

ft

C.

Plant

Ph sical

Ins ection

The

NRC inspectors,

with component accessibility input from licensee

personnel,

established

a list of 12 types of components for physical

inspection.

All were accessible

at the time of inspection,

during

plant operation.

The inspectors

examined characteristics

such

as

mounting configuration, orientation, interfaces,

model

number,

ambient environment,

and physical condition.

No concerns

were

identified during the physical inspection

except

as noted in the

individual component discussions

in sections

4.A.(4) and 4.D.

D.

Detailed

Review of uglification Files

The

NRC inspectors

examined

SCEW sheets

and files for 16 selected

equipment

types to verify the qualified status of equipment within

,the scope of 10 CFR 50.49.

In addition to comparing plant service

conditions with qualification test conditions

and verifying the

bases for these gonditions,

the inspectors

selectively reviewed

areas

such

as required post-accident

operating

time compared to the

duration of time the equipment

has

been

demonstrated

to be qualified;

similarity of tested

equipment to that installed in the plant (e.g.,

insulation class,

materials of components

of the equipment,

tested

configuration compared to installed configuration,

and documentation

of both); evaluation of adequacy of test conditions;

aging calcu-

lations for qualified life and replacement

interval determination;

effects of decreases

in insulation resistance

on equipment

performance;

adequacy of demonstrated

accuracy;

evaluation of test

anomalies;

and applicability of Eg problems reported in IE INs/

Bulletins and their resolution.

As indicated in section 4.A.(1) above,

the files were difficult to

audit and the inspectors

had to ask.numerous

questions

to develop-

necessary

information.

Even though the licensee

is vigorously

pursuing

a course that appears

to be resolving program

and file

deficiencies,

the file review identified six component-specific

Potential

Enforcement/Unresolved

Items

and two Open Items, of the

16

items reviewed

as follows.

( 1)

Static-0-Ring pressure

switch, pc.

no.

PS-70-279.

-

No

accuracy requirement

was listed for the plant application,

and the licensee

could not demonstrate

during the inspection

that the accuracy

measured

during type testing

was adequate

for the application.

Another concern relates

to the cable

14

I

V

ll

rr

entrance

seal.

The walkdown inspection

and subsequent

questioning

revealed

dependence

on

a cable seal

internal

to the conduit,

and the conduit seal

was not qualified.

The type test did not qualify the internal seal,

since it

was shi'elded

from the harsh environment

by stainless

steel

conduit extending from the switch housing electrical

port to the test vessel

port.

The licensee

subsequently

stated that

an analysis

indicated that the pressure

switch

is not required to function in a hostile steam environment,

contrary to the environment specified in the files.

According

to the licensee,

these

devices

are required only for the Loss of

Coolant Accident which does not produce

a steam environment

at their location.

The inspectors

also observed that no Eg-

related surveillance or maintenance

was required,

even though

the claimed qualified life is 40 years.

Static-0-Ring pressure

switches

comprise Potential

Enforcement/Unresolved

Item

50-220/85-13-02.

Valcor solenoid valve, pc. no.

SOV-39-14C. - Although conduit

was

used to seal

the cable entrance

path during the type test,

the walkdown inspection

revealed that no conduit seal

was

used in the'plant installation.

The licensee

responded

to

questioning

by stating that contrary to the environment specified

in the files, the component is not required to function in a

hostile steam environment.

According to the licensee,

these

devices

are required only for the Loss of Coolant Accident which

does not produce

a steam environment at their location.

The

licensee failed to identify any required surveillance or

maintenance

for a 40-year qualified life, but in this case

the

inspectors

noted that near-term

replacement with other qualified

valves is scheduled

and no degradation

that could invalidate

qualification is expected

in the interim.

Valcor solenoid valves

comprise Potential

Enforcement/Unresolved

Item 50-220/85-13-03.

General Electric EB-25 terminal blocks,

SCEW 711 - Documents

in the

E(} file did not identify where

and for what services

these

terminal blocks are used.

No functional

performance

requirements

were defined for plant service,

and the required

operating time was specified

on the

SCEW sheet

as

28 hours3.240741e-4 days <br />0.00778 hours <br />4.62963e-5 weeks <br />1.0654e-5 months <br />.

Wyle

gualification Test Plan

17655-14 specifies

an insulation

resistance

acceptance

criterion, without indicating the basis,

of

1 Megohm throughout the

LOCA test.

The actual

type test

values

dropped

below the acceptance

criterion for some terminals

8.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> into the test,

and after 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> the resistance

of two terminals

was below the test equipment limit of 50,000

ohms at

10 vdc.

Appendix I of Wyle test report 17722-1

recommends

ignoring insulation resistance

and instead

using voltage drop

measurements

as

an acceptance

criterion.

The stated voltage

drop criterion, allowing a decrease

from 137.5 vac to 102 vac,

again

was not related to any plant performance

requirements.

The

inspector could not conclude that this was acceptable

without

justification.

Leakage current measurements

were also made;

15

(4)

(5)

however,

the inspectors

determined

by reviewing the test report

that leakage current

and insulation resistance

measurements

were

made

on different terminals,

and leakage currents

were only

measured

from terminal points to ground,

except for additional

terminal-to-terminal

measurements

performed

on the last day of

the test.

The licensee

could not resolve

these

concerns

during

the inspection,

but did indicate that the qualification of this

equipment

could be established

by analyses

to shorten

the

required operating time.

General Electric EB-25 terminal blocks

constitute Potential

Enforcement/Unresolved

Item 50-220/85-13-04.

General Electric EB-5 terminal blocks,

SCEW 042 - Again

the

Eg file did not identify where

and for what services

the'terminal

blocks are used;

no functional performance

requirements

were defined for plant service;

and the required

operating

time was specified

on the

SCEW sheet

as

28 hours3.240741e-4 days <br />0.00778 hours <br />4.62963e-5 weeks <br />1.0654e-5 months <br />.

gualification was based

on Limitorque test report B0119, which

did not specify acceptance

test criteria applicable to the

NNPC

service.

Three hours into the

LOCA test, insulation resistance

decreased

to 20,000

ohms from terminal

B to ground.

No further resistance

data were taken until the end of the

fourth day,

when the value decreased

to 500 ohms.

On

August 26,

1985 the licensee

advised

by telephone that

he

planned to establish qualification based

on

a newly-

determined required operating time of one hour.

General

Electric EB-5 terminal blocks constitute Potential

Enforcement/Unresolved

Item 50-220/85-13-05.

n

Fisher 304 position switch, pc.

no.

39-11-1LSC - Although

these

switches

are scheduled

to be replaced

in spring 1986,

qualification was claimed

based

on

a

LOCA type test with

supporting analyses for thermal life and radiation.

Similarity between

the test

specimen

and plant equipment

was

based entirely on

a telephone

conversation

with a

Fisher sales

representative,

who stated that

no materials

changes

were

made during the involved manufacturing

time

interval.

The thermal life and radiation calculations

were

not based

on review of a material list, but rather

on

a

telephone

conversation

with a different Fisher sales

representative

who stated that the only non-metallic material

in the limit switch assembly is general

phenolic

used in the

Kulka (not Kukla) terminal strip according to the Vendor Contact

Report in the file.

The inspector 'also stated that telephone

memos

based

on calls to sales

representatives

are not acceptable

for documenting similarity evaluations

or as substitutes

for

engineering

analysis of thermal

aging

and radiation effects

on

the equipment.

Fisher

304 position switches constitute Potential

Enforcement/Unresolved

Item 50-220/85-13-06.

16

(6)

Rosemount

1151 transmitter,

pc.. no.

FT-36-06A - The file

~ not only failed to identify the required level of qualification

(addressed

generically in section 4.A.(1) above), it also did

not identify the procurement

date for this transmitter,

which

is not ori'ginal plant equipment,

so that the inspector could

determine

the applicable criteria.

In response

to questioning

the licensee

was able to provide evidence that in fact the

DOR Guidelines apply.

The file also failed to adequately

establish

the qualified life of the transmitter.

Wyle

analysis report 17655-XNR-2. 1 calculates

a life of 27 years

based

on an oven test of a model

1153 transmitter for

which no acceptance

criterion was identified except

"successful,"

and

on

a material analysis

provided in Patel

r'eport PEI-TR-82-12-10 for a model

1152 transmitter.

The

Wyle report erroneously

used

an activation energy of

~

0.78 ev for wire wound resistors

as limiting, although

this transmitter

has

the Type

E electronics

package,

which

Rosemount report 67710A (included in the file) states

uses

metal film ceramic resistors

instead.

The inspector further

noted that the 0.75 ev activation energy of Buna-N 0-rings

and.seals

appears

to be limiting.

Rosemount

1151 transmitters

constitute Potential

Enforcement/Unresolved

Item 50-220/

85-13-07.

(7)

(8)

Acoustic monitor coaxial cable;

Rockbestos

coaxial cable,

SCEW sheets

040 and 124, for automatic depressurization

system valve position instruments

- During 'the inspection

the licensee

was unable to provide procurement

documentation

that the installed cable

was similar to the cable for which

the file established

qualification, since the Document

Retrieval

Computer

was inoperable

near the end of the

inspection.

A future

NRC inspection will verify the

-similarity.

Acoustic monitor coaxial cable constitutes

Open

Item 50-220/85-13-10.

Laurence solenoid valve, pc. no. 50V-201.2-23 - During the

plant, physical inspection,

two gA-related questions

were

raised

concerning this valve.

First, the seismic

acceptability of the valve installation

was not obvious,

particularly with respect

to

a steel

clamp.

Second,

a

deformed gasket

was noted in the conduit coupling for a

related limit switch (although

a seal

was not required

for environmental qualification).

Licensee

review and

correction of these

items

as required will be addressed

in a future

NRC inspection.

Laurence

solenoid valve

constitutes

Open Item 50-220/85-13-11.

17

E.

IE Information Notices

and Bulletins

The

NRC inspectors

reviewed

and evaluated

NMPC's activities related

to the review of Eg-related

IE INs/Bulletins.

The inspectors's

review included examination of NMPC's procedures

and

Eg

documentation

packages

relative to

12 INs and

one Bulletin.

The

procedures

review determined that

NMPC does

have

a system for

distributing, reviewing,

and evaluating INs/Bulletins relative

to equipment within the scope of 10 CFR 50.49.

During the review

of individual component qualification files the

NRC inspectors

evaluated

NMPC's actions with respect

to INs/Bulletins and identified

no concerns.

18

25